HomeMy WebLinkAbout2544 NANCY GRAY AVE - SPECIAL INSPECTIONS - 11/18/2020November 18, 2020 Bellisimo, Inc. 3702 Manhattan Avenue, Suite 201 Fort Collins, Colorado 80526 Attn: Mr. Nico Campana (ncampana@bellisimoinc.com) Re: Foundation Drain and Damp Proofing Observation Lot 8, Block 2 – Bucking Horse 3rd Filing Fort Collins, Colorado EEC Project No. 15-01-052 Mr. Campana: As requested, Earth Engineering Company, Inc. (EEC) personnel have completed the construction observation services you requested for the referenced project. Those services included observations of the foundation drain placement and damp proofing at the referenced lot. The results of those observations are included with this report. On November 17th, 2020, EEC personnel observed the foundation drain for the referenced project. The foundation drain consisted of 4-inch perforated pipe enclosed in a filter fabric ‘sock’ and was connected to a basement sump pit. The gravel was not placed at the time of our observations and will be placed at a later date. The damp proofing consisted of a grey spray-on coating that appeared to cover all exterior below grade living areas of the basement walls. We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, or if we can be of further service to you in any way, please do not hesitate to contact us. Very truly yours, Earth Engineering Company, Inc. Michael J. Coley, P.E. Principal Engineer TD Structural Engineering, Inc. | 2909 Oxford Ct., Fort Collins, CO 80525 | 970.372.1140 | www.tdstructural.com November 12, 2020 Dominick Campana 3rdgenbuildersinc@gmail.com Observation Report Project: Sabino, 2544 Nancy Gray, Fort Collins, Colorado TDSE Project No.: 20-115 Plans/Details: Plans by TD Structural Engineering Inc. dated 10/8/2020 Observation Dates: 11/6 and 11/12/2020 Items Reviewed: footing and foundation wall sizes and reinforcing, UFER ground Notes: Observations indicate the footing and foundation wall sizes and reinforcing are in substantial conformance with the plans as noted above. In addition, the UFER ground has been placed in general accordance with NEC recommendations. Please let me know if you have any questions. Wendy Thomas Dworak, P.E. Structural Engineer/President TD Structural Engineering Inc.