HomeMy WebLinkAboutWORK ORDER - BID - 8080 EWF & DRAINAGE FOR PLAYGROUNDS (9)Dated:
Work Order Number:
Purchase Order Number:
Project Title:
Commencement Date:
Completion Date:
Maximum Fee: (time & reimbursable direct costs):
Project Description:
Scope of Services:
Acceptance
Service Provider City of Fort Collins
By: By:
Date: Date:
CC: Purchasing Director of Purchasing and Risk Management
$31,126.36
Service Provider agrees to perform the services
identified above and on the attached forms in
accordance with the terms and conditions contained
herein and in the Services Agreement between the
parties. In the event of a conflict between or
ambiguity in the terms of the Services Agreement
and this work order (including the attached forms)
the Services Agreement shall control.
The attached forms consisting of ____ (_) pages
are hereby accepted and incorporated herein by
this reference, and Notice to Proceed is hereby
given.
EXHIBIT "A"
WORK ORDER FORM
Bedrock Slingers
PURSUANT TO AN AGREEMENT BETWEEN
THE CITY OF FORT COLLINS
if over $30,000
6/1/2016
AND
10/5/2015
User
see quote 42282
Troutman Playground Surfacing conversion
10/5/2015
removal of existing surfacing and replacement with engineered wood fiber for
Troutman playground
Jordan Kamps
10/5/15
Contractor: City of Fort Collins - Park & Rec
Contact: Jill Wuertz
Email: jwuertz@fcgov.com
Date: 10/5/2015
Phone: 970-219-1573
Job: Troutman Park
Description Unit x amount Price
Pit Excavation: Remove 16" of subgrade (sand and clay) over 4767 SF and
dispose at Ft Collins Rec Center. 1 x $12,500.00 $ 12,500.00
4" of 3/4" rock option: Purchase, delivery and placement of 85 tons of 3/4" rock 85 tons x $47.00 $ 3,995.00
Fabric: Fabric purchased for bottom of pit 4767 SF x $.08 $ 381.36
Labor for fabric: Labor to install fabric 4 hrs x $105.00 $ 420.00
J-Drain: Purchase of J Drain 7 rolls x $195.00 $ 1,365.00
J-Drain Install: Installation of J-Drain at 6' centers for bottom of pit 3 hrs x $105.00 $ 315.00
EWF: Purchase, delivery and installation of Playsoft 12" deep with compaction 235 CY x $30.00 $ 7,050.00
Metal Planks: Use of metal planks to protect turf 1 x $1,600.00 $ 1,600.00
Drainage Option: Grade pit towards drain pipe, add pipe and trench in with gravel
to move water to South end 1 x $3,500.00 $ 3,500.00
Total $ 31,126.36
Jill Wuertz
Payment Terms: Net 30, unless current contract reflects other terms.
All overdue invoices over 60 days will incur a late fee of $75 or 1.75% of the balance (whichever is greater)
added to the original invoice amount for each 30 day period past terms.
To accept this proposal, please sign below and fax or email back.
ACCEPTANCE OF PROPOSAL
Signature _______________________________________________________ Date ______/______/20____
If you have any questions, please call Jordan at 970.566.2329 and thank you for your consideration!
Jordan Kamps, Manager
Bid includes all labor and materials. Bid excludes turf damage as some will be necessary to load trucks. Estimated
time from start to finish is 5 work days. Please note that extra work like the rock and additional drainage is
expected on this site due to standing water. We have offered a couple of options and the total would be a not to
exceed the amount shown.
Bid Proposal: 42282
6564 N. County Rd. 11C
Loveland, CO 80538
Dispatch 970.817.0909
Fax 970.622.9755
www.bedrockslingers.com
www.groundsolutionsco.com