Re: Harmony Duct Bank Phase 2 – Change Order 2
Dear Ms. McTague:
Exponential Engineering Company (EEC) is requesting a change order to provide
the City of Fort Collins with additional professional engineering services for the
Harmony Duct Bank Phase 2 project.
EEC proposes the following not to exceed price agreement for the scope listed herein
as follows:
Not-to-Exceed
Harmony Duct Bank Phase 2: Change Order 2 $17,760
The price provided is for the work scope outlined in this letter only. Any work outside
of this scope will be considered extra and negotiated with the City of Fort Collins.
Scope of Work:
1. Base Map Survey (Section 5): Lat40 will survey new pothole and elevation
information as required by the modified vault locations and duct bank routing.
EEC will coordinate potholing and pothole survey. Lat40 will coordinate traffic
control.
2. Base Map Profile Drawings (Section 5): Lat40 will create new profile drawings
as required for the reroute onto the travel lane of Harmony Road from west
of Timberline Road to the western edge of the Union Pacific Railroad
easement. New elevation information will be surveyed as required by the
modified route in areas not previously surveyed.
3. Line Route Modification Plan and Profile Drawings (Section 5): Provide
modified duct bank route and vault locations as required for reroute onto
travel lane of Harmony Road from west of Timberline Road to the western
edge of the Union Pacific Railroad easement. Rerouting will include office
and field investigation and modifications of route as required by the utility
locates for construction in new route. Add the new electrical infrastructure to
the base map plan and profile drawings provided by Lat40.
Page 2 of 2
HARMONY DUCT BANK PHASE 2: CHANGE ORDER 2
4. Railroad Crossing Permitting – Assist with creation and submittal of
permitting package for Union Pacific Railroad crossing. This includes
preparation of modified drawings specific to the crossing, preparation of
required forms, and interpretation of requirements relevant to engineering
and design.
Harmony Duct Bank Phase 1 and 2 Items Not Included in Scope of Work:
1. Utility locates for potholing and construction will be ordered by Colorado
Boring Company.
2. Colorado Boring Company will provide potholing services. The potholes used
for engineering will also be used for construction.
Please call me at (970) 207-9648 x117 if you have any questions or need additional
information. EEC looks forward to working with you on this project.
Sincerely,
Tyler Swaney, P.E.
EXPONENTIAL ENGINEERING COMPANY
Electrical Engineer
ESTIMATE OF ENGINEERING SERVICES COSTS
PROJECT: FTCL-1502
PROJECT TITLE: Harmony Duct Bank Phase 2 - Change Order 2
DATE: 1/11/2017
PROJECT MANAGER: T. Swaney
PROJECT ENGINEER: S. Benoit
BILLING GROUP:
20.0% PM 5.0% QC
TASK DESCRIPTION # OF DWGS Engineer I-2 Engineer II-2 Senior Designer Project Controls
Manager (Select One) (Select One) (Select One) Engineer II-2 Engineer II-2 TOTAL HOURS
TOTAL LABOR
COSTS
$132.00 $155.00 $100.00 $125.00 $0.00 $0.00 $0.00 $155.00 $155.00
HOURS HOURS HOURS HOURS HOURS HOURS HOURS HOURS HOURS
Coordinate Potholing & Pothole Survey 2 0.5 11 5 $682.50
Coordinate Base Map Profile Drawing 2 0.5 11 5 $682.50
Line Route Modifications 00 0 $0.00
Line Routing 16 16 0.5 7242 $5,169.50
Plan View 4 16 0.5 5228 $3,275.50
Profile View 8 12 0.5 5228 $3,403.50
Railroad Permitting Assistance 4 2 0.5 2110 $1,255.50
00 0 $0.00
00 0 $0.00
00 0 $0.00
00 0 $0.00
00 0 $0.00
00 0 $0.00
TOTAL HOURS 32 4 46 3 0 0 0 21 9
TOTAL LABOR COSTS $4,224.00 $620.00 $4,600.00 $375.00 $0.00 $0.00 $0.00 $3,255.00 $1,395.00
TOTAL HOURS AND LABOR COSTS: 115 $14,469.00
TOTAL HOURS AND ROUNDED LABOR COSTS (TO BE USED IN PROPOSAL): 115 $14,470.00
AVERAGE BILLING GROUP RATE: $0.00
REIMBURSABLE EXPENSES RATE QTY COST REIMBURSABLE TRIP EXPENSES - TRIP 1
Prints and Plots (22" X 34") BW $1.20 $0.00 Trip 1 Name:
Prints (22" x 34") COLOR $10.00 $0.00 EXPENSE RATE QTY # PEOPLE # OF TRIPS COST Labor Costs $14,470.00
Copies (11" x 17") $0.20 $0.00 Mileage $0.775 $0.00 Reimbursable Expenses $0.00
Copies (11" x 17") COLOR $0.50 $0.00 Airfare $750.00 $0.00 Outside Services $3,290.00
Copies (8.5" x 11") $0.10 $0.00 Per Diem (per day) $46.00 $0.00 Trip 1 $0.00
Copies (8.5" x 11") COLOR $0.25 $0.00 Lodging (per night) $125.00 $0.00 Trip 2 $0.00
High Level Design and Analysis Software $12.50 $0.00 Car Rental (per day) $50.00 $0.00 Billing Group Total $17,760.00
PSS/E Power Systems Analysis Software $100.00 $0.00 Parking and Tolls (total) $15.00 $0.00
GPS Survey Grade Equipment (per week) $1,500.00 $0.00 (Other) $0.00
GPS Survey Grade Equipment (per day) $500.00 $0.00 (Other) $0.00
Arc Flash Labels (each) $1.50 $0.00 (Other) $0.00
(Other) $0.00 TOTAL "TRIP 1" REIMBURSABLE EXPENSES: $0.00
(Other) $0.00 TOTAL ROUNDED "TRIP 1" REIMBURSABLE EXPENSES $0.00
(Other) $0.00
(Other) $0.00 REIMBURSABLE TRIP EXPENSES - TRIP 2
TOTAL REIMBURSABLE EXPENSES: $0.00 Trip 2 Name:
TOTAL ROUNDED REIMBURSABLE EXPENSES $0.00 EXPENSE RATE QTY # PEOPLE # OF TRIPS COST
Mileage (per mile) $0.775 $0.00
OUTSIDE SERVICES (SUB'S, ETC.) RATE QTY COST Airfare $750.00 $0.00
Lat40 Pothole Survey $2,200.00 1 $2,200.00 Per Diem (per day) $46.00 $0.00
Traffic Control $1,090.00 1 $1,090.00 Lodging (per night) $125.00 $0.00
$0.00 Car Rental (per day) $50.00 $0.00
$0.00 Parking and Tolls (total) $15.00 $0.00
$0.00 (Other) $0.00
TOTAL OUTSIDE SERVICES: $3,290.00 (Other) $0.00
0% Markup $0.00 (Other) $0.00
TOTAL OUTSIDE SERVICES WITH MARKUP: $3,290.00 TOTAL "TRIP 2" REIMBURSABLE EXPENSES: $0.00
TOTAL ROUNDED OUTSIDE SERVICES $3,290.00 TOTAL ROUNDED "TRIP 2" REIMBURSABLE EXPENSES $0.00
COST SUMMARY
002 - DESIGN SERVICES