HomeMy WebLinkAboutWORK ORDER - RFP - 8111 CONSTRUCTION MANAGEMENT & INSPECTION ON-CALL (4)Page 1 of 5
1315 Oakridge Drive – Suite 120
Fort Collins, CO 80525
ditescoservices.com
Delivery by email to:
bbuckman@fcgov.com
August 27, 2015
Mr. Brad Buckman, PE, CFM
Civil Engineer II
City of Fort Collins Engineering Department
281 N. College Avenue
Fort Collins, CO 80521
RE: Construction Management Scope of Services
McClelland Turn Lane Improvements
Dear Brad:
Please find attached a detailed scope of work for Construction Management Services related to the McClelland
Drive Right Turn Lane Improvements. Our proposal is for services during the anticipated length of the project from
September through late November 2015. Depending on phasing of the work and availability of asphalt during
middle to late November, portions of the project may extend to spring 2016.
Thank you for the opportunity to work on this project. We greatly value our relationship with the City of Fort Collins
and look forward to another successful project.
Please let me know if you have any questions or require further information regarding this proposal. I can be
reached by phone at 970.988.8605 and email keith.meyer@ditescoservices.com.
Sincerely,
Keith Meyer, P.E.
Enc. Scope of work
Cc: Bill Renz - Ditesco
Ryan Wordekemper - Ditesco
Erika Keeton – City of Fort Collins
file
Page 2 of 5
Exhibit A
McClelland Drive Right Turn Lane Improvements
Scope of Services
Construction Bid No. 8157
Project Understanding
The City of Fort Collins is constructing a right turn lane from northbound McClelland Drive onto eastbound Drake
Road to facilitate a priority lane configuration for the MAX BRT bus system. Currently, the MAX BRT shares a lane
with normal traffic. The new turn lane will give MAX its own lane to operate from thereby reducing travel delay time.
The project is being delivered through a lowest, qualified bidder (hard bid) delivery. Bids are expected to open in
early September with construction following approximately 20 days later. Construction is expected to be complete
in early winter 2015 with the possibility of minor work remaining in spring 2016.
Simultaneous to the McClelland turn lane work, the City will also be extending the Swallow southbound MAX BRT
station bus pull out and sidewalk connection to the station platform.
Phase: Construction Management
During this phase, Ditesco will provide part time Construction Management and Inspection services to assist in
work coordination and ensure compliance with contract documents/specifications.
• We will conduct weekly progress meetings on site (or other location) with the general contractor and their
subcontractors. We will provide meeting minutes for all meetings.
• We will review and recommend approval of pay applications to the City of Fort Collins, review and manage
contract changes for approval by the City, generate and coordinate responses to RFIs and provide for
overall administration of the construction contract.
• Our staff will perform daily site inspections to ensure quality construction and conformity to the plans and
specifications. Inspections will include all flatwork, curb, gutter, sidewalk, subgrade, proof roll and HMA
paving. We will also document daily work progress in the form of daily logs.
• We will assist in review of all project submittals providing comments directly to the general contractor.
• Ditesco staff will review all material test reports. We will comment on reports not meeting specifications
and recommend remediation measures if necessary. We will ensure the appropriate numbers of tests are
taken and that they are sampled according to industry standards and the project specifications. We will
coordinate all testing activities with the selected material testing contractor who will perform the testing
through an existing contract with the City.
• We will maintain a photographic log of the project documenting pre-construction, construction and post
construction conditions. This work is expected to include brief descriptions of each photograph with a
filename, time and date reference.
• As needed, we will coordinate work between the City, general contractor and outside agencies (e.g. utility
companies) affected by the project.
• We will maintain project records including contracts, schedules (overall job and three week look-ahead),
progress meeting minutes, material test results, weekly reports, correspondence, pay applications, change
orders, routine photographs, submittals, RFIs, permits, and post construction close-out paperwork (punch
lists, lien waivers, substantial completion/final acceptance).
• We will conduct a final punch list walk through and inspect the completed installation of the turn lane and
associated work.
Page 3 of 5
• Ditesco personnel will ensure that an as-built plan set is maintained and transmitted to the City upon
completion of the project. This will be a redlined drawing set maintained by our staff and will be
coordinated with plan changes that may be documented by the general contractor.
Phase: Post Construction
• During the Post Construction Phase Ditesco staff will compile all job records in both an electronic and
hardcopy (paper) format for submission to the City. We will make sure all warranty information is prepared
and warranty walk through meetings are scheduled at the 1 and 2 year intervals.
Deliverables
• Deliverables will include full project documentation presented in tabbed binders or vertical files including:
construction correspondence, pay applications, change orders, field orders, schedules, submittals,
transmittals, reports, photographs, meeting notes, record drawings and other relevant information produced
throughout the construction phase. All documents will also be provided in an electronic form on a portable
drive City use.
Schedule
The anticipated schedule for construction of the McClelland Turn Lane Project is as follows:
Construction: September through November 2015
Fee Estimate
We have based our fee estimate on the following assumptions:
• Work to include Swallow Station bus pull out extension/sidewalk improvements
• 3 month project timeframe (approximately 60 working days; 12 weeks)
• Construction to begin around September 2015 with completion in November 2015
• Daily Construction Management/Inspection effort is part time for 3 months
• Temporary trailer office space is not provided
• Material testing services are NOT included as part of Ditesco’s scope of work
Estimated Fee: $32,325.00
Estimated Reimbursable Expenses: $ 436.00
Total: $32,761.00
A detailed task breakdown is included. Please find this on page 5 of this scope of work proposal.
The fee shown above is to be billed on a time and material not-to-exceed basis based on the rates shown in the
table on page 4 and 5 of this proposal. All reimbursable expenses will be billed at direct cost.
Page 4 of 5
Ditesco
2015-2016 Wage Rate Schedule
Principal/Professional Engineer: $120.00 - $160.00 per hour
Project Manager: $100.00 - $130.00 per hour
Construction Manager/Resident Engineer: $110.00 - $125.00 per hour
Project Engineer: $85.00 - $110.00 per hour
Inspector: $75.00 - $95.00 per hour
CAD: $65.00 - $85.00 per hour
Administrative: $45.00 - $65.00 per hour
Subcontractor markup: 8%
Mileage Reimbursement: IRS rate
All other costs at direct expense
Terms 30 days net
City of Cort Collins - McClelland Right Turn Lane Project 8/27/2015
Keith Meyer Bill Renz
Ryan
Wordekemper
Cassidy Hill
Principal Project Project Administrative
(hrs) Manager (hrs) Engineer (hrs) (hrs)
$130 $110 $85 $55
Task 1: Construction Management (Construction Phase) $32,325
1.1 Review Construction Contracts 2 0 2 0 $430 contract review and cost negotiations/checks
1.2 Review Construction Plans and Specifications 2 0 2 0 $430 final review of bid docs for readiness
1.3 Create and compile job files 0 0 2 0 $170 set up job files for project
1.5 Pre-Bid Attendance 0 0 2 0 $170
1.6 Preconstruction Photographs 0 0 2 0 $170
1.7 Preconstruction Meeting (minutes, contact lists, etc.) 0 2 2 2 $500 attendance and management of precon meeting
1.8 Schedule review 0 2 1 0 $305 review contractor submitted schedule
1.9 Submittal/shop drawing coordination and record keeping 0 4 8 0 $1,120
1.10 Construction progress meetings (1 per week for 6 weeks) 5 5 12 18 $3,210 attendance and management of progress meetings
1.12 Contract Management (pay applications, change orders, etc.) 0 4 6 0 $950 processing all contract paperwork
1.13 RFI Response 1 4 2 0 $740 answering contractors formal RFIs
1.14 Construction Management (on site - part time for 6 weeks) 5 24 120 0 $13,490 site inspection and construction management; 4 hrs per day
1.15 Daily Construction Logs 0 0 60 0 $5,100 compiled daily during construction
1.16 Job Files 0 4 24 18 $3,470
test reports, minutes, correspondence, photos, davis bacon
compliance, etc.
3.1 Punch list walk through 0 2 2 0 $390
3.2 Record Drawing Compilation 0 0 4 0 $340
3.3 Close out paperwork (substantial and final completion, etc.) 0 0 2 0 $170
3.4 Project Close Out (compilation of files, photos, job records, etc.) 0 0 2 4 $390
3.5 Warranty walkthrough (11th and 23rd months) 0 4 4 0 $780
Reimbursable
Mileage @ $0.56 per mile $336 $336
Photocopies, project binders/files, etc. $100 $100
Work Effort Subtotal 15 55 259 42 $32,325
Subtotal Reimbursable Items $436
Cost per labor category $1,950 $6,050 $22,015 $2,310
Grand Total $32,761
Phase/Task Description
Classification
Task Sub-
Total
Notes
Reimbursable
Expenses
Page 5 of 5