HomeMy WebLinkAboutPrebid - BID - 8046 ARTHUR DITCH BRIDGE REPLACEMENT - OAK & WHITCOMB1
ARTHUR DITCH BRIDGE
REPLACEMENT – OAK & WHITCOMB
INTERSECTION
BID NUMBER: 8046
PRE-BID MEETING
December 23rd, 2014
10AM @ 215 North Mason – Rm 2E
City of Fort Collins – Engineering Department
Capital Projects Group
2
INTRODUCTIONS
Engineering – Capital Projects
Dean Klingner – Cap. Proj. Manager 221-6511
Tracy Dyer – Project Manager 222-0855
Jeff Usher – Project Inspector 720.270.2653
Purchasing
John Stephen – Senior Buyer 221-6777
3
ATTENDANCE
Please be sure to register
Bid Opening
January 8th, 2015 @ 3:00pm (Our Clock)
Location - 215 North Mason Street
Submit Bids to Purchasing Department
4
IMPORTANT CONTRACT DATES
Pre-Construction Meeting
Mandatory Meeting prior to Commencing Construction
Date and Time to be determined after Contract Award
Construction Start Date
Approximately Late January – Early February 2015
One Hundred Twenty Day (120) Calendar Day Contract
5
IMPORTANT CONTRACT DATES
Substantial Completion
One-Hundred (100) Day Substantial Completion*
April 15th, 2015 Ditch flow target date
Final Acceptance
Twenty (20) Calendar Days from Substantial Completion*
*Date will be dependent on completion of contract and
notice to proceed.
6
CONTRACT DOCUMENTS BID #8035
Plan Sheets
Prepared by: JUB Engineering, Inc / Stantec
Specification Book
Prepared by: JUB Engineering / City of Fort Collins
Subgrade – Subsurface Investigation work on file with City.
7
PROJECT LIMITS
8
SUMMARY OF WORK
Erosion control
Concrete box removal*
*Emergency box repair ~10 years ago, exact limits unknown, precast section
installed, possibly salvageable.
Structural excavation
Cast in-place box installation
Inlet and stormwater pipe installation
9
SUMMARY OF WORK
Waterline lowering: 4” to 8” back to 4” with casing
Concrete curb and gutter, access ramps
Asphalt milling / overlay and full depth asphalt pavement
Parkway irrigation and turf restoration
Traffic control
10
SUMMARY OF WORK
Method for Handling Traffic
All Plans must be approved by Syl Mireles – COFC Traffic
11
SUMMARY OF WORK
Construction Staking
Provided by the City of Fort Collins
48 Hours (Minimum) Required for Notification
Testing
Paid for by the City of Fort Collins thru CTL Thompson
Contractor will coordinate w/ City PM, testing as required
Striping
Provided by the City of Fort Collins
Floodplain Use Permit
Will be obtained and managed by Engineering
12
PROJECT COORDINATION
Area residents
Access to temporary parking
Maintaining safe pedestrian access at all times
Touchstone Facility
South East corner
Fairly constant stream of patients / customers
City Traffic / Light & Power
Grade adjustment of manhole access on NW corner.
Xcel Energy
No known conflicts at this time
13
HIGHLIGHTS OF GENERAL CONDITIONS
Superintendents
The General Contractor SHALL employ a superintendent
whose sole responsibility is to monitor and coordinate all
facets of the work, including project decision making.
14
HIGHLIGHTS OF GENERAL CONDITIONS
Substantial Completion - Defined
• Box Removals, Utilities, Structural Excavation, Box
installation, Backfill -- April 15th, 2015
Liquidated Damages – Substantial Completion
If the Contractor goes past the 100 calendar days* for
substantial completion, damages in the amount of One
Thousand Four Hundred Dollars ($1400.00) for each
calendar day will be assessed
15
HIGHLIGHTS OF GENERAL CONDITIONS
Final Acceptance - Defined
• Completion and Acceptance of: Completion of Sidewalks,
Curb and Gutter, Asphalt Patching / Paving, Landscape
Restoration, Removal of Tree Protection, Removal of
Erosion Control Items (except those as directed by the City
to remain in place), Irrigation / Landscape and Punch List
Items
Liquidated Damages – Final Acceptance
If the Contractor goes past the 20 calendar days for final
acceptance, damages in the amount of One Thousand Four
Hundred ($1400.00) for each calendar day will be assessed
16
HIGHLIGHTS OF GENERAL CONDITIONS
Project Coordination Meetings
Weekly On-Site Meetings (including ticket
collection)
Contractor to update Schedule weekly. The
Contractor may be required to submit
additional Schedules dependent upon progress
of the project.
17
HIGHLIGHTS OF GENERAL CONDITIONS
Construction Hours
Standard Working Hours are from 7:00am to 6:00pm
Monday through Friday
Weekend Work and / or Extended Hours Work may be
granted. Requests for either must be made in Writing a
minimum of 72 hours in advance. Requests are subject
to approval by the City of Fort Collins.
18
HIGHLIGHTS OF GENERAL CONDITIONS
Haul Routes
Request to keep construction related traffic off of
Whitcomb as much as possible.
Site Clean Up
The construction work shall be kept and accomplished in
a neat, clean and orderly fashion
Street sweeping may be required in order to minimize
vehicle tracking and to meet EPA storm water quality
requirements
Dust control will be required as necessary
19
TRAFFIC CONTROL
Contractor Responsibilities:
Maintain vehicle, bicycle, and pedestrian traffic at all
times. ALL detours for ALL modes of transportation shall
be approved by the City prior to construction.
Maintain access to all local businesses
Review all upcoming lane closure needs and /or changes
in traffic control set up at Weekly Progress Meetings
Traffic Control Plans need to be submitted to the City
seven (7) days prior to setup
20
EROSION CONTROL - SWMP
Contractor Responsibilities:
Erosion Control in accordance with Sheets 24 - 27
The Contractor is responsible for maintaining and
repairing all erosion control devices throughout the
project
Contractor will designate a SWMP Administrator prior to
the start of construction. The SWMP Administrator will
conduct weekly inspections and submit a signed, log of
activity weekly to the City.
In the instance of groundwater, a State Dewatering
Permit may be required (30 day approval)*
21
MATERIAL SUBMITTALS
Reviewed by the City
Process Time – 5 days per submittal
WEATHER DAYS
See “Summary of Work” Section
Monthly Anticipated Calendar Days Lost to
Adverse Weather Conditions
22
COMPONENTS OF IMPROVMENTS
23
Removal of Asphalt
Demo plan sheet
24
Removal of Portions of Structure (RCB) &
Structural Excavation
Material recycle options: Barker Construction, Colorado Iron /
Metal and City of Fort Collins
25
Utility Installation: Storm
Relocation of storm line / inlets
26
Utility Installation: Waterline
Water line upsize and lowering
27
Cast in Place Box
Cast in-place single cell
28
Pedestrian Ramp Improvements
All four corners, ADA
Compliant slopes and
truncated dome
installation.
29
Pavement Section
HMA Repair Sections:
Note: Project is located in a defined flood plain, final surfaces
are designed to be built according to plan and floodplain controls.
30
Landscape Restoration
Coordination / Work Area:
31
Landscape Restoration
Coordination / Work Area:
32
Thanks for Attending!
Questions and Clarifications can be Directed to:
John Stephen – Senior Buyer
Office (970) 221.6777
Email jstephen@fcgov.com
AND
Tracy Dyer – Engineering Proj. Mngr. - Capital Projects
Office (970) 222.0855
Email tdyer@fcgov.com