HomeMy WebLinkAboutPrebid - BID - 7673 NORTH COLLEGE IMPROVEMENTS PROJECT - CONIFER TO WILLOX11
North College Improvements Project
Conifer to Willox
Federal Aid Project No. STE M455-106
PRE-BID CONFERENCE
August 5, 2014
2:00 P.M.
215 N. Mason Street
Community Room
City of Fort Collins
Engineering Dept.
Capital Improvements Program
22
INTRODUCTIONS
• Engineering:
• Capital Projects Program:
• Dean Klingner - Program Manager 221-6511
• Matt Baker - Project Manager 224-6108
• Kyle Lambrecht - Project Manager 221-6566
• Randy Maizland – Project Engineer 218-5658
• Joe Crabill - Construction Inspector 222-1134
• Purchasing:
• John Stephen - Purchasing Agent 221-6777
• Traffic:
• Syl Mireles - Traffic Eng. Tech 221-6815
• Consultant Engineers:
• Interwest Consulting Group
• Bob Almirall, P.E. 970-460-8487
33
ATTENDANCE
• Please be sure to register
• BID OPENING
• When: August 20 @ 3:00 P.M.
• Where: 215 North Mason Street (2nd Floor)
44
Vicinity Map
55
IMPORTANT CONTRACT DATES:
• AWARD CONTRACT
• Approximately Early-September 2014
• PRE-CONSTRUCTION MEETING
• Mandatory Meeting Prior to Start of Construction
• Date to be determined after contract is awarded
• CONSTRUCTION START DATE
• Approximately Mid-September 2014
• Approximately 300 Working Days
• SUBTANTIAL COMPLETION
• Calendar date: October 31, 2015
• FINAL COMPLETION
• 30 Calendar days after Substantial
66
SUMMARY OF WORK
North College Avenue:
• Reconstruction and widening of approximately 0.5 mile of 4-lane arterial
• Concrete Pavement w/ RCI layer and asphalt overlay
• New curb and gutter, sidewalk, landscaped parkway and medians
• Storm sewer pipes, manholes, inlets and water quality structures
• Water main relocation/installation and new fire hydrants
• Unclassified excavation, embankment and muck excavation as needed
• Urban Design elements
• 13,164 SY of Concrete Pavement (8” thick)
• 1,212 TONS HMA Reflective Crack Interlayer
• 2,424 TONS HMA (Grading S)(100)(PG 64-28) (2” thick)
• Traffic control and Surveying to be provided by the Contractor
• Temporary striping provided by the Contractor
• Signal work, and Final signing and striping are by City forces.
77
North College Imp Project – Conifer to
Willox
88
CDOT Local Agency Project
UDBE goal for this project is 10%
OJT goal is 1280 hours
Contractors to be on CDOT’s prequalified list
Bid proposal must include:
– CDOT 606 Anti-Collusion Affidavit
– CDOT 714 UDBE Assurance
Bids will not be accepted if they do not have these forms
Fuel Cost Adjustment option
Low bidder to receive:
Form 605, Form 621, Form 715, and Form 718
These forms must be returned by 4:30 pm the following day (August 21st)
Monthly payments will not be processed until all documentation
required by CDOT for federally funded projects has been
submitted to the City.
99
PROJECT OVERVIEW
• Phasing
• Fall 2014 – West side removals, storm utility and roadway
• Spring through Fall 2015 – East side construction and medians
• Traffic control – US287
• 1 Southbound lane, 2 Northbound lanes, and 1 center turn lane
• Access to businesses to remain open at all times
• Coordination with other utilities
• Contractor responsible to acquire all appropriate permits and submit
required documentation
• SWMP – permit and inspections
• Dewatering Permit (60 days to obtain)
• Permit for work within CDOT ROW
• CDOT Form 205 for each subcontractor
• TCS Diaries, Payrolls
• Two historic properties
1010
Project Overview
• Partnering session prior to construction
• Public Information Services bid item
• No designated staging area provided
• Plans have:
– Tabulation of Utilities
– Tabulation of Removals and resets
– Tabulation of Concrete Items
– Tabulation of Surfacing Items
– Tabulation of Storm water Quantities
– Tabulation of Erosion Control
– Tabulation of Electrical Items
– Tabulation of Urban Design Elements
– Tabulation of Irrigation Quantities
1111
HIGHLIGHTS FROM GENERAL CONDITIONS AND
GENERAL REQ’S:
• SUPERINTENDENTS:
• The General Contractor SHALL employ a full time Superintendent whose sole
responsibility is to monitor and coordinate all facets of the work
• LIQUIDATED DAMAGES:
• SUBSTANIAL COMPLETION:
• The contractor will need to meet substantial completion requirements by October
31, 2015. Substantial Completion is defined as all roadway improvements complete,
traffic following in the lane arrangements shown on the plans for finished roadway,
all sidewalk and enhanced crosswalks complete, all landscape and irrigation work,
including the medians and center of the roundabout, installed and approved, and all
erosion control installed/functioning. If the Contractor goes past the October 31,
2015 substantial completion date, damages in the amount of Three Thousand
Nine Hundred Dollars ($3,9000.00) for each calendar day will be assessed.
• FINAL ACCEPTANCE
• Final acceptance must be met within 30 days of Substantial Completion. Liquidated
damages in the amount of Three Thousand Nine Hundred Dollars ($3,900.00) for
each calendar day will be charged if this schedule has not been met.
1212
HIGHLIGHTS FROM GENERAL CONDITIONS AND
GENERAL REQ’S:
• WARRANTY:
• All workmanship and material issues will be resolved during the correction
period prior to final acceptance as per CDOT.
• Hot Mix Asphalt Warranty Bond for $275,000
• 2 year Concrete warranty
• CONSTRUCTION TIME:
– Calendar date of completion, October 31, 2015, approximately 300
working days
• Standard Hours of Operation
• 7:00 AM thru 6:00 PM - Monday thru Friday.
• Given the scope of the proposed improvements, the City will allow extended
working hours
• Extended Hours requests must be made in writing a minimum of 5 days
prior to the request date
1313
HIGHLIGHTS FROM GENERAL CONDITIONS AND
GENERAL REQ’S:
• PROJECT MEETINGS:
• Once a week at the construction office, time to be determined.
• Agree to quantities weekly
• Monthly payments confirm acceptance of quantities by the
Contractor. ALL quantity disputes MUST be resolved prior to
monthly progress payments.
• PROGRESS AND SCHEDULE REVISIONS:
• Prior to construction, initial schedule must be submitted and approved
• Schedules shall be updated weekly
• The Contractor may be required to submit additional schedules
depending on the progress of the project.
• Record Drawings Plan Set
• Contractor will be required to keep record drawings
1414
HIGHLIGHTS FROM GENERAL CONDITIONS AND GENERAL
REQ’S:
• HAUL ROUTES:
• Arterial and Collector streets only. Contractor will not be allowed to
use residential streets to access the site with trucks hauling
materials.
• SITE CLEAN-UP:
• The construction work shall be kept and accomplished in a neat,
clean and orderly fashion.
• Tracking pads and street sweeping will need to be used in order to
minimize tracking and meet EPA storm water quality requirements.
• Dust control will be required.
1515
Highlights from Specifications
1616
PHASING
• Phase I - West side utilities, concrete roadway paving
and landscaping. East side alley paving.
2 Lanes Northbound
1 Lane Southbound
Center Turn Lane
1717
PHASING
• Phase II - East side utilities, concrete roadway paving
and landscaping.
2 Lanes Northbound
1 Lane Southbound
Center Turn Lane
1818
PHASING
• Phase III – Median construction, landscaping and final
asphalt RCI and 2” overlay.
Traffic Control TBD
1919
Remove headwall (31 LF) – STA 63+40
Remove misc. foundations (42 EA)
SECTION 202 - REMOVALS
Remove Palomino sign foundation
2020
SECTION 202 - REMOVALS
Remove existing canopy edge at 1304 – Roulon’s
See project special for structural inspection requirements Section 202 Page 54
2121
SECTION 202 - REMOVALS
Remove and return to owner (Page 53)
• Carport at 1405 North College (verify this is on plans)
• Satellite Dish at 1311 North College (verify this is on plans)
• Antique Equipment at 1295 North College
• Decorative Landscape Boulders
2222
• Removal of post lights (Montclair)
• Removal of private lights (4)
SECTION 202 - REMOVALS
• Removal of planters (13)
• Removal of brick planter (Montclair)
2323
SECTION 202 - REMOVALS
• Removal of concrete barrier curb at the Ever Open Café
• Removal of bollards at Acme Machine
• Removal of steel structure (1505)
2424
SECTION 202 - REMOVALS
Remove Business Signs
Budget Host Inn Sign
2525
Removal of asphalt mat (8 to 12 Inch)
SECTION 202 - REMOVALS
Removal of concrete pavement 5,562
SY – This includes concrete pavement
that may have asphalt over it after
milling is completed
Planning
2626
Typical Roadway Section
2727
203 Unclassified Excavation – 5120 CY
203 Blading – 10 Hours
203 Muck Excavation – 2500 CY
203 Embankment – 1080 CY
SECTION 203 – EARTHWORK
Geogrid & Base are incidental to the muck-ex quantity
2828
203 Potholing
• City potholing and utility survey during design does not preclude
contractors from being required to do their own potholing.
• City pothole info is show in the plans for information only.
SECTION 203 – EARTHWORK
2929
SECTION 206 – EARTHWORK
206 Structure Backfill* (FLOWFILL) – 1,859 CY
*All shallow utilities and pipe structures shall be backfilled
with flowfill. Payment based on tickets collected
All storm pipe trenches
must be flowfilled. The
flowfill is NOT incidental
to the pipe installation.
Pipe trench excavation
shall be limited to neat
lines per CDOT spec’s.
3030
207 Topsoil (Varying depth) –
1,666 CY
Topsoil certified lab testing results
must be submitted for review prior
to acceptance and placement.
SECTION 207 – TOPSOIL
3131
SECTION 208 – Erosion Control
• Contractor will obtain and maintain the SWMP from the Colorado Dept
of Public Health and Environment (CDPHE)
• The Erosion Control Plans provided are not the SWMP. However,
plan quantities were calculated from the Erosion Control Plan.
• Erosion Control is broken into several measurable pay items
• Silt fence, concrete washout structure, inlet protection, etc.
• Contractor is required to have an Erosion Control Supervisor that shall
enforce all policies that apply to this project.
3232
210 Reset Mailbox (Each) - 14
SECTION 210 – RESET STRUCTURES
3333
210 Relocate Water Meter – 13 each
210 Relocate Water Services– 11 each
210 Adjust Valve Box – 11 Each
210 Adjust Water Meter – 2 Each
210 Adjust Manholes – 8 Each
210 Adjust Monitoring Wells – 2 Each
210 Adjust Structure (Water Quality Outfall Structure in Ponds at Poudre)
SECTION 210 – RESET STRUCTURES
3434
SECTION 304 – Pavement Section
• 304 Aggregate Base Course (Class 6) (6” depth) –
15,405 TONS
3535
SECTION 403 – HOT MIX ASPHALT
• 403 Hot Mix Asphalt (Reflective Crack Interlayer) – 1,212 Tons
• Product Contact Info
• Road Science, LLC
• 918-524-7100
• 403 - Hot Mix Asphalt (Patching) (Grading S) (75) (PG 64-22) (Private
drives) – 858 Tons
• 403 - Hot Mix Asphalt (Grading S)(75)(PG64-22)(Public Side Streets) –
822 Tons
• 403 - Hot Mix Asphalt (Grading S)(100)(PG64-28) – 2,424 Tons
• 403 – Leveling Course (Grading SX)(100)(PG64-22) – 602 Tons
3636
SECTION 412, 601 and 608 –
CONCRETE
• 601 – Masonry Walls – 245 LF (located at Palomino Hotel)
• 412 - Concrete Pavement (8 Inch)(Roadway) – 13,164 SY
• 412 - Concrete Pavement Drive Approach (8 Inch) – 1,306 SY
• 608 - Concrete Sidewalk (6 Inch) – 3,550 SY
• 608 – Colored Concrete Crosswalk (11 Inch) – 348 SY
• 608 – Curb & Gutter (Various Types) – 13,062 LF
412 – Add-On For Fast Track – 200 SY
3737
SECTION 603 – STORM UTILITY
West Side Storm Sewer – Hickory to Car Wash (Approx. 2300 LF RCP)
East Side Storm Sewer – Conifer to Bristlecone (Approx.
1285 LF RCP)
3838
SECTION 603 – STORM UTILITY
Masonry W
• Trench to be excavated to neat lines at 18 inches on each side of pipe
• Bedding is incidental to pipe installation but flowfill is NOT
• Flowfill paid separately measured by tickets collected
3939
SECTION 603 & 604 – STORM
UTILITY
• Conifer Street future NECCO connection
See Plan Sheet 135 for details
M.H. Special (Open Bottom)
M.H. Special with SAFL Baffle (WQ Unit)
4040
AREA INLETS
Area inlets behind
sidewalks
Direct connection
Detail Sheet 136
4141
MANHOLE SPECIAL
See M.H. Detail Sheet 136
West side 30” RCP ties into existing dual 27” CMP
4242
Waterline
4343
Waterline
4444
Waterline
• 8” Waterline (PVC 900) & 6” Waterline (PVC 900)
– All Fittings Incidental to Installation
• Epoxy Coated Fittings
• Stainless Steel Bolts
• Tracer Wire and Ground Rod
• Gate Valves will be Measured
• Backfill shall be Flowfill
– Paid per ticket, but excavation will meet cross-section
for Stormpipe installation
• Will not pay for flowfill outside the neatline!
4545
Waterline
• New Fire Hydrants
– Waterous Pacer
250, with Weather
Shield Nut (5 ¼”),
Right Hand Open
4646
Medians
4747
Medians
4848
Medians
• Removal of Pavement
4949
Medians
Median Curb Special Curb and Gutter Type 2
(Section IB)
5050
Medians
• Boulders
•Mulch
• Clusters of
Plants
• Trees
• Irrigation
5151
Medians
• Boulder Alignment to be Surveyed
• Top of Boulder Elevation Specified in Plans
5252
Medians
• Planting to be clustered
5353
Medians
• Cross Section
5454
Medians
• Median Cover Material
– Standard Grey Concrete
5555
Medians
Median 1 – Irrigation POC Median 2 – Irrigation POC
5656
Medians
Median 3 – Irrigation POC Median 4 – Irrigation POC
5757
Medians
All Medians have an Undrain Outfall Connected to the
Stormsystem
5858
Urban Design
5959
Urban Design
Corner Treatments
• Concrete Pavers
•4”x8”
•8”x8”
• Borgert Untumbled Holland
Stone, Milstream Color
• Concrete Underlayment
Incidental
• Seat Walls
• Stenciled Street Names
• Enhanced Crosswalks
• Concrete Sidewalk (6”)
6060
Urban Design
Landscaping
• Topsoil
• Inorganic/Organic Mulch
• Organic Mulch provided by City,
Contractor hauls & places
• Deciduous Trees
• Ornamental Trees
• Deciduous Shrubs
• Evergreen Shrubs
• Ornamental Grasses
• Perennials
• Tree Grates and Frames
6161
Urban Design
Irrigation
• Bid as Lump Sum
• Two ¾” taps
• Areas Behind Walk
• Must make system operational
during construction
• Western States Bank
• McDonalds
• North College Car Wash
• Albertsons Development
• North College Community, LLC
• Budget Host Inn
6262
Urban Design
• Landscape
Establishment/Maintenance
• Shall be from initial installation through
final acceptance
• Contractor not responsible for warranty
requirements on the irrigation and
landscaping following final acceptance
• Includes
• Watering
•Mowing
• Weeding
• Fertilizing
• Cultivating/Pruning
• Maintain depths of mulching material
• Replacement of dead/dying plants
6363
Urban Design
Pedestrian Lights
• Light Standards – 36 EA
• Light Foundations – 36 EA
• Lighting Control Center – 3 EA
• 2” & 1” Electrical Conduit
• Wiring – Lump Sum
• Aluminum wiring specified
• Pursue Joint Trench
Agreement with City L&P
• Art in Public Places J-Box
6464
Urban Design
Art In Public Places
• Contractor to construct
foundations
• Artist to install pieces
• Wired for lighting
6565
Surveying/Mobilization
6666
Surveying
• Construction
Surveying to be
provided by the
Contractor
6767
Mobilization
• Mobilization is a Lump Sum
item
• Field Office (Special)
• Public Information Services
• Liaison with Businesses
Owners
• Dedicated Individual for
position
• Must meet requirements of
specifications
• Coordinate with City Staff
6868
Traffic Control
6969
Phases I & II
• Anticipate the following:
– Two Northbound Lanes
– One Southbound Lane
– One Center Turn Lane
• Coordinate with City of Fort Collins for Approval
• Access to Businesses shall be provided at all times!
– Arrangements in advance when impacting access
• Additional Lane Closures will be considered on as
needed basis
7070
Phases III & IV
• Construction of the Medians
• Coordinate with City of Fort Collins for:
– Lane Configurations
– Approval
• Access to Businesses shall be provided at all times!
– Arrangements in advance when impacting access
7171
Traffic Control
• Traffic Zone Traffic Control – LS
– Covers all traffic control necessary for the project
– Plans developed by Contractor
– Approved by City of Fort Collins at least two
weeks prior to start date
• Flagging - HR
• Traffic Control Management - Day
• Traffic Control Inspection – Day
7272
Traffic Control
• Business Access Specialty
Signs
– Cannot block business
access points with traffic
control
• Portable Message Sign
Panel
– Up and above what is
necessary for project
– Used as directed by City
7373
Traffic Control
• Wont be restricting
oversize vehicles up to
14’ wide
• Emergency Vehicle
Consideration
• Temp. Striping
– Performed by the
Contractor
– Incidental to Traffic
Control (LS) item
7474
Thanks For Attending!
• Any Questions or concerns can be addressed to:
• Randy Maizland
• Cell: (970) 218-5658
• Email: rmaizland@fcgov.com
– Matt Baker
• Office – (970-221-6108
• Cell – (970) 222-0748
• Email: mbaker@fcgov.com
• Kyle Lambrecht
• Office: (970) 221-6566
• Cell: (970) 692-9209
• Email: klambrecht@fcgov.com