CHANGE ORDER
NO. #7
PROJECT TITLE: Consulting Support for Asset Register and Work Order Management
CONTRACTOR: Excergy Corporation
WORK ORDER NUMBER:#2
PO NUMBER: 9162678
DESCRIPTION:
1. Reason for Change: Due to Staff time constraints, competing work priorities and a scope of work
change for Work Order #2 to accommodate additional Maximo improvements, WO #2 completion date
needs to be extended to December 31, 2018.
2. Description of Change: Continue improving the 2013 Water Resources & Treatment Maximo
implementation by developing new metrics to be used with KPIs, re-build Maximo queries, re-configure
user Start Centers, and assist Utilities IT with developing new Maximo reports.
3. Change in Work Order Price: None
4. Completion Date (if Changed): 12/31/2018
ORIGINAL WORK ORDER PRICE $ 0.00
TOTAL APPROVED CHANGE ORDER $ 0.00
TOTAL PENDING CHANGE ORDER $ 0.00
TOTAL THIS CHANGE ORDER $ 0.00
TOTAL % OF THIS CHANGE ORDER %
TOTAL C.O.% OF ORIGINAL WORK ORDER %
ADJUSTED WORK ORDER COST $ 0.00
CONTRACTOR: Excergy Corporation
By: Date:
Name: James Ketchledge Title: President Excergy Corporation
ACCEPTANCE: Date:
Jason Graham, acting on behalf of Carol Webb, Water Reclamation & Biosolids
Manager
ACCEPTANCE: Date:
Rick Morford, Project Manager
REVIEWED: Date:
Pat Johnson, Senior Buyer
DocuSign Envelope ID: A45E7A57-E7F5-41E8-87F9-4C086E014983
8/6/2018
8/6/2018
8/6/2018
8/7/2018
Change Order Form (for Work Orders)
Official Purchasing Form
Last updated 10/2017
ACCEPTANCE: Date:
Coy Althoff, Utilities Asset Manager
Change Order Comments Here:
Due to the high demand put on the City of Fort Collins Water Production and Water Reclamation facilities
during Summer months staff time must be reallocated to their primary duties of maintaining the facilities.
Maximo tasks identified in Work Order #2 and assigned to city staff will be completed as time allows
during this high demand period.
With the high demand on WR&T staff there is a need to further refine the scope of what they are being
tasked with. Below is that refined scope definition.
WR&T Change Order #7 Scope Objective:
Water Resources & Treatment staff together with Excergy support will continue to improve the WR&T
2013 Maximo implementation by developing Key Performance Indicators (KPI), reports, configuration
and re-development of Maximo queries which shall include re-configuration of User Start Centers.
Measuring progress for this scope objective will be done through regularly scheduled bi-weekly
Production Support meetings between the Excergy team and WR&T staff.