WORK ORDER FORM
PURSUANT TO A MASTER AGREEMENT BETWEEN
THE CITY OF FORT COLLINS
AND
MICHAEL BAKER INTERNATIONAL, INC.
WORK ORDER NUMBER: 254902200-BAKER-18-01
PROJECT TITLE: Replacement of Riprap at Linden Avenue
over Poudre River
ORIGINAL BID/RFP NUMBER & NAME: 8331 Bridge Inspection, Maintenance,
Repair & Replacement Program
MASTER AGREEMENT EFFECTIVE DATE: September 16, 2016
WORK ORDER COMMENCEMENT DATE: July 27, 2018
WORK ORDER COMPLETION DATE: September 14, 2018
MAXIMUM FEE: (time and reimbursable direct costs): $7,320.00 (Seven thousand three hundred
twenty dollars)
PROJECT DESCRIPTION/SCOPE OF SERVICES: See attached.
Service Provider agrees to perform the services identified above and on the attached forms in
accordance with the terms and conditions contained herein and in the Master Agreement between
the parties. In the event of a conflict between or ambiguity in the terms of the Master Agreement
and this Work Order (including the attached forms) the Master Agreement shall control.
The attached forms consisting of 3 (three) page(s) are hereby accepted and incorporated herein,
by this reference, and Notice to Proceed is hereby given after all parties have signed this
document.
SERVICE PROVIDER: Date:
Danielle Smith, Operations Manager - Transportation
ACCEPTANCE: Date:
Caleb Feaver, Project Manager
REVIEWED: Date:
Elliot Dale, Senior Buyer
ACCEPTANCE: Date:
Gerry Paul, Purchasing Director
(if greater than $60,000)
DocuSign Envelope ID: 82EC5C65-430F-43D9-9F59-D8B94DBD49B5
7/27/2018
7/27/2018
7/30/2018
Exhibit “A”
WORK ORDER FORM
PURSUANT TO AN AGREEMENT BETWEEN
THE CITY OF FORT COLLINS
AND
MICHAEL BAKER INTERNATIONAL, INC.
DATED: July 27, 2018
Work Order No. _______6__________
Purchase Order No. ________________
Project title: Bridge Inspection, Maintenance, Repair and Replacement Program
Replacement of Riprap at Linden Avenue over Poudre River
Commencement Date: July 27, 2018, 2018
Completion Date: September 14, 2018
Maximum Fee: $7,320.00 (See attached Fee Schedule)
PROJECT DESCRIPTION:
This scope of work is for replacement of the existing riprap at the abutments of the Linden Avenue Bridge over the
Poudre River with grouted riprap. This effort includes the preparation of two (2) bridge hydraulic sheets prepared in
conformance with CDOT standards. This scope also includes scour calculation analysis and verification that the
proposed stream section is in conformance with the current effective FEMA model for the Poudre River, which will
be documented in a “No Rise” Memorandum to be prepared by Baker and submitted to the City’s Stormwater
Department. It is anticipated in this scope that the proposed grouted rip rap section will return the hydraulic section
of the Poudre River beneath the Linden Avenue Bridge to its existing plan condition as defined in the “As Constructed”
plans for the Linde Street Bridge, Cache La Poudre River, Structure from STA 10+12.71 to STA 12+17.29 (Project #
305-2150000) provided to Baker by the City on June 26, 2018.
This scope of work does not include the following:
• Structural modifications to the Linden Avenue Bridge over the Poudre River
• Updates to the FEMA effective model or CLOMR/LOMR application process
• Preparation of a Floodplain Use Permit (prepared by City, if necessary)
• Scour protection work at the bridge pier
• Re-Grading beyond the extents necessary to support the proposed rip rap section
• Lighting (aesthetic or security) or any other aesthetic or urban design enhancements
• Environmental Permitting or Documentation beyond the completion of a “No Rise” Memorandum as
previously discussed
DocuSign Envelope ID: 82EC5C65-430F-43D9-9F59-D8B94DBD49B5
Exhibit A - Work Order Form
Bridge Inspection, Maintenance, Repair and Replacement Program – Replacement of Riprap at Linden Avenue over Poudre River
July 2018 2 of 3
CONTRACT TYPE:
This contract will follow a Time and Materials (Not to Exceed) contract type. All work will follow a Time &
Materials (T&M) contract type. Rates will follow the job category rate table established with the Master
Contract for the 2017/2018 work cycle.
TEAM RESPONSIBILITIES AND AUTHORITY:
Michael Baker is the prime design consultant and will be responsible for managing all consultant related
activities for this project, as authorized and directed by the City. There are no subconsultants included on
the Michael Baker Team.
All deliverables will be in the following current software platforms:
(1) PDF, Microsoft Word, Excel, and Access
(2) Others as applicable
GUIDELINES AND REFERENCES (CURRENT VERSION UNLESS NOTED OTHERWISE):
Applicable standards include:
(1) CDOT Bridge Design Manual
(2) CDOT Bridge Detail Manual
(3) City of Fort Collins Code, Chapter 10 (Flood Prevention and Protection)
(4) FHWA Hydraulic Engineering Circular No. 18 (Evaluating Scour at Bridges)
(5) FHWA Hydraulic Engineering Circular No. 23 (Bridge Scour and Stream Instability Countermeasures)
(6) Any other applicable documents as approved by the City
SCOPE OF SERVICES
There are two primary elements that will completed as part of this project. These are:
(1) Project Administration
(2) Scour Protection Design & Documentation
I. Project Administration
Upon notice to proceed, Baker will perform project administration duties throughout the length of the contract.
Invoices will be provided to the City on a monthly basis and will include a billing summary and a progress report for
work performed during the current billing period and project to date.
The following meetings are anticipated:
(1) One Site Meeting
II. Scour Protection Design & Documentation
Michael Baker will prepare design documentation and produce plans for the construction of the proposed scour
protection of the Linden Avenue over Poudre River abutments. Michael Baker will also prepare a “No Rise”
DocuSign Envelope ID: 82EC5C65-430F-43D9-9F59-D8B94DBD49B5
Exhibit A - Work Order Form
Bridge Inspection, Maintenance, Repair and Replacement Program – Replacement of Riprap at Linden Avenue over Poudre River
July 2018 3 of 3
Memorandum for the project area. All documents will receive a quality assurance and quality control (QA/QC)
review, in accordance with the Baker Way, prior to submittal.
DELIVERABLES
The following is an estimate of the deliverables required for this project. As the project develops, the type and number
of deliverables may vary. Refer to the detailed discussions above for further information. All inspection information
shall be compiled onto a single CD and delivered to the City at the end of the project.
Project Administration (Ongoing)
(1) Monthly progress reports with monthly invoices
(2) Meeting and telephone conversation documentation
Inspections (Delivered at End of Project)
(3) One 11x17 printed copy of design plans, signed and stamped by the Engineer of Record
(4) One PDF file of the design plans (11x17)
(5) One PDF file of the “No Rise” Memorandum
(6) Quality Control review of all project deliverables prior to submittal
SCHEDULE
Work shall commence on, or after, July 27, 2018 and shall be completed by September 14, 2018
FEE
Classification Sen. Project Mgr. Engineer III Associate I
Rate $185.00 $135.00 $80.00
1 Project Administration Hours Hours Hours
Data Collection & Project Set Up 3
Invoicing (Monthly) 3
Project Meeting 3 3
2 Scour Projection Design & Documentation
Scour Analysis and Design 6
Plan Preparation 6 20
No-Rise Memorandum & Model Verification 8
QA/QC 2 2 2
Hours 11 25 22
Fee $2,035.00 $3,375.00 $1,760.00
ODCs
Mileage (1 Roundtrip to FC) $100
Printing & Miscellaneous $50
Total ODC $150
Total Fee $7,320.00
Linden Avenue Bridge over Poudre River