WORK ORDER FORM
PURSUANT TO A MASTER AGREEMENT BETWEEN
THE CITY OF FORT COLLINS
AND
LORIS AND ASSOCIATES
WORK ORDER NUMBER: 400903821-LORIS-18-01
PROJECT TITLE: Power Trail and Harmony Road Grade
Separated Crossing Project Phase 1 –
Alternatives Analysis and Feasibility Study
ORIGINAL BID/RFP NUMBER & NAME: 8730 Engineering Design and Support
Services for the Power Trail Grade
Separated Crossing at Harmony Road
MASTER AGREEMENT EFFECTIVE DATE: July 24, 2018
WORK ORDER COMMENCEMENT DATE: July 27, 2018
WORK ORDER COMPLETION DATE: March 31, 2019
MAXIMUM FEE: (time and reimbursable direct costs): $308,263 (Three hundred eight thousand
two hundred sixty three dollars)
PROJECT DESCRIPTION/SCOPE OF SERVICES: See attached
Service Provider agrees to perform the services identified above and on the attached forms in
accordance with the terms and conditions contained herein and in the Master Agreement between
the parties. In the event of a conflict between or ambiguity in the terms of the Master Agreement
and this Work Order (including the attached forms) the Master Agreement shall control.
The attached forms consisting of 7 (Seven) page(s) are hereby accepted and incorporated herein,
by this reference, and Notice to Proceed is hereby given after all parties have signed this
document.
SERVICE PROVIDER: Date:
Peter Loris, Senior Vice President
ACCEPTANCE: Date:
Caleb Feaver, Project Manager
REVIEWED: Date:
Elliot Dale, Senior Buyer
ACCEPTANCE: Date:
Gerry Paul, Purchasing Director
(if greater than $60,000)
DocuSign Envelope ID: 381C86A4-241C-4C70-8013-696547D69393
7/26/2018
7/26/2018
7/27/2018
7/27/2018
100 Superior Plaza Way, Suite 220, Superior, CO 80027 Phone (303) 444-2073 otak.com
Work Plan (Work Order #1)
Power Trail Grade Separated Crossing at Harmony Road
1. Project Kick-off Phase
a. Kick-off Meeting – LORIS, Interwest, BHA Design, Lithos, ERO, 360 Rail Services, and Apex will
attend a kick-off meeting in Fort Collins. LORIS will prepare the agenda and meeting summary.
b. Mapping
i. Interwest will provide mapping prepared by the City, including property ownership. Use mapping
provided by the City. LORIS will convert the survey to LORIS layer standards. Supplemental survey
will be provided by King Surveyors through a direct contract with the City of Fort Collins.
ii. Interwest will obtain utility company as-constructed drawings to confirm locations as identified by
surface locating. The as-constructed drawings could also provide preliminary vertical utility
information.
iii. Potholing – Interwest will coordinate and monitor potholing performed by Colorado Utility Finders.
The pothole information will be surveyed by King Surveyors, through a Fort Collins Work Order, with
horizontal and vertical data added to the topographic mapping by King.
c. Utility Meetings and Coordination
i. UPRR – LORIS, Interwest and 360 Rail will meet once with the UPRR to determine construction
requirements adjacent to the RR, in the railroad ROW (if needed) and for at-grade railroad crossings.
ii. Platte River Power – Interwest will meet once with Platte River Power to determine utility line
construction/relocation requirements, timeline to relocate and agreements required.
iii. Xcel, Century Link, Comcast, Level 3, Fort Collins Loveland Water District, City Utilities, and other
utilities as needed. Interwest will perform up to fifteen (15) utility company meetings to establish
relocation (if required) requirements and write a meeting summary.
iv. Drainage – Interwest will meet with City Utilities and irrigation companies to determine construction
and drainage modification requirements.
v. Report – Interwest will provide a utility memo that summarizes their findings.
d. Geotechnical Engineering
i. Lithos will perform four (4) deep borings for bridge/ underpass foundations and nine (9) shallow
borings for pavement and trail design for the Alternative Analysis. Depending on the option selected,
additional borings may be required during future design phases.
ii. Groundwater Analysis – Four piezometers will be installed, and water elevation monitored for at
least four seasons.
iii. Pavement design – Lithos will provide pavement design requirements.
iv. Lithos will provide a geotechnical report to summarize their findings and provide recommendations
for: shallow foundations, deep foundations, underpass construction (cut & cover and tunneling),
soil lateral load criteria, soluble sulfate content, and water table. Geotechnical recommendations
will be applicable to tunneling and tunneling recommendations will be provided in 2.a.i.
e. Environmental
i. Studies – ERO will perform initial environmental assessments for wetlands, threatened and
endangered (T&E) species, noxious weeds, migratory birds, SB40, 6(f) and 4(f), hazardous
materials, and historic properties. Noise surveys will not be performed.
ii. Each ERO resource specialist will coordinate directly with CDOT to determine the level of effort
necessary for reporting on and evaluating impacts to each resource type.
DocuSign Envelope ID: 381C86A4-241C-4C70-8013-696547D69393
Work Plan – Work Order #1
Power Trail Grade Separated Crossing at Harmony Road Page 2 of 3
June 27, 2018
iii. Reporting – ERO will provide reports documenting the environmental resources found per
CDOT requirements.
f. Urban Design
i. Contextual site analysis – BHA will document historical context and architectural features at
and around the project location.
ii. Contextual structural analysis – BHA will document the architectural design utilized in various
grade separated crossings along the Power Trail and other pertinent projects in the vicinity. BHA
will also collect and share relevant design context for ‘world class’ grade separated crossings
elsewhere to explore the range of potential for the trail crossing as a gateway feature, community
asset, or neighborhood identifier.
2. Alternative Analysis and Feasibility Study
a. Option Development I
i. Underpass Options – The LORIS team will evaluate both vertical and horizontal alignments for bridge
and underpass options.
1. Tunneled underpass – LORIS and Lithos will determine the feasibility of tunneling, and provide a
cost estimate for tunneling the underpass. Lithos will prepare a feasibility memo report. At this
time, we anticipate the tunnel option would be located adjacent to the railroad. Interwest will
coordinate utility requirements and provide design concepts
for drainage modifications. BHA will provide two (2) urban design alternatives for the tunnel and
retaining walls.
2. Cut and cover underpass – LORIS will develop a conceptual standard precast underpass design. At
this time, we anticipate the underpass would be located further west to provide sufficient length
from the railroad tracks to facilitate lane shifts for phased construction; however, we will also
evaluate an option east of the UPRR. Interwest will provide utility and drainage impacts and
modifications. BHA will provide two (2) similar urban design alternatives for the tunnel and retaining
walls.
ii. Overpass
1. Structures – LORIS will evaluate two (2) overpass structure alternatives. One will be using pre-
engineered structural members, and the second will use a custom structure. LORIS will provide
constructability options. BHA will provide two (2) urban design alternatives for the structures.
iii. Trail – LORIS will develop trail designs pertinent to the grade separated crossing alternatives. Loris
and BHA will develop and analyze the remaining alignments north and south to connect to the existing
trail system, including grading impacts, drainage conditions, and potential affects to adjacent
properties. Interwest will evaluate and provide design concepts for drainage modification.
iv. Environmental – ERO will assess impacts and permitting requirements for each alternative.
v. Cost Opinions – Loris, Interwest, Lithos and BHA will prepare construction cost opinions for their
scope of work.
vi. Alternative Comparison Matrix – LORIS will prepare an overview matrix to quickly compare the various
project considerations with respect to each alternative.
b. City Review/Coordination
i. Meeting – LORIS, Interwest, and BHA, will attend three (3) review meetings with the City of Fort
Collins core project team.
c. UPRR, PRPA, and Utility Review I
i. Meeting – LORIS and Interwest will attend up to five
(5) utility review/coordination meetings. 360 Rail will attend meetings and perform coordination with
the UPRR.
DocuSign Envelope ID: 381C86A4-241C-4C70-8013-696547D69393
Work Plan – Work Order #1
Power Trail Grade Separated Crossing at Harmony Road Page 3 of 3
June 27, 2018
d. Option Development II
i. Alternative Analysis Revisions – Our design team will revise plan drawings, based on review
meeting
comments. One option or options could be eliminated prior to starting these revisions.
ii. Prepare Structure Selection Memo – LORIS will prepare a Structure Selection Report which
summarizes the findings, recommendations, and costs of the Alternative Analysis. Other
subconsultants will supplement the report respective to their disciplines.
e. Meetings with Primary Stakeholders
i. LORIS and BHA will meet with property and business owners within the immediate area who will
be most impacted by the design and construction. We anticipate two (2) small group meetings
with immediate property owners.
f. Public Meeting I
i. Preparation – LORIS, BHA and Lithos will prepare presentation graphic boards for a public
meeting. Displays will include illustrative color rendered site/ landscape plans, 3D Sketchup
Models and color rendered perspective illustrations.
ii. Meeting – LORIS, BHA, Lithos and Interwest will attend one (1) public meeting in Fort Collins.
g. City Boards and Commissions Updates (anticipated by City staff)
i. Loris, BHA, and Intrawest will provide assistance to city staff as needed for updates to Parks
and
Recreation Board, Transportation Board, Art in Public Places Board, Landmark Preservation
Commission, Planning and Zoning Board.
h. Option Development III
i. Update Alternative Analysis – Our design team will update the Alternative Analysis based on
review and public meeting comments.
ii. Update Structure Selection Report – LORIS will revise the Structure Selection Report per option
development revisions.
j. UPRR, PRPA and Utility Review II
i. Meeting – LORIS and Interwest will attend up to five
(5) utility meetings in Fort Collins. 360 Rail will provide UPRR coordination.
k. Preferred Alternative Selection
i. Alternative Selection – The City of Fort Collins will select a preferred alternative
ii. Final Structure Selection Report – LORIS’s team will prepare a final Structure Selection Report.
l. Meetings with Primary Stakeholders
i. LORIS and BHA will meet with property and business owners within the immediate area who will be
most impacted by the design and construction to review the preferred structure alternative. We
anticipate two (2) small group meetings with immediate property owners.
ii. Public Meeting II – LORIS, BHA, and Interwest will prepare presentation graphic boards to present the
preferred alternative at a public meeting. Displays will include illustrative color rendered site/landscape
plans, 3D Sketchup Models and color rendered perspective illustrations of the preferred structure
alternative and trail alignment.
DocuSign Envelope ID: 381C86A4-241C-4C70-8013-696547D69393
ID Task Name Duration Predecessors
1 Proposals Due 0 days
2 Consultant Selection 14 days 1
3 Notice to Proceed 30 days 2
4
5 1.0 Project Kick-off Phase 25 days
6 Kick-off Meeting 5 days 3
7 Mapping 10 days 6
8 Utility Meetings & Coord 20 days 6
9 Geotechnical 20 days 6
10 Environmental 20 days 6
11 Urban Design 20 days 6
12
13 2.0 Alternative Analysis and
Feasibility Study
150 days
14 Option Development I 40 days 11
15 City Review/Coordination 150 days 11
16 UPRR, PRPA and Utility Review I 10 days 14
17 Option Development II 20 days 14
18 Meetings with Primary Stakeholders 10 days 17
19 Public Meeting I 10 days 18
20 Boards & Commissions Updates 20 days 19
21 Option Development III 20 days 20
22 UPRR, PRPA and Utility Review II 20 days 20
23 Preferred Alternative Selection 10 days 22
24 Meetings with Primary Stakeholders 10 days 23
25 Public Meeting II 10 days 24
5/8 5/8
5/9 5/28
5/29 7/9
7/10 8/13
7/10 7/16
7/17 7/30
7/17 8/13
7/17 8/13
7/17 8/13
7/17 8/13
8/14 8/14 3/11
8/14 10/8
8/14 3/11
10/9 10/22
10/9 11/5
10/9 10/22
10/23 11/5
11/6 12/3
12/4 12/31
12/4 12/31
1/1 1/14
1/15 1/28
1/29 2/11
A M J J A S O N D J F M A
Half 1, 2018 Half 2, 2018 Half 1, 2019
Power Trail Grade Separated Crossing at Harmony Road
Loris and Associates Page 1 Fri 6/22/18
DocuSign Envelope ID: 381C86A4-241C-4C70-8013-696547D69393
TASK # TASK NAME TASK DETAIL Task ID
Dan PM -
Bridge
Scott --
Under-
pass
Trail PE Road PE
Structur-
al PE
Detailer Admin LORIS Subtot
LORIS
Expense
LORIS Total Interwest Lithos ERO Clanton BHA Apex & 360 SUBS Subtot
TEAM
Subtot
RATES Rate: 165 180 150 145 125 95 80
Utility &
Drainage
Geotech Environ Lighting Urban Traffic & RR
10-SUR 11-GEO 12-Env 24-HYD 24-HYD 24-HYD
1.0 Project Kick-off\
a. Kick-off Meeting
Meeting Prepare for Meeting 2-MTG 2 1 1 $ 660 $ 660 $ - $ 660
Attend Meeting 2-MTG 4 4 4 $ 1,980 $ 75 $ 2,055 $ - $ 2,055
Minutes of Meeting 2-MTG 0.5 0.5 2 $ 473 $ 473 $ - $ 473
Site Walkthrough 2-MTG 2 2 2 $ 990 $ 990 $ - $ 990
b. Mapping Same day as kick-off meeting
Mapping Convert FC survey to LORIS'
teams survey standards
3-PPR 2 4 $ 800 $ 800 $ - $ 800
Potholing Allowance -- 20 holes at $300
each plus traffic control (4@1450,
plus permits ($500), Primary
coordination by Interwest
3-PPR 4 $ 600 $ 12,300 $ 12,900 $ - $ 12,900
Survey -- allowance for King 3-PPR 4 $ 600 $ 15,000 $ 15,600 $ - $ 15,600
c. Utility Meetings and
Coordination
Obtain Existing Information 1-PMG 1 $ 150 $ 150 $ - $ 150
Meetings Inerwest will coordinate and
attend up to 15 utility meetings to
develop relocation requirements,
as necessary.
1-PMG 2 2 $ 630 $ 630 $ 11,570 $ 11,570 $ 12,200
Interwest will prepare meeting
notes for each utility.
1-PMG 1 1 $ 315 $ 315 $ - $ 315
d. Geotechnical
Engineering
Geotechnical Lithos borings and testing 1-PMG 2 $ 330 $ 330 $ 28,842 $ 28,842 $ 29,172
Recommendations report 1-PMG 1 0.5 0.5 $ 330 $ 330 $ - $ 330
e. Environmnetal
Field Work and Reports ERO Field investigations 1-PMG 2 $ 330 $ 330 $ 11,900 $ 11,900 $ 12,230
Findings reports 1-PMG 1 $ 165 $ 165 $ - $ 165
f. Urban design
Obtain Existing Information BHA will log existing landscape
items that would require
replacement or relocation for each
alternate
1-PMG 2 $ 330 $ 330 $ 3,021 $ 3,021 $ 3,351
TASK # TASK NAME TASK DETAIL Task ID
Dan PM -
Bridge
Scott --
Under-
pass
Trail PE Road PE
Structur-
al PE
Detailer Admin LORIS Subtot
LORIS
Expense
LORIS Total Interwest Lithos ERO Clanton BHA Apex & 360 SUBS Subtot
TEAM
Subtot
b. City
Review/Coordination
Meeting Prepare for Meeting 2-MTG 1 1 2 $ 645 $ 645 $ - $ 645
Attend Meetings (3) 2-MTG 12 4 12 $ 4,500 $ 225 $ 4,725 $ - $ 4,725
Minutes of Meeting 2-MTG 0.5 0.5 6 $ 1,073 $ 1,073 $ - $ 1,073
c. UPRR, PRPA & Utility
Review I
Meeting Prepare for Meeting 2-MTG 1 $ 150 $ 150 $ - $ 150
Attend Meeting 2-MTG 4 $ 600 $ 75 $ 675 $ - $ 675
Minutes of Meeting 2-MTG 1 $ 150 $ 150 $ - $ 150
d. Option Development II It is possible than an option or two
could drop out at this level;
however, we are not eliminating
any for the purpose of this fee.
Project Management 1-PMG 4 $ 660 $ 100 $ 760 $ - $ 760
Regular Design Meetings Two (2) 2-MTG 8 4 8 $ 3,240 $ 150 $ 3,390 $ - $ 3,390
Quality Control 7-QC 4 $ 660 $ 660 $ - $ 660
Cut-and-cover Underpass Plan and profile, impacts and
costs
24-HYD 1 4 16 $ 3,205 $ 3,205 $ - $ 3,205
Tunneled Underpass General layout with costs 25-ROA 1 2 8 $ 1,685 $ 1,685 $ - $ 1,685
Pre-engineered Truss
Overpass
General layout and costs 31-VEH 4 4 4 $ 1,540 $ 1,540 $ - $ 1,540
Custom Structure
Overpass
General layout, minimal design
and costs
21-DRA 8 24 8 $ 5,080 $ 5,080 $ - $ 5,080
Iconic Structure Overpass General layout, minimal design
and costs
21-DRA 16 40 16 $ 9,160 $ 9,160 $ - $ 9,160
Trail 21-DRA 1 2 24 $ 4,125 $ 4,125 $ - $ 4,125
Environmental 1-PMG 2 $ 300 $ 300 $ - $ 300
Traffic Apex ananysis of underpass
option during construction
1-PMG 1 1 2 $ 635 $ 635 $ 9,000 $ 9,000 $ 9,635
Cost Opinions 1-PMG 2 2 2 8 8 $ 3,150 $ 3,150 $ - $ 3,150
Alternative Comparison
Matrix
1-PMG 1 1 4 1 1 $ 1,215 $ 1,215 $ - $ 1,215
Structure Selection Report 1-PMG 4 1 16 1 4 $ 3,885 $ 3,885 $ - $ 3,885
e. Meetings with Primary
Stakeholders
Meeting Prepare for Meeting 2-MTG 2 $ 300 $ 300 $ - $ 300
TASK # TASK NAME TASK DETAIL Task ID
Dan PM -
Bridge
Scott --
Under-
pass
Trail PE Road PE
Structur-
al PE
Detailer Admin LORIS Subtot
LORIS
Expense
LORIS Total Interwest Lithos ERO Clanton BHA Apex & 360 SUBS Subtot
TEAM
Subtot
Alternative Comparison
Matrix
1-PMG 1 1 4 1 1 $ 1,215 $ 1,215 $ - $ 1,215
Structure Selection Report 1-PMG 4 12 4 $ 2,960 $ 2,960 $ - $ 2,960
i. UPRR, PRPA & Utility
Review II
Meeting Prepare for Meetings 2-MTG 2 $ 300 $ 300 $ - $ 300
Attend Meetings 2-MTG 8 $ 1,200 $ 75 $ 1,275 $ - $ 1,275
Minutes of Meetings 2-MTG 2 $ 300 $ 300 $ - $ 300
j. Preferred Alternative
Selection
Meeting 3-PPR 4 4 $ 1,260 $ 75 $ 1,335 $ - $ 1,335
Final Structure Selection
Report
3-PPR 4 8 2 $ 2,110 $ 2,110 $ - $ 2,110
k. Meetings with Primary
Stakeholders
Meeting Prepare for Meeting 2-MTG 2 $ 300 $ 300 $ - $ 300
Attend Meetings (2) 2-MTG 8 $ 1,200 $ 150 $ 1,350 $ - $ 1,350
Minutes of Meeting 2-MTG 2 $ 300 $ 300 $ - $ 300
l. Public Meeting II
Meeting Prepare for Meeting 2-MTG 2 1 4 2 4 8 $ 2,660 $ 2,660 $ - $ 2,660
Attend Meeting 2-MTG 6 6 $ 1,890 $ 75 $ 1,965 $ - $ 1,965
Meeting follow-up 2-MTG 2 $ 300 $ 300 $ - $ 300
ADDITIONAL
REIMBURSIBLE
EXPENSES
$ - $ -
$ 2,643
$ 2,643 $ 2,643
199 68 275 109 186 146 0 982
$ 32,835 $ 12,240 $ 41,250 $ 15,733 $ 23,188 $ 13,870 $ - $ 139,115 $ 29,100 $ 168,215 $ 19,110 $ 38,342 $ 11,900 $ - $ 46,696 $ 24,000 $ 140,048 $ 308,263
$ 139,115
$ 139,115
PHASE TOTALS
Project Kick-off 20.5 8.5 24 0.5 4.5 0 0 $ 9,148 $ 27,375 $ 36,523 $ 11,570 $ 28,842 $ 11,900 $ - $ 3,021 $ - $ 55,333 $ 91,856
Alternative Analysis 178.5 59.5 251 108 181 146 0 $ 129,968 $ 1,725 $ 131,693 $ 7,540 $ 9,500 $ - $ - $ 43,675 $ 24,000 $ 84,715 $ 216,408
FIR Design 0 0 0 0 0 0 0 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ -
ROW Phase 0 0 0 0 0 0 0 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ -
FOR Design 0 0 0 0 0 0 0 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ -
Advertisement & Construction 0 0 0 0 0 0 0 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ -
TOTAL HOURS/FEE 199 68 275 109 186 146 0 $ 139,115 $ 29,100 $ 168,215 $ 19,110 $ 38,342 $ 11,900 $ - $ 46,696 $ 24,000 $ 140,048 $ 308,263
Total Hours
Total Amount
DocuSign Envelope ID: 381C86A4-241C-4C70-8013-696547D69393
Attend Meetings (2) 2-MTG 8 $ 1,200 $ 150 $ 1,350 $ - $ 1,350
Minutes of Meeting 2-MTG 2 $ 300 $ 300 $ - $ 300
f. Public Meeting I
Meeting Prepare for Meeting 2-MTG 2 1 6 2 8 16 $ 4,220 $ 4,220 $ - $ 4,220
Attend Meeting 2-MTG 6 6 $ 1,890 $ 75 $ 1,965 $ - $ 1,965
Meeting follow-up 2-MTG 4 $ 600 $ 600 $ - $ 600
g. Updates to Boards
and Commisions
Meeting Prepare for Meetings 2-MTG 4 2 8 2 8 8 $ 4,270 $ 4,270 $ - $ 4,270
Attend Meeting NIC 2-MTG $ - $ 75 $ 75 $ - $ 75
h. Option Development III
General
Project Management 1-PMG 4 $ 660 $ 100 $ 760 $ - $ 760
Regular Design Meetings 2-MTG 8 4 8 $ 3,240 $ 150 $ 3,390 $ - $ 3,390
Quality Control 7-QC 4 $ 660 $ 660 $ - $ 660
Cut-and-cover Underpass 24-HYD 4 8 8 $ 2,640 $ 2,640 $ - $ 2,640
Tunneled Underpass Assume not progressed to this
level
25-ROA $ - $ - $ - $ -
Pre-engineered Truss
Overpass
Assume not progressed to this
level
31-VEH $ - $ - $ - $ -
Custom Structure
Overpass
21-DRA 2 12 8 $ 2,590 $ 2,590 $ - $ 2,590
Iconic Structure Overpass 21-DRA 4 24 8 $ 4,420 $ 4,420 $ - $ 4,420
Trail 21-DRA 12 $ 1,800 $ 1,800 $ - $ 1,800
Environmental 1-PMG 1 $ 150 $ 150 $ - $ 150
Cost Opinions 1-PMG 2 1 2 4 4 $ 1,890 $ 1,890 $ - $ 1,890
DocuSign Envelope ID: 381C86A4-241C-4C70-8013-696547D69393
BHA will provide a drawing that
summarizes their findngs.
1-PMG 1 0.5 0.5 0.5 0.5 $ 465 $ 465 $ - $ 465
2.0 Alternative Analysis
and Feasibility
Study
a. Option Development I High level alternative selection.
Underpass layout, utility impacts,
obtain photos and costs of various
bridge options.
Project Management 1-PMG 8 $ 1,320 $ 100 $ 1,420 $ - $ 1,420
Regular Design Meetings Coordination and review meetings
with FC Two (2)
2-MTG 8 4 8 $ 3,240 $ 150 $ 3,390 $ - $ 3,390
Quality Control 7-QC 4 $ 660 $ 660 $ - $ 660
Cut-and-cover Underpass Layout, potential utility impacts (5
meetings) and costs. Evaluate
primarily on west side of tracks,
but also evaluate east side.
24-HYD 3 12 32 24 $ 9,575 $ 9,575 $ 7,540 $ 7,540 $ 17,115
Tunneled Underpass Mostly by Lithos 25-ROA 2 2 2 $ 850 $ 850 $ 9,500 $ 9,500 $ 10,350
Pre-engineered Truss
Overpass
Layout and costs. Photos by
BHA.
31-VEH 4 1 4 8 8 $ 3,150 $ 3,150 $ - $ 3,150
Custom Structure
Overpass
Photos by BHA and costs by
LORIS
21-DRA 4 1 8 8 $ 2,570 $ 2,570 $ - $ 2,570
Iconic Structure Overpass Photos by BHA and and costs by
LORIS
21-DRA 8 2 8 4 $ 3,000 $ 3,000 $ - $ 3,000
Trail Trail connections north and south. 21-DRA 2 16 8 $ 3,490 $ 3,490 $ - $ 3,490
Environmental ERO. Loris coordination. 1-PMG 2 $ 330 $ 330 $ - $ 330
Urban Design BHA. LORIS coordination. 1-PMG 2 $ 330 $ 330 $ 41,032 $ 41,032 $ 41,362
Railroad 360 Rail assumes services forthis
work order. Actual services could
vary.
1-PMG 2 $ 330 $ 330 $ 15,000 $ 15,000 $ 15,330
Cost Opinions 1-PMG 4 4 8 16 8 8 $ 6,660 $ 6,660 $ - $ 6,660
Alternative Comparison
Matrix
1-PMG 2 1 8 1 1 $ 1,980 $ 1,980 $ - $ 1,980