CHANGE ORDER
NO. 1
PROJECT TITLE: DWRF Digester Bldg. MCC HVAC Impromt
CONTRACTOR: Carollo Engineering
WORK ORDER NUMBER:
PO NUMBER: 9174667
DESCRIPTION:
1. Reason for Change: Change in project engineering cost
2. Description of Change: Engineering time on site during construction was over-estimated and less
time was required than originally assumed. Attached is the PO
3. Change in Work Order Price: $8,232.60
4. Completion Date (if changed): NA
ORIGINAL WORK ORDER PRICE $ 26,046.00
TOTAL APPROVED CHANGE ORDER 00.00
TOTAL PENDING CHANGE ORDER 00.00
TOTAL THIS CHANGE ORDER $8,232.60
TOTAL % OF THIS CHANGE ORDER 31%
TOTAL C.O.% OF ORIGINAL WORK ORDER 31%
ADJUSTED WORK ORDER COST $ 17,813.14
CONTRACTOR: Carollo Engineering
By: Date:
Name: Title:
ACCEPTANCE: Date:
Eileen Dornfest, Civil Engineer III
REVIEWED: Date:
Pat Johnson, Senior Buyer
ACCEPTANCE: Date:
Matt Fater, Interim Civil Engineering Director
DocuSign Envelope ID: AC32D297-664D-4939-BABE-01A3E72EED18
July 12, 2018
July 16, 2018
Jason Garside Vice President
July 18, 2018
July 16, 2018