Loading...
HomeMy WebLinkAboutAddenda - RFP - 8134 VINE LEMAY BNSF IMPROVEMENTS PROJECT (2)ADDENDUM NO. 1 SPECIFICATIONS AND CONTRACT DOCUMENTS Description of RFP 8134: Vine / Lemay / BNSF Inprovements Project OPENING DATE: 3:00 PM (Our Clock) July 8, 2015 To all prospective bidders under the specifications and contract documents described above, the following changes/additions are hereby made and detailed in the following sections of this addendum: 1. The opening date listed on Rocky Mountain E-Purchasing was incorrect. The correct opening date is 3:00 PM (our clock) on July 8, 2015 as stated in the RFP document. 2. Attachments The following attachments were referenced in the RFP but were inadvertently not included in the RFP document. Those attachments are included in this addendum and referenced as follows: Exhibit 1 – East Vine / Lemay Intersection Realignment Project Development Report Exhibit 2 – 30% Design Plans for East Vine Drive Relocation (Suniga Drive) Exhibit 3 – Suniga / Lemay Multi-Modal and Freight Connectivity Project  2015 TIGER Grant Application Narrative  2015 TIGER Grant Appendix C – Benefit / Cost Analysis  2015 TIGER Grant Appendix D – Letters of Support Please contact John Stephen, CPPO, LEED AP, Senior Buyer at (970) 221-6777 with any questions regarding this addendum. RECEIPT OF THIS ADDENDUM MUST BE ACKNOWLEDGED BY A WRITTEN STATEMENT ENCLOSED WITH THE BID/QUOTE STATING THAT THIS ADDENDUM HAS BEEN RECEIVED. Financial Services Purchasing Division 215 N. Mason St. 2nd Floor PO Box 580 Fort Collins, CO 80522 970.221.6775 970.221.6707 fcgov.com/purchasing EAST VINE/LEMAY INTERSECTION REALIGNMENT PROJECT DEVELOPMENT REPORT PREPARED FOR PREPARED BY EXHIBIT 1 EAST VINE/LEMAY INTERSECTION REALIGNMENT PROJECT DEVELOPMENT REPORT SEPTEMBER 12, 2014 PREPARED FOR CITY OF FORT COLLINS 281 NORTH COLLEGE AVENUE FORT COLLINS, CO 80524 970-221-6376 PREPARED BY AECOM 717 17TH STREET, SUITE 2600 DENVER, CO 80202 EAST VINE/LEMAY INTERSECTION REALIGNMENT PROJECT DEVELOPMENT REPORT TABLE OF CONTENTS SECTION PAGE EXECUTIVE SUMMARY 1. PROJECT BACKGROUND 1 1.1 Site Location 1 1.2 Project Setting and Need 1 1.3 Funding for Transportation 2 2. LEMAY REALIGNMENT 3 2.1 Overview 3 2.2 Purpose and Need 3 2.3 Alternative Descriptions 6 2.4 Interim Improvements and Phasing 14 2.5 Transportation Performance Analysis 15 2.6 Environmental Analysis: Key Impact Issues 18 2.7 Cost Opinions 23 2.8 Risk Analysis 25 2.9 Alternative Comparison 27 3. PROJECT DEVELOPMENT PROCESS AND SCHEDULE 32 3.1 Project Development Process 32 3.2 Preliminary Design Process 32 3.3 Environmental Process 32 3.4 Final Design and Construction Process 35 4. PROJECT FUNDING STRATEGIES 36 4.1 Potential Funding Approach 36 4.2 Pros and Cons Associated with the Funding Approach Strategies 41 APPENDIX A. Construction Cost Opinion B. Lemay/Vine 2035 Traffic Analysis Memorandum C. Analysis of Vehicle Delay from Train Operations D. Cultural Resources in the Study Area E. CDOT Standard Form 128 F. Project Funding and Finance Analysis LIST OF TABLES TABLE PAGE Table 1 Level of Service Conditions under No Build and At Grade Alternative Conditions (2035 - without Consideration of Railroad Operations) 16 Table 2 System Performance at PM Peak Hour under Various Scenarios 17 Table 3 Build Alternative Total Project Cost Opinions 23 Table 4 Feasibility-Level Criteria: Selected Broad Considerations and Fatal-Flaws 29 Table 5 Concept-Level Criteria: Selected Considerations for Comparative Analysis 30 Table 6 Estimated Local Developer and Street Oversizing Funds for the At-Grade Alternative 38 Table 7 Estimated Local Developer and Street Oversizing Funds for the Overpass Alternative 40 Table 8 Potential TIGER Funding Strategy for the Remaining Overpass Alternative Costs 40 LIST OF FIGURES FIGURE PAGE Figure 1 Proposed Lemay Avenue Realignment 1 Figure 2 East Vine and Lemay (4-Lane Arterial Street) Roadway Cross Section 7 Figure 3 Realignment At-Grade Intersection Alternative – Conceptual Plan 9 Figure 4 Example Arterial At-Grade Crossing – W. Horsetooth Road 10 Figure 5 Realigned/Overpass Visualization Rendering 10 Figure 6 Realignment/Overpass Alternative – Conceptual Plan 11 Figure 7 Realigned/Underpass Example – Wadsworth Bypass Arvada, CO 12 Figure 8 Realignment/Underpass Alternative – Conceptual Plan 13 Figure 9 Key Environmental Considerations Map 19 Figure 10 Project Development Anticipated Expenditures, S-Curve 24 Figure 11 Annual Construction Expenditure Flow for the Overpass Alternative 39 EXECUTIVE SUMMARY Project Description The Lemay Avenue realignment and intersection improvements would construct a new arterial facility and intersection slightly to the east of the existing Lemay Avenue alignment. This realignment allows for a number of interim and ultimate solutions that include new at-grade intersections or overpass/underpass of the railroad and existing E. Vine Drive. The realignment relieves several issues that currently constrain the existing alignment and intersection, which allows for the major project improvements and benefits to be achieved. Project Improvements and Benefits The project will address the following primary needs: Safety: The project will improve safety and reduce risks for pedestrians, cyclists, vehicles and the railroad. The existing crossing intersection has averaged thirteen crashes per year between 2010 and 2012 and does not fully comply with new safety standards for crossings with vehicles, bicycles and pedestrians. Neighborhood Connectivity: The project will improve multi-modal and neighborhood connectivity by establishing safer and more connected pedestrian/cyclist options and by providing an appropriately scaled roadway network and access points that are less impacted by heavier arterial traffic. Traffic Congestion: The project will reduce traffic delays that significantly impacts mobility when trains are operating at the existing crossing. Previous Planning Efforts that Provide Basis for Project ü Plan Fort Collins (2011) ü City Plan (2011) ü City of Fort Collins Master Street Plan (2011) ü City of Fort Collins Capital Improvement Plan (2011) ü Mountain Vista Sub-Area Plan (2010) ü Northside Neighborhoods Plan (2005) ü I-25 Corridor Plan (2001) ü Larimer County Master Plan (1997) Project Planning The intersection improvements and realignment of Lemay Avenue at East Vine Drive is a vital capital improvement project resulting from a series of planning efforts that provide the basis for directing and guiding growth in the community. Project Alternatives Three alternatives have been identified through a scoping process with an initial overview of alternative characteristics and screening. Preliminary scoping includes constructability, costs, potential environmental impacts, and improving neighborhood connectivity. Preliminary Alternatives Scoping Summary Realigned Lemay - At Grade Realigned Lemay - Overpass Realigned Lemay - Underpass Primary Elements Creates Realigned Lemay and a segment of proposed New Vine to current Arterial Standards, relocating intersection away from BNSF Crossing. Removes existing at-grade crossing, constructing New Lemay crossing to current safety standards Removes existing at-grade crossing, constructing a New Lemay overpass bridge over BNSF and existing E. Vine. Removes existing at-grade crossing, constructing a New Lemay underpass with bridges for BNSF and existing E. Vine. Permitting and Approval Risks PUC approvals for new at- grade crossing uncertain. BNSF approvals required and will likely require relocation of switching yard. General PUC and BNSF approvals required. Removes at-grade crossing risk. General PUC and BNSF approvals required. Removes at-grade crossing risk, but may be disruptive to BNSF operations. Environmental Considerations General noise and construction impacts Noise and visual impacts to the historic neighborhoods High ground water table due Developer Local Street Portion , $1.45* City Street Oversizing Portion , $5.16 M** Additional Funding Required, $17.99 M Scenario Example: At-Grade Funding * Timing of funds/cash flow issue if project precedes development. ** Timing of funds/cash flow issue due to size of contribution required from this source. Funding The project could use a combination of local and federal funding sources: • Local: Sources include the potential future City sales tax for capital projects, developer street frontage obligations and street oversizing. • Federal: Sources include the Highway Safety Improvement Program (HSIP) or Surface Transportation Program (STP), TIGER Discretionary Grant Program, and/or EDA Public Works and Economic Adjustment Assistance Programs. Funding Scenario Example: The Realigned Lemay At-Grade Alternative Cost and Funding: • Cost between $24 to $25 million. • Funding approach could rely entirely on City funds as federal funds may be unreliable. • The project could advance prior to full funding by advancing project design and development while other financing options for construction could be explored, such as bonds backed by sales tax revenues or federal program applications. Project Development Next Steps The next step in the process is to begin a more thorough data collection, preliminary design and funding evaluations that will address the following key questions: • Is the added long-term cost/benefit of realignment and grade separation necessary to address anticipated 2035 congestion and delay, or could a realignment and at-grade intersection be sufficient as a near-term solution that could then transition at a later date? Will a new at-grade crossing be allowed by the PUC and BNSF, and would BNSF consider switching yard relocation? • Is the added cost of an underpass to address visual and noise impact issues appropriate when a lower cost overpass would result in similar traffic performance without the higher cost and risk concerns, such as drainage issues, caused by the underpass? • Does the currently unknown cost of relocation of the railroad switching yard and its ability to reduce railroad crossing/switching-related system congestion justify the expenditure? • Can the existing at-grade crossing of existing E. Vine and existing Lemay remain in a limited configuration for pedestrians/cyclists. 1 1. PROJECT BACKGROUND 1.1 Site Location The existing East Vine Drive and Lemay Avenue intersection is located one-mile north east of downtown Fort Collins. Figure 1 presents a map showing the Lemay Avenue realignment (green) and associated roadway network improvements. Chapter 2 provides Lemay realignment details. Figure 1 Proposed Lemay Avenue Realignment 1.2 Project Setting and Need The realignment of Lemay at its intersection with East Vine has emerged as a vital component of a series of Fort Collins’ planning processes and outcomes dating back to 1997, including: Plan Fort Collins (2011) City Plan (2011) City of Fort Collins Master Street Plan (2011) City of Fort Collins Capital Improvement Plan (2011) Mountain Vista Sub-Area Plan (2010) 30% Design for Realigned Vine Drive Northside Neighborhoods Plan (2005) I-25 Corridor Plan (2001) Larimer County Master Plan (1997) East Vine Drive is a two lane road running parallel to the BNSF railroad tracks and Lemay Avenue is a two lane road serving as a north-south arterial one mile east of College Avenue. The intersection is controlled by a signal with an outdated at-grade crossing immediately south of the intersection. Significant delays to traffic and disruption to local connectivity when trains operated during the morning and evening commutes. The delays are compounded when BNSF is using the switching yard located just 1. Grade Separation and Realignment of the Vine/Lemay Intersection 2. East Vine Drive Realignment from College to Lemay 3. East Vine Drive Realignment from Lemay to Timberline 2 east of Lemay Avenue where trains travel back and forth across the crossing for switching operations. Switching yard activities result in an average of 6 minutes of delay at the existing intersection. Without action/ improvements, delays will continue and the delay associated with the at-grade crossing will continue to rise. In 2035, traffic will operate at Level of Service (LOS) of F and train movements will cause traffic delays of up to 30 minutes at the intersection. The intersection has averaged thirteen crashes per year between 2010 and 2012 and does not fully comply with new safety standards for crossing with vehicles, bicycles and pedestrians. There are no sidewalks on East Vine. East Vine has little to no shoulder with no sidewalk. Lemay has dedicated bike lanes and a detached sidewalk south of the crossing, there is a narrow shoulder and no sidewalks to the north. Additional details about the project’s purpose and need are provided in Section 2.2. 1.3 Funding for Transportation Fort Collins has roadway construction standards and facility performance requirements that link additional vehicle trips generated from new development to completion of necessary roadway construction, including identification of funding commitments. This impact fee system requires private sector improvements including street oversizing requirements. The City’s funding process also includes traditional municipal tax base mechanisms supplemented by a dedicated local “Building on Basics” (BOB) ¼ cent sales tax. In order to appropriately allocate the City’s financial resources, Fort Collins prioritizes planning improvements and uses a well-established Asset Management system to evaluate transportation infrastructure conditions to efficiently plan and maximize maintenance investments. At this time, the proposed improvements are too costly for immediate or short-term funding by the City or State of Colorado. City of Fort Collins’ policies create four primary challenges: 1. Careful management and expenditure of available local funding over time 2. Prioritization of local funding expenditures to optimize value and benefits under existing and future scenarios 3. Application of appropriate funding burdens on the City and land developers 4. Development of compelling arguments necessary to obtain other sources of funding when development needs and community benefits are beyond the means of local funding sources, and when development benefits have regional or statewide values and benefits. Individual land development proposals, whether small, moderate, or large in scale, often face considerable road capacity development costs to comply with Fort Collins policies. In most instances, these costs are part of doing business in Fort Collins and necessary for new development to maintain the quality of life in Fort Collins and to pay their own way for added impacts to the street network. However, impact fee funds alone cannot always pay for the needed improvements and are not intended to be used to “fix” city-wide capacity and safety issues. The City has standard metrics used in determining both the Developer Local Street and City Street Oversizing Portion. The costs for the Lemay Avenue portion of these improvements are presented in Section 2.7 of this report and details are provided in Appendix A. 3 Additional local funding could be provided based on the outcome of future elections, but additional local/federal funding mixes would be needed to get the project built. This may include the use of bonding since the improvements will likely occur before some local sources would be available (i.e. development fees, or property tax revenues associated with a TIF). Details are provided in Chapter 4 Project Funding and Finance Analysis. 2. LEMAY REALIGNMENT 2.1 Overview The realignment of Lemay has been studied for many years as a way to address a variety of issues at the existing East Vine/Lemay intersection. Chapter 1 characterized the regional and local issues. Chapter 2 further defines the purpose and need for the realignment and describes potential alternatives, phasing considerations, environmental factors, costs and criteria for comparative evaluation of the alternatives. 2.2 Purpose and Need The purpose of the proposed action is to improve existing and future safety, provide additional roadway capacity, increase property accessibility, address degraded facility conditions and make improvements to comply with new design standards to facilitate sustainable smart-growth and economic development objectives at the local, regional and state-wide level. The individual needs for the proposed action are described and supported in the following discussions. These discussions clarify why the improvement is needed, and why these improvements are needed now. Safety At-grade roadway/railroad crossings create a host of safety issues addressed by a variety of engineering solutions. The at-grade East Vine/Lemay/Burlington Northern Santa Fe (BNSF) railroad intersection has been in place for many years and does not fully comply with new safety standards involving interaction with vehicles, bicycles or pedestrians. The physical layout of the intersection, surrounding constraints and proximity to the Railroad Crossing results in an outdated and substandard design that results in safety risks. The safety benefits resulting from the proposed action were evaluated using two methods: 1. Federal Railroad Administration (FRA) Web Accident Prediction System (WBAPS). 2. Methodology in the Highway Safety Manual, 1st Edition, described in section 4.4.2.13 “Excess Expected Average Crash Frequency with EB Adjustment.” The FRA Web Accident Prediction System estimates the number of train-motor vehicle crashes that can be expected with the current at-grade configuration. The Highway Safety Manual methodology estimates the number of expected multi-vehicle, single-vehicle, and pedestrian crashes at an intersection. The two results were summed to identify safety risks and to obtain benefit estimates. 4 The Federal Highway Administration has established crash cost estimates based on crash severity. Those values are published in the Highway Safety Manual (HSM) in 2001 dollars. Using the methodology described in the HSM to convert to current values the following cost values were used: Fatal Crash = $5,377,400 Injury Crash = $84,100 Property Damage Only Crash = $9,700 From 2010 through 2012 there was an average of thirteen crashes per year at the Lemay/Vine intersection. Capacity The existing roadway network at and near the existing East Vine/Lemay intersection is constrained by rail operations at grade crossings operations, and as a result is failing to meet current travel demands when trains cross Lemay and other north south routes in the area. The existing East Vine/Lemay intersection Level of Service (LOS) is rated B based on traffic volumes alone, but when freight rail operations occur, the intersection LOS falls to F. The Highway Capacity Manual defines LOS for signalized and unsignalized intersections in relation to overall travel time delay, or delay associated with a particular movement through an intersection, as follows: LOS Signalized Intersection Unsignalized Intersection A ≤10 seconds ≤10 seconds B 10-20 seconds 10-15 seconds C 20-35 seconds 15-25 seconds D 35-55 seconds 25-35 seconds E 55-80 seconds 35-50 seconds F ≥80 seconds ≥50 seconds LOS A through D is typically considered acceptable. LOS E and F are typically considered unacceptable. The duration of the train movements is based on train lengths, speeds and local operations (switching). The train speeds are often relatively slow because many trains are switching tracks to access the BNSF yard where a switching station is located. The switching site is located just east of the intersection. Switching movements involve slow train speeds, and often require trains to change direction more than once. The result is blocked north/south roadway travel for extended periods. The following problems occur when trains block the intersection: · Local travel behavior and patterns change becoming inefficient adversely impacting other roads and intersections. · North/south backups prevent neighborhood accessibility for extended periods. 5 · The street network is slow to recover. Long queues and delays linger for nearly a half hour after the train departs. This shows up as a near doubling of delay with a train compared to existing conditions on days when there isn’t a train. In the future, depending on the pace of the Mountain Vista Area development, congestion at the existing intersection will reach LOS F within 5 to 10 years based on traffic volumes alone Further discussion regarding the recurring effects of the freight rail operations on the existing intersection LOS is described in the Lemay/Vine 235 Traffic Analysis Memorandum (See Appendix B). Accessibility and Mobility The traditional grid network in the established areas of Fort Collins does not extend into the project area. The only north/south roadways connecting completely through this area are US 287 (College Avenue), Timberline Road, Lemay Avenue and I-25. US Highway 287 is located one mile to the west of Lemay. Timberline is located over one mile to the east of Lemay. I-25 is almost three miles east of Lemay Avenue. More specifically, the roadway network and the lack of capacity along Vine Drive and Lemay Avenue and through the Vine/Lemay/BNSF intersection create long-term gaps in the regional roadway network. Accessibility and mobility are important at the East Vine/Lemay intersection because the intersection provides an important freight rail operation into and out of Fort Collins and distinct opportunities for future bus transit operations that could connect this growing area to the City’s emerging rapid transit network. In addition, the intersection provides a primary link for local neighborhood linkage and regional motorists and dedicated routes for cyclists in all directions. BNSF, bus transit, vehicle, bicycle and pedestrian accessibility and mobility are currently limited by intersection safety, capacity and existing roadway configuration and conditions. An important BNSF railroad storage and switching yard is located approximately 2,000 feet east of the intersection. Facilities for pedestrians include formal cross walks at the intersection, but informal and substandard facilities to connect a recently constructed pedestrian pathway located on the west side of Lemay south of East Vine. No transit operations are in place in the area and no room is available for stops or stations without improvements. Two neighborhoods are located immediately adjacent to the Lemay/BNSF intersection. The primary access to both of these neighborhoods is from Lemay and Vine. Access to both neighborhoods is frequently constrained by traffic congestion. The desire to keep some level of neighborhood connectivity through the existing at-grade crossing is acknowledged as being important and should be considered as the project develops. Dedicated marked bicycle lanes exist along East Vine and Lemay, but terminate prior to the intersection in all directions. Roadway Maintenance, Design Standards and Sustainability Vine Drive and Lemay Avenue are in a poor state of repair characterized by deficient bridges, substandard conditions and accelerating deterioration caused by increasing truck and automobile volumes. Structures along Vine Drive are over 60 years old and the structures along Lemay Avenue are 6 over 45 years old. Two bridges along these roads are functionally obsolete due to inadequate width and are in a state of rapid deterioration. Neither roadway meets current City standards for their roadway designations or their existing and projected traffic volumes. Pavement and bridge management systems are used by the City to determine the optimal time for surface treatment repairs and reconstruction based on minimizing life cycle costs. The Proposed Action has been prioritized through an infrastructure assessment and would be managed by the City’s established system performance management tools. The infrastructure assessment characterizes investments that will reduce life cycle costs. The existing at grade Vine/Lemay intersection fails to meet current design or performance standards. Existing intersection design deficiencies include: · Level of Service F traffic operations · Lack of auxiliary lanes · Small turning radii requiring Jersey barriers for protection · Lack of adequate facilities for pedestrians · Inadequate drainage facilities · Discontinuous bicycle lanes for cyclists Fort Collins has a strong commitment to sustainable smart growth. The Proposed Action meets Fort Collins’ sustainability program goals by providing convenient, healthy and sustainable multimodal transportation options for residents, workers and economically disadvantaged populations (non-drivers, senior citizens and persons with disabilities), in a manner that coordinates transportation and land use planning decisions that have been developed with public participation. If no improvements are made in the near future, the existing sub-standard roadway network will continue to deteriorate and unmanageable congestion will increase. This delay and the related impacts will deter private sector investment and the expansion of existing economic enterprises and activity under both short-term and long-term scenarios. These conditions will make it difficult for the City to attract new enterprises, and may cause some enterprises to relocate entirely, fueling a cycle of economic downturn. 2.3 Alternative Descriptions Five Proposed Action Alternatives are presented in the following discussions. a. No Action Alternative The No Action, or No Build, Alternative would maintain existing conditions at the East Vine/Lemay intersection. Other planned and funded improvements in the roadway network would be completed, but no changes to the intersection would be made. The No Action Alternative would not achieve the project’s purpose or address any of the identified needs. The No Action Alternative is often used as a baseline condition for the other alternatives through the forecast year of 2035. The Project Development Report simply identifies this possibility, but does not analyze this alternative. 7 b. At-Grade Crossing Alternatives Existing Intersection Location Upgrades The Existing Intersection Location Alternative involves making a broad range of improvements at the existing intersection of East Vine and Lemay. The primary improvements would involve · Widening East Vine to the north to provide for two lanes, bike lanes and sidewalks in both directions. The minimum improved cross section would be 115 feet wide (four 12’ lanes, two 8’ bike lanes and two 6’ sidewalks with 10’ landscape buffer and a 19’ center median) per the Larimer County Urban Street Standards. · Widening Lemay to the east, west or east and west to provide for two lanes, bike lanes and sidewalks in both directions. The minimum improved cross section would be the same as Vine. · The intersection would be increased in size to provide four 12’ right turn lanes and four 12’ left turn lanes that integrate into the median. · Railroad crossing safety requirements set by the Colorado Public Utility Commission (PUC) would include safety gates across all lanes of Lemay on the north and south sides of Lemay and related improvements for cyclists and pedestrians. The East Vine and Lemay (4-Lane Arterial Street) roadway cross section are the same (See Figure 2). Figure 2 East Vine and Lemay (4-Lane Arterial Street) Roadway Cross Section The footprint of these improvements creates substantial impacts primarily due to the following site development constraints: · The proximity of private property and residences on the west side of Lemay north of East Vine and the proximity of private property and residences on the east of Lemay south of East Vine requires unavoidable Right of Way (ROW) acquisition and residential displacement in one or both of the locations. If the residences south of East Vine are protected, then the power lines 8 on the west side of Lemay south of East Vine and the landscape area with the path would be displaced. If the residences to the north of East Vine are protected, virtually all of the large trees and natural areas associated with Dry Creek (riparian and wetlands habitat) would be displaced. A skewed intersection to avoid residential displacement is not feasible given the presence and proximity of the railroad tracks. · The proximity of private property and residences on the north side of East Vine and the fixed location of the railroad and its associated safety buffer on the south side of East Vine requires displacement of the residences on the north side of East Vine. · If the required intersection improvements were made, traffic queues would block access points to the northern or southern neighborhood under normal traffic signal operations. The frequency and magnitude of this unavoidable effect would be increased when trains are present. Based on these substantial and unavoidable impacts, the Existing Intersection Location was not advanced for further consideration. Realigned At-Grade Intersection The Realigned At-Grade Intersection Alternative is presented in Figure 3 on the following page with an example of an existing Arterial At-Grade Crossing shown in Figure 4. In summary, this alternative: · Reroutes Lemay east around Andersonville, ties back in to old Lemay south of Conifer Street upgrades Lemay to 4-Lane Arterial per Master Plan and downgrading Old Vine and Old Lemay to Local Streets. The final disposition on the ultimate configuration of the existing crossing is not considered in this analysis and will be determined at a later stage. This applies to all of the build alternatives. · Creates the new Vine Road from Old to Lemay through the realigned Lemay to a connector road south the Old Vine to a 4-lane Arterial Standard (per Transportation Master Plan). · Closure of Old Vine east of Old Lemay to east of Dry Creek Crossing · Installs new signalized intersection at New Vine and Lemay intersection. · Creates collector access road from Old Vine Road to New Vine Road east of Dry Creek Crossing. · Constructs access to Lemay realignment from Old Lemay and Buckingham Street. · Constructs access from Alta Vista to New Vine Street at Old Lemay. · Bike lanes and sidewalks will be installed on Both Vine Street and Lemay Avenue with sidewalks on the collector access road. The existing Old Vine road can be utilized as a trail access on either side of the crossing. · Creates new at-grade crossing to current PUC Standards without having an intersection or pedestrian crossing of Lemay; however, a lack of PUC approval would prove to be fatal for this alternative · Constructs a new box culvert for New Lemay at Dry Creek Old Lemay Ave Conifer St Main St Buckingham St E Lincoln Ave Alta Vista Andersonville/ San Cristo DRY CREEK RAILROAD CROSSING PROPOSED DRY CREEK BOX CULVERT PROPOSED AT-GRADE RAILROAD YARD SWITCH New Lemay Ave New Vine Dr VINE BYPASS EXISTING AT-GRADE CROSSING PROPOSED SIGNALIZED INTERSECTION *SEE NOTE 1 POSSIBLE PEDESTRIAN/ BIKE CROSSING 10th St 9th St 11th St Old Vine Dr Projection: Data Sources: NAD 1983 UTM Zone 13 ESRI, City of Ft. Collins, AECOM, US Census REALIGNMENTALTERNATIVE REALIGNMENT AT GRADE INTERSECTION ALTERNATIVE I Date Modified: Image Date: July 2, 2014 April 2011 717 17th Street Suite 2600 Denver, CO 80202 PROPOSEDALIGNMENT PROPOSED ALIGNMENT MAPGRADE EXTENT AT-GRADEAT- Fort Collins Windsor Loveland ¦¨§25 «¬14 ¤£287 «¬14 0 200 400 Feet Legend At-Grade Alignment Proposed Sidewalk Limits of Temporary Improvements 10 Figure 4 Example Arterial At-Grade Crossing – W. Horsetooth Road c. Grade Separated Alternatives Realignment/Overpass The Realigned/Overpass Alternative is presented in Figure 6, on the following page, with a contextual visualization shown in Figure 5 below. In summary, this alternative: · Reroutes Lemay east around Andersonville, ties back in to old Lemay south of Conifer Street upgrading Lemay to 4-Lane Arterial per Master Plan and downgrading Old Vine and Old Lemay to Local Streets. · Creates new Vine Road from Old Lemay to realigned Lemay, upgrading New Vine to 4-Lane Arterial per Transportation Master Plan. · Installs a new signalized intersection at New Vine and Lemay intersection. · Constructs access to Lemay realignment from Old Lemay and Buckingham Street. · Constructs access from Alta Vista to New Vine Street at Old Lemay. · Creates an overpass structure and fill walls that carry Lemay over the BNSF Tracks and Old Vine Road. · Bike Lanes and sidewalks will be installed on Both Vine Street and Lemay Avenue. · Constructs a new box culvert for New Lemay at Dry Creek. Figure 5 Realigned/Overpass Visualization Rendering ( ( ((((((( ( ( ((((((( ( ( Old Lemay Ave Conifer St Main St Buckingham St E Lincoln Ave Alta Vista Andersonville/ San Cristo EXISTING AT-GRADE CROSSING AIRPORT RUNWAY DRY CREEK PROPOSED OVERPASS PROPOSED DRY CREEK BOX CULVERT New Lemay Ave New Vine Dr PROPOSED FILL WALLS PROPOSED SIGNALIZED INTERSECTION POTENTIAL FOR OLD VINE DR TO REMAIN OPEN (TEMPORARY CONDITION) *SEE NOTE 1 *SEE NOTE 2 10th St 9th St 11th St Old Vine Dr Projection: Data Sources: NAD 1983 UTM Zone 13 ESRI, City of Ft. Collins, AECOM, US Census REALIGNMENTALTERNATIVE REALIGNMENT OVERPASS INTERSECTION ALTERNATIVE I Date Modified: Image Date: July 2, 2014 April 2011 717 17th Street Suite 2600 Denver, CO 80202 PROPOSEDALIGNMENT PROPOSED ALIGNMENT MAP EXTENT OVERPASS Fort Collins Windsor Loveland ¦¨§25 «¬14 12 Realignment/Underpass The Realigned/Underpass Alternative is presented in Figure 8 on the following page with an example underpass project shown in Figure 7 below. In summary, this alternative: · Reroutes Lemay east around Andersonville, ties back in to old Lemay south of Conifer Street upgrading Lemay to 4-Lane Arterial per Master Plan and downgrading Old Vine and Old Lemay to Local Streets. · Creates new Vine Road from Old Lemay to the realigned Lemay, upgrading New Vine to 4-Lane Arterial per Transportation Master Plan. · Install new signalized intersection at New Vine and Lemay intersection. · Construct access to Lemay realignment from Old Lemay and Buckingham Street · Construct access from Alta Vista to New Vine Street at Old Lemay. · Bike Lanes and sidewalks will be installed on Both Vine Street and Lemay Avenue with sidewalks. · Construct water-tight walls on either side of Lemay due to the high groundwater table. The underpass cannot gravity drain, so a pump station would also be needed. · Construction of a siphon to convey the dry creek flows under the Lemay underpass. · Construct a BNSF bridge and Old Vine bridge over relocated Lemay. Figure 7 Realigned/Underpass Example – Wadsworth Bypass Arvada, CO ( ( ( ( ((((((( ( ( (( ((( ( ( (((((((( ( ( ( Old Lemay Ave Conifer St Main St Buckingham St E Lincoln Ave Alta Vista Andersonville/ San Cristo PROPOSED SIGNALIZED INTERSECTION EXISTING AT-GRADE CROSSING DRY CREEK PROPOSED RAILROAD PROPOSED SIPHON FOR DRY CREEK New Lemay Ave New Vine Dr PROPOSED CUT WALLS POTENTIAL OLD VINE BRIDGE (TEMPORARY CONDITION) *SEE NOTE 1 *SEE NOTE 2 10th St 9th St 11th St Old Vine Dr Projection: Data Sources: NAD 1983 UTM Zone 13 ESRI, City of Ft. Collins, AECOM, US Census REALIGNMENTALTERNATIVE REALIGNMENT UNDERPASS INTERSECTION ALTERNATIVE I Date Modified: Image Date: July 1, 2014 April 2011 717 17th Street Suite 2600 Denver, CO 80202 PROPOSEDALIGNMENT PROPOSED ALIGNMENT 14 2.4 Interim Improvements and Phasing The following discussion addresses how the Build Alternatives could be constructed in phases. Each discussion describes feasible interim improvement sequences and characterizes the basic benefits of phased implementation. Each Build Alternative could benefit from reduced freight rail operations or reduced delay from slow moving trains where the speeds are limited by the nearby location and operations of the BNSF railroad switching yard. Alternatives that would entirely relocate the Rail Alignment are not considered feasible and/or would be well beyond the scope of this analysis. However, alternatives that would reduce the effects of the train crossings by reducing travel delays and safety concerns for motorists, cyclists and pedestrians may be feasible. The primary possibility would be to work with BNSF to relocate the switching yard to a location beyond the Mountain Vista subarea plan boundaries. This phasing option is discussed first. Switching Yard Relocation: Reduced Delay from Slow Moving Trains Relocation of the BNSF switching yard to another location well away from the Vine/Lemay intersection would allow trains to pass through the area without speed reductions associated with switching yard operations. This change would substantially reduce traffic delays along Lemay north and south of East Vine. The public cost to relocate the switching station relocation would be substantial and could cost from between $10 million to $15 million dollars depending on the availability of land and yard development costs. Realigned At-Grade Intersection The Realigned At-Grade Intersection in itself could be an interim phase prior to Grade Separation. The construction activities for the Realigned At-Grade Intersection would require specific coordination activities with the railroad operations. The coordination activities primarily involve limiting impacts to railroad operations and construction of the at-grade crossing near the railroad tracks. Installation of track panels will be accomplished during limited windows, allowing train operations to continue. A shoe-fly is not likely a feasible or needed approach as the switch to the yard is immediately east of the crossing. Phasing and constructability is feasible for the at-grade intersection. Realigned/Overpass The Realigned/Overpass design could be accomplished in phases that involve construction of the Realigned At-Grade Intersection with our without relocation of the railroad switching station. These interim improvements could defer construction of the overpass. When this alternative is constructed, the work will occur in phases to address site constraints. The constraints primarily involve railroad operations and construction of the overpass. Construction of the sub structure and piers will be out of BNSF ROW, but placing of the girders will need to be coordinated and conducted to limit impacts to railroad operations. Full closure of the line is not expected. Phasing and constructability is feasible for the Realigned/Overpass. 15 Realigned/Underpass The Realigned/Underpass design could be accomplished in phases that involve construction of the Realigned At-Grade Intersection with our without relocation of the railroad switching station. These interim improvements could defer construction of the underpass. When this alternative is constructed, the phasing of the underpass bridges will present substantial challenges. Construction of the roadway bridge will require full closure of Old Vine. Construction of the BNSF bridge may be cost prohibitive as the line will need to stay in operation. A shoe-fly will require nearly 1500 feet of length on either side of the crossing. This would shut down the existing at-grade crossing of Lemay and impact use of the storage yard. Additionally the shoe fly would need to be 25 feet from the mainline and there is not enough room without impacting Old Vine or the residents of Andersonville. Alternative approaches to build the bridge in-situ are costly and time intensive given the high water table. Phasing and constructability could be a fatal flaw for the Realigned/Underpass. 2.5 Transportation Performance Analysis Safety The Realigned at-Grade Intersection alternative would provide better at grade pedestrian and bicycle crossings at the new intersection. The new intersection would improve vehicle safety by meeting railroad/road intersection design requirements. By separating the Vine/Lemay intersection from the railroad crossing, the effects of overlapping conflicts and complexity that exists at the existing intersection and railroad crossing would be significantly reduced/eliminated. Maintaining an existing at- grade crossing in any configuration, regardless of mode, will still introduce conflicts that may not be deemed acceptable by regulatory agencies or the railroad. The Realigned/Overpass Alternative would provide a safer grade separated route for pedestrians and cyclists crossing the railroad. The Realigned/Overpass Alternative is estimated to reduce the number of crashes by 52 percent on an annual basis resulting in an overall safety savings of $174,572 per year or 4.35 million 2013 present value dollars. The Realigned/Underpass Alternative would have the same safety benefits as the Realigned/Overpass Alternative, but would add the potential flood risk to access and safety if measures to pump water from the low point of the underpass were inoperable or ineffective during a flood event. Capacity As described in the Lemay/Vine 2035 Traffic Analysis Memorandum dated March 4, 2014 (Appendix B) and summarized in Table 1, the capacity benefits of the At Grade Alternative, without consideration of railroad operations, is substantial. 16 Table 1 Level of Service Conditions under No Build and At Grade Alternative Conditions (2035 - without Consideration of Railroad Operations) PRIMARY INTERSECTION MOVEMENT 2035 NO BUILD ALTERNATIVE 2035 AT GRADE BUILD ALTERNATIVE Northbound F A Southbound F A Eastbound F D Westbound D D OVERALL F B Note: · The year when LOS E is reached is dependent on when development occurs. With committed (approved but not built) developments, this threshold may be reached within 5 to 10 years. The benefits of introducing the overpass and underpass alternatives are not as easily measured by the same intersection level-of-service metrics. Therefore, a brief analysis was conducted to measure the system effects that are caused by train crossing movements. Two train crossing scenarios were considered as follows: Scenario 1-Thru Train Movement: This represents delays associated with a train crossing without using the switching yard resulting in a 3-minute train crossing time. This time is based on observations at other train crossing locations in the City including the Drake railroad crossing. Scenario 2- Switching Train Movements: This represents delays associated with a train crossing that uses the switching yard resulting in a 6-minute train crossing time. This time was observed at the existing Vine/Lemay intersection. Table 2 illustrates changes in system total delay, the number of vehicle trips disrupted and the system delay involved per vehicle using these scenarios. For additional details, refer to Appendix C. 17 Table 2 System Performance at PM Peak Hour under Various Scenarios Existing Conditions No Trains Existing Conditions Switching Train Movement (Scenario 2) 2035 Conditions At Grade Alternative No Trains 2035 Conditions At Grade Alternative Thru Train Movement (Scenario 1) 2035 Conditions At Grade Alternative Switching Train Movement (Scenario 2) Total Delay (Hours) 84.9 153.2 200.4 203.4 233.3 Vehicle- Trips 6,560 6,489 9,539 9,541 9,537 Seconds Per Vehicle Trip 46.6 85.0 75.6 76.7 88.1 Notes: · Train blockage times were based on recent data from traffic signal preemption logs. · 55 records were reviewed presenting an average duration train blockage of 6.1 minutes. This duration was used to represent the average time of a blockage associated with switching station impacts. · 39 records were reviewed for locations away from the switching station. These records presented an average train blockage of 3.2 minutes. This duration was used to represent average time of blockage associated with crossings away from the switching station. · Results are based on 30 runs of each scenario using the CORSIM model · Roadway network impacts elsewhere were not identified. · Existing conditions include the intersections of Lemay/Mulberry, Lemay/Magnolia, Lemay/Lincoln and Lemay/Vine (including RR delay). 2035 scenarios include the same intersections plus the delay at the railroad crossing which is no longer adjacent to the Lemay/Vine intersection. · At Grade Alternative effects from the train are reduced as a result of added storage capacity i.e. 4-lanes on Lemay rather than just two lanes at the tracks and at adjacent intersections. · A total delay cost from the trains would require converting the data from the p.m. peak hour to a daily estimate. In summary: · The new Vine/Lemay at-grade intersection that would be constructed north of the railroad crossing provides adequate capacity in the year 2035 and beyond, however the effects of train crossing at old Vine Avenue would remain a concern. · The existing street network system is slow to recover from a train crossing event where the train 18 Accessibility and Mobility The benefits of moving the intersection to the east with the Realigned At-Grade Intersection Alternative would shift queues to locations that would eliminate neighborhood accessibility and mobility issues The Realigned/Overpass and Realigned/Underpass Alternatives: · Substantially enhance system interconnectivity and substantially reduce road and railroad delay. · Improve access and mobility for all travel modes, local residents and motorists providing long- term, efficient access and mobility connecting Downtown Fort Collins, other community commercial districts, employment centers and other community resources while removing a constraint to future transit in the planning area. · Create local streets and pedestrian conditions near the access points to the two nearby neighborhoods by relocating two major arterials providing the opportunity to maintain the local connectivity. Grade separation would improve congestion and provide better mobility for cyclists. Roadway Maintenance and Design Standards All of the Build alternatives would be designed and constructed to meet applicable roadway maintenance and design standards. The Build Alternatives would replace existing pavements with 30- year design life pavement. The inadequate bridges would be replaced with structures with a design life of 75 years. The new infrastructure will allow safe travel for automobiles, trucks, buses, cyclists and pedestrians while meeting estimated traffic demands through 2035. 2.6 Environmental Analysis: Key Impact Issues The study area presents various environmental issues for consideration in relation to the three Build Alternatives. The following discussion characterizes these issues and potential effects. Figure 9 presents a map of the key environmental considerations. ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! N Lemay Ave Conifer St Main St Buckingham St E Lincoln Ave Alta Vista Andersonville/ San Cristo CULTURAL SITE 5LR10638 PARK ROMERO HOUSE & PARK (MUSEO DE LAS COLONIAS) AIRPORT RUNWAY DRY CREEK CITY OF GREELEY BURIED PIPELINE 10th St 9th St 11th St E Vine Dr BIKE LANE ENDS Projection: Data Sources: NAD 1983 UTM Zone 13 ESRI, City of Ft. Collins, AECOM, US Census, USFWS, NRHP, FEMA LEMAYREALIGNMENT LEMAY AVENUE REALIGNMENT I Date Modified: Image Date: May 8, 2014 April 2011 717 17th Street Suite 2600 Denver, CO 80202 EENNVVIIRROONNMMEENNTTAALL 20 Private Property Acquisition for Public Right of Way, Land Use Compatibility, Environmental Justice The study area is composed of private property and City owned right of way for the local public street network. Agricultural, residential, and industrial land uses are present the study area. A church is located along Lemay at San Cristo Street. Residences include single family homes and some mobile homes. The two neighborhoods in the study area are occupied primarily by Hispanic people and people with lower than average household incomes relative to other neighborhoods within the City of Fort Collins. The percentage of Hispanics in these neighborhoods exceeds 50 percent. The existing right of way with along East Vine and Lemay (9th Street and Lindenmeier Road) is approximately 60 feet and 70 feet, respectively, in the vicinity of the East Vine/Lemay intersection. Additional right of way would be needed to widen or realign either road. Realigning East Vine and Lemay would require acquisition of active farmland. A formal analysis of the loss of agricultural land would be needed. The overpass could present the potential for privacy effects by creating views of gardens and residential windows from the elevated roadway. Aviation clear zone issues should be considered in relation to the private airport located southeast of the Andersonville/San Cristo neighborhood. Small airplanes and helicopters use or have used this airfield. Airplane takeoffs and/or landings would occur over the Lemay realignment. The height of the anticipated overpass and related lighting fixtures should be considered if potential aviation issues arise. Pedestrian and Bicycle Paths and Lanes A landscaped pedestrian path is located along the west side of Lemay south of East Vine. This path was created with development of an industrial property located west of San Cristo Street. Signed bicycle lanes are provided in all four directions from the East Vine/Lemay intersection. However, lane markings providing adequate room for cyclists end near the intersection. Widening of East Vine and Lemay along their existing alignments would require a future cross section of each roadway that provides for striped bicycle lanes. Parks and Recreation Areas Two parks are present in the study area. Alta Vista Park is centrally located within the Alta Vista neighborhood. Dry Creek flows though this park. Romero Park is centrally located in the Andersonville/San Cristo neighborhood near the Romero/10th Street intersection. Direct effects on these parks are not anticipated. Air Pollutant Emissions, Dust and Odor Existing motor vehicle emissions along East Vine and Lemay likely do not and probably would not in the future create pollutant concentrations in excess of the one-hour and eight-hour limits for carbon monoxide. Construction period particulate matter (windblown dust) and construction equipment and vehicle exhaust emissions and odors could create nuisances at residences located within close proximity to 21 earthmoving, paving and other construction operations. These effects would be more pronounced for construction along East Vine and Lemay, but would occur with the Lemay realignment despite larger distances between the sources and receptors. Noise Noise levels at existing residential receptors at the existing intersection are relatively high due to motor vehicle volumes and railroad operations. Increasing vehicle volumes and speeds at peak hour in the future will increase noise levels. Construction and post-construction activity would create higher noise levels at existing residential receptors along East Vine and Lemay. Based on future traffic volumes and vehicle speeds approaching and departing from the controlled intersection, the overall noise levels may approach applicable standards and reach levels that require mitigation analysis at immediately adjacent residences. Mitigation such as noise walls may be ineffective due to frequent breaks in the walls allowing for private property access. Noise from the realignment options for Lemay would be similar during the construction period. Long- term motor vehicle noise at residences from the underpass design would less than those associated with the at-grade and overpass option. A noise analysis will be needed. Visual Quality/Aesthetics Visual quality and aesthetics is an important issue for the alternatives. A wider cross section along East Vine and Lemay would further urbanize the rural setting of the two existing neighborhoods by adding more pavement, reducing setbacks, and by displacing native trees and natural landscapes. The underpass and overpass would also urbanize the setting. The overpass would add a new and substantial visual element to the landscape. The underpass would be less visible from nearby vantage points. Water Resources and Wetlands Dry Creek, a small surface water channel, is located in the study area. This channel provides habitat values for invasive Russian olive trees and other plant species. A small portion of this channel provides riparian habitat and may include wetlands and/or waters of the U.S. that are regulated by the U.S. Army Corps of Engineers under Section 404 of the Clean Water Act. Shallow groundwater is likely present in the study area, but the details within the study area are not fully defined. Improvements to East Vine would not impact water resources, but widening of Lemay north of East Vine would impact the portion of the existing drainage channel associated with riparian habitat and possibly wetlands. The overpass would likely disrupt the portion of the channel that does not provide much habitat value. 22 The underpass would likely encounter shallow groundwater and would require special facilities to address drainage and flooding standards. Biological Resources Most of the study area is currently developed. Agricultural, residential and industrial activities and facilities limit habitat values. Small undeveloped areas, fallow agricultural land and large trees provide some habitat value. The presence and absence of state and federally protected species and critical habitat values have not been checked, but substantial roadway improvement limitations of this type are not anticipated. However, Prairie dogs have established themselves in the open land on the west side of Lemay south of East Vine. Chapter 6 of the City of Fort Collins Natural Areas Wildlife Management Guidelines provides prairie dog management guidelines. Widening of Lemay south of East Vine would have an incidental displacement effect on the existing colony in this location. Formal procedures outlined in the prairie dog management guidelines would be implemented to address this effect. The other alternatives are not expected to impact prairie dogs. All prairie dog findings would need to be checked prior to actual construction. Migratory birds are protected under the Migratory Bird Treaty Act. Surveys would be needed prior to construction to protect migratory birds, especially in potential nesting areas. Geology and Soils The geology and soil conditions within the study area do not present substantial design or construction constraints. Typical geotechnical analysis and engineering design requirements for the overpass and underpass designs would be expected to resolve any limitations presented by existing geology and soil conditions. Cultural Resources The Andersonville/San Cristo and Alta Vista neighborhoods and individual properties within them have historical significance relative to City of Fort Collins and National Register of Historic Places criteria. Although neither neighborhood is a designated historic district, numerous properties within them contribute toward that status, and two properties are eligible for listing in the National Register of Historic Places. 5LR10638 741 Lindenmeier Road 5LR10122 425 Tenth Street, Romero House, Museo del las Tres Colonias See Figure 9, Refer to Appendix D for additional information. No direct effects on either of the two properties eligible for listing would be expected. Fewer and less involved indirect effects from the realignment of Lemay would be expected due to the buffer distance between the new alignment and the neighborhoods. Additional consultation and coordination with the State Historic Preservation Officer (SHPO) will be needed. 23 Hazardous Materials A Phase I Environmental Site Assessment has not been prepared. Based on basic site reconnaissance, the potential for hazardous materials to be present in soils and groundwater in the study area exists, but the probability of substantial issues that constrain the design or construction of alternatives due to health and safety risks or remediation costs is low. Septic tank leach field issues may be present where excavation is needed near residences. Public Utilities and Services A network of public utilities is present in the study area See Figure 9). High voltage overhead power lines are present along a portion of Lemay south of East Vine. Lower voltage overhead lines service both neighborhoods. Water lines are present within the rights of way for East Vine and Lemay to serve both neighborhoods. A pipeline alignment constructed about 2009 is present in the study area. The alignment is shown in the base aerial used for Figure 9. 2.7 Cost Opinions Probable cost opinions were developed for the alternatives and are shown in Appendix A. The total project costs include all of the construction costs, including mobilization and force accounts, Right-of- way acquisition, Project development, formalizing downgraded segments of Vine and Lemay to local Streets, and construction management and inspection fees. Table 3 identifies the overall costs and the primary items that determine the project costs. Table 3 Build Alternative Total Project Cost Opinions Relocated Build Alternative Full Development Costs (2014 Dollars) Primary Drivers of Cost At-Grade $24 to $25 Million* · Likely Relocation of BNSF Yard $10M ** · Roadway Improvements · Dry Creek Box Culvert · Railroad Crossing Equipment · Uncertainty in PUC process Overpass $27 to $28 Million · Roadway Improvements · Dry Creek Box Culvert · Approach Fill and Walls · Bridge over BNSF and Old Vine Underpass $41 to $42 Million · Roadway Improvement · Dry Creek Siphon Structure · Water-tight Cut Walls for Underpass · Railroad Bridge Construction on Active Line · Old Vine Bridge · Pump Station for Underpass Drainage *(Approximately $1.6 Million would involve temporary construction –to be removed if a grade separation was constructed as a later phase) ** Costs are planning level value, additional detail analysis is needed Right-of-Way Acquisition Costs 24 Right of Way acquisition costs were based on recent property transfers in the project vicinity. The estimate for this project area included consideration of a variety of factors. Key issues for cost estimating included existing development dedications, likelihood of future development along the new alignments and current condition of the property. Project Development Costs Project development costs were estimated at 12.5% of the estimate construction cost. These costs include additional early project planning, environmental processes and permits, and preliminary and final design Project Expenditures over Time The project expenditures would occur in three phases over what would likely be a five year period with planning and right of way acquisition occurring in the first year, final design in the second year, and two to three years of construction beginning in the third year. The graph presented in Figure 10 illustrates anticipated expenditures for the overpass alternative as an example for the five year period. This assumes a traditional design, bid, build delivery method and assuming no fiscal escalation. Alternative delivery methods, such as design-build, are not being considered at this time. Figure 10 Project Development Anticipated Expenditures, S-Curve 25 2.8 Risk Analysis The Proposed Action presents a variety of design, construction and regulatory risks. The follow discussion clarifies those risks at this point in the project development process. Design and Construction Risks Design risks include the possibility that early, conceptual layouts have flaws that necessitate costly or time consuming resolution efforts. One example of a design risk that may be problematic for the underpass alternative is the need for stormwater management under normal conditions and flood conditions. Normal conditions may necessitate costly equipment to keep the underpass dry, passable and safe, especially in winter. Flood conditions, likely to drive design considerations, may generate water conveyance and disposal problems that add to project construction and long-term operation and maintenance costs. Construction risks include labor and material rate increases tied to market demand as the national and regional economies recovery, placing higher demands on both. This could escalate project budget estimates and result in project completion delays. Additional risks during construction could also involve encountering site issues such as high groundwater. This risk would be greatest for the underpass alternative. Standard measures can be applied to address the anticipated design and construction risks. Public Utility Commission Risks The Colorado Department of Regulatory Agencies, Public Utility Commission (PUC) mission is to “serve the public interest by effectively regulating utilities and facilities so that the people of Colorado receive safe, reliable, and reasonably-priced services consistent with the economic, environmental and social values of our state.” One of the PUC’s responsibilities is to regulate railroad safety. State jurisdiction over railroad safety is extremely broad, however most areas have been preempted by the federal government. The PUC retains primary jurisdiction over all public highway-rail crossings, including opening, closing, upgrading, overpasses or underpasses, and the allocation of costs. All economic jurisdiction over railroads that are part of the national railroad system come under the jurisdiction of the Surface Transportation Board. In accordance with 49 CFR Part 659 and CRS 40-18, the Colorado Public Utilities Commission has responsibility for the oversight of the safety and security of rail fixed guideway (RFG) systems within the state. While the authority of the Federal Regulations extends to RFG systems which have received or are receiving federal, the Colorado Statute grants this authority to any RFG system operating within the state, whether receiving federal funds or not. 26 The project development risks of the alternatives include potential time, delays and costs associated with: · Design that complies applicable requirements · Details needed to be developed for submittal the PUC · Negotiations and supplements necessary to obtain all of the necessary PUC approvals · Conditions associated with PUC approvals · The possibility that the PUC will deny approval to a desired alternative, especially creating a new at-grade crossing given vehicle, pedestrian and cycling conditions expected in year 2035. These risks can be managed through the use of experienced designers familiar with PUC requirements and demonstrating a successful record of approvals. However, recent actions by the PUC have shown a desire to grade separate train and arterial road crossings. Railroad Risks Roadway projects that relate to the interests of railroads experience various risks in addition to those associated with PUC risks. Railroads are private sector entities unlike public agencies and utilities. Railroads are not motivated to improve roadway operations and can solely focus on their own operational requirements. Roadway projects that require physical changes to railroad tracks such as modifications at road/railroad crossings must obtain approval from railroad owner/operators. In addition, any work that occurs within or near their right of way having any direct or indirect effect on safety or operations requires railroad owner/operator approval. Each of the alternatives involves negotiations with BNSF and their final approval before the City can proceed, including discussions on options for keeping the existing at-grade crossing open to limited access. These risks can be managed through the use of experienced designers familiar with BNSF safety and operation needs, and demonstrating a successful record of negotiations with BNSF. Environmental Risks The environmental evaluation, impact documentation and permitting processes for the Proposed Action present budget and schedule risks linked to known and unknown considerations. The environmental issues are described in Section 2.6. The environmental screening process for the alternatives is described in Section 2.9. The environmental impact documentation process is described along with other project development issues in Chapter 3. The key environmental issues that present risks are manageable, but include: · Noise impacts including a formal noise analysis and the potential for mitigation. · Aesthetics and views into backyards and windows (privacy and visual quality issues). · Flooding, stormwater management and drainage facilities · Wetlands and migratory birds 27 · Cultural resources, indirect effects on two neighborhoods with historic elements · Public controversy over potential effects and differences between the alternatives The alternative screening, NEPA compliance and permitting processes each present risks. The screening process may be able to reduce the number of alternatives that need to be considered, but it may also introduce new alternatives or options that require evaluation. Various permits will be required. These permits, sensitive issues and seasonal restrictions (migratory bird nesting) may generate delays and/or added project costs. These risks can be managed through the use of experienced NEPA consultants familiar with applicable NEPA process management strategies, including the use of upfront commitments to avoid, minimize and mitigate effects with the design that are subject to review under NEPA. 2.9 Alternative Comparison Comparison of the Alternatives requires the development and use of evaluation criteria based on the project’s purpose and need statements and the City of Fort Collins’ “Triple Bottom Line” considerations. The purpose and need for the Proposed Action are described in Section 2.2. The Triple Bottom Line considerations involve sustainability principles and the need to balance social, economic and environmental impacts and outcomes. A screening process typically involves different levels of comparison. Two levels of comparison are recommended for this project. 1. Feasibility-Level Criteria: Broad considerations and fatal-flaws 2. Concept-Level Criteria: Key considerations for comparative analysis The following criteria provide a framework for future evaluation of the alternatives. At this stage, the criteria are presented as a set of primary qualitative and quantitative questions. Feasibility-Level Criteria: Broad Considerations and Fatal-Flaws The following Yes/No questions establish whether an alternative should be considered fatally flawed by not meeting fundamental project requirements. If an alternative subjected to these questions generates a yes answer to all of these questions, it should move forward for evaluation under the Concept-Level Criteria. 1. Does the alternative fully address motor vehicle, bicycle and pedestrian safety concerns? 2. Does the alternative meet applicable safety requirements for railroad operations? 3. Does the alternative provide adequate safety for residences in close proximity to adjacent roadways and the railroad? 4. Does the alternative address future capacity needs for an extended period (interim to 2035)? 5. Does the alternative address future community and local area accessibility and mobility needs? 6. Does the alternative adequately address existing neighborhood accessibility problems caused by traffic queues? 7. Does the alternative cause significant unavoidable environmental effects? - Require residential displacement that would substantially alter the character of existing neighborhoods? 28 - Adversely impact cultural resources (historic buildings or historic districts)? - Adversely impact community facilities and/or neighborhood cohesion? - Other? Concept-Level Criteria: Key Considerations for Comparative Analysis The following Good/Fair/Poor questions allow for a qualitative assessment of the relative merits of an alternative such that especially good alternatives are advanced and especially poor alternatives are eliminated from further, more detailed evaluation. 1. How well does the alternative address: - Motor vehicle and railroad conflicts? - Bicycle routes and cyclists needs for safe travel through the intersection? - Pedestrian routes and their need for safe travel through the intersection? - Railroad travel speeds? - Motor vehicle Level of Service in 2035? - Community mobility? - Neighborhood access? 2. How effectively are environmental effects of the alternatives avoided or minimized: - Private Property Acquisition for Public Right of Way? - Land Use Compatibility? - Environmental Justice? - Existing Pedestrian and Bicycle Paths and Lanes? - Parks and Recreation Areas? - Noise? - Visual Quality/Aesthetics? - Water Resources, Flooding and Drainage? - Biological Resources and Wetlands? - Geology and Soils? - Cultural Resources? - Hazardous Materials? - Public Utilities and Services? - Other? 3. How effective is the project: - Constructability? - Cost? - Intersection Performance (Delay) 2035? The next phase of the project development process will include refining the alternatives and a full evaluation of them using the defined criteria. Table 4 and Table 5 present an initial evaluation of selected evaluation criteria. 29 Table 4 Feasibility-Level Criteria: Selected Broad Considerations and Fatal-Flaws (Yes/No) SCREENING QUESTION/ ALTERNATIVE Railroad Switching Station Relocation Realignment At-Grade Intersection Realignment Overpass Realignment Underpass Does the alternative fully address motor vehicle, bicycle and pedestrian safety concerns? No Yes Yes Yes Does the alternative meet applicable safety requirements for railroad operations? Yes Yes Yes Yes Does the alternative provide adequate safety for residences in close proximity to adjacent roadways and the railroad? Yes Yes Yes Yes Does the alternative address future capacity needs for an extended period (interim to 2035)? No No Yes Yes Does the alternative address future community and local area accessibility and mobility needs? Yes Yes Yes Yes Does the alternative adequately address existing neighborhood accessibility problems caused by traffic queues? No Yes Yes Yes Does the alternative avoid significant unavoidable environmental effects? Require residential displacement that would substantially alter the character of existing neighborhoods? Adversely impact cultural resources (historic buildings or historic districts)? Adversely impact community facilities and/or neighborhood cohesion? Other? Yes Yes Yes Yes The key issues are: · The switching yard relocation and the at grade alternative do not provide adequate capacity in 2035. · The switching yard relocation does not address safety or neighborhood access · The underpass has drainage, high water table, cost, constructability and risk issues relative to the overpass alternative. 30 Table 5 Concept-Level Criteria: Selected Considerations for Comparative Analysis (Good/Fair/Poor) SCREENING QUESTION/ ALTERNATIVE Railroad Switching Station Relocation Realignment At-Grade Intersection Realignment Overpass Realignment Underpass How well does the alternative address: Motor vehicle and railroad conflicts? Fair Fair Good Good Bicycle routes and cyclists needs for safe travel through the intersection? Fair Fair Good Good Pedestrian routes and their need for safe travel through the intersection? Fair Fair Good Good Railroad travel speeds? Fair Fair Good Good Motor vehicle Level of Service in 2035? Poor Fair Good Good Community mobility? Fair Good Good Good Neighborhood access? Fair Good Good Good How effectively are environmental effects of the alternatives avoided or minimized: Private Property Acquisition for Public Right of Way Good Fair Fair Fair Land Use Compatibility Fair Good Fair Good Environmental Justice? Fair Good Fair Good Existing Pedestrian and Bicycle Paths and Lanes? Poor Good Good Good Parks and Recreation Areas? Good Good Good Good Noise? Fair Fair Fair Good Visual Quality/Aesthetics? Good Good Fair Good Water Resources, Flooding, Drainage Good Good Good Poor Biological Resources/Wetlands? Good Fair Fair Fair Geology and Soils? Good Good Good Fair Cultural Resources? Fair Good Fair Good Hazardous Materials? Good Good Good Fair Public Utilities and Services? Good Good Good Good How effective is the project: Cost? TBD Good Fair Poor Constructability and Risks? Fair Poor Good Poor Intersection Performance (Delay) 2035? Poor Fair Good Good 31 Key Alternatives Benefits, Risks and Decision Drivers The Realigned At-Grade Alternative: • Will likely face higher PUC and Railroad approval risks as compared to the grade separated alternatives due to Lemay Avenue’s designation as an Arterial roadway. • Can manage train crossing delays to a comparable level as the grade separated options; however, to achieve this, delays must get down to a three-minute train crossing. The only way to achieve this is to relocate of the BNSF Yard, at a significant cost to the City of Fort Collins, nearly doubling the cost of constructing the At-Grade Alternative improvements. The Realigned/Overpass and Realigned/Underpass Alternatives: • Fully removes the conflicts and delays associated with the train crossing. Both the PUC and BNSF would find these alternatives safer and a low risk once completed • Improves mobility for all travel modes by providing efficient access from northeast Fort Collins to Downtowns, other commercial districts, employment centers, and community resources while also removing a known constraint to future bus transit in the region. • Improves local street and pedestrian conditions near the access points to the two nearby neighborhoods by relocating two major arterials and devolving the existing roads to local streets. • The underpass alternative has a high ground water table due to the close proximity to Dry Creek; resulting in complex construction. Additionally, constructing the new BNSF bridge will be challenging while keeping the tracks operational (there is no viable shoe-fly option). These conditions result in high risk and expensive costs for construction, but do not create approval risks. • The overpass option can be constructed over the existing tracks with limited impacts to BNSF operations using conventional construction techniques. These conditions result in low risk yet moderate costs for construct; however the bridge would be nearly 30 feet in the air and would require walls in some locations creating visual impacts for the adjacent neighborhood. 32 3. PROJECT DEVELOPMENT PROCESS AND SCHEDULE 3.1 Project Development Process The City of Fort Collins project development process typically involves the following steps: • Infrastructure Needs Assessment Existing Conditions Streetscape Requirements Bicycle and Transit Mobility Needs Traffic Safety Traffic Operations Parking • Public Input • Development and Evaluation of Alternatives (Environmental Analysis, Compliance & Permitting) • Selection of Preferred Alternative • Preliminary Design: Evaluation of Design Options and Phasing/Prioritization, 30% Complete Plans • Recommended Implementation Strategy • Final Design/Construction This Project Development Report is associated with the Infrastructure Needs Assessment step. 3.2 Preliminary Design Process The Preliminary Design process involves refinement of conceptual designs, evaluation of alternatives and design options, and the development of initial phasing and prioritization plans. The preliminary design process is completed with delivery of 30% Complete Plans. The evaluation of alternatives frequently involves environmental clearance, compliance and documentation steps, including some environment permitting steps. Some environmental permits and follow-up compliance occurs during the Final Design process. When federal facilities, resources, and/or decisions are required for project implementation, the National Environmental Policy Act (NEPA) applies. The Federal Highway Administration (FHWA) administers NEPA with support from the Colorado Department of Transportation (CDOT) and local governments. The applicable NEPA, environmental clearance and permit processes are described in Section 3.3. Details about the NEPA process are available in CDOT’s NEPA Manual: http://www.coloradodot.info/programs/environmental/nepa-program/nepa-manual 3.3 Environmental Process NEPA Requirements and Documentation As a result of the interagency partnerships forged during the project planning process and context- sensitive planning and design efforts, the City anticipates the applicable environmental compliance processes for the alternative will be straight forward. If the project obtains federal funding, the City 33 anticipates that a NEPA Categorical Exclusion (CatEx) process will be appropriate. A CatEx may be possible after defining efforts to avoid, minimize and mitigate potential effects with design solutions and applicant commitments and coordinating with FHWA, CDOT Region 4 environmental staff and regulatory agencies. A CatEx requires that the proposed action: · Does not induce significant impacts to planned growth or land use for the area · Does not require the relocation of significant numbers of people · Does not have a significant impact on any natural, cultural, recreational, historic or other resource · Does not involve significant air, noise or water quality impacts · Does not have significant impacts on travel patterns · Does not otherwise, either individually or cumulatively, have any significant environmental impacts, and are, therefore, excluded from the requirement to prepare an EA or EIS In additional to these requirements, the proposed action should be well understood and not present substantial public controversy. Based on the CDOT NEPA Manual, the overpass and underpass options may qualify for a “Non- Programmatic” Cat Ex as follows: D3. Bridge rehabilitation, reconstruction, or replacement or the construction of grade separation to replace existing at-grade railroad crossings A Non-Programmatic CatEx requires CDOT and FHWA approval. CDOT and FHWA have agreed on certain actions that are typically appropriate for this approach. These project types must meet the criteria for a CatEx in the Council on Environmental Quality (CEQ) regulations (CEQ, 40 CFR § 1508.4) and the evaluation criteria specified in Part A of the regulation (FHWA, 23 CFR § 771.117). Prior to initiating a Non-Programmatic CatEx project, the FHWA Non-Programmatic Categorical Exclusion Environmental Review Summary form must be reviewed. If any of the following questions, which are included on page one of the form, can be answered in the positive, further investigation will be required in order to determine if a Non-Programmatic CatEx is appropriate for the project: · If an Individual Clean Water Act Section 404 permit is required, does the USACE object to a CatEx class of environmental document? · If the project adversely affects endangered or threatened species and/or their critical habitat, does the US Department of Interior Fish and Wildlife Service (USFWS) object to the CatEx class of environmental document? Neither of these issues presents a process constraint for the overpass of underpass alternatives. However, the three items in bold text below should be evaluated carefully. The other issues should not present a process constraint. 34 · If a DOT letter of consent is required for easement, does the federal land management agency have unresolved issues with the environmental analysis? · Is there any substantial controversy on environmental grounds? · In addition, if any of the following questions, which are also included on page one of the FHWA Non-Programmatic Categorical Exclusion Environmental Review Summary form, can be answered in the positive and cannot be other resolved by amending the planned action, the project should not be approved as a Non-Programmatic CatEx: · Are significant environmental impacts expected? · Are there any inconsistencies with the federal, state, or local law, requirement or administration determination relating to the environmental aspects of the action expected? · Does this project add additional capacity, as defined by NFRMPO as regionally significant? · Is there substantial construction on a new alignment? · Will the project significantly change traffic patterns? · Are there significant impacts expected to properties protected by Section 4(f) of the US DOT Act or Section 106 of the National Historic Preservation Act? · Is the right-of-way required significant because of its: size, location, use, or relationship to remaining property and abutting properties? · Is there a substantial noise increase (greater than 10 A-weighted decibels [dBA]) or noise levels greater than allowable by CDOT guidelines and mitigation is not reasonable and feasible? The additional capacity and its regional significance can be addressed by citing the purpose of the improvements as one means of facilitating planned growth. The nature of the construction on the new alignment and the purpose of the project to improve traffic safety and circulation patterns can be explained the same way and can be supported by safety improvements from the railroad grade separation. The CatEx process would be documented through the use of CDOT Standard Form 128 and supplement technical documentation (See Appendix D). CDOT Form 128 requires two signatures, one for the top portion and one for the bottom portion. Top portion (Parts A and B) involve investigating whether there are environmental areas of concern with regard to the project. The Top portion (Parts A and B) are usually needed for right-of-way plan authorization and obligation of funds for right-of-way acquisition unless these areas do not have important environmental impacts and if the right-of-way is being purchased with non-federal funds. The Bottom portion (Parts C, D, and E) are used for applicable environmental permits and for ensuring environmental commitments are in the final plans and specifications. The Bottom portion (Parts C, D, and E) needed for project advertisement and obligation of funds. The entire step by step process is described in Chapter 5 of CDOT’s NEPA Manual. Environmental Clearances and Permits The following list identifies anticipated environmental clearances and permits for the overpass and underpass alternatives. Top Half of 128 Air Quality Hot Spot Analysis Not Required Noise Required Hazardous Materials Required (Initial Site Assessment) 35 Threatened and Endangered Species Clearance Letter Required Wetland Delineation Required Paleontology Required Archaeology* Required History* ** Required Historic Bridge Required 4(f) Not Required 6(f) Not Required *Consultation and Coordination Literature Review) ** De minimis documentation Bottom Half of 128 404 Permit TBD 401 Certification TBD 402 Certification TBD Construction Dewatering Certification Required Floodplains Development Permit TBD SB 40 Not Required Wetland Finding TBD APCD Bridge/Structure Demo Permit Not Required Hazardous Materials (Phase II) TBD 6(f) Completion Not Required Completion of the environmental process allows the City to proceed with Right of Way acquisition and the Final Design and Construction process. 3.4 Final Design and Construction Process The Final Design process typically involves development of the final plans, specifications and cost estimates, along with the necessary final permitting, right-of-way clearances, and utility relocation coordination. Project construction can be accomplished through a variety of delivery methods. The methods that could be considered include Design-Bid-Build, Design-Build, and CM/GC (Construction Manager at Risk). The construction delivery method for this project has not been identified. Each delivery method has trade-off advantages and disadvantages depending on the project characteristics. Determining the construction delivery method that is best suited for a project involves a number of project characteristics, including but not limited to: · Construction Schedule · Funding Availability Schedule · Project Complexity · Risks 36 4. Project Funding Strategies This section discusses combinations of potential local and federal funding sources that could be pursued to advance the Vine/Lemay project and the potential issues associated with each strategy. Two project alternatives are considered in the funding approach analysis: 1) at-grade improvements and 2) a grade separated overpass. The analysis begins by summarizing the costs, funding gaps and timing issues, and potential sources to fill these gaps. Lastly, the pros and cons associated with the funding approach strategies are highlighted. Given the extent of the Vine/Lemay project costs, it will require a combination of sources to advance the project. As a result, a political champion for the project will be needed in order to garner support at the local and regional levels to get the project funded. The strength of the support largely will be based on the project’s potential benefits and impacts to the City as well as the larger region, which will need to be considered and shared with the public and potential funding partners. The competition for public funds (both local and federal) is significant, because there are many important projects out there but increasingly limited funds. As a result, the benefits and impacts associated with the Vine/Lemay project need to be effectively communicated with all potential funding partners, including City residents, which often requires a political champion. Details of the various local funding sources and federal funding partners can be found in Appendix F. 4.1 Potential Funding Approach This section summarizes potential funding approaches for the at-grade and overpass alternatives. These alternatives represent the range of potential funding that would be needed to construct improvements to the Vine/Lemay intersection, and as a result the range of potential funding sources that would be needed. The focus in this section is on identifying potential sources and combinations of sources that could be used to fund the project. The issues associated with receiving funds in time to meet construction expenditures is a concern for the project; however, once the funding sources have been secured, these funds could be leveraged through TIFIA, Grant Anticipation Revenue Vehicles (GARVEEs), or other bonding mechanisms to get the funds needed up front for construction. These financing vehicles would allow the project to be constructed in a timely manner, while repaying the loan and/or bond issue over a specified time with future, committed revenue streams. As a result, the primary focus is on identifying sources of these revenue streams for the project. Most Applicable Project Funding Sources The local and federal sources of funds discussed in this chapter that are most applicable and realistic for the Vine/Lemay project include the following: · Local: City Sales Tax (BOB or KFCG) - If the 0.25% BOB sales tax is extended, it would provide a source of potential funds for the Vine/Lemay project. In addition, approximately $3.4 million in KFCG sales tax revenues (17%) are potentially available for other street and transportation needs. As a result, the funds would not be able to pay for the entirety of the project, but may be a viable source for the local match to federal funds. 37 · Federal: Highway Safety Improvement Program (HSIP) or Surface Transportation Program (STP) – These programs are part of the Federal-aid highway program annual appropriations. HSIP funding is specifically available for grade crossing improvements and removal of high-risk at-grade crossings under the Railway-Highway Crossing Program. In addition, the program funds projects that remove hazardous road locations or any project on a public road that is consistent with the State Strategic Highway Safety Plan (SHSP). STP provides flexible funding that may be used by states and localities for projects to preserve and improve the conditions and performance of any federal-aid highway, bridge, or tunnel project on any public road, pedestrian and bicycle infrastructure, and transit capital projects. The use of these funds will require gaining support at the regional MPO level to get the project included in the region’s Transportation Improvement Program (TIP), as well the State Transportation Improvement Program (STIP). CDOT and the MPO are responsible for allocating federal-aid highway program funds to projects through the local TIP and state TIP. As a result, having a political champion to sell the benefits of the project will be particularly helpful in trying to secure these funds. Due to the competition for these funds, it is estimated that the at-grade alternative would have trouble securing these funds, while the overpass alternative likely would not receive more than $5 million; however, through continued project development and communication of project benefits, the overpass alternative could warrant the consideration of a larger funding share. · Federal: TIGER Discretionary Grant Program - The TIGER program is highly applicable to roads and rail, since its eligible categories include, among others, freight rail projects and any federally-eligible highway or bridge project. TIGER has been continued for six rounds to date and through the annual appropriations process. Future rounds depend either on year-to-year appropriations or the program’s permanent authorization in the successor to MAP-21; the President’s budget recommendation includes $1.25 billion annually for four more years. The safety and economic development components of the overpass alternative fit nicely with TIGER’s evaluation criteria due to the grade separation and removal of rail-highway conflicts; however, the competition for these funds is quite extensive. With additional local, committed funding sources, partnerships, and engineering, it would be worthwhile for the City to consider applying during future TIGER rounds. In urban areas, the minimum TIGER award is $10 million dollars, and the most competitive TIGER projects tend to keep the local match at 50%; therefore, the overpass alternative potentially could receive between $10 million and $14 million with a successful TIGER application. It is not recommended that the at-grade alternative pursue TIGER funds, because it does not remove or reduce to opportunity for rail- highway conflicts as it is currently defined. · Federal: EDA Public Works and Economic Adjustment Assistance Programs – These EDA Programs provide assistance to distressed communities to help them attract or expand businesses and generate long-term jobs. The project would be eligible under the programs because it proposes to improve an access road to a future commercial business center, thereby supporting employment growth in the region. Recent average grant awards have been approximately $1 million. As a result, the grant program could provide supplemental revenues for the project but would not be able to provide a significant contribution. Applications are competitively evaluated in quarterly funding cycles (deadlines on March 14, June 13, and October 17) and decisions generally are made within 20 business days of the funding cycle deadline. An applicant may submit an application at any time to receive feedback on the application’s competitive and technical merits. If this is an opportunity that the City would like to consider further, it is recommended that they take advantage of this ability to receive 38 feedback on their application to determine its likelihood of success as well as if there are additional components that would better position the project for an award. In addition to these funding programs, the TIFIA program could be a mechanism for the overpass alternative to leverage future revenue streams from the City sales tax and/or future federal-aid highway program funds (HSIP or STIP). A TIFIA project must be reasonably anticipated to cost at least $25 million for rural projects, and the definition of rural for TIFIA purposes includes cities of less than 250,000 population.1 Therefore, only the overpass project would be eligible for the TIFIA program. While TIFIA’s normal interest rate for secured loans can be as low as the rate on 30-year US Treasuries, 10% of TIFIA’s budget authority is set aside for rural projects at reduced interest rates to as low as one-half the Treasury rate—offering the City a competitive opportunity to leverage any secured funding streams. The potential mix of funding strategies for each alternative is discussed below. At-Grade Alternative The cost of the realignment of the at-grade Vine/Lemay intersection is estimated to be $13.6 million from planning through construction. It is assumed that the time required to complete the project (including planning and engineering) would be approximately four to five years, with most of the costs associated with construction occurring during the last two years. There are some vacant parcels north of Vine Drive on Lemay Avenue that, upon development, would be required to build portions of Lemay Avenue in conjunction with the Street Oversizing Program. The City has estimated the portion of the alternative’s costs that could be funded by the City’s Street Oversizing Program as well as the Developer’s Local Street Portion (associated with access to several currently undeveloped sites), which are summarized in Table 6. While the Local Street Portion is directly tied to the development of the adjacent parcels, if the capital project came before the development of these parcels the money would have to come from another source. However, future receipt of the Local Street Portion could be used to pay back these funds over time. Table 6 Estimated Local Developer and Street Oversizing Funds for the At-Grade Alternative ($M) Total Project Cost $ 24.60 Developer Local Street Portion $ 1.45 City Street Oversizing Portion $ 5.16 Amount Remaining to be Funded $ 17.99 Source: AECOM Cost Estimate (May 2014) and City Estimates of Street Portions After the application of these local street portion/oversizing funds, nearly $18 million in funding would still be required for the at-grade alternative. The funding approach analysis estimates that the remaining costs would have to be funded primarily through the City’s sales tax, which could be feasible based on the current assumption that the City would only be able to provide $5 million to $10 million in sales tax revenues towards the project. The options for funding the at-grade alternative with sources other than City funds are rather limited due to the current definition of this alternative. In order for the alternative to be competitive for other 1 Fort Collins population is 144,000 according to Census 2010. See: http://quickfacts.census.gov/qfd/states/08/0827425.html 39 federal-aid highway funds or federal discretionary grants like HSIP, STP, and TIGER, train blockages must be reduced to create travel time savings, safety improvements, and emissions reduction benefits in the region. As this alternative is currently defined, it excludes relocating the rail yard that is the source of these blockages and provides limited opportunity to reduce the likelihood of rail-highway conflicts. As a result, the potential benefits associated with improved traffic flow during non-blocked time periods are not likely to be significant enough to gain the support of larger funding programs such as HSIP, STP, or TIGER. In order to improve the competitiveness of the at-grade project, it is recommended that the City consider making the alternative a joint project with BNSF to move the rail yard and look for opportunities to improve BNSF operations with the implementation of the combined project. This could potentially reduce the number of trains blocking the grade crossing and improve the movement of freight in the region—generating significant community benefits in travel time savings, vehicle operating cost savings, safety improvements, and emissions reductions and making the project more attractive to the local voters, regional economic developers, and funding partners. Overpass Alternative The cost of the Lemay Avenue overpass alternative is estimated to be $26.6 million from planning through construction. It is assumed that the time required to complete the project (including planning and engineering) would be five years, with most of the costs associated with construction occurring during the last two years, as shown in Figure 11. Figure 11 Annual Construction Expenditure Flow for the Overpass Alternative Source: AECOM There are some vacant parcels north of Vine Drive on Lemay Avenue that, upon development, would be required to build portions of Lemay Avenue in conjunction with the Street Oversizing Program. The City has estimated the portion of the alternative’s costs that could be funded by the City’s Street Oversizing $0 $5,000,000 $10,000,000 $15,000,000 $20,000,000 $25,000,000 $30,000,000 Year 1 Year 2 Year 3 Year 4 Year 5 40 Program as well as the Developer’s Local Street Portion (associated with access to several currently undeveloped sites), which are summarized in Table 7. While the Local Street Portion is directly tied to the development of the adjacent parcels, if the capital project came before the development of these parcels, the money would have to come from another source. However, future receipt of the Local Street Portion could be used to pay back these funds over time. Table 7 Estimated Local Developer and Street Oversizing Funds for the Overpass Alternative ($M) Total Project Cost $ 27.60 Developer Local Street Portion $ 1.29 City Street Oversizing Portion $ 4.46 Amount Remaining to be Funded $ 21.85 Source: AECOM Cost Estimate (May 2014) and City Estimates of Street Portions After the application of these local street portion/oversizing funds, an additional $20.85 million in funding would still be required for the overpass alternative. The funding approach analysis estimates that the remaining costs potentially could be funded through a combination of the City’s sales tax, Federal HSIP/STP, TIGER, and EDA funds, due to the types of benefits and economic development impacts that could accrue to the City and larger region by removing the rail-vehicle conflicts through grade separation. While there is an opportunity for a greater variety of funding source for the overpass alternative, it is not recommended that the City pursue a wide variety of sources initially due to the complications associated with timing and getting commitments from multiple funding partners. If one funding partner backs out, the margin is tight enough that it is possible the City and remaining funding partners may not be able to make up the difference. As a result, it is recommended that the City pursue one additional federal funding source to fund a larger share of the project costs, such as TIGER. A sample funding approach strategy is summarized in Table 8, assuming a TIGER award equal to 50% of the project’s costs. Given what is known about the proposed overpass alternative, the project has the potential to be competitive in the TIGER evaluation process due to its potential for significant travel time savings, vehicle operating cost savings, safety improvements, and emissions reductions associated with the grade separation, as well as the potential of the project to facilitate economic development and provide “ladders of opportunity” for regional job growth. If the TIGER award would be closer to $10 million, the approach would still be viable given low contributions assumed from other federal funds. Table 8 Potential TIGER Funding Strategy for the Remaining Overpass Alternative Costs ($M) Federal: TIGER $ 13.80 Local: City Sales Tax Cash (new BOB/KCFG) $ 7.00 Federal: HSIP/STP/EDA $ 1.05 Total $ 21.85 Even though it appears that the project would be competitive in the TIGER evaluation process, the success rate of applications is low due to the volume of competitive projects and the limited funding available. A political champion could help improve the project’s standing in the evaluation process, but there is never a guarantee of success. If the project is not successful in winning a TIGER grant, or if it is not available to the project, then another similarly large federal funding program will have to be aggressively pursued—potentially a combination of HSIP and STP funds. If the City can contribute between $5 to $10 million towards the project from BOB/KFCG sales tax, then at least $1185 to $16.85 41 million in other funds would still need to be secured. This is not a small amount; however, if the project is marketed correctly and the benefits fully explored and communicated, it is not impossible. 4.2 Pros and Cons Associated with the Funding Approach Strategies The funding approaches considered for both alternatives highlight the major concern for the Vine/Lemay project: a large funding source is not readily or currently available to the City. The best source of local funds is the local option sales tax, which will need to be extended with a new voter referendum. Even with the passage of a new BOB sales tax, it is not likely to provide more than $5-$10 million towards the project, which means that between $3 million and $12 million in additional funds would still be needed to construct the project alternatives. These local funds would need to be secured before additional funding partners could be pursued to demonstrate local commitment to the project. At-Grade Alternative The at-grade alternative funding approach is relatively straightforward, as it would likely have to be funded entirely with City funds. The simplicity of the approach adds to the ease of getting it constructed due to limited project partners and requirements; however, there is also the greatest financial risk associated with this approach as it would be difficult for the City to fund it entirely from sales tax revenues. Any cost overruns or revenue shortfalls would need to be funded by the City. This project also has greater timing issues in terms of the funds being available when construction costs occur. With the City as the primary source of funding (particularly as the Developer Local Street Portion is likely to occur at the end or after construction), the project may have to wait until all the sales tax revenues are available, which could take several years. If the City would like to advance the construction of the project before all funds are in hand, they will have to issue bonds backed by the BOB sales tax because Federal financing programs such as TIFIA would not be available to the at-grade alternative due to the lower cost and lower competitiveness of the project benefits. The City has not issued bonds backed by the BOB sales tax to date, but it has been discussed internally with City staff. The City would have to weigh the implications of leveraging future revenues for current projects, which may impact the City’s ability to fund future projects. Overpass Alternative The overpass alternative has a higher cost, however, it also offers a more varied funding approach due to the opportunity to competitively pursue non-City funding, including Federal HSIP/STP, TIGER, and EDA funds. The alternative more closely aligns with regional goals for reduced rail-highway conflicts and improved access to economic development sites, which are attractive to regional and federal funding partners. The removal of rail-highway conflicts with the overpass alternative would result in significant travel time savings, vehicle operating cost savings, safety improvements, and emissions reductions associated with grade separation. While additional funding sources are available to the overpass alternative, it would still need to rely heavily on City sales tax revenues to construct the project due to the scale of the investment and the local match requirements associated with federal funds. While there are several federal funding sources that the overpass alternative could pursue, it is recommended that the City begin by trying to attract funding from one larger federal program such as HSIP, STP, or TIGER. Initially pursuing one larger program would allow the City to minimize the difficulties associated with managing and getting firm commitments from numerous funding partners. 42 As the project moves through the planning and development process, additional beneficiaries and funding partners could be identified and pursed to fill in any remaining gaps in project funding. A political champion for the project also could help identify these additional beneficiaries and garner the necessary support at the local, regional, and federal levels. The benefits and impacts associated with the Vine/Lemay project will need to be effectively communicated with all potential funding partners, including City residents, and a strong political champion can help deliver this essential message. The issues associated with receiving funds in time to meet construction expenditures is a concern for the alternative; however, it is not as great of a concern as the at-grade alternative. Once the funding sources have been secured, these local and federal funds could be leveraged through TIFIA, Grant Anticipation Revenue Vehicles (GARVEEs), or other bonding mechanisms to get the funds needed up front for construction. These financing vehicles would allow the project to be constructed in a timely manner, while repaying the low interest loan and/or bond issue over a specified time with future, committed revenue streams. 5. PROJECT DEVELOPMENT NEXT STEPS The next step in the process is to begin a more thorough data collection, preliminary design and funding evaluations that will address the following key questions: · Is the added long-term cost/benefit of realignment and grade separation necessary to address anticipated 2035 congestion and delay, or could a realignment and at-grade intersection be sufficient as a near-term solution that could then transition at a later date? Will a new at-grade crossing be allowed by the PUC and BNSF, and would BNSF consider switching yard relocation? · Is the added cost of an underpass to address visual and noise impact issues appropriate when a lower cost overpass would result in similar traffic performance without the higher cost and risk concerns, such as drainage issues, caused by the underpass? · Does the currently unknown cost of relocation of the railroad switching yard and its ability to reduce railroad crossing/switching-related system congestion justify the expenditure? · Can the existing at-grade crossing of existing E. Vine and existing Lemay remain in a limited configuration for pedestrians/cyclists. 43 APPENDIX A. Construction Cost Opinions B. Lemay/Vine 2035 Traffic Analysis Memorandum C. Analysis of Vehicle Delay from Train Operations D. Cultural Resources in the Study Area E. CDOT Standard Form 128 F. Project Funding and Finance Analysis 44 Intentionally Left Blank 1 APPENDIX A CONSTRUCTION COST OPINIONS 2 Intentionally Left Blank 9/2/2014 16:24 UNITS QUANTITY UNIT COST TOTAL COST Removals General SY 100,195 $4 $400,780 Railroad Apertenunces - Temporary EA 8 $20,000 $160,000 Track Panels - Temporary LF 120 $1,000 $120,000 Track Signalling - Temporary LS 1 $150,000 $150,000 Intersection Signals EA 1 $240,000 $240,000 ABC (Class VI) CY 10,060 $25 $251,500 ABC (Class VI) - Temporary CY 4,535 $25 $113,375 Pavement Ton 22,305 $75 $1,672,875 Pavement - Temporary Ton 10,055 $75 $754,125 Sidewalk SF 65,550 $6 $393,300 Sidewalk - Temporary SF 22,845 $6 $137,070 Curb and Gutter LF 19,985 $20 $399,700 Curb and Gutter - Temporary LF 10,044 $20 $200,880 Culvert LF 160 $2,500 $400,000 Project Construction Bid Items $5,393,605 % USED COST Project Construction Bid Items Project Dependent N/A $5,393,605 (A) Contingencies (BNSF Complications) (15% - 30%) of (A) 20.00% $1,078,721 (B) ITS/Lighting (6-10%) of (A+B) 6.00% $388,339.56 (C) Default = 6% Drainage/Utilities (3-10% )of (A+B) 10.00% $647,232.60 (D) Default = 6% Signing and Striping (1-5%) of (A+B) 4.00% $258,893.04 (E) Default = 5% Construction Signing & Traffic Control 5 to 25% of (A+B) 15.00% $970,849 (F) Default = 20% Mobilization (4 to 10%) of (A+B+C+D+E+F) 7.00% $611,635 (G) Default = 7% Total of Construction Bid Items (A+B+C+D+E+F+G) $9,349,275 (H) Force Account - Utilities (1 to 2%) of (H) 2.00% $186,985 (I) Default = 2% Force Account - Misc. (10 to 15%) of (H) 10.00% $934,927 (J) Default = 12% Subtotal of Construction Cost (H+I+J) $10,471,188 (K) Right of Way Acquisition and Easements % of (H) 2.50% $261,780 (L) Planning and NEPA % of (H) 2.50% $261,780 (M) Preliminary and Final Engineering % of (H) 10.00% $1,047,119 (N) Construction Management/Inspection % of (H) 15.00% $1,570,678 (O) Local Street Construction LF 3600 $300 $1,080,000 (P) Relocate Freight Switching Yard LS $10,000,000 (Q) Total Project Cost (K+L+M+N+O+P+Q) $24,692,544 (R) Comparative Cost Opinion Realingment At-Grade Intersection Alternative Modified by AECOM % RANGE Vine and Lemay Opinion of Probable Cost_Rev 6 .xlsx 9/2/2014 16:24 UNITS QUANTITY UNIT COST TOTAL COST Removals General SY 84,470 $4 $337,880 Intersection Signals EA 1 $240,000 $240,000 Embankment CY 124,636 $10 $1,246,360 ABC (Class VI) CY 11,360 $25 $284,000 Pavement Ton 25,190 $75 $1,889,250 Sidewalk SF 85,065 $6 $510,390 Curb and Gutter LF 23,025 $20 $460,500 Bridge SF 25,245 $175 $4,417,875 Culvert LF 230 $2,500 $575,000 Retaining Walls (DH <= 10-FT) SF 6,480 $50 $324,000 Retaining Walls (DH >= 10-FT) SF 10,145 $100 $1,014,500 Project Construction Bid Items $11,299,755 % USED COST Project Construction Bid Items Project Dependent N/A $11,299,755 (A) Contingencies (15% - 30%) of (A) 20.00% $2,259,951 (B) ITS/Lighting (6-10%) of (A+B) 3.50% $474,590 (C) Default = 6% Drainage/Utilities (3-10% )of (A+B) 15.00% $2,033,956 (D) (High groundwater complications) Default = 6% Signing and Striping (1-5%) of (A+B) 2.33% $315,941 (E) Default = 5% Construction Signing & Traffic Control 5 to 25% of (A+B) 11.50% $1,559,366 (F) Default = 20% Mobilization (4 to 10%) of (A+B+C+D+E+F) 7.00% $1,256,049 (G) Default = 7% Total of Construction Bid Items (A+B+C+D+E+F+G) $19,199,608 (H) Force Account - Utilities (1 to 2%) of (H) 1.25% $239,995 (I) Default = 2% Force Account - Misc. (10 to 15%) of (H) 6.25% $1,199,976 (J) Default = 12% Subtotal of Construction Cost (H+I+J) $20,639,579 (K) Right of Way Acquisition and Easements % of (H) 1.25% $257,995 (L) Planning and NEPA % of (H) 2.50% $515,989 (M) Preliminary and Final Engineering % of (H) 10.00% $2,063,958 (N) Construction Management/Inspection % of (H) 15.00% $3,095,937 (O) Local Street Construction LF 3600 $300 $1,080,000 (P) Total Project Cost (K+L+M+N+O+P) $27,653,458 (Q) Comparative Cost Opinion Realingment Overpass Intersection Alternative Modified by AECOM % RANGE Vine and Lemay Opinion of Probable Cost_Rev 6 .xlsx 9/2/2014 16:24 UNITS QUANTITY UNIT COST TOTAL COST Removals General SY 113,403 $4 $453,612 Intersection Signals EA 1 $240,000 $240,000 Excavation CY 88,025 $15 $1,320,375 ABC (Class VI) CY 11,780 $25 $294,500 Pavement Ton 26,120 $75 $1,959,000 Sidewalk SF 72,635 $6 $435,810 Curb and Gutter LF 24,330 $20 $486,600 Bridge SF 9,240 $200 $1,848,000 Retaining Walls (DH <= 10-FT) SF 6,235 $150 $935,250 Retaining Walls (DH >= 10-FT) SF 34,320 $250 $8,580,000 Project Construction Bid Items $16,553,147 % USED COST Project Construction Bid Items Project Dependent N/A $16,553,147 (A) Contingencies (BNSF Complexities) (15% - 30%) of (A) 30.00% $4,965,944 (B) ITS/Lighting (6-10%) of (A+B) 2.15% $462,660 (C) Default = 6% Drainage/Utilities (3-10% )of (A+B) 25.00% $5,379,773 (D) (+Sump pump and Siphon) Default = 6% Signing and Striping (1-5%) of (A+B) 1.50% $322,786 (E) Default = 5% Construction Signing & Traffic Control 5 to 25% of (A+B) 7.00% $1,506,336 (F) Default = 20% Mobilization (4 to 10%) of (A+B+C+D+E+F) 7.00% $2,043,345 (G) Default = 7% Total of Construction Bid Items (A+B+C+D+E+F+G) $31,233,992 (H) Force Account - Utilities (1 to 2%) of (H) 0.80% $249,872 (I) Default = 2% Force Account - Misc. (10 to 15%) of (H) 4.00% $1,249,360 (J) Default = 12% Subtotal of Construction Cost (H+I+J) $32,733,224 (K) Right of Way Acquisition and Easements % of (H) 0.75% $245,499 (L) Planning and NEPA % of (H) 1.55% $507,365 (M) Preliminary and Final Engineering % of (H) 10.00% $3,273,322 (N) Construction Management/Inspection % of (H) 12.00% $3,927,987 (O) Local Street Construction LF 3600 $300 $1,080,000 (P) Total Project Cost (K+L+M+N+O+P) $41,767,397 (Q) Comparative Cost Opinion Realingment Underpass Intersection Alternative Modified by AECOM % RANGE Vine and Lemay Opinion of Probable Cost_Rev 6 .xlsx Intentionally Left Blank 1 APPENDIX B LEMAY/VINE 2035 TRAFFIC ANALYSIS MEMORANDUM 2 Intentionally Left Blank 1 APPENDIX C ANALYSIS OF VEHICLE DELAY FROM TRAIN OPERATIONS 2 Intentionally Left Blank APPENDIX C ANALYSIS OF VEHICLE DELAY FROM TRAIN OPERATIONS The following analysis of delay along Lemay from Mulberry to Vine characterizes the impacts from train operations under existing conditions and anticipated conditions in 2035 (forecast volumes, geometry, and at grade intersection relocation). Scenarios The following p.m. peak hour scenarios were considered. 1) Existing conditions without a train. 2) Existing conditions with a 6-minute train blockage. 3) 2035 conditions without a train. 4) 2035 conditions with a 6-minute train blockage. 5) 2035 conditions with a 3-minute train blockage. Train Operations with and without Switching The train blockage times were based on recent data from City of Fort Collins traffic signal preemption logs. One week of preemption records (i.e. trains) at Lemay/Vine were evaluated. A total of 55 records, with an average duration train blockage of 6.1 minutes, were identified. Consequently, 6.1 minutes was used to represent the average time of a blockage that accounts for switching yard impacts. To estimate blockage time if the switching yard were relocated, preemption logs for the same mainline track were evaluated where it crosses Drake Road in Fort Collins. Trains do not routinely stop or perform switching activities near Drake. Again, one week of preemption records at the Drake crossing were evaluated. A total of 39 records, with an average train blockage of 3.2 minutes, were identified. Consequently, 3.2 minutes was used to represent the average blockage time where there is no switching activity. The data was collected for different weeks so there is some uncertainty that the number of trains is indicative of increased activity due to switching. Modeling CORSIM traffic simulation software was used to analyze traffic delay from train operations. Since CORSIM is a stochastic model, a total of 30 runs were performed for each scenario. The reported results are the average of the 30 runs for each scenario. Train operations have an effect network-wide rather than at just one location, so the results report the total delay for the entire modeled network for each scenario in order to see the net difference comparing with a train versus without a train. Results The results, presented in Table 1, represent the total delay during the p.m. peak hour experienced by vehicles throughout the model network. For existing conditions, the intersections of Lemay/Mulberry, Lemay/Magnolia, Lemay/Lincoln and Lemay/Vine (including RR delay) are included. For the 2035 scenarios, these intersections, plus the delay at the railroad crossing which is no longer adjacent to the Lemay/Vine intersection, are included. Table 1 Total Delay during the P.M. Peak Hour Experienced by Vehicles Throughout the Model Network. Existing Conditions Without a Train Existing Conditions with a 6-Minute Train Blockage 2035 Conditions At Grade Alternative without a Train 2035 Conditions At Grade Alternative with a 3-Minute Train Blockage 2035 Conditions At Grade Alternative with a 6-minute Train Blockage Total Delay (Hours) 84.9 153.2 200.4 203.4 233.3 Vehicle-Trips 6,560 6,489 9,539 9,541 9,537 Seconds Per Vehicle Trip 46.6 85.0 75.6 76.7 88.1 Discussion Currently, the street network is slow to recover from a 6-minute train event. Watching the simulation reveals that long queues and delays linger for nearly a half hour after the train departs. This shows up as a near doubling of delay with a train compared to existing conditions on days when there isn’t a train. In 2035, overall traffic volume and delays are projected to be higher (mostly at Lemay/Mulberry in the simulation), but the effects from the train are reduced as a result of added storage capacity i.e. 4-lanes on Lemay rather than just two at the tracks and at adjacent intersections. There is also a noticeable difference (30 hours of delay) between the 6-minute and 3-minute train event. There are two questions that should be answered: 1. Is the cost of delay due to trains enough to justify the cost of a grade separation? and 2. Is the cost of the added delay due to switching enough to justify the cost of moving the switching yard? To get a total delay cost from the trains, the data from the p.m. peak hour would need to be converted into a daily estimate. This task has not been performed and may not be necessary because if the “grade separation option”, i.e. no trains, is compared to the “no switching yard option”, i.e. 3-minute train, there is only about a 1.5% increase in delay. Assuming the cost of relocating the switching yard is significantly less than the grade separation, it can be concluded that moving the switching yard is a better option in terms of delay reduction than a grade separation. This finding prompts the question of whether or not relocating the switching yard is cost effective. This answer requires additional analysis. 1 APPENDIX D CULTURAL RESOURCES IN THE STUDY AREA The Andersonville/San Cristo and Alta Vista neighborhoods, along with the Buckingham neighborhood located outside of the study area, share a common heritage. Each is a product of the sugar beet industry, a Colorado economic empire that emerged after the turn of the twentieth century. These neighborhoods supplied laborers to the sprawling and towering sugar beet factory complex they encircled and to the beet fields that surrounded it. In 2004, a Survey Report entitled “The Sugar Factory Neighborhoods: Buckingham, Andersonville, Alta Vista was prepared. The survey inventoried 175 properties in the three Sugar Factory Neighborhoods. The following discussion summarizes the findings of the Survey Report. Buckingham contained the most properties – 88. Andersonville had the smallest number at 38, and Alta Vista had 49. Only a few properties in Buckingham, Andersonville, and Alta Vista retain high enough levels of historical significance and physical integrity to be considered individually eligible for the National Register of Historic Places or the Colorado State Register of Historic Properties. Slightly more were found individually eligible as Fort Collins Landmarks. Moreover, just under half (48%) could be considered contributing to a potential district, but the percentage varies from neighborhood to neighborhood. The 1983 survey had determined that Buckingham and Andersonville lacked enough integrity to be considered National Register districts. However, this current survey determined that more than half of the properties in Buckingham and Andersonville contribute to their respective, potential districts. In 1983 the Alta Vista neighborhood was officially determined to be eligible for the National Register. But urban renewal programs in the mid and late 1980s significantly undermined the integrity of Alta Vista, leaving it with only 38.7% of properties contributing to a district. Andersonville, when considered as a whole, retains sufficient integrity to be considered a National Register and a Fort Collins Landmark district; slightly more than half (52.6%) of the properties contribute to a district. The Alta Vista neighborhood contains the northernmost collection of historic adobe structures in North America. This culturally and historically important neighborhood is one of the original groups of residences associated with the former sugar beet industry in Fort Collins, which was prosperous from the turn of the century through World War II. The neighborhood is eligible for designation as Fort Collins Landmark, and is eligible for listing in the National Register of Historic Places and the Colorado State Register of Historic Places. Alta Vista, when considered as a whole, does not retain sufficient integrity to be considered a National Register and a Fort Collins Landmark district; only 38.7% of developed parcels contribute to a potential district. However, the original core of Great Western-constructed adobe houses remains relatively intact. Given the historical and architectural significance of this group of adobe houses, this report recommends the creation of a National Register and Fort Collins Landmark district of the 35 properties roughly bound by Main Street to the north, Martinez Street on the east, Lindenmeier Road to the west, and East Vine Drive to the south. This area contains 18 contributing properties (51.4%), including one, 741 Lindenmeier Road (5LR10635), found to be eligible for individual listing on the National Register. 2 Andersonville (District 5LR989) Properties surveyed: 38 Contributing to a potential district: 20 (52.6%) Eligible for listing on the National Register: 1 Eligible for listing as a Fort Collins Landmark: 1 (including NR property) Not eligible / not contributing: 18 (47.4%) Alta Vista (District 5LR990) Properties surveyed: 49 Contributing to a potential district: 19 (38.7%) Eligible for listing on the National Register: 1 Eligible for listing as a Fort Collins Landmark: 10 (including NR property) Not eligible / not contributing: 30 (61.2%) The following resources were identified as eligible for listing on the National Register of Historic Places: 5LR10638 741 Lindenmeier Road 741 Lindenmeier Road 5LR10122 425 Tenth Street, Romero House The Lindenmeier Road property is significant under Criterion A for its association with the early development of the Alta Vista area and the sugar beet industry. Moreover, it is important for its relationship to German-Russian and Hispanics laborers, both of whom resided at this address. The property is also significant under Criterion C because it is an intact sugar beet workers’ shanty with an accompanying and intact German-Russian outbuilding complex. Despite numerous additions and remodeling, the house still embodies the spirit of working-class vernacular architecture, growing organically with need and financial ability. Properties such as this one were commonplace in the Buckingham, Andersonville, and Alta Vista neighborhoods prior to massive urban renewal projects in the late 1970s and ‘80s. This is the only remaining property of this level of physical integrity in the Sugar Factory Neighborhoods. It should be considered individually eligible for the National Register of Historic Places, the Colorado Register of Historic Properties, and as a Fort Collins Landmark. 3 The Romero House provides the setting for the Museo del las Tres Colonias. This resource is located next to Romero Park. Museo de las Tres Colonias 4 There are four defined purposes of the Museo: 1. The adobe historic house museum helps interpret family life in the tres colonias between 1927 and 1940. 2. The Museo offers education programs about contributions made by the His-panic community. 3. Volunteers explain to visitors the significance of the sugar-beet industry to the Fort Collins community. 4. The Museo is the focal point for continuous celebration of Hispanic culture, and promotes acceptance, understanding, and social justice for all. The Romero House property is significant under Criterion A for its association with the development of the Andersonville Neighborhoods, especially early Hispanic settlement. It is also significant under Criterion B for its association with John Romero, an early leader of the Hispanic Community in Fort Collins and an advocate of migrant workers’ rights. The house is significant under Criterion C because it is the only adobe residence in Andersonville and one of the few remaining in the Fort Collins. It is particularly important because of the vivid archival records that explain its construction. This property is already listed as a City of Fort Collins Landmark and should be considered individually eligible for the National Register of Historic Places, and the Colorado Register of Historic Places. Additional baseline information is available from the Fort Collins Landmark Preservation Committee and at the following websites: http://www.fcgov.com/historicpreservation/pdf/sugar-factory-doc.pdf http://www.fcgov.com/historicpreservation/pdf/top20list.pdf http://museodelastrescolonias.org/Museo/Museo.html 1 APPENDIX E CDOT STANDARD FORM 128 2 Intentionally Left Blank COLORADO DEPARTMENT OF TRANSPORTATION CATEGORICAL EXCLUSION DETERMINATION Date: Revision Date: Project Code #: Project #: Project Name: Project Description: A. Categorical Exclusion Project Determination 1. This project fits Categorical Exclusion or Programmatic CE number 2. CDOT Form #463 dated (Revised ) is attached. B. Clearance Actions REQUIRED DATE COMPLETED REQUIRED DATE COMPLETED If not checked is Not Applicable If not checked is Not Applicable Air Quality (hot spot analysis) Paleontology Noise Archaeology Hazardous Materials History - ISA Checklist Historic Bridge - MESA (or Phase I) 4(f) Threatened or Endangered Species 6(f) Agreements Wetland Delineation (survey) Other All required clearance actions indicated have been completed for the work described in the CDOT Form #463 referenced above. No significant environmental impacts will result from this project. All Permits and Additional Requirements indicated in Part C below will be obtained before project advertisement/construction. Implementation of project shall include required mitigation commitments. RPEM Signature Date Region # I concur in the above category designation and the scope of environmental clearance/permits indicated. FHWA Division Administrator Signature (when required) (Please return form to RPEM) Date C. Permits and Additional Requirements REQUIRED DATE COMPLETED REQUIRED DATE COMPLETED If not checked is Not Applicable If not checked is Not Applicable 404 Permit Division of Wildlife SB 40 401 Certification Wetland Finding 402 Certification APCD Bridge/Structure Demo Permit - Const Dewatering Certification Hazardous Materials (Phase II) Const Stormwater Cert CDPS 6(f) Completion Floodplains Development Permit Other D. Comments E. Environmental Project Certification All clearance and permit requirements for this project have been completed and mitigation included in the set of plans and specifications dated . The appropriate documentation is on file in the Region office. RPEM Signature Date Note to Project Manager: Any changes to the plans and specifications after the date of the RPEM signature in Part B that affect environmental impacts or mitigation must be approved by the RPEM. Distribution: Previous editions are obsolete and may not be used CDOT Form #128a 5/06 RPEM (original); copies to: Project Manager, Region Right of Way (if ROW required), Central Files Instructions for CDOT Form #128, Categorical Exclusion Determination 1. Completion of CDOT Form #128 is required for all Categorical Exclusion (CE) projects. Parts A and B must be completed for right of way authorization and obligation of federal funds. Parts A, B, C, and E must be completed prior to project advertisement. 2. FHWA signature is required for all federally funded CEs unless programmatic approval has been granted. Following signature, the FHWA will retain a copy of the 128 and return the original to the RPEM. The RPEM will be responsible for distributing copies within CDOT and maintaining the original within the Region. (Programmatic means the types of projects determined by FHWA that may be automatically excluded from FHWA category designation approval because of their type and actions and based on an evaluation using agreed upon criteria.) 3. FHWA approval may be requested for federally funded projects that are programmatically granted CE status if a 404 permit is required. The purpose for the request shall be stated in Part D, Comments. 4. If FHWA signature is not required, the RPEM will enter "N/A" on the FHWA concurrence line of Part B. 5. The project actions which qualify a project for CE designation must be entered in Part A, #1 of the 128. The designation must be taken from 23 CFR 771.117 (a) - (d) or from the current list of additional programmatic CEs approved by the FHWA. The CE designation comes from the June 24, 1998 CDOT/FHWA expanded CE list. Paragraph (a) CEs require a transmittal letter of explanation to FHWA. 6. If it is necessary for the Environmental Programs Branch to prepare a 128 for Statewide projects, the EPB manager will be responsible for clearances, certification, and appropriate distribution. 7. If project revisions change the clearance/permit requirements, revised CDOT Forms #128 and #463 are required. 8. In Part E the RPEM must indicate the set of plans and specifications (Final Office Review, advertisement, award, etc.) which were reviewed prior to certification. The date of these plans must be provided. 1 APPENDIX F PROJECT FUNDING AND FINANCE ANALYSIS The following discussion identifies potential funding and financing strategies to complete the Vine/Lemay project in the short-term and that might be expanded as a program to address the larger City-wide Railroad grade crossing projects. The identified strategies do not provide a specific financial plan, but offer a framework for developing a future financial plan as the project continues to develop. F.1 Local Funding and Financing Options This section documents local funding and financing programs and identifies those most likely to be applicable to the Vine/Lemay project and any associated development resulting from the project. Each source is briefly discussed, the revenue levels and timing are outlined, and the programs are evaluated with respect to their ability to support the Vine/Lemay project. The discussion first addresses traditional City transportation infrastructure funding sources and their current capacity to support the Vine/Lemay project, including: · Street Oversizing Program · City Sales Tax Revenues In addition to the sources listed above, local financing opportunities for the Vine/Lemay project are considered, including: · Tax Increment Financing (TIF) · Leveraging Future Local Sales Tax Revenues · Colorado State Infrastructure Bank (CO SIB) The section concludes with a matrix that describes the most likely local funding or financing sources. a. Overview of Traditional Local Sources Traditionally, the City of Fort Collins has used development impact fees and the City’s dedicated 0.25% sales tax revenues to fund infrastructure investments. This section provides an overview of these sources, their current capacity, and any issues associated with their use to fund a portion of the Vine/Lemay project. Street Oversizing Program The City’s Street Oversizing Program helps ensure that funds for street widening projects are collected and distributed where and when they are needed. As part of the program, the City requires that developers pay impact fees for street costs associated with the traffic growth the development is expected to generate. The fees are collected Citywide and placed in the Street Oversizing Fund to be used Citywide and are not dedicated to specific projects. The Street Oversizing Program only pays for the “oversized” portion of the street. Developers are required to dedicate right-of-way and construct their local access portion of arterials and collectors. Using broad percentages, the Street Oversizing Fund pays for 60% of arterial roadway costs, and 2 developers are required to construct and finance the remaining 40% (20% from either side) of the arterial abutting their property. Fee Schedule and Revenues The impact fee schedule is established each year and assessed based on the type of development and its size. For residential development, the fee is a fixed fee per dwelling unit by type of residence (single family, duplex, apartment, etc.) For commercial development, the fee is a per square foot cost based on the type of commercial use (shopping center, movie theater, day care, office, etc.) Since the City considers the benefits of street oversizing to be communitywide, the Transportation Impact Fee structure is uniform for all areas of the City. Residential building permits pay the established fee schedule; while 90% of the commercial and industrial developments use the independent fee calculation process based on the Traffic Impact Study submitted by the development. Annual impact fee revenue depends on the number and size of projects that are issued building permits each year. For FY 2012, approximately $3.2 million in transportation impact fee revenues were collected, and the average annual revenues for the last five years have been approximately $2 million as shown in Table F1. Table F1 Historic Transportation Impact Fee Revenues (FY 2008-FY2012) Annual Transportation Impact Fee Revenues FY 2012 $3,294,063 FY 2011 $1,441,107 FY 2010 $2,121,165 FY 2009 $641,491 FY 2008 $2,910,656 Average $2,081,696 Source: City of Fort Collins Comprehensive Annual Financial Reports, FY 2008 through FY 2012 Timing The impact fee is paid by developers when they receive a City of Fort Collins building permit. For transportation projects involving Street Oversizing funding, the development property contributes funds and right-of-way dedication prior to construction, so funding is received up front. City projects are required to have all funding in place prior to bidding, so funding for the developers local access portion must be received. Developers typically complete their infrastructure and are reimbursed prior to the issuance of building permits. This is a cash flow management issue for the fund. Reimbursement agreements would exaggerate the cash flow issue that the Street Oversizing Fund normally has when reimbursing for improvements prior to issuing building permits by significantly delaying revenues. 3 Potential Issues for Vine/Lemay There are state and local legislative limits on how impact fees may be used. Impact fees may not be used to correct existing deficiencies. The majority of the cost for the Vine/Lemay project would not be related to development impacts. Rather, the improvements are due to the following: · Shortage in capacity and substandard infrastructure that existed prior to 1980; and · Congestion due to current residents’ increased VMT and regional (county) growth. Additionally, the Street Oversizing Fee calculation did not include the Vine/Lemay grade separation. As a result, the use of the Street Oversizing Fund is not a viable option to pay for a portion of the Vine/Lemay project. However, there are some vacant parcels north of Vine Drive on Lemay Avenue that, upon development, would be required to build portions of Lemay Avenue in conjunction with the Street Oversizing Program. City Sales Tax The current local sales tax rate for the City of Fort Collins is 3.85%. Voters have dedicated portions of the local sales tax to funds that could be used to help pay for the Vine/Lemay capital project, including the 0.25% Building on Basics (BOB) program and the 0.85% Keep Fort Collins Great (KFCG) program. The 0.25% BOB tax was passed by voters in 2005, to fund projects that improve the quality of life in Fort Collins, including projects such as the Museum/Discovery Science Center, Lincoln Center Renovation, Harmony Road, Intersection Improvements/Signals, North College Avenue, and Timberline Road. The BOB tax revenues have provided more than $36 million toward total project costs of $65 million, and provide operations and maintenance funds for the projects for seven years. The BOB tax expires on December 31, 2015, and an extension is proposed on the April 15, 2015 ballot. The 0.85% KFCG tax was passed by voters in November 2010, and provides funding for projects through December 31, 2020. The KFCG tax revenues are allocated towards projects as follows: · 33% for street maintenance and repair; · 17% for other street and transportation needs; · 17% for police services; · 11% for fire protection and other emergency services; · 11% for parks maintenance and recreation services; and · 11% for community priorities other than those listed above, as determined by the city council. Revenues Sales tax revenue receipts depend on the volume of retail sales and the general economic condition of the City. For FY 2012, approximately $6.6 million in BOB revenues were collected, while $21.7 million in KFCG revenues were collected. The average annual BOB revenues for the last five years have been approximately $5.8 million as shown in Table F2 below; however, the KFCG revenues have only been in place since FY 2011. The City Finance Department anticipates that future sales tax revenues will increase by approximately 2% per year. 4 Table F2 Historic Sales Tax Revenues for BOB and KFCG (FY 2008 through FY 2012) Annual 0.25% BOB Revenues (expires 12/31/2015) Annual 0.85% KFCG Revenues (expires 12/31/2021) FY 2012 $6,638,228 $21,752,164 FY 2011 $5,816,587 $19,818,263 FY 2010 $5,611,156 na FY 2009 $5,191,310 na FY 2008 $5,567,128 na Average $5,764,882 $20,785,214 Source: City of Fort Collins Comprehensive Annual Financial Reports, FY 2008 through FY 2012 Timing The selection of the BOB and KFCG projects generally starts about 18 months before the election. The selection process includes internal staff research and analysis along with input from the City Council. The City Council makes the final decision on which projects make the list. The larger projects generally are identified on the ballot; however, there are some cases where more flexible programs, such as arterial intersection improvements, pedestrian plan funds, bike plan funds, etc., are included. Similarly, the language of the KFCG tax allocates 17% to other street and transportation needs. To be included in these more flexible programs, the Vine/Lemay project would need to be involved in the two-year budget cycle, which will be underway in April for FYs 2015-2016. Potential Issues for Vine/Lemay The current BOB tax is 100% committed to current projects. There is a possibility that funds allocated in 2015 for “arterial intersection improvements” could be used for Vine/Lemay; however, these funds have been informally committed to other projects. In addition, the funds available for these arterial improvements are significantly less than the costs associated with the Vine/Lemay project. If the BOB tax is extended, it would provide a source of potential funds for the Vine/Lemay project. Similarly, the KFCG tax allocates some funding for capital transportation projects. The funding from this tax is approximately $20 million per year; however, it is dedicated to certain types of investments, including 17% for other street and transportation needs (or approximately $3.4 million per year). As a result, the funds would not be able to pay for the entirety of the project, but may be a viable source for the local match to federal funds. b. Overview of Additional Local Financing Sources It is clear that the cost of the Vine/Lemay project is too great for the project to be entirely funded by the City and State in the short-term. As a result, this section will explore potential local financing options available to fund the project, including but not limited to Tax Increment Financing (TIF), Colorado State Infrastructure Bank (CO SIB), and revenue bonds (backed by sales tax revenues). 5 Tax Increment Financing The City of Fort Collins has established an Urban Renewal Authority (URA) to identify and revitalize areas of the City and to provide a funding mechanism to encourage redevelopment of these areas. The main funding tool is TIF generated through property taxes. TIF is a funding mechanism that takes advantage of anticipated increases in property values. The tax rates on property owners within the tax increment district are not raised, but rather the existing tax revenues remain dedicated to the jurisdiction and the tax revenues off of the property value increase are dedicated to a fund for the public improvements. TIF is a value capture mechanism in that it charges a fee on the incremental increase in value that results from the transportation investment. Potential Issues for Vine/Lemay The Vine/Lemay intersection is currently not within the boundaries of the City’s North College URA. Given the current political environment surrounding the URA, as well as the fact that the surrounding lands are predominately agricultural and not redevelopment sites, the City has indicated that it is unlikely the area would be included within the URA boundaries. As a result, TIF is not considered a viable funding source for the Vine/Lemay project. Leveraging Future Sales Tax Revenues Bonds backed by future BOB or KFCG revenues could be issued to help advance the construction of the Vine/Lemay project, particularly given that the costs and funding needs are greater than the annual sales tax revenues available. The City has not issued bonds backed by the BOB sales tax to date, but it has been discussed internally with City staff. Given the size of the annual BOB and KFCG tax revenues and the City’s continued and committed capital project needs, it is unlikely that the bonding capacity would add enough revenue to get the project funded at the local level without additional revenues from other local or federal sources. In addition, when considering bonding, it is important for the City to weigh the implications of leveraging future revenues for current projects, which may potentially impact the City’s ability to fund future projects. Another opportunity for leveraging sales tax revenues includes the use of these revenues to repay low- interest loans from programs such as the Colorado State Infrastructure Bank, Transportation Infrastructure Finance and Innovation Act (TIFIA), or the Railroad Rehabilitation and Improvement Financing (RRIF) Program, which are described in greater detail in the sections that follow. 6 Colorado State Infrastructure Bank State Infrastructure Banks (SIBs) were created in the 1990s as a mechanism for states to finance transportation projects. SIBs are similar to any other bank in that they can offer funds in the form of loans and credit assistance to public and private project sponsors. The banks are capitalized with federal funds and state matching funds from sources like local tax options and dedicated funds from local, state, and federal budgets. They also provide an opportunity to leverage private funds for public goods and create partnerships. In addition, multi-state banks have been created, typically for projects that cross state borders. The SIB, unlike a standard bank, is not-for-profit, and offers loans at low interest rates. To continue offering capital assistance, the SIBs rely on bonds, principal repayments, and interest and fees to generate additional funds for new projects.2 The Colorado SIB is a program that provides interest bearing loans, for a period of no longer than 10 years, to either private or public sponsors of public transit projects in the State of Colorado. It is a program designed to complement traditional Federal-aid transportation grants, thus providing projects in the State with greater flexibility in financing infrastructure projects. In order for a project to qualify for a loan from the CO SIB, it must be one of the following:3 · Commission-authorized project: includes, but is not limited to, “planning, environmental impact studies, feasibility studies, engineering, construction, reconstruction, resurfacing, restoring, rehabilitation, or replacement of a public or private transportation facility within the state” · Right of way acquisition: includes “the acquisition of real or personal property, or interests therein, for a public or private transportation facility within the state” · Federal-aid project: includes “any highway, transit, aviation, rail, or other transportation project within the state that is eligible for financing or financial assistance under state or federal law” · Maintenance project: includes any project that involves “maintenance, repair, improvement, or construction of any public or private highway, road, street, parkway, transit, aviation, or rail project within the state” · Safety project: any project that involves “the acquisition, improvement, or construction of rights-of-way, bridges, tunnels, railroad-highway crossings, drainage structures, signs, guardrails, or protective structures within this state” For a project to be eligible to receive a loan from the CO SIB, it is imperative that it does not include a facility or other transportation project that is limited to private use only. Additionally, the CO SIB has only set aside $3.8 million in its highway account, which is the maximum loan amount available for a project.4 2 Puentes, Robert, and Jennifer Thompson. "Banking on Infrastructure: Enhancing State Revolving Funds." The Brookings Institute, Sept. 2012. 3 Code of Colorado Regulations, 2 CCR 605-1 Rules and Regulation by the Colorado Department of Transportation for the Colorado State Infrastructure Bank, Rule III: Eligibility Requirements for Financial Assistance. 4 Based on a conversation with Will Ware at OFMB on March 19, 2014. 7 Potential Issues for Vine/Lemay The projected costs of the Vine/Lemay project are significantly greater than the funding currently available in the CO SIB for highway projects. However, the source could help the City leverage existing local dedicated sales tax revenues at a low interest rate as the local match to federal funds. A CO SIB loan would allow the City to help finance the local portion of the project cost without the additional expenses associated with issuing bonds. Given the limited funding currently available in the CO SIB, the application would have to clearly meet all of the committee’s criteria and objectives for highway projects. c. Summary of Local Sources (Matrix) Given the extent of the Vine/Lemay project costs, the City and State cannot fund the project in the immediate or short-term. However, in order to secure federal funding to advance the project, local funds will be required as match. Table F3 highlights the key components of the most viable local funding sources for the Vine/Lemay project. For each source it provides a description, discusses the eligibility criteria, average or typical funding levels/awards, and timing for application/receipt of funds. Table F3 is not a financial plan, but rather a menu of potential sources that could help provide a local match for the Vine/Lemay project in the short-term. 8 Intentionally Left Blank 9 Table F3 Summary of Local Funding and Financing Sources Program Description of Program Eligibility Criteria Evaluation Criteria Funding Levels and Typical Award Timeframe/Deadlines Links to Materials Dedicated Local Sales Tax Revenues The 0.25% Building on Basics (BOB) was passed by voters in 2005 and expires December 31, 2015. An extension is proposed for the April 14th ballot. The 0.85% Keep Fort Collins Great (KFCG) was passed by voters in November 2010 and expires December 31, 2020. The BOB funds projects that improve the quality of life in Fort Collins, including roadway improvements. The KFCG allocates 17% of its revenues towards other street and transportation needs. The selection of the BOB and KFCG projects generally starts about 18 months before the election. The larger projects generally are identified in the ballot; however, there are some cases where there is flexibility for types of projects such as arterial intersection improvements, pedestrian plan funds, bike plan funds, etc. For FY 2012, approximately $6.6 million in BOB revenues were collected, while $21.7 million in KFCG revenues were collected. The average annual BOB revenues for the last five years have been approximately $5.8 million To be included in these more flexible programs, the Vine/Lemay project would need to be involved in the 2-year budget cycle, which will be underway in April for 2015-16. http://www.fcgov.com/bob/ http://www.fcgov.com/kfcg/ Leveraging Future Local Sales Tax Revenues The City could potential issue bonds backed by future BOB (its potential extension) or KFCG sales taxes to fund projects in excess of annual revenues in the near-term. 10 Intentionally Left Blank 11 F.2 Federal Funding and Financing Options This section documents federal funding and financing programs and identifies those most likely to be applicable to the Vine/Lemay project and any associated development resulting from the project. Each program and its enabling legislation are briefly discussed, the funding levels are outlined, and the programs are evaluated with respect to their status and applicability. The discussion first addresses the federal programs that are most applicable to the Vine/Lemay project. These are divided into United States Department of Transportation (USDOT) programs involving capital grants and those involving loans and other forms of financing assistance as well as a potential program from the Economic Development Administration’s (EDA), including: · USDOT Grant Programs (MAP-21) o Railway-Highway Crossings Program o Highway Safety Improvement Program (HSIP) o Surface Transportation Program (STP) o Transportation Investment Generating Economic Recovery (TIGER) · USDOT Financing Programs (MAP-21) o Transportation Infrastructure Finance and Innovation Act (TIFIA) o Railroad Rehabilitation & Improvement Financing (RRIF) · EDA Public works and Economic Adjustment Assistance Programs Table F4 highlights the key components of the most viable federal funding and financing sources for the Vine/Lemay project. For each source it provides a description, discusses the eligibility criteria, average or typical funding levels/awards, and timing for application/receipt of funds. Table F4 is not a financial plan, but rather a menu of potential federal sources that could be used to help fund a portion of the Vine/Lemay project. 12 Intentionally Left Blank 13 Table F4 Matrix of Federal Funding and Financing Sources Program Federal Agency Description of Program Eligibility Criteria Qualifying Aspects of Project Funding Levels and Typical Award Matching Requirements Timeframe/Deadlines Links to Materials Railway-Highway Crossings Program FHWA/FRA The program funds safety improvements to reduce the number of fatalities, injuries, and crashes at public grade crossings. (1) The Section 130 program funds are eligible for projects at all public crossings including roadways, bike trails and pedestrian paths. Fifty percent of a State's apportionment is dedicated for the installation of protective devices at crossings. The remainder of the funds apportionment can be used for any hazard elimination project, including protective devices. In accordance with 23 USC 130(i), the funds can be used as incentive payments for local agencies to close public crossings provided there are matching funds from the railroad. Also, in accordance with 23 USC 130(h), the funds can be used for local agencies to provide matching funds for State-funded projects. Typically Section 130 projects are funded at a 90% federal share, however certain projects under 23 USC 120(c)(1) allow for up to a 100% federal share. (1) Project removes an at-grade rail crossing. FY 2013: $220M ($3.16M apportioned to Colorado) FY 2014: $220M ($3.17M apportioned to Colorado) Each state's funding level is determined based on the following: 50% is based on the formula factors for the Surface Transportation Program (STP) as in effect the day before the enactment of MAP-21, and 50% based on the number of public railway-highway crossings The Federal share is 90% Not Described A State may use up to 2% of its railway- highway crossings funds for compilation and analysis of data for the required annual report to the Secretary on the progress that is being made implementing the program. 14 Program Federal Agency Description of Program Eligibility Criteria Qualifying Aspects of Project Funding Levels and Typical Award Matching Requirements Timeframe/Deadlines Links to Materials Transportation Investment Generating Economic Recovery (TIGER) USDOT The program provides grants to surface transportation projects that will have a significant impact on the nation, a metropolitan area, or a region. Projects are awarded on a competitive basis based on the "primary" and "secondary" selection criteria outlined on the program's website. Applicants should be prepared to obligate grant funds by September 30, 2016. Eligible projects include: highway or bridge projects under Title 23, U.S.C.; public transportation projects under Chapter 53 of Title 49, U.S.C.; freight rail projects; high speed and intercity passenger rail projects; and port infrastructure investments. Applicants must detail the benefits their project would deliver for five long-term outcomes: safety, economic competitiveness, state of good repair, livability and environmental sustainability. DOT also evaluates projects on their expected contributions to economic recovery, as well as their ability to facilitate innovation and new partnerships. Eligible applicants are State, local, and tribal governments including U.S. territories, transit agencies, port authorities, MPOs, and other political subdivisions of State or local governments. Surface transportation improvements include grade- separating rail and road. Project provides user benefits by improving safety and removing congestion, thereby reducing emissions and travel times for users. 15 Program Federal Agency Description of Program Eligibility Criteria Qualifying Aspects of Project Funding Levels and Typical Award Matching Requirements Timeframe/Deadlines Links to Materials Railroad Rehabilitation & Improvement Financing (RRIF) FRA Under RRIF, loans and loan guarantees were issued to finance development of railroad infrastructure. (1) Funds could be used to acquire, improve, or rehabilitate intermodal or rail equipment or facilities, including track, components of track, bridges, yards, buildings, and shops; refinance outstanding debt incurred for the purposes already listed; and develop or establish new intermodal or railroad facilities. Eligible borrowers included: railroads, states and local governments, government sponsored authorities and corporations, joint ventures that include at least one railroad, and limited option freight shippers who intend to construct a new rail connection. (1) The infrastructure project proposes to grade- separate the railroad from the road, and the RRIF financing can be used for infrastructure projects. The program is authorized to provide loans guarantees up to $35 billion, with up to $7 billion for projects benefiting railroads other than Class 1. 33 loans have been executed at over $1.7 billion, with loan agreements totaling nearly $980 million. Colorado received a $155 million loan in 2010 under the Denver Union Station Project Authority. Direct loans could finance up to 100% of the project with repayment over 35 years and interest rates equal to the cost of borrowing to the government. 16 Intentionally Left Blank 17 F.3 Recommended Funding Approach Strategies This section discusses combinations of potential local and federal funding sources that could be pursued to advance the Vine/Lemay project and the potential issues associated with each strategy. Two project alternatives are considered in the funding approach analysis: 1) at-grade improvements and 2) a grade separated overpass. The analysis begins by summarizing the costs, funding gaps and timing issues, and potential sources to fill these gaps. Lastly, the pros and cons associated with the funding approach strategies are highlighted. Given the extent of the Vine/Lemay project costs, it will require a combination of sources to advance the project. As a result, a political champion for the project will be needed in order to garner support at the local and regional levels to get the project funded. The strength of the support largely will be based on the project’s potential benefits and impacts to the City as well as the larger region, which will need to be considered and shared with the public and potential funding partners. The competition for public funds (both local and federal) is significant, because there are many important projects out there but increasingly limited funds. As a result, the benefits and impacts associated with the Vine/Lemay project need to be effectively communicated with all potential funding partners, including City residents, which often requires a political champion. a. High Level Range of Potential Funding Approach Strategies This section summarizes potential funding approaches for the at-grade and overpass alternatives. These alternatives represent the range of potential funding that would be needed to construct improvements to the Vine/Lemay intersection, and as a result the range of potential funding sources that would be needed. The focus in this section is on identifying potential sources and combinations of sources that could be used to fund the project. The issues associated with receiving funds in time to meet construction expenditures is a concern for the project; however, once the funding sources have been secured, these funds could be leveraged through TIFIA, Grant Anticipation Revenue Vehicles (GARVEEs), or other bonding mechanisms to get the funds needed up front for construction. These financing vehicles would allow the project to be constructed in a timely manner, while repaying the loan and/or bond issue over a specified time with future, committed revenue streams. As a result, the primary focus is on identifying sources of these revenue streams for the project. Most Applicable Project Funding Sources The local and federal sources of funds discussed in this chapter that are most applicable and realistic for the Vine/Lemay project include the following: · Local: City Sales Tax (BOB or KFCG) - If the 0.25% BOB sales tax is extended, it would provide a source of potential funds for the Vine/Lemay project. In addition, approximately $3.4 million in KFCG sales tax revenues (17%) are potentially available for other street and transportation needs. As a result, the funds would not be able to pay for the entirety of the project, but may be a viable source for the local match to federal funds. · Federal: Highway Safety Improvement Program (HSIP) or Surface Transportation Program (STP) – These programs are part of the Federal-aid highway program annual appropriations. HSIP funding is specifically available for grade crossing improvements and removal of high-risk 18 at-grade crossings under the Railway-Highway Crossing Program. In addition, the program funds projects that remove hazardous road locations or any project on a public road that is consistent with the State Strategic Highway Safety Plan (SHSP). STP provides flexible funding that may be used by states and localities for projects to preserve and improve the conditions and performance of any federal-aid highway, bridge, or tunnel project on any public road, pedestrian and bicycle infrastructure, and transit capital projects. The use of these funds will require gaining support at the regional MPO level to get the project included in the region’s Transportation Improvement Program (TIP), as well the State Transportation Improvement Program (STIP). CDOT and the MPO are responsible for allocating federal-aid highway program funds to projects through the local TIP and state TIP. As a result, having a political champion to sell the benefits of the project will be particularly helpful in trying to secure these funds. Due to the competition for these funds, it is estimated that the at-grade alternative would have trouble securing these funds, while the overpass alternative likely would not receive more than $5 million; however, through continued project development and communication of project benefits, the overpass alternative could warrant the consideration of a larger funding share. · Federal: TIGER Discretionary Grant Program - The TIGER program is highly applicable to roads and rail, since its eligible categories include, among others, freight rail projects and any federally-eligible highway or bridge project. TIGER has been continued for six rounds to date and through the annual appropriations process. Future rounds depend either on year-to-year appropriations or the program’s permanent authorization in the successor to MAP-21; the President’s budget recommendation includes $1.25 billion annually for four more years. The safety and economic development components of the overpass alternative fit nicely with TIGER’s evaluation criteria due to the grade separation and removal of rail-highway conflicts; however, the competition for these funds is quite extensive. With additional local, committed funding sources, partnerships, and engineering, it would be worthwhile for the City to consider applying during future TIGER rounds. In urban areas, the minimum TIGER award is $10 million dollars, and the most competitive TIGER projects tend to keep the local match at 50%; therefore, the overpass alternative potentially could receive between $10 million and $14 million with a successful TIGER application. It is not recommended that the at-grade alternative pursue TIGER funds, because it does not remove or reduce to opportunity for rail- highway conflicts as it is currently defined. · Federal: EDA Public Works and Economic Adjustment Assistance Programs – These EDA Programs provide assistance to distressed communities to help them attract or expand businesses and generate long-term jobs. The project would be eligible under the programs because it proposes to improve an access road to a future commercial business center, thereby supporting employment growth in the region. Recent average grant awards have been approximately $1 million. As a result, the grant program could provide supplemental revenues for the project but would not be able to provide a significant contribution. Applications are competitively evaluated in quarterly funding cycles (deadlines on March 14, June 13, and October 17) and decisions generally are made within 20 business days of the funding cycle deadline. An applicant may submit an application at any time to receive feedback on the application’s competitive and technical merits. If this is an opportunity that the City would like to consider further, it is recommended that they take advantage of this ability to receive feedback on their application to determine its likelihood of success as well as if there are additional components that would better position the project for an award. 19 In addition to these funding programs, the TIFIA program could be a mechanism for the overpass alternative to leverage future revenue streams from the City sales tax and/or future federal-aid highway program funds (HSIP or STIP). A TIFIA project must be reasonably anticipated to cost at least $25 million for rural projects, and the definition of rural for TIFIA purposes includes cities of less than 250,000 population.5 Therefore, only the overpass project would be eligible for the TIFIA program. While TIFIA’s normal interest rate for secured loans can be as low as the rate on 30-year US Treasuries, 10% of TIFIA’s budget authority is set aside for rural projects at reduced interest rates to as low as one-half the Treasury rate—offering the City a competitive opportunity to leverage any secured funding streams. The potential mix of funding strategies for each alternative is discussed below. At-Grade Alternative The cost of the realignment of the at-grade Vine/Lemay intersection is estimated to be $13.6 million from planning through construction. It is assumed that the time required to complete the project (including planning and engineering) would be approximately four to five years, with most of the costs associated with construction occurring during the last two years. There are some vacant parcels north of Vine Drive on Lemay Avenue that, upon development, would be required to build portions of Lemay Avenue in conjunction with the Street Oversizing Program. The City has estimated the portion of the alternative’s costs that could be funded by the City’s Street Oversizing Program as well as the Developer’s Local Street Portion (associated with access to several currently undeveloped sites), which are summarized in Table F5. While the Local Street Portion is directly tied to the development of the adjacent parcels, if the capital project came before the development of these parcels the money would have to come from another source. However, future receipt of the Local Street Portion could be used to pay back these funds over time. Table F5 Estimated Local Developer and Street Oversizing Funds for the At-Grade Alternative ($M) Total Project Cost $ 24.60 Developer Local Street Portion $ 1.45 City Street Oversizing Portion $ 5.16 Amount Remaining to be Funded $ 17.99 Source: AECOM Cost Estimate (May 2014) and City Estimates of Street Portions After the application of these local street portion/oversizing funds, nearly $18 million in funding would still be required for the at-grade alternative. The funding approach analysis estimates that the remaining costs would have to be funded primarily through the City’s sales tax, which could be feasible based on the current assumption that the City would only be able to provide $5 million to $10 million in sales tax revenues towards the project. The options for funding the at-grade alternative with sources other than City funds are rather limited due to the current definition of this alternative. In order for the alternative to be competitive for other federal-aid highway funds or federal discretionary grants like HSIP, STP, and TIGER, train blockages must be reduced to create travel time savings, safety improvements, and emissions reduction benefits in the region. As this alternative is currently defined, it excludes relocating the rail yard that is the source of 5 Fort Collins population is 144,000 according to Census 2010. See: http://quickfacts.census.gov/qfd/states/08/0827425.html 20 these blockages and provides limited opportunity to reduce the likelihood of rail-highway conflicts. As a result, the potential benefits associated with improved traffic flow during non-blocked time periods are not likely to be significant enough to gain the support of larger funding programs such as HSIP, STP, or TIGER. In order to improve the competitiveness of the at-grade project, it is recommended that the City consider making the alternative a joint project with BNSF to move the rail yard and look for opportunities to improve BNSF operations with the implementation of the combined project. This could potentially reduce the number of trains blocking the grade crossing and improve the movement of freight in the region—generating significant community benefits in travel time savings, vehicle operating cost savings, safety improvements, and emissions reductions and making the project more attractive to the local voters, regional economic developers, and funding partners. Overpass Alternative The cost of the Lemay Avenue overpass alternative is estimated to be $26.6 million from planning through construction. It is assumed that the time required to complete the project (including planning and engineering) would be five years, with most of the costs associated with construction occurring during the last two years, as shown in Figure F1. Figure F1 Annual Construction Expenditure Flow for the Overpass Alternative Source: AECOM There are some vacant parcels north of Vine Drive on Lemay Avenue that, upon development, would be required to build portions of Lemay Avenue in conjunction with the Street Oversizing Program. The City has estimated the portion of the alternative’s costs that could be funded by the City’s Street Oversizing Program as well as the Developer’s Local Street Portion (associated with access to several currently undeveloped sites), which are summarized in Table F6. While the Local Street Portion is directly tied to the development of the adjacent parcels, if the capital project came before the development of these $0 $5,000,000 $10,000,000 $15,000,000 $20,000,000 $25,000,000 $30,000,000 Year 1 Year 2 Year 3 Year 4 Year 5 21 parcels, the money would have to come from another source. However, future receipt of the Local Street Portion could be used to pay back these funds over time. Table F6 Estimated Local Developer and Street Oversizing Funds for the Overpass Alternative ($M) Total Project Cost $ 27.60 Developer Local Street Portion $ 1.29 City Street Oversizing Portion $ 4.46 Amount Remaining to be Funded $ 21.85 Source: AECOM Cost Estimate (May 2014) and City Estimates of Street Portions After the application of these local street portion/oversizing funds, an additional $20.85 million in funding would still be required for the overpass alternative. The funding approach analysis estimates that the remaining costs potentially could be funded through a combination of the City’s sales tax, Federal HSIP/STP, TIGER, and EDA funds, due to the types of benefits and economic development impacts that could accrue to the City and larger region by removing the rail-vehicle conflicts through grade separation. While there is an opportunity for a greater variety of funding source for the overpass alternative, it is not recommended that the City pursue a wide variety of sources initially due to the complications associated with timing and getting commitments from multiple funding partners. If one funding partner backs out, the margin is tight enough that it is possible the City and remaining funding partners may not be able to make up the difference. As a result, it is recommended that the City pursue one additional federal funding source to fund a larger share of the project costs, such as TIGER. A sample funding approach strategy is summarized in Table F7, assuming a TIGER award equal to 50% of the project’s costs. Given what is known about the proposed overpass alternative, the project has the potential to be competitive in the TIGER evaluation process due to its potential for significant travel time savings, vehicle operating cost savings, safety improvements, and emissions reductions associated with the grade separation, as well as the potential of the project to facilitate economic development and provide “ladders of opportunity” for regional job growth. If the TIGER award would be closer to $10 million, the approach would still be viable given low contributions assumed from other federal funds. Table F7 Potential TIGER Funding Strategy for the Remaining Overpass Alternative Costs ($M) Federal: TIGER $ 13.80 Local: City Sales Tax Cash (new BOB/KCFG) $ 7.00 Federal: HSIP/STP/EDA $ 1.05 Total $ 21.85 Even though it appears that the project would be competitive in the TIGER evaluation process, the success rate of applications is low due to the volume of competitive projects and the limited funding available. A political champion could help improve the project’s standing in the evaluation process, but there is never a guarantee of success. If the project is not successful in winning a TIGER grant, or if it is not available to the project, then another similarly large federal funding program will have to be aggressively pursued—potentially a combination of HSIP and STP funds. If the City can contribute between $5 to $10 million towards the project from BOB/KFCG sales tax, then at least $1185 to $16.85 million in other funds would still need to be secured. This is not a small amount; however, if the project is marketed correctly and the benefits fully explored and communicated, it is not impossible. 22 b. Pros and Cons Associated with the Funding Approach Strategies The funding approaches considered for both alternatives highlight the major concern for the Vine/Lemay project: a large funding source is not readily or currently available to the City. The best source of local funds is the local option sales tax, which will need to be extended with a new voter referendum. Even with the passage of a new BOB sales tax, it is not likely to provide more than $5-$10 million towards the project, which means that between $3 million and $12 million in additional funds would still be needed to construct the project alternatives. These local funds would need to be secured before additional funding partners could be pursued to demonstrate local commitment to the project. At-Grade Alternative The at-grade alternative funding approach is relatively straightforward, as it would likely have to be funded entirely with City funds. The simplicity of the approach adds to the ease of getting it constructed due to limited project partners and requirements; however, there is also the greatest financial risk associated with this approach as it would be difficult for the City to fund it entirely from sales tax revenues. Any cost overruns or revenue shortfalls would need to be funded by the City. This project also has greater timing issues in terms of the funds being available when construction costs occur. With the City as the primary source of funding (particularly as the Developer Local Street Portion is likely to occur at the end or after construction), the project may have to wait until all the sales tax revenues are available, which could take several years. If the City would like to advance the construction of the project before all funds are in hand, they will have to issue bonds backed by the BOB sales tax because Federal financing programs such as TIFIA would not be available to the at-grade alternative due to the lower cost and lower competitiveness of the project benefits. The City has not issued bonds backed by the BOB sales tax to date, but it has been discussed internally with City staff. The City would have to weigh the implications of leveraging future revenues for current projects, which may impact the City’s ability to fund future projects. Overpass Alternative The overpass alternative has a higher cost, however, it also offers a more varied funding approach due to the opportunity to competitively pursue non-City funding, including Federal HSIP/STP, TIGER, and EDA funds. The alternative more closely aligns with regional goals for reduced rail-highway conflicts and improved access to economic development sites, which are attractive to regional and federal funding partners. The removal of rail-highway conflicts with the overpass alternative would result in significant travel time savings, vehicle operating cost savings, safety improvements, and emissions reductions associated with grade separation. While additional funding sources are available to the overpass alternative, it would still need to rely heavily on City sales tax revenues to construct the project due to the scale of the investment and the local match requirements associated with federal funds. While there are several federal funding sources that the overpass alternative could pursue, it is recommended that the City begin by trying to attract funding from one larger federal program such as HSIP, STP, or TIGER. Initially pursuing one larger program would allow the City to minimize the difficulties associated with managing and getting firm commitments from numerous funding partners. As the project moves through the planning and development process, additional beneficiaries and funding partners could be identified and pursed to fill in any remaining gaps in project funding. A political champion for the project also could help identify these additional beneficiaries and garner the 23 necessary support at the local, regional, and federal levels. The benefits and impacts associated with the Vine/Lemay project will need to be effectively communicated with all potential funding partners, including City residents, and a strong political champion can help deliver this essential message. The issues associated with receiving funds in time to meet construction expenditures is a concern for the alternative; however, it is not as great of a concern as the at-grade alternative. Once the funding sources have been secured, these local and federal funds could be leveraged through TIFIA, Grant Anticipation Revenue Vehicles (GARVEEs), or other bonding mechanisms to get the funds needed up front for construction. These financing vehicles would allow the project to be constructed in a timely manner, while repaying the low interest loan and/or bond issue over a specified time with future, committed revenue streams. ÄÄÄ EXHIBIT 2 - 30% DESIGN PLANS FOR EAST VINE DRIVE RELOCATION (SUNIGA DRIVE) G1 6 26 G2 7 26 I1 22 26 I2 23 26 I3 24 26 I4 25 26 I5 26 26 26 PP1 8 26 PP2 9 PRELIMINARY PLANS NOT FOR CONSTRUCTION 26 PP3 10 26 PP4 11 26 PP5 12 26 PP6 13 26 PP7 14 26 PP8 15 26 PP9 16 26 PP10 17 26 PP11 18 26 PP12 19 26 PP13 20 26 PP14 21 26 T1 2 U1 3 26 U2 4 26 U3 5 26 Improved Condition SUNIGA/LEMAY MULTI-MODAL AND FREIGHT CONNECTIVITY PROJECT June 4, 2015 Existing Condition EXHIBIT 3 Improving Access and Quality of Life for All SUNIGA/LEMAY MULTI-MODAL AND TIGER Discretionary Grant Application FREIGHT CONNECTIVITY PROJECT Table of Contents APPLICATION LETTER ........................................................................................i EXECUTIVE SUMMARY ......................................................................................1 A. PROJECT DESCRIPTION .................................................................................4 B. PROJECT LOCATION .......................................................................................6 C. PROJECT PARTIES ...........................................................................................9 D. GRANT FUNDS & SOURCES ...........................................................................9 E. SELECTION CRITERIA .....................................................................................11 I. PRIMARY SELECTION CRITERIA ...........................................................11 a. STATE OF GOOD REPAIR ............................................................11 b. ECONOMIC COMPETITIVENESS ................................................14 c. QUALITY OF LIFE ........................................................................14 d. ENVIRONMENTAL SUSTAINABILITY ..........................................19 e. SAFETY ........................................................................................19 II. SECONDARY SELECTION CRITERIA ......................................................21 a. INNOVATION .............................................................................21 b. PARTNERSHIP ............................................................................23 F. RESULTS OF BENEFIT/COST ANALYSIS ...........................................................24 G. PROJECT READINESS AND APPROVALS ........................................................25 H. FEDERAL WAGE RATE CERTIFICATION ..........................................................29 I. SUMMARY OF DIFFERENCES FROM PRE-APPLICATION.......................................30 APPENDIX (ATTACHED SEPARATELY) A. Mountain Vista SubArea Plan B. Project Development Report C. Benefit/Cost Analysis D. Letters of Support -Senator Michael F. Bennet, Colorado -Senator Cory Gardner, Colorado -Congressman Jared Polis, 2nd District Colorado -Gregory E. Dunaway, AVP Engineering Services, BNSF Railway -Darin Atteberry, Fort Collins City Manager -Terri Blackmore, Executive Director, North Front Range MPO -Marc Engemoen, Public Works Director, Larimer County -David May, President & CEO, Fort Collins Area Chamber of Commerce -Matt Robenalt, Executive Director, Downtown Development Authority -Julie Brewen, CEO/Executive Director, Fort Collins Housing Authority -Olga Duvall, Chair, Fort Collins Transportation Board Improving Access and Quality of Life for All | i SUNIGA/LEMAY MULTI-MODAL AND TIGER Discretionary Grant Application FREIGHT CONNECTIVITY PROJECT June 4, 2015 Secretary Anthony Foxx U.S. Department of Transportation 1200 New Jersey Ave, SE Washington, DC 20590 Subject: TIGER Grant Application for the Fort Collins, CO - Suniga/Lemay Multi-Modal and Freight Connectivity Project Dear Secretary Foxx: The City of Fort Collins, Colorado is pleased to submit this application for the Department of Transportation’s National Infrastructure Investments under the Consolidated and Further Continuing Appropriations Act, 2015. The Suniga/Lemay Multi-Modal and Freight Connectivity Project is the end product of collaboration and partnerships between the City of Fort Collins, Larimer County, Downtown Development Authority, the Poudre School District, Burlington Northern Santa Fe (BNSF) Railway, the North Front Range Metropolitan Planning Organization, major landowners, major existing and future employers in Fort Collins, project site neighbors, and the general public. The City’s planning process leadership manifests itself in strong support for the proposed improvements and clear and consistent support for the long-term vision supported by the proposed improvements. This application requests funding to support a grade separation of the BNSF Railway and Lemay Avenue intersection located northeast of Downtown Fort Collins. The full project cost is $27 Million, of which $17 Million, or 63%, is requested of the TIGER program. The remaining $10M (37%) would be funded through a combination of public and private sources. The proposed improvements have been identified as a result of 30 years of community planning. This project plays a critical role in providing vital and urgent transportation infrastructure necessary to address current and anticipated needs. It embodies TIGER’s emphasis on Ladders of Opportunity through building infrastructure that will increase connectivity to employment, education and other services, contribute to community revitalization and enhance the quality of life of existing and future residents. TIGER funding for the proposed improvements makes possible subsequent local government and private sector land development investments that will guide community revitalization and economic opportunity in the region over the next 25 years. The proposed improvements are vital early components linked to the City’s Mountain Vista SubArea Plan. Together, the Mountain Vista SubArea Plan and more recent Project Development Report provide the catalyst for: • Community Revitalization: One of the fundamental aims of this project is to complete critical transportation improvements that will enhance connectivity for underserved neighborhoods. Residents of both the Alta Vista and Andersonville neighborhoods (located at the Vine/Lemay intersection) suffer from the constraints of severe congestion on a daily basis. This limits connectivity to employment, schools, goods and services. • Diverse Housing and Employment Opportunities: This project will help facilitate the development of new housing and employment opportunity in a priority infill area near downtown Fort Collins. In recent years, this area has become the focus of increased economic activity, including the recent construction of the Woodward, Inc. Corporate Headquarters (1,700 employees) along Improving Access and Quality of Life for All | ii SUNIGA/LEMAY MULTI-MODAL AND TIGER Discretionary Grant Application FREIGHT CONNECTIVITY PROJECT Lemay Drive. Safe and efficient transportation connections are necessary to sustain this new growth. • Multi-modal Connectivity and Safety: A primary emphasis of this project is to foster a safe, connected, resilient and accessible system for all modes of travel. This project is a critical part of the City’s Enhanced Travel Corridor network, which is intended to provide a system of multi-modal corridor connections between key activity centers, access to high frequency transit service and bicycle and pedestrian facilities. • Commerce and Accessibility Improvements: The existing Vine/Lemay intersection, which includes the BNSF Railway crossing, is severely congested, with limited options to expand through or turn capacity due to land use constraints. Construction of a grade separated configuration will help alleviate congestion along existing roadways and the BNSF rail corridor, which in turn helps improve rail operations and the overall ability to move goods and services efficiently. The transportation improvements identified in this application were part of an application submitted in the 2013 TIGER funding cycle under the title “Vine/Lemay Project.” Since that time, the City has taken a number of proactive steps to advance the environmental, design and funding processes for the project, and has narrowed the project scope. The new project, Suniga/Lemay Multi-Modal and Freight Connectivity Project, focuses on the grade separation of Lemay at the BNSF (the City renamed the new Vine Drive to “Suniga Drive” in early 2015). Recent project advancements over the past two years include the following: • The City published a detailed Project Development Report including an alternatives screening and environmental analysis process in September 2014. • The City appropriated 1 Million dollars in 2015 funds to advance final design of the project • The City and the BNSF have a long-standing partnership and have constructed numerous safety and freight reliability improvements throughout Fort Collins. The BNSF will contribute 5% of the theoretical cost of the grade separation as specified in 23 CFR 646.210. This demonstrates their commitment to address the City’s #1 transportation capital improvement project. • The City has secured half of the right-of-way along the Lemay Avenue realignment and is in active negotiations for the remainder of the right-of-way, which will help streamline future construction. • The City is securing developer local street obligation funds to contribute to this project. The project schedule focuses on the primary goal of having all pre-construction activities completed to allow for obligation of construction funds by March of 2017 at the latest, and if alternative delivery is selected, this obligation could be as early as September 2016. Enclosed is the City of Fort Collin’s grant application and supporting information referenced in the submittal. If additional information is needed for your consideration, please contact Dean Klingner, P.E., Civil Engineer, City of Fort Collins, 970-221-6511, dklingner@fcgov.com. The City would be pleased to provide additional details about the project and the rationale for TIGER grant funding. Sincerely, Rick Richter Rick Richter Director of Infrastructure Services City of Fort Collins Improving Access and Quality of Life for All | 1 SUNIGA/LEMAY MULTI-MODAL AND TIGER Discretionary Grant Application FREIGHT CONNECTIVITY PROJECT EXECUTIVE SUMMARY The Suniga/Lemay Multi-Modal and Freight Connectivity Project is the end product of 30 years of collaboration and partnerships between a full range of public and private sector entities. The City’s leadership manifests itself in strong support for the proposed improvements and land use planning. Each improvement plays a critical role in providing vital and urgent transportation infrastructure necessary to address current and anticipated needs. TIGER funding for the proposed improvements helps leverage local government and private sector land development investments that will guide economic development in the region over the next 25 years. The proposed improvements are vital early components linked to the City’s Mountain Vista SubArea Plan. Together, the Mountain Vista SubArea Plan and the proposed “enabling infrastructure” investments provide the catalyst for: • Community Revitalization: Facilitates the transportation connectivity necessary to revitalize existing disadvantaged and underserved neighborhoods and link to employment citywide, thereby improving quality of life. • Diverse Housing and Employment Opportunities: Directs new development and employment to a priority infill area near downtown. • Multi-modal Connectivity and Safety: Fosters a safe, connected resilient and accessible system for all modes of travel. • Commerce and Accessibility Improvements: Alleviates congestion along the BNSF rail corridor to help enhance operations and the overall ability to move goods and services. A variety of quotes from the Mountain Vista SubArea Plan are presented in this application. The plan itself is presented at Appendix A. Submittal Highlights State of Good Repair Vine Drive and Lemay Avenue are in a poor state of repair characterized by deficient bridges, substandard conditions and accelerating deterioration caused by increasing truck and automobile volumes. Neither roadway meets City standards for their current roadway designations or their existing and projected traffic volumes. This project would improve the resiliency of the Improving Access and Quality of Life for All | 2 SUNIGA/LEMAY MULTI-MODAL AND TIGER Discretionary Grant Application FREIGHT CONNECTIVITY PROJECT Economic Competitiveness One of the fundamental aims of this project is to complete critical improvements that will increase opportunity for economic growth. If no improvements are made in the near future, the existing sub-standard roadway network will continue to deteriorate and unmanageable congestion will increase. This delay and the related impacts will deter private sector investment and the expansion of existing economic enterprises and activity under both short-term and long-term scenarios. These conditions will make it difficult for the City to attract new enterprises, and may cause some enterprises to relocate entirely, fueling a cycle of economic downturn. Quality of Life and Sustainability The proposed improvements will enhance conditions at two historic residential areas, reduce congestion, and make the entire area more accessible. The project will enhance modal connectivity and improve accessibility and transport for economically disadvantaged populations. Life-cycle analysis is integrated into the City’s Asset Management Program and contract requirements along with Value Engineering (VE). Survey results collected as part of the 2009 Pedestrian Plan indicated that both Vine Drive and Lemay Drive rank in the top three least favorite places to walk in the City of Fort Collins. Figure 1: Illustration of the Proposed Lemay Grade Separation over BNSF and Vine Drive Safety The proposed improvements address substantive safety issues by replacing non- standard facilities and replacing an at grade railroad crossings with a grade separated facility. Innovation The project is a model of innovative project delivery. The project has been innovative from the beginning, including a highly collaborative and accelerated project delivery. The project will include features that reduce capital and long-term costs, protect the environment, improve mode choice and safety, and preserve long-term multi-modal benefits. Partnership The Suniga/Lemay Multi-Modal and Freight Connectivity Project is the end product of 30 years of collaboration and partnerships between a full range of public and private sector entities. The City’s leadership manifests itself in strong support for the Improving Access and Quality of Life for All | 3 SUNIGA/LEMAY MULTI-MODAL AND TIGER Discretionary Grant Application FREIGHT CONNECTIVITY PROJECT Project Readiness and Approvals This project has been envisioned and included in major City transportation plans for over 30 years. This extensive and long range planning would provide immediate improvements in mobility and access for existing neighborhoods, and would maximize the potential for integrated land use and transportation as the area grows and develops over time. The City has advanced the project design by completing conceptual design and an alternatives analysis in 2014, as well as appropriating $1M in funding in 2015 to advance the design and right-of-way review. The Vine/Lemay Project Development Report (published in September 2014) provides a robust description of the purpose and need, range of alternatives and environmental impacts. This study will assist in streamlining future NEPA clearance as federal funding becomes available. The project is currently envisioned to be delivered using traditional design-bid- build approach, however if phasing of the improvements becomes critical the City is prepared to deliver via an innovative Contractor Manager/General Contractor (CMGC) method or Design- Build (DB) method. These alternative delivery methods would be considered if they are determined to appropriately manage risk for cost, schedule, and quality. The table below shows the cost breakdown of the major project components. The table below shows the approximate sources of local funding which constitute $10M toward the overall $27M project. In addition to the local funding sources above, BNSF is committed to contributing 5% of the grade separation cost. The exact dollar amount will be confirmed in the coming months. The table below outlines anticipated benefits of the project with associated metrics. The calculated regional output for the project is $46M. The regional earnings would be $13.3M. Benefit Category Measured Benefit Travel Time Savings, Total Delay Reduction 23,157 hours per year $466,614 per year Total Crash Reduction Cost Savings $173,570 per year Fuel Savings 32,224 gallons per year Improving Access and Quality of Life for All | 4 SUNIGA/LEMAY MULTI-MODAL AND TIGER Discretionary Grant Application FREIGHT CONNECTIVITY PROJECT A. PROJECT DESCRIPTION The project involves the realignment of Lemay Avenue and construction of a new bridge over the railroad and Vine Drive, which directly parallels the railroad. This new bridge will allow existing Vine Drive to be reduced to a collector street with a more robust arterial and multi- modal version of Suniga Drive constructed approximately one thousand feet to the north, thereby eliminating the at-grade railroad crossing, and associated safety and congestion effects of an intersection and roadway directly adjacent and parallel to the railroad. The City of Fort Collins will provide 37 percent ($10 Million) of the $27 Million project cost with the balance ($17 Million) requested of the TIGER program. The source of the local funds comes from a dedicated City appropriation to the project, City General Fund monies, BNSF contribution, developer obligation, and partner agency funds. Although the Colorado Public Utilities Commission could ultimately require three grade-separated railroad crossings in this area (per the Mountain Vista SubArea Plan), the top priority for a grade separation is at the BNSF/ Lemay Railroad crossing. Both the Union Pacific Railroad (UPRR) and BNSF railroad lines serve the northeast portion of Fort Collins. Their operations include a shared railroad switching yard along the existing Vine Drive between Lemay Avenue and Timberline Road, and a UPRR switching yard along Riverside Avenue between Mulberry Street and Lincoln Avenue. Both are secondary lines providing additional capacity to other BNSF and UPRR railroad facilities in Weld County. The existing at grade crossing at the Vine/Lemay intersection operates at Level of Service F conditions on a regular basis. This occurs primarily when long, slow-moving trains impede north/south traffic flow as they pass through the intersection. Long queues on Lemay often prohibit residential ingress and egress north and south of Vine. The grade separation would delay the need for the other grade separations while allowing a substantial amount of planned development to occur and associated infrastructure funding to accrue. Specifically, the new development would help cover costs for the remaining improvements as development occurs. Improving Access and Quality of Life for All | 5 SUNIGA/LEMAY MULTI-MODAL AND TIGER Discretionary Grant Application FREIGHT CONNECTIVITY PROJECT The project will help facilitate connectivity for all modes of travel, including enhancements for bicyclists, pedestrians and transit users. Enhanced Bicycle Travel The City’s 2014 Bicycle Master Plan integrates best practices and innovative thinking to develop a comprehensive set of strategies for safe and comfortable bicycling citywide. As part of the plan, all streets proposed with this project (existing Vine, Lemay and Suniga) will incorporate state of the art bicycle facilities based on the concept of improving safety, comfort and accessibility for cyclists of all ages and skill levels. Transit Accommodations Bus Route 8 currently serves the western edge of this subarea and runs through northeast Fort Collins via Vine Drive, Lemay Avenue, Conifer Street and College Avenue. This route provides connections to the River District, the Larimer County Department of Human Services, the North College Corridor, and Old Town Fort Collins. This project is currently envisioned to be delivered using traditional design-bid-build approach, however if phasing of the improvements becomes critical the City is prepared to deliver via an innovative Contractor Manager/General Contractor (CMGC) method or Design-Build (DB) method. These alternative delivery methods would be considered if they are determined to appropriately manage risk for cost, schedule, and quality. In summary, these improvements have been identified as a result of 30 years of community planning. The project plays a critical role in providing vital and urgent transportation infrastructure necessary to address current and anticipated needs. This project has garnered a broad range of support from the congressional level to the local level. Letters of Support, provided in Appendix D, include the following: Senator Michael F. Bennet, Colorado Senator Cory Gardner, Colorado Congressman Jared Polis, 2nd District Colorado Gregory E. Dunaway, BNSF Railway Darin Atteberry, Fort Collins City Manager Terri Blackmore, Executive Director, North Front Range MPO Marc Engemoen, Public Works Director, Larimer County David May, President & CEO, Fort Collins Area Chamber of Commerce Matt Robenalt, Executive Director, Downtown Development Authority Improving Access and Quality of Life for All | 6 SUNIGA/LEMAY MULTI-MODAL AND TIGER Discretionary Grant Application FREIGHT CONNECTIVITY PROJECT B. PROJECT LOCATION The project is located within the 1,500 acre Mountain Vista SubArea, a primarily undeveloped area within the northeast portion of the City of Fort Collins, Colorado. The national, state, regional and local settings of the proposed improvements are presented in Figures 2-5. The Mountain Vista SubArea is projected to accommodate a significant portion of Fort Collins’ future growth. Figures 2-5 clarify the strategic importance of the project area relative to the Interstate system, Colorado’s state highway system and the planning and development conditions in Fort Collins. Importance to the Region and Community Investment in the proposed project is necessary for the health and continued prosperity of Downtown Fort Collins and management of the City’s and Colorado’s economic growth. This grade separation of BNSF/ Lemay is part of the City’s larger strategy to revitalize existing neighborhoods, provide more efficient and direct access to employment, and improve quality of life for existing and future residents. Federal funding for the anticipated improvements is critical because strong, smart and phased growth in this area is constrained by “enabling” infrastructure with costs that exceed the capacity of traditional, innovative and private sector funding mechanisms in place in Fort Collins. 80 25 76 70 70 25 Fort Collins Denver  WYOMING UTAH Improving Access and Quality of Life for All | 7 SUNIGA/LEMAY MULTI-MODAL AND TIGER Discretionary Grant Application FREIGHT CONNECTIVITY PROJECT Figure 4: Mountain Vista Framework Plan Improving Access and Quality of Life for All | 8 SUNIGA/LEMAY MULTI-MODAL AND TIGER Discretionary Grant Application FREIGHT CONNECTIVITY PROJECT PROPOSED GRADE SEPARATED RAIL CROSSING OTHER FUTURE GRADE SEPARATED RAIL CROSSING STREET (EXISTING) STREET (PROPOSED) RAILROAD INTERSTATE LEGEND Vicinity Map 25 ANDERSONVILLE NEIGHBORHOOD WOODWARD, INC. CAMPUS ALTA VISTA NEIGHBORHOOD VINE DRIVE EXISTING SUNIGA DRIVE LEMAY AVE. . LINDENMEIR R D. N COLLEGE AVE. TIMPBERLINE DR. MOUN BNSF SWITCHING YARD TAIN VISTA DR. 2 3 1 ANHEUSER BUSCH N Improvement Grade Separation of the Vine/ Lemay RR Intersection 2 Proposed Suniga Drive from College to Lemay Proposed Suniga Drive from Lemay to Timberline CSU DOWNTOWN FORT COLLINS 1 3 REALIGNED LEMAY *Future development (not included as part of this funding request) * * Figure 5: Vine/Lemay Intersection Local Context Map Improving Access and Quality of Life for All | 9 SUNIGA/LEMAY MULTI-MODAL AND TIGER Discretionary Grant Application FREIGHT CONNECTIVITY PROJECT C. PROJECT PARTIES The project is the end product of collaboration and partnerships between the City of Fort Collins, Larimer County, CDOT, utilities, the Poudre School District, BNSF Railroad, the North Front Range Metropolitan Planning Organization, major landowners, major existing and future employers in Fort Collins (Anheuser Busch and Woodward), project site neighbors, and the general public. The City’s planning process leadership manifests itself in strong support for the proposed improvements and clear and consistent support for the long-term vision supported by the proposed improvements. Please refer to Appendix D for letters of support. D. GRANT FUNDS & SOURCES This project proposes a grade separation of the Vine/Lemay Intersection with a realignment of Lemay Avenue to the east (see Figure 6). The following table shows the total cost of project improvements ($27M), of which $17M (63%) is requested of the TIGER Discretionary Grant program. Improvement Cost Grade Separation of the Vine/ BNSF/ Lemay Intersection $ 12M Construction of Four-Lane Arterial Roadways $ 8M Bicycle/Pedestrian Facilities and Landscaping $ 6M Neighborhood Street (Local Street) Construction $ 1M $ 27M The following table shows the sources of local funding which constitute $10M (37%) of the $27M project. In addition to the local funding sources above, BNSF is committed to contributing 5% of the grade separation cost. The exact dollar amount will be confirmed in the coming months. Local Funding Sources Cost 1. City of Ft. Collins 2015 Appropriation to Project $ 1M 3. Street Over-sizing $ 5M 4. Local Street Developer Obligation $ 1.5M 5. City General Fund $ 2.5M TOTAL $ 10M Improving Access and Quality of Life for All | 10 SUNIGA/LEMAY MULTI-MODAL AND TIGER Discretionary Grant Application FREIGHT CONNECTIVITY PROJECT Figure 6: Proposed Project Design Improving Access and Quality of Life for All | 11 SUNIGA/LEMAY MULTI-MODAL AND TIGER Discretionary Grant Application FREIGHT CONNECTIVITY PROJECT E. SELECTION CRITERIA I. Primary selection criteria The proposed improvements are a high priority for the state, region and local communities. The long term outcomes of investing TIGER funding for construction of the project are in direct alignment with the TIGER grant goals. The long-term outcomes, or benefits, are measurable and significant. The following discussions describe and quantify long-term benefits of this project. a. State of Good Repair i. The project is part of and consistent with relevant state, local or regional efforts to maintain transportation facilities in a state of good repair. Vine Drive and Lemay Avenue are in a poor state of repair characterized by deficient bridges, substandard conditions and accelerating deterioration caused by increasing truck and automobile volumes. Structures along Vine Drive are over 60 years old. Structures along Lemay Avenue are over 45 years old. Two bridges along these roads are functionally obsolete due to inadequate width and are in a state of rapid deterioration. Neither roadway meets City standards for their current roadway designations or their existing and projected traffic volumes. The existing street network in the project area lacks basic facilities for pedestrians and continuous routes for bicycles creating an unsafe and discouraging environment for these modes of travel. The existing at grade Vine/Lemay intersection fails to meet current standards and operates with failing levels of service due to capacity and long, slow trains passing through the intersection. Existing intersection design deficiencies include: • Level of Service F traffic operations • Lack of auxiliary lanes • Small turning radii requiring Jersey barriers for protection Photo 1: Vine/Lemay Intersection Looking West Photo 2: Vine/Lemay Intersection Looking Northeast at Jersey Barriers and Lack of Pedestrian and Bicycle Facilities and a Lack of Turning Lanes Photo 3: Vine/Lemay Intersection Looking West at Traffic Operations and Congestion Improving Access and Quality of Life for All | 12 SUNIGA/LEMAY MULTI-MODAL AND TIGER Discretionary Grant Application FREIGHT CONNECTIVITY PROJECT • Lack of adequate facilities for pedestrians, and inadequate, discontinuous facilities for cyclists Photos 1-5 clarify existing conditions. The project will replace existing pavements with 30-year design life pavement. The inadequate bridges will be replaced with structures with a design life of 75 years. The new infrastructure will allow safe travel for autos, commercial trucks, public transit, bicyclists and pedestrians while meeting estimated traffic demands through 2035. ii. The project will rehabilitate, reconstruct and upgrade a current surface transportation project that threatens future economic growth and stability due to its poor condition. Investment in this project is inherently necessary for the continued viability and resiliency of the transportation network in the greater Fort Collins area and management of Colorado’s economic growth. If left unimproved, the poor condition of the roadway network will threaten future transportation efficiency, mobility of goods and people and economic growth. This project directly addresses those concerns. In addition, it would improve the ability to withstand the occurrence of an emergency or major disaster by grade separating roadway from rail operations, and by creating a more direct and efficient link for entry and exit into the heart of downtown. TIGER grant funding is needed to supplement City funding programs. Without supplemental funding for the project, existing residents and employees of businesses in the vicinity will suffer from inadequate infrastructure for all modes and unnecessary delays due to rail movements. This funding and timing gap will allow accelerated deterioration of these roadways and will encourage unplanned growth in agricultural areas away from the City Center. State Benefits Colorado’s roadway network has deteriorated and a lack of funding for improvements is a serious impediment to economic growth and future development. The economic health of Fort Collins, Colorado’s 5th largest City, is a key contributor to the economic health of Colorado as a whole. Investment in the project will strengthen the interdependent national, state and local roadway network by enhancing offline roadway conditions and critical system interconnectivity. Regional Benefits North Central Colorado and Larimer County, especially the northeast region of Fort Collins, face growth pressures that require coordinated land use planning and critical infrastructure investments that are beyond existing local and state funding capabilities. The roadway system to Improving Access and Quality of Life for All | 13 SUNIGA/LEMAY MULTI-MODAL AND TIGER Discretionary Grant Application FREIGHT CONNECTIVITY PROJECT of Lemay Avenue. The roadway network and the lack of capacity along Vine Drive and Lemay Avenue and through the Vine/Lemay/BNSF intersection create long-term gaps in the regional roadway network. The planned improvements would substantially enhance system resiliency and interconnectivity while reducing roadway delays. Local Community Benefits Plans for grade separating Lemay Avenue from the BNSF Railroad, have been developed for over the last 30 years by the City of Fort Collins and regional partners. The City of Fort Collins ensures that all parts of the City are served by an adequate, robust, and multi-modal transportation network through policy tools such as the Adequate Public Facilities Ordinance. Without Federal funding, the City is at risk of being forced to deny development proposals in the Mountain Vista master-planned area of northeast Fort Collins because Vine Drive, Lemay Avenue and the Lemay/BNSF crossing do not pass the City’s “minimum level of service criteria” in their existing condition of disrepair. One of the fundamental aims of this project is to complete critical improvements that will enhance connectivity for existing underserved neighborhoods and increase opportunity for economic growth. Residents of both the Alta Vista and Andersonville neighborhoods (located at the Vine/Lemay intersection) suffer from the constraints of congestion. Community outreach confirms that many struggle with egress from their neighborhoods on a consistent, daily basis due to traffic back-ups along Lemay. This limits connectivity to employment, schools and goods and services. The community of Fort Collins has established a strong economic foothold, and has adopted plans for future residential, commercial and industrial growth that is infeasible without the project. If no improvements are made in the near future, the existing sub-standard roadway network will continue to deteriorate and unmanageable congestion will increase. This delay and the related impacts will deter private sector investment and the expansion of existing economic enterprises and activity under both short-term and long-term scenarios. These conditions will make it difficult for the City to attract new enterprises, and may cause some enterprises to relocate entirely. iii. The project is appropriately capitalized up front and uses asset management approaches that optimize long-term cost structure. Funding for City infrastructure is rooted in Improving Access and Quality of Life for All | 14 SUNIGA/LEMAY MULTI-MODAL AND TIGER Discretionary Grant Application FREIGHT CONNECTIVITY PROJECT b. Economic Competitiveness This project brings multiple benefits. The primary benefit is for the local community – both in improving access and creating ladders of opportunity related to job growth. This project will help revitalize the area, and will improve the community’s local and regional access to employment, education and goods and services. The grade separation will alleviate congestion and delays, thereby enhancing long-term efficiency and reliability in the transportation network. This is crucial for the two neighborhoods closest to the intersection, who will benefit from decreased travel time and transportation costs due to existing delays. In addition, the project will increase the economic productivity of the larger area, which is situated northeast of Downtown in a traditionally underserved area. In recent years, this area has become a focus of new economic activity, as reflected in the current construction of the Woodward, Inc. Corporate Headquarters along Lemay Drive south of the Vine/Lemay intersection. Woodward’s campus will house between 600 and 700 employees on opening day (late 2015) and will gradually ramp up to approximately 1,700 employees. This project will enhance employee access to the campus, and will help alleviate congestion pressures along Lemay Drive. Finally, the project will facilitate efficient and reliable freight movement through removing an at-grade crossing of the BNSF Railroad. This improvement will help boost economic productivity and efficiency in the moving of goods and services, while enhancing safety for all modes of transportation and for all users. A full benefit cost analysis is included as Appendix C. In summary: • The project will improve long-term efficiency, reliability and cost-competitiveness in the movement of workers and goods. • The project will make improvements that allow for new investments in expansion, hiring, or other growth of private sector production in economically distressed areas. • The City will strive to ensure that a reasonable balance between employment and housing is maintained as well as a balance between basic and non-basic jobs. The primary intent is to create a relative balance between the wages generated by various types of employment and housing prices. The primary intent of this project is to provide Ladders of Opportunity which increase connectivity, support workforce development Improving Access and Quality of Life for All | 15 SUNIGA/LEMAY MULTI-MODAL AND TIGER Discretionary Grant Application FREIGHT CONNECTIVITY PROJECT ii. The project will enhance modal connectivity and reduces congestion on existing modal assets. The existing roadway network is failing to meet current travel demands, in particular the Level of Service at the intersection of Vine and Lemay is rated ‘F’, with daily delays during peak traffic exacerbated by freight rail operations. The congestion is causing changes to travel behavior that are inefficient and adversely affecting regional travel. Recent figures specific to the Union Pacific rail crossing at Vine and Riverside Drives (in close proximity to the project area) indicate that over a 7 year period between 2007 and 2014, the duration of preemptions increased approximately three minutes. The number of preemptions longer than 15 minutes increased from 10 (in 2007) to 86 (in 2014) and the longest duration between 6:00 AM and 6:00 PM increased from approximately 22 minutes to 1 hour 11 minutes. All of these figures demonstrate a trend that the City is experiencing at rail crossings citywide, including the Vine/ Lemay intersection. By grade separating the Vine/BNSF/Lemay intersection and realigning Lemay, not only will congestion be reduced, but there will also be benefits related to changes in travel patterns that will result in higher efficiency and reduced congestion throughout the transportation system. iii. The project will improve accessibility and transport for economically disadvantaged populations, non-drivers, senior citizens and persons with disabilities and will make goods, commodities, and services more readily available to these groups. The single-family neighborhoods of Alta Vista and Andersonville are located immediately adjacent to the Lemay/BNSF intersection. These historic neighborhoods are currently occupied by a primarily Hispanic population with lower average household incomes than other neighborhoods within the City of Fort Collins. The Alta Vista neighborhood contains the northernmost collection of historic adobe structures in North America. This culturally and historically important neighborhood is one of the original groups of residences associated with the former sugar beet industry in Fort Collins, which was prosperous from the turn of the century through World War II. The neighborhood is eligible for designation as Fort Collins Landmark, and is eligible for listing in the National Register of Historic Places and the Colorado State Register of Historic Places. The primary access to both of these Improving Access and Quality of Life for All | 16 SUNIGA/LEMAY MULTI-MODAL AND TIGER Discretionary Grant Application FREIGHT CONNECTIVITY PROJECT This project has emerged as a vital component of a series of planning processes and outcomes including: • East Vine/Lemay Intersection Realignment Project Development Report (2014) • City of Ft. Collins Bicycle Plan (2014) • Lincoln Corridor Plan (2014) • Pedestrian Plan (2011) • Plan Fort Collins (2011) • City Plan (2011) • City of Fort Collins Master Street Plan (2011) • City of Fort Collins Capital Improvement Plan (2011) • Mountain Vista Sub-Area Plan (2010) • Suniga 30% Design Plans (2009) • Transport Strategic Operating Plan (2009) • Northside Neighborhoods Plan (2005) • I-25 Corridor Plan (2001) • Larimer County Master Plan (1997) The Mountain Vista subarea plan is the guiding policy document to implement a community- based vision. In Fort Collins, a “SubArea Plan” provides a framework of community-based principles, policies and implementation strategies recommended by the Planning & Zoning and Transportation Boards and adopted by City Council. The Mountain Vista Subarea Plan represents a strong framework between land use and transportation, and direct link to the Transportation Master Plan and City Plan (the comprehensive plan for Fort Collins). Thus, the Mountain Vista Subarea Plan is an element of City Plan and provides more detailed policy direction for future implementation decisions. The planning process for the Subarea Plan update included extensive public involvement from property owners within the project area, including, but not limited to, Anheuser-Busch InBev, Poudre School District (PSD), service and utility providers, Burlington Northern Santa Fe Railway, area residents, Boards and Commissions, and City Council. The planning process was divided into three main sections. The first phase (March 2008 - August 2008) primary tasks included identifying background information associated with the project start up. The project team identified key issues, existing conditions and plan objectives. A reevaluation of the original vision, goals and policies was conducted to assess refinement of this foundational language. The team set up meetings with individual property owners and provided updates to Boards and Commissions during this phase. Phase II (August 2008 - March 2009) focused Improving Access and Quality of Life for All | 17 SUNIGA/LEMAY MULTI-MODAL AND TIGER Discretionary Grant Application FREIGHT CONNECTIVITY PROJECT • Nine updates to the Planning & Zoning Board. • Three updates to the Transportation Board. The original schedule was extended several times to thoroughly address public concerns. The multi-modal transportation outcomes link the City’s emerging bus rapid transit system, existing bus service and bicycle and pedestrian infrastructure plans with the new Mountain Vista roadway network and street cross-sections and supporting facilities. The City’s Structure Plan, Master Street Plan, and zoning designations establish a foundation and direction for the SubArea’s future development decisions. The project is a critical part of the City’s Enhance Travel Corridor network. Both City Plan and Transportation Master Plan identify four Enhanced Travel Corridors (ETCs). The purpose of these corridors is to provide multi-modal connections between key activity centers and access to high frequency transit service and bicycle and pedestrian facilities. Improving Access and Quality of Life for All | 18 SUNIGA/LEMAY MULTI-MODAL AND TIGER Discretionary Grant Application FREIGHT CONNECTIVITY PROJECT Figure 7: Multi-modal Street Cross-Section Options for Suniga, Lemay and Other Mountain Vista SubArea Plan Roadways Examples of planned street cross-sections are shown in Figure 7. Realignment of Suniga Drive is a major component of the ETC planned for northeast Fort Collins. The project will incorporate bicycle, pedestrian and transit needs into the project. All the roadways will be built to the City of Fort Collins standards which are complete streets, with full bike lanes, separated sidewalks and transit facilities. The City of Fort Collins was recently recognized as a Platinum level bike friendly city by the League of American Bicyclists. This project provides a critical element of bicycle infrastructure both north/south on the Lemay realignment and east/west on Suniga. The housing element of the plan helps the jobs/ housing balance within the City, supports the downtown and provides affordable housing within a diverse mix of zoning designations. At this point, the planning process has effectively addressed community planning controversies. Improving Access and Quality of Life for All | 19 SUNIGA/LEMAY MULTI-MODAL AND TIGER Discretionary Grant Application FREIGHT CONNECTIVITY PROJECT d. Environmental Sustainability In March 2015, the Fort Collins City Council unanimously adopted some of the most aggressive goals in the nation to reduce community greenhouse gas emissions: 20 percent below 2005 by 2020 and 80 percent by 2030, which would put the community on a path to be carbon neutral by 2050. The City’s 2015 Climate Action Framework lays out the path to achieve these goals, many of which relate to transportation, environmental sustainability and smart growth. This project helps further the Climate Action Framework by making transport faster and more convenient, enhancing multi- modal options and facilitating development close to the urban core. The following are anticipated sustainability benefits from this project: • Congestion reduction realized by the project is estimated to be 23,157 hours per year. • Annual air pollutant emission reductions would be substantial (CO -1,856 kg/year, NOx -352 kg/year, VOCs – 416 kg per year). • Interconnected traffic signals that reduce delay and stop and- go traffic conditions. LED traffic signals will also reduce energy consumption by 80%. • Use of local materials that reduce the embodied energy of construction. • The incorporation of Low Impact Development best practices to reduce storm water impacts. • The grade-separation, and elimination of the railroad at-grade crossing, creates a “quiet- zone”. These improvements will eliminate the need for the train to sound a warning horn (which is required) at the intersection. This has a major positive impact to the neighborhoods and residents living adjacent to the project. In order to control City operation and maintenance costs, the City recently instituted a set of Low Impact Development (LID) Standards that will apply to this project. The standards require industry best practices for controlling costs. One primary focus area is improving storm water quality and minimizing site runoff. Another focus area involves long-term roadside maintenance and watering costs. These costs are minimized by low maintenance and naturally sustaining vegetative plantings. This approach has been recently developed through the City’s Streetscape Standards which emphasize low- water, native, and xeric planting concepts. With respect to energy costs, the new facilities will use Liquid Emitting Diode (LED) traffic signal Improving Access and Quality of Life for All | 20 SUNIGA/LEMAY MULTI-MODAL AND TIGER Discretionary Grant Application FREIGHT CONNECTIVITY PROJECT e. Safety The grade-separation of the Vine and Lemay intersection from the BNSF railroad eliminates a difficult at-grade crossing of this railroad line, with inherent safety benefits. The new alignments and intersections will be built to current safety standards, upgrading a situation that is outdated and substandard. In addition, the project would reduce delays for emergency services, thereby improving safety for area residents. Completion of the grade separation improvement alone would result in a $174,572 accident reduction cost savings per year. The grade separation savings result from the elimination of the at grade highway-rail crossing and from the intersection improvements that will be constructed. There were two components to the crash reduction: 1. Reduction in train/car crashes and 2. Reduction in other intersection crashes. 3. The safety benefits were evaluated using two methods: 4. Federal Railroad Administration (FRA) Web Accident Prediction System (WBAPS). 5. Methodology in the Highway Safety Manual, 1st Edition, described in section 4.4.2.13 “Excess Expected Average Crash Frequency with EB Adjustment.” The FRA Web Accident Prediction System estimates the number of train-motor vehicle crashes that can be expected with the current at grade configuration. The Highway Safety Manual methodology estimates the number of expected multi-vehicle, single-vehicle, and pedestrian crashes at an intersection. The two results were summed to get the final benefit estimate. The Federal Highway Administration has established crash cost estimates based on crash severity. Those values are published in the Highway Safety Manual (HSM) in 2001 dollars. Using the methodology described in the HSM to convert to current values the following cost values were used: Fatal Crash = $5,377,400 Injury Crash = $84,100 Property Damage Only Crash = $9,700 From 2010 through 2012 there was an average of thirteen crashes per year at the Vine/Suniga intersection. With the improvements it is estimated that this number of crashes will be reduced by 52 percent on an annual basis. That results in an overall safety savings of $174,572 per year or 4.35 million present value dollars. Photo 6: Existing Congestion Along Lemay Avenue Looking South. Improving Access and Quality of Life for All | 21 SUNIGA/LEMAY MULTI-MODAL AND TIGER Discretionary Grant Application FREIGHT CONNECTIVITY PROJECT II. Secondary selection criteria a. Innovation The project is a model of innovative project delivery. The project has been innovative from the beginning, including a highly collaborative and accelerated project delivery. The project will include features that reduce capital and long-term costs, protect the environment, improve mode choice and safety, and preserve long-term multi- modal benefits. Collaborative Comprehensive Community Planning The project is critical component of master- planned growth in northeast Fort Collins that has a 30-year history of collaboration and a result embraced by the community and region. The project improvements are a well-defined implementation priority set forth in a series of planning documents, including: • East Vine/Lemay Intersection Realignment Project Development Report (2014) • City of Ft. Collins Bicycle Plan (2014) • Lincoln Corridor Plan (2014) • Pedestrian Plan (2011) • Plan Fort Collins (2011) • City Plan (2011) • City of Fort Collins Master Street Plan (2011) • City of Fort Collins Capital Improvement Plan (2011) • Mountain Vista Sub-Area Plan (2010) • Suniga 30% Design Plans (2009) • Transport Strategic Operating Plan (2009) • Northside Neighborhoods Plan (2005) • I-25 Corridor Plan (2001) • Larimer County Master Plan (1997) Safe, Integrated, Multi-modal Connectivity The roadway cross-sections and grade separation provide distinct facilities and routes for buses, other motor vehicles, cyclists and pedestrians, along with connectivity to the City’s emerging light rail system. The transportation network will provide access, mobility, and connectivity for all travel modes. Residents, businesses, and visitors will have a choice of traveling via automobile, walking, bicycling and transit. Multi-modal transportation needs in this subarea are vitally connected to city, county and regional transportation systems. The multi- modal transportation network and land uses in this subarea were planned in conjunction with each other. Key connections for all travel modes will be provided between the Community Commercial District, Employment and Industrial Districts, Community Park, and other activity centers. The transportation network in this subarea will also Improving Access and Quality of Life for All | 22 SUNIGA/LEMAY MULTI-MODAL AND TIGER Discretionary Grant Application FREIGHT CONNECTIVITY PROJECT Consistent with the Land Use Code, the transportation system within this subarea will have: 1) Arterial corridors providing safe and efficient multi-modal access to and through the subarea, including major features such as railroad under/overpasses (where necessary), and significant landscape mitigation features; 2) Multi-modal connections to and across the arterial corridors, including pedestrian and bicycle connections, providing convenient access to and from the local networks that serve individual developments and buildings; and 3) Integrated local networks with direct, convenient interconnections between developments and surrounding areas. According to the Mountain Vista Subarea Plan, the extension of Suniga Drive will be designated as part of the Mountain Vista/North College Enhanced Travel Corridor (ETC). The ETC will be designed for high frequency transit service, with enhanced bicycle and pedestrian facilities. The ETC will serve as a link between downtown Fort Collins, the Timberline Road/Power Trail ETC, this subarea’s Community Commercial District, Employment District, Community Park, school site, and a future park-n-ride at I-25. Sustainability The planning area and infrastructure improvement reflect context-sensitive design, avoidance and minimization of environmental impacts and embrace sustainable design in terms of project design features and specifications. The emphasis of the Mountain Vista Plan is economic sustainability. Mountain Vista’s business center will accommodate the long-term Employment and Industrial land use growth demands of Fort Collins, providing a variety of business and industry types and sizes, compatible with surrounding land uses. Capital Cost and Life-Cycle Cost Reduction The City has demonstrated careful analysis of project design to reduced project capital, operation and maintenance costs. Life-cycle analysis is integrated into the City’s Asset Management Program and contract requirements along with Value Engineering (VE). VE will be applied to each of the proposed projects. The City has extensive experience VE and includes VE in all major engineering projects in the City. Alternative Delivery The City of Fort Collins has identified Construction Management General Contracting (CMGC) or Design Build as a potential alternative delivery methods to reduce costs and streamline project delivery for the proposed improvements. The Improving Access and Quality of Life for All | 23 SUNIGA/LEMAY MULTI-MODAL AND TIGER Discretionary Grant Application FREIGHT CONNECTIVITY PROJECT b. Partnership Jurisdictional & Stakeholder Collaboration The project is the end product of collaboration and partnerships between the City of Fort Collins, Larimer County, DDA, the Poudre School District, BNSF Railroad, the North Front Range Metropolitan Planning Organization, major landowners, major existing and future employers in Fort Collins (Anheuser Busch and Woodward), project site neighbors, and the general public. Progress with other enabling infrastructure is now underway with water line construction, overall roadway planning, and associated right of way efforts. Disciplinary Integration As is evident from the many collaborators and partners connected to the Mountain Vista SubArea Plan and the proposed improvements, there is a united effort to move this enabling infrastructure from planning to construction. This breadth of support from non-transportation public and private agencies is clear indication of the importance of this project in realizing the vision for centrally located, transit oriented, land development in northeast Fort Collins and the economic health of the region. The proposed Letters of Support for this project are shown in Appendix D. improvements will connect existing and new communities in an efficient, environmentally sustainable manner that will benefit the citizens of northern Colorado for years to come. The City and our partners are proud of this ground- breaking demonstration of regional cooperation. Improving Access and Quality of Life for All | 24 SUNIGA/LEMAY MULTI-MODAL AND TIGER Discretionary Grant Application FREIGHT CONNECTIVITY PROJECT F. RESULTS OF BENEFIT/COST ANALYSIS Costs and Benefits Investment of federal dollars for the proposed improvements will generate long-term benefits that are in direct alignment with the goals of the American Recovery and Reinvestment Act. The project’s analysis of costs and benefits is presented in Appendix C. The long-term outcomes, or benefits, are measurable and significant. The project enables future development designed to create 15,065 jobs on 1,256 acres of job producing land use. The grade separation alone will generate 23,157 hours of delay reduction per year and $174,572 in accident reduction cost saving per year. Annual air pollutant emission reductions would be substantial (CO -1,856 kg/year, NOx -352 kg/ year, VOCs – 416 kg per year). Railroad delay reductions and at grade crossing maintenance savings and benefits associated with improved emergency vehicle access would also be expected. The northeast employment district is uniquely marketable with available large parcel sizes, direct access to an improved I-25 interchange, and railroad access. The economic benefits of this development are real and substantial. Important community benefit includes: • Job Creation for Low Income Workers (through best practice hiring programs and utilization of apprenticeship programs) • Maximum Practicable Opportunities for SBE, DBE, Veteran Owned Small Businesses and Service Disabled Veteran Small Businesses • Use of Community Based Organizations in Connecting Disadvantaged Business Workers with Economic Opportunities • Support for Entities that have a Sound Track Record on Labor Practices and Compliance with Federal Laws Ensuring Safety and Equity The project is ready for implementation and will create 600 construction- related jobs. • Best Practices in Compliance with National Civil Rights and Equal Opportunity Laws Mountain Vista’s business center will accommodate the long-term Employment and Industrial land use growth demands of Fort Collins, providing a variety of business and industry types and sizes, compatible with surrounding land uses. Improving Access and Quality of Life for All | 25 SUNIGA/LEMAY MULTI-MODAL AND TIGER Discretionary Grant Application FREIGHT CONNECTIVITY PROJECT G. PROJECT READINESS AND APPROVALS Technical Feasibility The following highlights the key aspects of technical feasibility that achieve project readiness: • This project has been envisioned and included in major City transportation plans for over 30 years. This extensive and long- range planning maximizes the potential for integrated land use and transportation and allows incremental accommodation of the ultimate plan as nearby properties change and develop. The recent construction of the Woodward, Inc. Corporate Campus south of the intersection along Lemay Avenue demonstrates the desirability of this area for development as well as the challenges due to increasing congestion and inadequate infrastructure. • BNSF has expressed a commitment to fund a portion of the grade separation. The City has completed numerous projects with the BNSF including both a bicycle/pedestrian overpass and underpass in 2013 and 2014. These projects helped improve long-term safety and accessibility, were constructed with minimal disruption to railroad service and strengthened the City’s relationship with the BNSF. The City understands the BNSF and PUC processes and design standards, which will help streamline the project design and construction. • The City has advanced the project design by completing conceptual design and an alternatives analysis in 2014, as well as appropriating $1M in funding in 2015 to advance the design and right-of-way review. • All of the necessary right-of-way for the southeast quadrant of the Vine/Lemay/BNSF intersection has been secured and is owned by the City of Fort Collins. The City is currently in negotiations with the lone property owner in the northeast quadrant. The City is presently preparing legal descriptions and will be making an initial right-of-way offer to the property owner in the Summer of 2015. • The project is currently envisioned to be delivered using traditional design-bid-build approach, however if phasing of the improvements becomes critical the City is prepared to deliver via an innovative Contractor Manager/General Contractor (CMGC) method or Design- Build (DB) method. These alternative delivery methods would be considered if they are determined to appropriately manage risk for cost, schedule, and quality. Financial Feasibility The City of Fort Collins has recent history with major construction projects in the area and with arterial construction projects similar in nature to this project definition. The following summarizes the capital cost break-down of the project components, and the overall Federal Grant vs. Local Match “Fort Collins has weathered the recession better than many communities throughout the country,” said City Manager Darin Atteberry. “This top rating from Moody’s reflects our dedication to sound financial management and Improving Access and Quality of Life for All | 26 SUNIGA/LEMAY MULTI-MODAL AND TIGER Discretionary Grant Application FREIGHT CONNECTIVITY PROJECT funding for the project. The following highlights the key aspects of financial feasibility that achieve project readiness: • The basis for the cost estimate is a thorough and professional planning process undertaken with an extensive public involvement component, multi-agency coordination, and City Council approval. The project cost estimate is outlined in detail in the City’s Project Development Report (2014), attached as Appendix B. Cost magnitudes are verified by similar recently completed projects such as the reconstructed Interchange at SH 392 & I-25. • All streets for the project will be built in accordance with the Larimer County Urban Area Street Standards and other applicable standards. Cost estimates for these street components are based on recent construction cost data for similar streets built to the same standards in the region. • The City of Fort Collins has an AAA Credit Rating from Moody’s. • Moody’s Investors Service has assigned the City of Fort Collins a AAA issuer rating with a stable outlook as part of a bond refinancing. The City is refinancing the 2004 Certificates of Participation (COP) bonds used to build the Police building and acquire various open space properties. The refinanced COPs received an Aa1 rating. The AAA rating is the highest offered by the credit rating agency; only 4.8% of the governments rated by Moody’s have received the AAA designation. • The City of Fort Collins has consistently managed millions of dollars’ worth of federal transportation grants over the past 20+ years. • In the past 5 years, the City has successfully managed over $100 million worth of Federal- Aid grant projects. Project Schedule The City of Fort Collins has already been working through the planning phases of the project development process and early right-of-way review. The project has community support through the planning process, and has completed a detailed Project Development Report which identifies environmental resources of concern and streamlines future NEPA clearance. The project schedule (see Figure 8) focuses on the primary goal of having all pre-construction activities completed to allow for obligation of construction funds by August of 2017 at the latest, and if alternative delivery is selected this obligation could be as early as September 2016. The City has continually advanced the project Improving Access and Quality of Life for All | 27 SUNIGA/LEMAY MULTI-MODAL AND TIGER Discretionary Grant Application FREIGHT CONNECTIVITY PROJECT • The proposed roadway improvements have already considered and addressed the key environmental issues: ◦ Historic neighborhoods and specific properties within the adjacent residential neighborhoods are protected by generous roadway buffers leaving the historic properties and surrounding contexts undisturbed by the project improvement requirements. In fact, future conditions will be less disruptive than under existing conditions. ◦ The ditch north of Vine will be fully protected and will remain viable during and after construction. ◦ Protection of all residential structures and neighborhoods will be achieved through realigning Lemay. Indirect impacts on existing residential uses will be reduced by buffers between neighborhood boundaries and the perimeter of the construction disruption footprints. ◦ There are no protected species or habitats (wetlands or other) that present the potential to complicate the environmental clearance or project permitting processes. Assessment of Project Risks and Mitigation Strategies The City of Fort Collins will employ a number of innovative methods to control risks of project delivery. They include: Project Delivery Risk: Environmental Clearances • Through the 2014 Project Development Report, the City conducted an extensive process to analyze and screen project alternatives, and to evaluate the environmental issues of key concern. This process positions the project for streamlined NEPA clearance, anticipated to be a Categorical Exclusion. The public outreach process will continue through the NEPA and final design phase to gather valuable feedback on the selected alternative. ID Task Name Start Finish 1 Sub-Area Planning Tue 9/1/09 Fri 5/24/13 2 City Project Development Activities Mon 5/27/13 Fri 5/9/14 3 Alternatives Analysis (PEL) Study Mon 5/12/14 Fri 9/12/14 4 Design/ROW review Funding Appropriation Thu 1/1/15 Thu 1/1/15 5 Advanced ROW review activities Fri 1/2/15 Thu 6/4/15 6 Design procurement Fri 6/5/15 Thu 8/13/15 7 Preliminary Design and Final Alternative Fri 8/14/15 Thu 1/14/16 8 Streamlined NEPA Clearance (CATEX or Template EA) Fri 1/15/16 Thu 6/30/16 9 Final Design and Bid Packaging Fri 1/15/16 Thu 9/22/16 10 Right of Way Acquisition Fri 2/26/16 Thu 11/3/16 11 BNSF RR Agreement Complete Fri 1/15/16 Thu 8/11/16 12 Local, Federal, State Requirements Met Fri 11/4/16 Fri 11/4/16 Improving Access and Quality of Life for All | 28 SUNIGA/LEMAY MULTI-MODAL AND TIGER Discretionary Grant Application FREIGHT CONNECTIVITY PROJECT Project Delivery Risk: Construction Cost and Design/Construction Schedule Overlap • The City is committed to use alternative delivery through design/build or CM/GC if it is determined to add value by effectively managing scope, schedule and cost risks. One example of where alternative delivery could help to achieve innovation and efficiency is in the simultaneous procurement of construction contractor while final design is progressing. This can add value by involving the construction contractor earlier in the process while still maintaining control of the risks during the design phase. This example can help to achieve the highest level of control on project features that are outside of the scope and budget, and will reduce lost time due to long duration overlaps in design and construction procurement packaging. The City will evaluate project delivery options as an early action in the preliminary design phase of the project. Project Delivery Risk: Right of Way Acquisition • By engaging the design team in the Right of Way acquisition process, the City will have maximum control on the schedule to achieve timely acquisition. By investing early in the 2014 Project Development Report that includes design that anticipated the right- of-way needs and requirements, this risk is reduced by identifying, understanding critical issues and opportunities, and working early to engage with property owners. The City has already begun this process and this will result in significantly reduced risk to the project delivery. Project Delivery Risk: Pre-Construction Activities Cost • The City of Fort Collins is committed to using local funding for the pre-construction activities for the project. This will ensure the TIGER Discretionary Grant Funds are used for the construction activities that result in the highest benefits for increasing the economic competitiveness and job creation. Improving Access and Quality of Life for All | 29 SUNIGA/LEMAY MULTI-MODAL AND TIGER Discretionary Grant Application FREIGHT CONNECTIVITY PROJECT H. FEDERAL WAGE RATE CERTIFICATION The City of Fort Collins submits this application for the funding of the Suniga/Lemay Multi-Modal and Freight Connectivity Project in northern Colorado. In response to item in the 2015 Notice of Funding Availability, the following information is provided: Federal Wage Rate The City of Fort Collins certifies that it will comply with the Federal Wage Rate Certification requirements of subchapter IV of chapter 31 of title 40 of the United States Code, as required by the FY 2015 Appropriations Act. Signed, Rick Richter Director of Infrastructure Services City of Fort Collins Improving Access and Quality of Life for All | 30 SUNIGA/LEMAY MULTI-MODAL AND TIGER Discretionary Grant Application FREIGHT CONNECTIVITY PROJECT I. SUMMARY OF DIFFERENCES FROM THE PRE-APPLICATION It is important to note that the funding request submitted in the pre-application differs from the overall budget and funding request identified in this final application. The pre-application included the following funding request and summary of project costs: TIGER Request: $34,000,000 Total Project Cost: $42,500,000 Total Federal Funding $34,000,000 Total Non-Federal Funding: $8,500,000 The pre-application costs included future roadway improvements that the City has determined would be best to construct separate from this project. Thus, the focus of this final application is on the funding of the grade separation of Lemay over the BNSF railroad, which is of highest priority. Future roadway improvements (including full construction of Suniga Drive) have independent utilty from this project and will be constructed as future funding sources become available. As outlined in this final application, the cost of the grade separation of Lemay over the BNSF totals $27 million. The local contribution to this project is $10 Million, which represents a 37% match toward the overall $27 Million project cost. The funding request of the TIGER program is $17 Million. The following table provides a breakdown of the cost of each major improvement. Improvement Cost Grade Separation of the Vine/ BNSF/ Lemay Intersection $ 12M Construction of Four-Lane Arterial Roadways $ 8M Bicycle/Pedestrian Facilities and Landscaping $ 6M Neighborhood Street (Local Street) Construction $ 1M $ 27M The following table shows the sources of local funding which constitute $10M (37%) of the $27M project. In addition to the local funding sources above, BNSF is committed to contributing 5% of the grade separation cost. The exact dollar amount will be confirmed in the coming months. Local Funding Sources Cost 1. City of Ft. Collins 2015 Appropriation to Project $ 1M 3. Street Over-sizing $ 5M 4. Local Street Developer Obligation $ 1.5M 5. City General Fund $ 2.5M TOTAL $ 10M APPENDIX C: BENEFIT/COST ANALYSIS SUNIGA/LEMAY MULTI-MODAL AND FREIGHT CONNECTIVITY PROJECT TIGER Discretionary Grant Application June 4, 2015 APPENDIX C SUNIGA/LEMAY MULTI‐MODAL AND FREIGHT CONNECTIVITY PROJECT BENEFIT/COST ANALYSIS BASE CASE ASSUMPTION The benefit cost analysis focuses on the option of building an overpass where Lemay Avenue intersects Suniga Drive and the BNSF railroad tracks, thereby eliminating the significant wait times caused when a train goes through the area. This option is compared against a “no build” scenario, which assumes the intersection remains as‐is, and becomes the base case assumption for the analysis. The base case assumes Lemay Avenue continues to cross the railroad tracks at grade. Due to the City of Fort Collins’ policy which requires Adequate Public Facilities for new development to occur, development in the area is significantly stunted unless this intersection issue is resolved. Existing and future traffic would continue to experience significant wait times when a train is in the area, causing excessive idling and vehicle emissions. BENEFITS Travel Time Savings Benefits The Suniga/Lemay/BNSF intersection is an important connection between northeast Fort Collins and the rest of the city. It provides primary access for residents and visitors to access Downtown. The number of vehicles has increased annually. The capacity for this intersection to accommodate existing and future traffic is significantly compromised because of its proximity to the railroad tracks. There is a switching yard close to the intersection which significantly extends the time it takes for trains to cross the intersection, causing significant time delays for travelers. Delay is reduced by eliminating train blockages and by providing more capacity at the new Suniga/Lemay intersection. Reduction in delay for train blockages was calculated as follows: 1,570 minutes/day x 320 days/year (<365 to account for lower traffic volumes on weekends) = 502,400 minutes/year or 8,373 hours/year x $20.15/vehicle‐hour value of time per person ($16.79/person assuming an average occupancy of 1.2) = $168,723/year. Reduction in delay from intersection improvements calculated at 2,772 minutes/day x 320 days/year x 1 hour/60 min. x $20.15 = $297,898/year. Total delay reduction = 23,157 hours/year x 20.15/hour = $466,614/year. Accident Reduction Benefits The grade separated intersection would reduce train/car crashes and other intersection crashes. The calculation of benefits was generated as follows: Reduction in train crashes estimated at: 0.0146 property damage only crashes/year 0.0074 injury crashes/year 0.0008 fatal crashes/year at the following costs: PDO ‐ $9,700 Injury ‐ $84,100 Fatal ‐ $5,377,400 Reduction in train/car crashes = $ 5,066/year. Reduction in other intersection crashes estimated at 5.03 property damage only crashes/year and 1.16 fatal or injury crashes/year at the following costs: PDO ‐ $9,700 Fatal or Injury ‐ $103,200 Reduction in other intersection crashes = $168,500/year. Total crash reduction cost savings = $173,570/year. Fuel Savings Benefits Improved operations would generate fuel consumption reductions as follows: Reduction in fuel consumption from elimination of idling at the railroad = 20.4 gallons/day * 320 days/year = 6,531 gallons/year Reduction in Fuel Consumption from intersection improvements = 80.3 gallons/day * 320 days/year = 25,698 gallons/year Total = 100.7 gallons/day * 320 days/year = 32,224 gallons/year @ $3.50/gallon = $112,784/year Vehicle Emissions Reduction Benefits When vehicles are waiting at the intersection for a train to pass, emissions such as nitrogen oxides, volatile organics (VOCs) and carbon dioxide pollute the air. Reduced air emissions due to the grade separated intersection were calculated based on factors applied to the avoided VHT resulting from the “no‐build” scenario. Emission reduction benefits would be as follows: From elimination of idling at the railroad: CO – 1.4 kg/day * 320 days/year = 456 kg/year NOx – 0.28 kg/day * 320 days/year = 89 kg/year VOC – 0.3 kg/day * 320 days/year = 106 kg/year From intersection improvements: CO – 5.8 kg/day *320 days/year = 1,856 kg/year NOx – 1.1 kg/day * 320 days/year = 352 kg/year VOC – 1.3 kg/day * 320 days/year = 416 kg/year Total: CO – 7.2 kg/day *320 days/year = 2,312 kg/year NOx – 1.38 kg/day * 320 days/year = 441 kg/year VOC – 1.6 kg/day * 320 days/year = 522 kg/year At‐Grade Railroad Maintenance Savings Benefits By removing the at‐grade railroad crossing, savings will be seen from the on‐going maintenance that otherwise would have occurred. Other Benefits Although not quantified for the purpose of the benefit‐cost analysis, there are other benefits associated with the project that deserve mention. The first being improved access for emergency vehicles. With the current at‐grade crossing, when a train is crossing there is not a viable alternative to allow emergency vehicles to cross from north to south, or vice versa. Depending on the length and direction of the train, an emergency vehicle could travel one mile to the east or west to attempt to cross the tracks; however, this may not be possible if the train is long and covers multiple intersections, or it causes a delay. Another benefit to note is the development potential for the area near the Suniga/Lemay intersection. Development is currently stunted because of the condition of the at‐grade crossing. The area directly to the north and northeast, also known as the Mountain Vista area, is the largest area of Fort Collins that remains undeveloped; and it will stay undeveloped unless the Suniga/Lemay intersection is improved. According to the 2009 Mountain Vista Subarea Plan, the area will accommodate a population increase of 13,347 by 2030. During the same time period, the area is planned to accommodate 15,065 jobs. EFFECTS ANALYSIS METHODOLOGY The U.S. Bureau of Economic Analysis (BEA) developed regional input‐output multipliers, known as RIMS (Regional Input‐Output Multiplier System). Originally developed in the 1970’s, BEA completed an enhancement a decade later, known as RIMS II, which provided the data for this particular analysis. RIMS II is based on an accounting framework called an input‐output (I‐O) table. For each industry, an I‐O table shows the distribution of the inputs purchased and the outputs sold. A typical I‐O table in RIMS II is derived mainly from two sources: BEA’s national I‐O table which shows the input‐output structure of nearly 500 U.S. industries, and BEA’s regional economic accounts which are used to adjust the national I‐ O table to reflect a region’s industrial structure and trading patterns. RIMS II multipliers by industry aggregation were purchased for the Fort Collins‐Loveland Metropolitan Statistical Area (MSA) to estimate the total economic impact of projects on regional output, earnings, and employment. For the purposes of this analysis, type II multipliers were used, which account for direct, indirect, and induced economic impacts. Construction Impacts One side of the analysis looks at the impacts of the actual construction of the transportation improvements. Industry aggregate multipliers were used for the construction industry. The estimated budget (project cost, or change in final demand) was multiplied by the total multipliers for output, earnings and employment; 1.7077, .4938, and 12.0873 respectively. For example, a $1,000,000 project would result in a $1.7 million change in output for all industries in the region, and a $493,000 change in earnings. The employment multiplier represents the total change in number of jobs that occurs in all industries for each $1 million investment. Thus, 12 jobs would be created as a result of this $1 million project. The total project cost of $27,000,000 was used for the analysis. See Table 1 for the results. Table 1: Economic Impacts for Construction of Improvements1 Construction Costs: Grade Separation of Suniga/Lemay/BNSF and Realignment of Lemay $27,000,000 Final‐demand multiplier: Output ($) 1.7077 Earnings ($) .4938 Jobs per $1 million 12.0873 Impact on: Regional output ($) $46,017,900 Regional earnings ($) $13,332,600 Regional employment (jobs) 600 Long‐Term Impacts In addition to the impacts that result from the physical construction of the improvements, the long‐term economic impacts were estimated using similar methodology. As previously mentioned, the Mountain Vista Subarea Plan projected the area to accommodate 15,065 jobs by 2030, which assumes full build out of the land. Assumptions were made regarding the distribution of job types based on the zoning for particular land uses, as follows: Total acres of commercial/employment land = 1,256  53% zoned for Employment, or office type use  46% zoned for Industrial, or manufacturing type use  9% zoned for School, or educational service type use  2% zoned for Commercial, or retail, service type uses The percentage distribution of job type was then applied to the total 15,065 jobs projected for the area, and the appropriate RIMS II multipliers were used. In some cases, multiple industry multipliers were averaged. For example, multipliers for professional services, administrative services, and financial services were averaged and that average multiplier was used to produce the economic impacts for that particular land use. Total jobs projected by 2030 = 15.065  53% or 7,984 jobs = professional/administrative/financial services  46%, or 5,423 jobs = manufacturing  9% or 1,356 jobs = education  2% or 301 jobs = food services/other services 1 The data used provides impacts on an annual basis; therefore, the analysis provides an overall snapshot of the economic impacts for a one‐year period, and may not be accurate over the entire span of the project. Final‐Demand Multiplier Direct‐Effect Multiplier Multiplier Industry Value added Earnings Employment Direct Earnings Direct Jobs Professional/admin/financial services 0.9629 0.50733 14.7534 1.5659 1.6187 Manufacturing 0.8277 0.3724 9.1724 1.5942 1.685 Food services/other services 0.95115 0.51415 18.23085 1.50255 1.42695 Education 1.1196 0.6596 24.3277 1.4145 1.307 Employment Category Final‐Demand Change (millions) Value Added (millions) Earnings (millions) Professional/admin/financial services $876 $ 843.5 $444.4 manufacturing $996.3 $824.6 $371.0 Food services/other services/ $23.5 $22.4 $12.1 Education $72.8 $81.5 $48.0 Total $1,968.7 $1,772.1 $875.6 It is important to understand the results of this analysis are based on critical assumption that constructing the improvements will open up development in the Mountain Vista area and ultimately result in the full build‐out projected during the 2009 planning process. In all likelihood, some development will occur in the area regardless of whether the improvements are made. The results provided here should be used cautiously; they are estimates based on a number of assumptions from the latest information available. SUMMARY OF BENEFITS BENEFIT CATEGORY MEASURED BENEFIT Travel Time Savings/Total delay reduction 23,157 hours/year $466,614/year Total Crash Reduction Cost Savings $173,570/year Fuel Savings 32,224 gallons/year $112,784/year Emission Reductions CO = 2,312 kg/year NOx = 441 kg/year VOC = 522 kg/year Other Benefits (Not Quantified) Road Maintenance Savings Emergency Vehicle Response Time Reduction, Increased Population +13,347 Additional Jobs +15,065 APPENDIX D: LETTERS OF SUPPORT SUNIGA/LEMAY MULTI-MODAL AND FREIGHT CONNECTIVITY PROJECT TIGER Discretionary Grant Application June 4, 2015 June 5, 2015 United States Department of Transportation Anthony Foxx, Secretary of Transportation 1200 Jersey Avenue, SE Washington, DC 20590 Dear Secretary Foxx; I am writing in support of the City of Fort Collins’ application for funding as a part of the 2015 Transportation Investment Generating Economic Recovery (TIGER) grant. The City of Fort Collins’ project, Suniga / Lemay Multi-Modal and Freight Connectivity Project, will provide funding for the construction of a grade separated crossing at the Burlington Northern Santa Fe (BNSF) railroad at Lemay Avenue and Vine Drive and the construction of Suniga Drive (New Vine Drive) from State Highway 287 to Timberline Road. The City of Fort Collins has done great due diligence in studying the need for such a project. After 30 years of study and continual increases in vehicle and train traffic, accidents and city growth, the City of Fort Collins has prioritized this project as its #1 transportation capital project. The City of Fort Collins has utilized an extensive planning process working in partnership with City Departments, BNSF, area businesses and local neighborhood groups to determine the best plan to appropriately serve the project area and increase the safety and vitality of the affected neighborhoods. The City of Fort Collins previously developed a land use and economic development plan for the surrounding area and has moved to the next phase of preliminary design for the project. The grade separated crossing proposed in the Suniga / Lemay Multi-Modal and Freight Connectivity Project is a critical part of the transportation infrastructure within the City of Fort Collins. Improvement of the intersection has become a safety issue for BNSF, emergency services, and the travelling public. Along with improved safety, additional benefits stemming from this project include: multi-modal and transit infrastructure, increased reliability in freight movement, revitalization of three underserved neighborhoods adjacent to the project area, and increased access to business and educational services for the citizens of Fort Collins. The Fort Collins Area Chamber of Commerce is excited about the prospect of improving multi-modal connections and relieving vehicle and train congestion in northeast Fort Collins. The Chamber is an active and forward-focused organization of 1,000 members, with a wide range of supporters from sole proprietors to large, multi-national corporations. Our organizations focus centers on the importance that the business perspective is heard and understood by public officials. Our Chamber has earned the prestigious national 5- star accreditation, putting us in the top 1% of all chambers throughout the United States. We offer our full support in the City of Fort Collins’ Suniga / Lemay Multi-Modal and Freight Connectivity Project application for funding. Sincerely, The Fort Collins Area Chamber of Commerce David L. May President & CEO June 5, 2015 United States Department of Transportation Anthony Foxx, Secretary of Transportation 1200 Jersey Avenue, SE Washington, DC 20590 Dear Secretary Foxx; I am writing in support of the City of Fort Collins’ application for funding as a part of the 2015 Transportation Investment Generating Economic Recovery (TIGER) grant. The City of Fort Collins’ project, Suniga / Lemay Multi-Modal and Freight Connectivity Project, will provide funding for the construction of a grade separated crossing at the Burlington Northern Santa Fe (BNSF) railroad at Lemay Avenue and Vine Drive and the construction of Suniga Drive (New Vine Drive) from State Highway 287 to Timberline Road. The City of Fort Collins has done great due diligence in studying the need for such a project. After 30 years of study and continual increases in vehicle and train traffic, accidents and city growth, the City of Fort Collins has prioritized this project as its #1 transportation capital project. The City of Fort Collins has utilized an extensive planning process working in partnership with City Departments, BNSF, area businesses and local neighborhood groups to determine the best plan to appropriately serve the project area and increase the safety and vitality of the affected neighborhoods. The City of Fort Collins previously developed a land use and economic development plan for the surrounding area and has moved to the next phase of preliminary design for the project. The grade separated crossing proposed in the Suniga / Lemay Multi-Modal and Freight Connectivity Project is a critical part of the transportation infrastructure within the City of Fort Collins. Improvement of the intersection has become a safety issue for BNSF, emergency services, and the traveling public. Along with improved safety, additional benefits stemming from this project include: multi-modal and transit infrastructure, increased reliability in freight movement, revitalization of three underserved neighborhoods adjacent to the project area, and increased access to business and educational services for the citizens of Fort Collins. The Fort Collins Hosing Authority (FCHA) is excited about the prospect of improving multi- modal connections and relieving vehicle and train congestion in northeast Fort Collins. The FCHA’s focus is a triple bottom line approach to providing affordable housing and supportive services. Our organization assists over 5,000 individuals in Fort Collins and throughout Larimer County. We are actively pursuing land bank opportunities in the northeast part of the City (Mountain Vista subarea) in an effort to meet citizen demand for affordable housing. I offer my full support in the City of Fort Collins’ Suniga / Lemay Multi-Modal and Freight Connectivity Project application for funding. Sincerely, Julie Brewen CEO/Executive Director Olga Duvall, Chair Eric Shenk, Vice Chair Transportation Board United States Department of Transportation Anthony Foxx, Secretary of Transportation 1200 Jersey Avenue, SE Washington, DC 20590 Dear Secretary Foxx; I am writing in support of the City of Fort Collins’ application for funding as a part of the 2015 Transportation Investment Generating Economic Recovery (TIGER) grant. The City of Fort Collins’ project, Suniga / Lemay Multi-Modal and Freight Connectivity Project, will provide funding for the construction of a grade separated crossing at the Burlington Northern Santa Fe (BNSF) railroad at Lemay Avenue and Vine Drive and the construction of Suniga Drive (New Vine Drive) from State Highway 287 to Timberline Road. The City of Fort Collins has done great due diligence in studying the need for such a project. After 30 years of study and continual increases in vehicle and train traffic, accidents and city growth, the City of Fort Collins has prioritized this project as its #1 transportation capital project. The City of Fort Collins has utilized an extensive planning process working in partnership with City Departments, BNSF, area businesses and local neighborhood groups to determine the best plan to appropriately serve the project area and increase the safety and vitality of the affected neighborhoods. The City of Fort Collins previously developed a land use and economic development plan for the surrounding area and has moved to the next phase of preliminary design for the project. The grade separated crossing proposed in the Suniga / Lemay Multi-Modal and Freight Connectivity Project is a critical part of the transportation infrastructure within the City of Fort Collins. Improvement of the intersection has become a safety issue for BNSF, emergency services, and the travelling public. Along with improved safety, additional benefits stemming from this project include: multi-modal and transit infrastructure, increased reliability in freight movement, revitalization of three underserved neighborhoods adjacent to the project area, and increased access to business and educational services for the citizens of Fort Collins. The City of Fort Collins Transportation Board (The Board) is excited about the prospect of improving multi-modal connections and relieving vehicle and train congestion in northeast Fort Collins. The Board is a citizen led, advisory group which examines issues relating to financing, the development and implementation of projects pertaining to multi-modal improvements, transportation congestion, and connectivity. The Board coordinates with other City boards, municipalities throughout the region, offers recommendations to the Fort Collins City Council on key transportation issues and solutions. The Board offers its full support in the City of Fort Collins’ Suniga / Lemay Multi-Modal and Freight Connectivity Project application for funding. Sincerely, Olga Duvall Transportation Board Chair 13 Final Procurement Package Mon 11/7/16 Fri 12/2/16 14 Construction Procurement Mon 12/5/16 Fri 2/10/17 15 Construction Notice to Proceed (funds obligated) Mon 2/13/17 Fri 3/24/17 16 Alternative Delivery Procurement (If needed) Fri 1/15/16 Thu 6/30/16 17 Alternative Delivery Construction NTP (If needed)(funds obligated) Fri 7/15/16 Thu 9/15/16 Qtr 2Qtr 3Qtr 4Qtr 1Qtr 2Qtr 3Qtr 4Qtr 1Qtr 2Qtr 3Qtr 4Qtr 1Qtr 2 Qtr 3Qtr 4Qtr 1Qtr 2Qtr 3Qtr 4 2013 2014 2015 2016 2017 Vine/Lemay Grade Separation Project Figure 8: Project Schedule by investing in preliminary planning, concept design and alternatives analysis. An additional $1M has recently been appropriated to advance the project design, clearances and right-of-way review. Required Approvals The project will build upon previous planning efforts to streamline the environmental clearances and reduce risks to project delivery. • In 2014, the City completed a Project Development Report that meet the requirements of a Planning and Environmental Linkage (PEL) study. This study is intended to help streamline any future NEPA clearance by narrowing the potential design options and evaluating potential environmental resources of concern. As a result of the extensive alternatives and environmental analysis completed for this study, the City anticipates completion of a streamlined NEPA clearance in the form of a Categorical Exclusion for the federally funded improvements. wise use of debt services; it’s great news for Fort Collins.” According to Moody’s, the AAA issuer rating reflects a stable local economy supported by the presence of Colorado State University, sound wealth levels typical of a college town, a large tax base, favorable debt levels, and sound fiscal operations. City and its consulting partners have broad and extensive experience with cost reductions and schedule accelerations using CMGC and Design Build approaches relative to traditional delivery methods.. The City is prepared to initiate the process immediately following confirmation of funding commitments to determine the most effective and efficient project delivery method. The goal is a high quality, cost-effective project that minimizes the time to reach construction while being compliant with all Federal-Aid regulations. • The goal is a high quality, cost-effective project that minimizes the time to reach construction while being compliant with all Federal-Aid regulations. • The City is currently under process to procure preliminary design and project delivery review. • The City will complete the design/ROW process with overmatch dollars to insulate risk from the Federal Grant Funds. MOUNTAIN VISTA SUBAREA PLAN CHAPTER 4 – FRAMEWORK PLAN 33 Figure 14 – Community Commercial District Diagram Potential hotel and supporting commercial Potential civic uses such as a branch library Community park multi-use trail underpass to CCD Grocery anchor Both Mountain Vista Drive and “Main Street” aligned southwest to mountain views Potential live/work units Employment office park emphasize connections to other destinations in Fort Collins and neighboring communities. The proposed improvements open the door to transit in the planning area. indications. LED traffic signals are proven to require 80% less energy than incandescent indications. Additional environmental benefits will include: • 25,698 gallons per year in fuel savings • Water savings from efficient urban development and design • Energy efficiency, reduce dependence on oil and reduced greenhouse gas emissions. The City’s recently adopted Lincoln Corridor Plan envisions a “Great Street” and model for sustainable practices. It reflects the City’s commitment to innovations in green infrastructure and investment in the long-term viability of streets within the transportation system. on design. Travel demand modeling by the consultant team determined future traffic volumes and street classifications for comparison between the 1999 and 2009 street networks. A market analysis was conducted to assess support for the amount of land use designations in the subarea. In October 2008, three framework plan alternatives were developed to compare different scenarios for land use, street patterns, open lands and other public facilities. In February 2009, three Plan map options were developed to further test land use and transportation choices. Based on public feedback, the project team integrated the successful elements of each alternative into a single draft framework plan. Phase III (March 2009 - September 2009) developed the final plan document. The Plan incorporates updated analysis data, land use and transportation recommendations, and implementation strategies to achieve the Plan. The team also coordinated public events throughout the planning process: • Six meetings with major property owners. • Four public open houses. • Three City Council work sessions. • Seven meetings with individual neighborhoods. neighborhoods is from Lemay and Vine. Access to both neighborhoods is frequently constrained by traffic congestion. The proposed design for grade separation will move these major arterials away from these neighborhoods while retaining existing access points for the residents. The grade separation bypass alignment will shift traffic further away from existing residences while substantially reducing traffic congestion. The project will make the entire area more accessible, and separate local traffic from growing through traffic. iv. The project results from a planning process which coordinated transportation land use planning decisions and encouraged community participation in the process. The project provides convenient, healthy and sustainable transportation options: • The project will enhance user mobility through creation of more convenient transportation options. • The project will enhance modal connectivity and reduces congestion on existing modal assets. • The project will improve accessibility and transport for economically disadvantaged populations, non-drivers, senior citizens and persons with disabilities and will make goods, commodities, and services more readily available to these groups. • The project results from a planning process which coordinated transportation land use planning decisions and encouraged community participation in the process. and revitalize the larger area. c. Quality of Life i. The project will enhance user mobility through creation of more convenient transportation options. The Mountain Vista Subarea Plan identified a transportation network to provide access, mobility, and connectivity for all travel modes. The Subarea Plan recommended three grade- separated railroad crossings including the proposed grade separation at Vine/BNSF/Lemay. The new realignment of Lemay separates the street intersection from the railroad crossing. In the short-term, this would allow additional capacity at both the intersection and crossing. Currently the existing intersection of Vine and Lemay, which includes the BNSF railroad crossing, is severely congested, with limited options to expand turn capacity due to existing land use and natural constraints. Lemay as a major north/ south arterial is severely constricted at this point. Creating a by-pass with a grade separated crossing and moving the major intersection north will be more convenient for the significant through traffic in this area. This project will also move the majority of traffic away from the two adjacent residential areas, while still providing access. traditional municipal tax base mechanisms supplemented by a dedicated local ¼ cent sales tax and the City’s development impact fee system requiring private sector improvements including street over-sizing requirements. In order to appropriately allocate the City’s financial resources, Fort Collins prioritizes planning improvements and uses a well-established Asset Management system to evaluate transportation infrastructure conditions to efficiently plan and maximize maintenance investments. The proposed improvements are too costly for immediate or short-term funding by the City or State of Colorado. The City of Fort Collins has a strong track record for maintenance of City transportation infrastructure assets. iv. This project includes a sustainable source of revenue available for long-term operations and maintenance. Pavement and bridge management systems are used by the City to determine the optimal time for surface treatment repairs and reconstruction based on minimizing life cycle costs. The proposed project has been prioritized through an infrastructure assessment and would be managed by the City’s established system performance management tools. The infrastructure assessment characterizes investments that will reduce life cycle costs. The requested TIGER funds will not be used for maintenance or operations of the project. When complete, all of the improvements will fall under the City’s jurisdiction. accommodate this planned growth is deteriorated and incomplete. The traditional grid network in the established areas of Fort Collins does not extend to this area. In fact, the only north/south roadways connecting completely through this area are US 287 (College Avenue), Lemay Avenue and I-25. US Highway 287 and Lemay Avenue are one mile apart. I-25 is another three miles east Photo 4: Railroad Facilities and Operations Looking East from a Location Just East of the Vine/Lemay/BNSF Intersection Photo 5: Deficient Structure Located on Lemay Avenue Looking North. ARIZONA KANSAS COLORADO OKLAHOMA NEW MEXICO NEBRASKA Figure 2: National and State Setting Figure 3: Regional and Local Setting (N.T.S.) FORT COLLINS Julie Brewen, CEO/Executive Director, Fort Collins Housing Authority Olga Duvall, Chair, Fort Collins Transportation Board $112,784 per year Emissions Reductions CO = 2,312 kg per year NOx = 441 kg per year VOC = 522 kg per year Other Benefits (Not Quantified) Road Maintenance Savings Emergency Vehicle Response Increased Population (+13,347) Additional Jobs (+15,065) Local Funding Sources Cost 1. City of Ft. Collins 2015 Appropriation to Project $ 1M 3. Street Over-sizing $ 5M 4. Local Street Developer Obligation $ 1.5M 5. City General Fund $ 2.5M TOTAL $ 10M Improvement Cost Grade Separation of the BNSF/Lemay Intersection $ 12M Construction of Four-Lane Arterial Roadways $ 8M Bicycle/Pedestrian Facilities and Landscaping $ 6M Neighborhood Street (Local Street) Construction $ 1M $ 27M proposed improvements and land use planning. Costs and Benefits The cost of the grade separation of the Suniga/Lemay intersection totals $27 million. The local contribution to this project is $10 Million, which represents a 37% match toward the overall $27 Million project cost. The funding request of the TIGER program is $17 Million. Detailed project costs are outlined in Appendix B, the Project Development Report. transportation system through separating roadway from rail and creating a more direct and efficient connection into and out of downtown. This project would also focus on improving the multi-modal transportation system to serve all modes safely and efficiently. The applicant must pay a fee of 1/2 of 1% of the loan amount to FRA for financing and legal reviews. FRA requires new applicants to attend an information session, submit a draft application, and then meet with FRA who will provide feedback on the draft application. Final applications are submitted, reviewed, and once approved, the loan conditions are negotiated and closed. http://www.fra.dot.gov/Page/ P0128 Public Works and Economic Adjustment Assistance Programs EDA Under the programs, grant funds are issued to provide investments that support construction, non- construction, technical assistance, and revolving loan fund projects. Grants and cooperative agreements are designed to leverage existing regional assets and support the implementation of economic development strategies that advance new ideas and creative approaches to advance economic prosperity in distressed communities. The investments are aimed at supporting economic development, supporting job creation, and attracting private investment in economically distressed areas. (1) Projects must be located in a Region that meets EDA’s distress criteria. Proposed projects should be consistent with an approved regional Comprehensive Economic Development Strategy (CEDS). Eligible organizations include a(n): district organization of a designated Economic Development District, Indian tribes, state/county/city or other political subdivision of a state, institution of higher education, public or private non-profit organizations. Beneficiaries of investments made under Public Works are those communities who satisfy one or more of the economic distress and/or “Special Need” criteria set forth in 13 C.F.R. § 301.3(a) and 13 C.F.R. § 300.3 to revitalize, expand, or upgrade their physical infrastructure to attract new industry, encourage business expansion, diversify their local economies, and generate or retain long-term private sector jobs and capital investments. Project improves an access-road to a future commercial business center, which will support employment growth in the region. Public Works: FY 2012: $111.6M FY 2013: $112.3M FY 2014: $40.5M (requested) The average size of a Public Works investment was $1.4M in FY 2013. Economic Adjustment Assistance: FY 2012: $50.1M FY 2013: $50.4M FY 2014: $66M (requested) The average award for the Economic Adjustment Assistance program was $820,000 in FY 2013. Typically 50%, but might vary. Projects may receive an additional amount, up to 30% of the project cost, based on the relative needs of the region, as determined by EDA. Applications are competitively evaluated in quarterly funding cycles (March 14, June 13, and October 17) and decisions generally are made within 20 business days of the funding cycle deadline. An applicant may submit an application at any time to receive feedback on the application’s competitive and technical merits. (1) https://ofmpub.epa.gov/apex/ watershedfunding/f?p=116:2:0: :NO::P2_X_PROG_NUM,P2_X_Y EAR:51,2014 http://www.grants.gov/web/gr ants/view- opportunity.html?oppId=24829 7 https://www.cfda.gov/index?s =program&mode=form&tab=st ep1&id=e5254fa16829ebe6a08d d1c79126ec8d http://www.osec.doc.gov/bmi/ budget/FY14CJ/EDA_FY_2014_C J_Final_508_Compliant.pdf (1) Taken from website Notes: FY2013 Apportionments from http://www.fhwa.dot.gov/legsregs/directives/notices/n4510765/n4510765_t1.cfm FY2014 Apportionments from http://www.fhwa.dot.gov/legsregs/directives/notices/n4510770t1.cfm TIGER I: $1.5B, average award $29.4M TIGER II: $600M, average award $8M FY 2011: $526.944M, average award $11.5M FY 2012: $500M, average award $10.6M FY 2013: $473.847M, average award $9.1M TIGER 2014: $600M Awards may not be less than $10M (except in rural areas) and not greater than $200M. Projects are more competitive if they demonstrate funding support above a 20% match for urban areas and a 0% match for rural areas. For TIGER 2014: April 28, 2014 The President's budget proposal includes 4 years with $1.25 billion annually. http://www.dot.gov/tiger http://www.dot.gov/sites/dot. gov/files/docs/TIGER%202014% 20NOFA_FINAL.pdf Transportation Infrastructure Finance and Innovation Act (TIFIA) USDOT The program provides Federal credit assistance in the form of direct loans, loan guarantees, and standby lines of credit to finance surface transportation projects of national and regional significance. TIFIA credit assistance provides improved access to capital markets, flexible repayment terms, and potentially more favorable interest rates than can be found in private capital markets or similar instruments. (1) To qualify for TIFIA assistance, a project must meet the following criteria: - Minimum project cost of $50M, or minimum $15M for ITS projects or minimum $25M for rural projects - Federal funding cannot exceed 33% of eligible costs or the amount of senior debt if the TIFIA loan does not have an investment grade rating - Senior debt obligations must receive an investment grade rating - The project must have a dedicated revenue source to pledge as repayment on the TIFIA loan Types of projects that are eligible for TIFIA assistance include: highway facilities, bridges, transit design and construction, passenger rail design and construction, public freight rail facilities, intermodal facilities, projects providing access to rail facilities, and port projects. The project can be considered to be of regional significance, as it will provide for the future development of a commercial district and transit service to this important employment center. Funding for credit subsidy: FY 2013: $690M FY 2014: $920M Based on historic subsidy costs, the budget authority could approximately support a lending capacity of FY 2013: $6.9B FY 2014: $9.2B Colorado has used the TIFIA program for 3 projects: - Denver Union Station, $145.6 million TIFIA direct loan, funded by the 0.4 percent FasTracks sales and use tax - Eagle Project (RTD), $280 million direct loan, funded by lien pledges on sales tax revenues - U.S. 36 Managed Lanes/BRT Project Segments 1 and 2, $54 million TIFIA direct loan, repaid by toll revenues collected on the managed lanes TIFIA offers three types of credit assistance: - Secured (Direct) Loans offers flexible repayment terms - Loan guarantees by the Federal government to institutional investors - Lines of credit to supplement project revenues Estimated timeframe for initial review is 30 days. The estimated timeframe for creditworthiness review is 45-90 days. Estimated timeframe for approval is 90 days after receipt of application. Estimated timeframe for execution of a credit agreement is 60 days from the application approval date. http://www.fhwa.dot.gov/ipd/ tifia/ http://www.fta.dot.gov/grants /12861.html Activities funded under this program are also eligible for funding under the broader HSIP eligibilities. The STP also includes eligibility for funding of railway-highway crossings projects. http://www.fhwa.dot.gov/map 21/factsheets/rhc.cfm http://safety.fhwa.dot.gov/xin gs/ Highway Safety Improvement Program (HSIP) FHWA The program seeks to achieve a significant reduction in traffic fatalities and serious injuries on all public roads, including non-State- owned public roads and roads on tribal lands. The HSIP requires a data- driven, strategic approach to improving highway safety on all public roads that focuses on performance. (1) A highway safety improvement project is any strategy, activity or project on a public road that is consistent with the data-driven State Strategic Highway Safety Plan (SHSP) and corrects or improves a hazardous road location or feature or addresses a highway safety problem. MAP- 21 provides an example list of eligible activities, but HSIP projects are not limited to those on the list. $220M of the HSIP program is set aside for the Railway-Highway Crossings program. Workforce development, training, and education activities are also an eligible use of HSIP funds. (1) Project eliminates an at- grade rail crossing, thereby reducing the likelihood of safety incidents. FY 2013: $2.39B* ($29.62M apportioned to Colorado) FY 2014: $2.41B* ($29.64M apportioned to Colorado) *Calculated as a sum of the estimated individual State HSIP apportionments Except as provided in 23 U.S.C 120(c) and 130, the Federal share is 90% Not Described From the State's HSIP apportionment, the following sums are to be set aside: -Railway-highway crossings -- $220 million. -A proportionate share of funds for the State's Transportation Alternatives (TA) program. -2% for State Planning and Research (SPR). http://safety.fhwa.dot.gov/hsi p/ http://www.fhwa.dot.gov/map 21/factsheets/hsip.cfm Surface Transportation Program (STP) FHWA The program provides flexible funding that may be used by States and localities for projects to preserve and improve the conditions and performance on any Federal-aid highway, bridge and tunnel projects on any public road, pedestrian and bicycle infrastructure, and transit capital projects, including intercity bus terminals. (1) Construction, reconstruction, rehabilitation, resurfacing, restoration, preservation, or operational improvements for highways, including designated routes of local access roads under 40 USC 14501. Replacement, rehabilitation, preservation, protection, and anti-icing/deicing for bridges and tunnels on any public road, including construction or reconstruction necessary to accommodate other modes. Highway and transit safety infrastructure improvements and programs, installation of safety barriers and nets on bridges, hazard eliminations, mitigation of hazards caused by wildlife, railway-highway grade crossings. Surface transportation planning. Intersections with high accident rates or levels of congestion. Construction and operational improvements for a minor collector in the same corridor and in proximity to an NHS route if the improvement is more cost-effective (as determined by a benefit-cost analysis) than an NHS improvement and will enhance NHS level of service and regional traffic flow. Project proposes the construction of a bridge to grade-separate the rail from the road, thereby improving performance of both modes. The project is in the proximity of two NHS routes (SH 14 and US Route 287). FY 2013: $10.0B* ($137.22M apportioned to Colorado) FY 2014: $10.1B* ($137.34M apportioned to Colorado) *Calculated as a sum of the estimated individual State HSIP apportionments Determined in accordance with 23 USC 120, including a special rate for certain safety projects and a new provision for increased Federal share for projects incorporating Innovative Project Delivery. Exceptions to 23 USC 120 are provided for certain freight projects, workforce development, training, and education activities, and Appalachian development highway system projects. Not Described 50% of a State's STP apportionment (after TA and SPR set-asides) is to be obligated in the following areas in proportion to their relative shares of the State's population: -Urbanized areas with population greater than 200,000 (this portion is to be divided among those areas based on their relative share of population) -Areas with population greater than 5,000 but no more than 200,000 (projects in these areas are to be identified for funding by the State in consultation with regional planning organizations, if any) -Areas with population of 5,000 or less The remaining 50% may be used in any area of the State. http://www.fhwa.dot.gov/map 21/factsheets/stp.cfm The City could also dedicate future BOB or KFCG revenues to repay low-interest federal or CO SIB loans. The City has issued bonds, but has not done so with BOB revenues. Additional discussions with City Finance Department would need to be held to discuss the potential bonding capacity and implications for future projects. Would depend on the bond rating of the City, interest rate, and projected future sales tax revenues. The timeframe for this financing source would be longer given that it would be a new financing structure for the City and has implications on planned use of future local dedicated sales tax revenues. Colorado State Infrastructure Bank (CO SIB) The program provides low-interest bearing loans to public or private sponsors of public transportation projects to help fund transportation projects in Colorado. Qualified projects include any commission-authorized project, right-of-way acquisition, federal-aid project, maintenance project, or safety project. Commission authorized projects include, but are not limited to, environmental impact studies, feasibility studies, engineering, construction, reconstruction, resurfacing, restoring, rehabilitation, or replacement of a public or private transportation facility within the state. Right-of-way acquisition is defined as "the acquisition of real or personal property, or interests therein, for a public or private transportation facility within the state". Federal projects include any highway, transit, aviation, rail, or other transportation project within the state that is eligible for financing or financial assistance under state or federal law. Maintenance project is one that is focused on maintenance, repair, improvement, or construction of any public or private highway, road, street, parkway, transit, aviation, or rail project within the state. Safety projects involve the acquisition, improvement, or construction of rights-of-way, bridges, tunnels, railroad-highway crossings, drainage structures, signs, guardrails, or protective structures within this state. The project must not include transportation facilities or other projects that will be restricted to private use. Project shall be evaluated on the following criteria: the type of project, whether it is a public/private partnership, financial need, repayment source, security provisions or sponsor's potential to secure the loan, evaluation of financial ratios and project's current financial condition, the term of financial obligation(no more than 10 years), project viability, project benefits to the transportation system, and whether or not their project is in the TIP/STIP. The committee determines the size of the loan based on the sponsor's ability to repay it within a specified period of time, regardless of cost of the project. Based on the committee's recommendation, the commission then sets the maximum amount of the loan that the project sponsor can get. Currently, $3.8 million in CO SIB funding is available for highway projects at a 2.5% interest rate (for 3rd and 4th quarter of FY 2014). The application process is on a rolling basis. The review process usually takes no longer than 2 months. The loan shall be repaid in no more than 10 years. http://www.coloradodot.info/business/budg et/colorado-state-infrastructure-bank-co- sib.html MAPCCOONNSSTTRRAAIINNTTSS EXTENT Fort Collins Windsor Loveland ¦¨§25 «¬14 ¤£287 «¬14 0 200 400 Feet Legend Flood Zones Regulatory Floodway 100-Year Floodplain Natural Habitat Areas Wet Meadow Riparian Forest Native Upland Plains Forest Emergent Wetland Aquatic Water Stormwater Wastewater Overhead Power Line Utilities Parcel Boundary National Wetlands Inventory Stream Ditch Railroad Bike Lane Community Path Transportation utilizes the switching yard. By the year 2035, the lingering congestion effects in the street network system continues up to 30 minutes after the train crossing event. This doubling of system delay and long-lasting residual system effects further demonstrates the need to make improvements. · The future effectiveness, year 2035, of the relocated at-grade crossing will greatly depend on whether the switching yard can be relocated or must stay: o If the switching yard is moved, system delays due to a train crossing event are negligible when compared to the delays encountered in the system without a train. o If the switching yard remains, system delays due to a train crossing event with switching movements are 16% higher than when the compared to the delays encountered in the system without a train. MAP EXTENT UNDERPASS Fort Collins Windsor Loveland ¦¨§25 «¬14 ¤£287 «¬14 0 200 400 Feet (Wall Legend Underpass Alignment Proposed Sidewalk Railroad Parcel Boundary Stream Ditch Water Stormwater Wastewater Utilities 1. Existing crossing may need to be closed to get railroad concurence on new overpass. Potential to remain open in limited capacity. 2. Old Vine to remain open until new Vine Connection to east is complete.. Possible to remain open in ultimate condition. ¤£287 «¬14 0 200 400 Feet (Retaining Wall Legend Overpass Alignment Proposed Sidewalk Parcel Boundary Stream Ditch Railroad Water Stormwater Wastewater Utilities 1. Existing crossing may need to be closed to get railroad concurence on new overpass. Potential to remain open in limited capacity. 2. Old Vine to remain open until new Vine Connection to east is complete.. Possible to remain open in ultimate condition. Water Stormwater Wastewater Utilities Ditch Stream Parcel Boundary Railroad 1. Existing crossing may need to be closed to get railroad concurence on new overpass. Potential to remain open in limited capacity. to proximity to Dry Creek Neighborhood Connectivity* The ability to maintain a pedestrian and bicycle crossing at the existing crossing location is possible, but will require both PUC and BSNF approvals. Continue to explore all complimentary strategies for improving safety and connectivity. Construction Risks Constructing new at-grade crossing while keeping BNSF operational will be difficult. General construction risks. Timing of placing bridge girders over operational tracks. Constructability of underpass in high groundwater, and constructing BNSF tracks is complex without a shoe-fly option. Total Project Cost $23 to $24 million $26 to $27 million $40-$41 million