March 15, 2018
Mr. Craig Kisling
City of Fort Collins Park Planning & Development
P.O. Box 580
215 North Mason
Fort Collins, CO 80522
RE: East Community Park Underdrain – Construction Proposal
Dear Craig,
We are pleased to offer our construction proposal for the East Community Park Underdrain Project.
Attached is a fee schedule based on our site visit March 6th, 2018 and the construction plans
provided by Anderson Engineers.
If you have any questions or concerns, please contact me at (970) 222-4124 or ghaas@garney.com.
Sincerely,
GARNEY COMPANIES, INC.
Gary Haas
Project Manager
Project: East Community Park Underdrain System
Date: March 15, 2018
Schedule of Values
Item Unit of Estimated Unit Item
Number Description Measure Quantity Cost ($) Cost ($)
UNDER DRAIN PIPING
1 Mobilization & Field Overhead LS 1 13,890.00 13,890.00
2 Traffic Control - Provided by CoFC LS 1 - -
3 Sediment & Erosion Control LS 1 410.00 410.00
4 Construction Dewatering LS 1 6,020.00 6,020.00
5 Potholing LS 1 - -
6 Install 12" SDR-35 PVC Piping LF 2,313 65.00 150,345.00
7 Install Precast Manholes EA 4 3,200.00 12,800.00
8 Topsoil Placement - Subcontractor LS 1 43,080.00 43,080.00
UNDER DRAIN PIPING
TOTAL ESTIMATED COST FOR CONSTRUCTION $ 226,545.00