CHANGE ORDER NO. 1
PROJECT TITLE: Utilities Cathodic Protection Program Master Plan Update
CONSULTANT: HDR Engineering Inc.
PROJECT NUMBER: PO 9173498 and BU 5020400914
DESCRIPTION:
1. Reason for change: Contract completion date change, more time is needed to complete the
master plan update analysis and report submittal.
2. Description of Change: the current contract completion date of February 28, 2018, will be
exceeded; thus this contract completion date revision.
3. Change in Contract Cost: No change in contract cost.
4. Change in Contract Time: Change contract completion date to June 1, 2018.
ORIGINAL CONTRACT COST $79,045.00
TOTAL APPROVED CHANGE ORDERS 0.00
TOTAL PENDING CHANGE ORDERS 0.00
TOTAL THIS CHANGE ORDER 0.00
TOTAL % OF THIS CHANGE ORDER 0%
TOTAL C.O.% OF ORIGINAL CONTRACT 0%
ADJUSTED CONTRACT COST $79,045.00
(Assuming all change orders approved)
ACCEPTED BY: DATE:
Consultant’s Representative
ACCEPTED BY: DATE:
Special Projects Manager
REVIEWED BY: DATE:
Chief Engineer
APPROVED BY: DATE:
Water Engineering & Field Services Interim Manager
APPROVED BY: DATE:
Purchasing Agent over $60,000
DocuSign Envelope ID: 7B995C5A-2A05-404C-808E-DE1746954243
1/8/2018
1/9/2018
1/11/2018
1/11/2018