SECTION 00950
CHANGE ORDER NO. 2
PROJECT TITLE: WTF Reservoir Drainage System Construction Project
CONTRACTOR: Hydro Construction
PROJECT NUMBER: PO9175096 and BU 5026310067
DESCRIPTION:
1. Reason for change: Additional site work items to complete the construction the Reservoir
Drainage System project will require additional time.
2. Description of Change: Additional section of inlet wall.
3. Change in Contract Cost: $0.00
4. Change in Contract Time: With the new modification the contract final completion will change
from March 31, 2018 to August 30, 2018. Substantial completion has been achieved.
ORIGINAL CONTRACT COST $163,358.00
TOTAL APPROVED CHANGE ORDERS $22,137.43
TOTAL PENDING CHANGE ORDERS $0.00
TOTAL THIS CHANGE ORDER $0.00
TOTAL % OF THIS CHANGE ORDER 0.0%
TOTAL C.O.% OF ORIGINAL CONTRACT
ADJUSTED CONTRACT COST
13.6%
$ 185,495.43
(Assuming all change orders approved)
ACCEPTED BY: DATE:
Contractor's Representative
ACCEPTED BY: DATE:
Special Projects Manager
REVIEWED BY: DATE:
Senior Engineer
APPROVED BY: DATE:
Water Production Manager
APPROVED BY: DATE:
Water Resources/Treatment Manager
2-28-18
REVIEWED BY: DATE:
Senior Buyer
APPROVED BY: DATE:
Purchasing Agent over $60,000