HomeMy WebLinkAboutCHANGE ORDER - RFP - 7220 WATER WW TREATMENT & SITE INFRASTRUCTURE DESIGN CONSTRUCTION CONTRACTOR (21)WTF CCB Phase 3 Contract Change Order November 2016 00950-1 SECTION 00950 CHANGE ORDER NO. 5 PROJECT TITLE: WTF Chlorine Contact Basin Phase 3 Construction CONTRACTOR: Hydro Construction PROJECT NUMBER: Business Unit 5020331000, PO9162138 DESCRIPTION: 1. Reason for change: City staff has requested modification of existing hatch to an alternative cover. The CCB will need to be taken off line in order to accomplish the modification and the next available opportunity will be in the Fall of 2018. 2. Description of Change: additional work items include removal of existing large hatch and the installation of an alternative cover. 3. Change in Contract Cost: $0.00 4. Change in Contract Time: With the new modification the contract final completion will change from March, 2018 to December 31, 2018. Substantial completion has been achieved. ORIGINAL CONTRACT COST TOTAL APPROVED CHANGE ORDERS TOTAL PENDING CHANGE ORDERS TOTAL THIS CHANGE ORDER $6,852,437.00 $833,818.00 $0.00 $0.00 TOTAL % OF THIS CHANGE ORDER 0.0% TOTAL C.O.% OF ORIGINAL CONTRACT 12.2% ADJUSTED CONTRACT COST $ 7,686,255.00 (Assuming all change orders approved) ACCEPTED BY: DATE: Contractor's Representative ACCEPTED BY: DATE: Special Projects Manager REVIEWED BY: DATE: Chief Engineer APPROVED BY: DATE: Water Production Manager APPROVED BY: DATE: Water Resources/Treatment Manager 2/28/18 REVIEWED BY: DATE: Senior Buyer APPROVED BY: DATE: Purchasing Director, over $60,000 DocuSign Envelope ID: BA4E80F1-1A49-4A65-882D-251DE64D5868 3/5/2018 3/5/2018 3/5/2018 3/5/2018