HomeMy WebLinkAboutCORRESPONDENCE - RFP - 8413 GEOTECHNICAL SERVICES ON-CALL (19)6/1/2018
400 North Link Lane | Fort Collins, Colorado 80524
Telephone: 970-206-9455 Fax: 970-206-9441
May 25, 2018
Downtown Development Authority
C/O Ditesco Project & Construction Services
2133 S Timberline, Unit 110
Fort Collins, Colorado 80525
Attention: Ms. Jenna Beairsto
Subject: Fee Estimate for Construction Observation
and Materials Testing Services
Downtown Alley Enhancements
West Mountain and Old Firehouse Alleys
Fort Collins, Colorado
Proposal No. FC-18-0246
At your request, CTL|Thompson, Inc. is pleased to provide this fee estimate for Construction
Observation and Materials Testing services for the Downtown Alley Enhancements - West Mountain
and Old Firehouse Alleys project located in Fort Collins, Colorado. We used the plans provided in
preparation of our proposal.
We anticipate that our estimate will be used for the basis of establishing a budget for the project and to
issue a purchase order for our services. Our estimated scope of services and associated fees were
prepared according to the terms and conditions of our professional services agreement with the City of
Fort Collins and are presented below.
Earthwork: Compaction testing will be required for alley subgrade. We estimate that a total of 24
site visits and 3 proctors will be necessary for this project.
Engineering Technician
24 days x 2 hrs/day x $70/hr
$3,360.00
Standard Proctor
3 tests x $100/ea
$300.00
Atterberg Limits
3 tests x $70/ea
$210.00
Gradation
3 tests x $50/ea
$150.00
Subtotal:
$4,020.00
Concrete Testing: Concrete testing will be required for the curb, sidewalk, and alleyways. We
estimate that a total of 38 concrete tests consisting of 5 cylinders each will be necessary for this
project.
Concrete Cylinders
38 tests x $180/test
$6,840.00
Subtotal:
$6,840.00
DOWNTOWN ALLEY ENHANCEMENTS
CTL | T PROPOSAL NO. FC-18-0246
2
Asphalt Testing: Compaction testing may be required for the asphalt patching in the roadways. We
estimate 3 site visits will be necessary.
Engineering Technician
3 days x 3 hrs/day x $70/hr
$630.00
Subtotal:
$630.00
TOTAL ESTIMATED FEE: $11,490.00
It should be emphasized that this estimate is based upon assumptions of actual quantities and
contractor’s schedule. The fee will be charged only for the actual hours and unit rates presented for
tests and observations requested by the owner, contractor or subcontractors who schedule the
services.
If we can be of further assistance, please contact us at your convenience.
Very truly yours,
CTL | THOMPSON, INC.
Heather Grubb
Field Department Manager