HomeMy WebLinkAboutCORRESPONDENCE - PURCHASE ORDER - 9183066Utilities Work Order Form Official Purchasing Form
Last updated 10/2017
WORK ORDER
PURSUANT TO A MASTER AGREEMENT BETWEEN
THE CITY OF FORT COLLINS
AND
DITESCO
WORK ORDER NUMBER: D - WRF-2018-13
PROJECT TITLE: DWRF Yard Piping Map Phase I
ORIGINAL BID/RFP NUMBER & NAME: 7515, Consulting Engineering Services for
Future W/WW & Stormwater Facilities Capital Improvements
MASTER AGREEMENT EFFECTIVE DATE: July 22, 2013
ARCHITECT/ENGINEER: Ditesco
OWNER’S REPRESENTATIVE: Eileen Dornfest
WORK ORDER COMMENCEMENT DATE: April 19, 2018
WORK ORDER COMPLETION DATE: July 31,2018
MAXIMUM FEE: (time and reimbursable direct costs): $9,650.00
PROJECT DESCRIPTION/SCOPE OF SERVICES: Complete phase 1 of DWRF yard piping
map. See attached supporting documentation.
Service Provider agrees to perform the services identified above and on the attached forms in
accordance with the terms and conditions contained herein and in the Master Agreement
between the parties. In the event of a conflict between or ambiguity in the terms of the Master
Agreement and this Work Order (including the attached forms) the Master Agreement shall
control.
The attached forms consisting of four (4) pages are hereby accepted and incorporated herein,
by this reference, and Notice to Proceed is hereby given after all parties have signed this
document.
SERVICE PROVIDER: Ditesco
By: Date:
Name: Title:
Page 1 of 7
DocuSign Envelope ID: 32088731-9687-4D43-8B3E-39F28348FE62
Owner/Manager
April 14, 2018
KEITH MEYER
Utilities Work Order Form Official Purchasing Form
Last updated 10/2017
OWNER’S ACCEPTANCE & EXECUTION:
This Work Order and the attached Contract Documents are hereby accepted and incorporated
herein by this reference.
ACCEPTANCE: Date:
Eileen Dornfest, Special Project Manager
REVIEWED: Date:
Pat Johnson, Senior Buyer
APPROVED AS TO FORM: Date:
Name,City Attorney's Title
(if greater than $1,000,000)
ACCEPTANCE: Date:
Owen Randall, Water Systems Engineering Division Manager
ACCEPTANCE: Date:
Jason Graham, Water Reclamation & Biosolids Division Manger
ACCEPTANCE: Date:
Carol Webb, Water Resources & Treatment Operations Manager
ACCEPTANCE: Date:
Kevin Gertig, Utilities Executive Director
(if greater than $1,000,000)
ACCEPTANCE: Date:
Gerry Paul, Purchasing Director
(if greater than $60,000)
ACCEPTANCE: Date:
Darin Atteberry, City Manager
(if greater than $1,000,000)
ATTEST: Date:
City Clerk
(if greater than $1,000,000)
Page 2 of 7
DocuSign Envelope ID: 32088731-9687-4D43-8B3E-39F28348FE62
April 12, 2018
April 12, 2018
May 15, 2018
April 16, 2018
May 16, 2018
Utilities Work Order Form Official Purchasing Form
Last updated 10/2017
ATTACHMENT A
WORK ORDER SCOPE OF SERVICES & COST DETAIL
Page 3 of 7
DocuSign Envelope ID: 32088731-9687-4D43-8B3E-39F28348FE62
Page 1 of 4
2133 S. Timberline Rd, Ste. 110
Fort Collins, CO 80525
ditescoservices.com
Delivery by email
edornfest@fcgov.com
March 20, 2018
Ms. Eileen Dornfest
City of Fort Collins
700 Wood Street
Fort Collins, CO 80524
RE: DWRF Mapping Work Order
Dear Eileen:
Thank you for giving Ditesco the opportunity to provide engineering support, and reconciliation of underground
utility mapping for the City of Fort Collins Drake Water Reclamation Facility (DWRF). Please find attached our
proposed scope of work to support a new work order; this has been provided to continue the work on the DWRF
base mapping project.
Please let me know if you have any questions or require further information regarding this proposal, I can be
reached by phone at 970.988.8605 and email keith.meyer@ditescoservices.com.
Sincerely,
Keith Meyer, P.E.
Enc. Scope
Cc: file
Page 4 of 7
DocuSign Envelope ID: 32088731-9687-4D43-8B3E-39F28348FE62
Page 2 of 4
Exhibit A
City of Fort Collins Utilities
On Call Services
Scope of Services
Project Understanding
The City of Fort Collins has project record drawings of work completed at the Drake Water Reclamation Facility
(DWRF) dating back to the 1950s. These documents are both hard copy and electronic providing information about
underground utilities on the site. The City of Fort Collins (COFC) Utilities Department would like to develop a base
map of all utilities at the DWRF site for future use. This tool would provide a better understanding for planning of
future Capital Improvement Projects and future master planning efforts.
The City of Fort Collins will utilize Ditesco’s on-call contract with the Utilities Department to develop an AutoCAD
Civil 3D utility map of the Drake Water Reclamation Facility. Ditesco will utilize the existing CAD files provided by
City to begin this base map effort. Ditesco will then further this effort through the use of as-built drawings, both hard
copy and electronic to develop a base map for the DWR Facility.
Phase 1 – Data Collection
Ditesco staff has participated in coordination meeting with DWRF staff to begin the process of base map
data collection; this has yielded (COMPLETE)
Ditesco staff completed initial planning meetings with City of Fort Collins staff to finalize the scope of the
utility mapping effort. (COMPLETE)
Ditesco staff will utilize COFC electronic project records to continue populating a Civil 3D base map. These
electronic records will be supplemented with hard copy project records. This work will include added map
book data to the AutoCAD base map.
Ditesco will scan any necessary hard-copies for electronic use. All scanned plan files will be furnished by
the City of Fort Collins.
Ditesco will participate in ongoing project review meetings with City of Fort Collins. These are assumed to
twice during this final phase of the AutoCAD mapping project.
Phase 2 – Mapping
Ditesco will utilize the selected base map layer naming structure for all waste water facilities. This has been
reviewed with City of Fort Collins staff prior to finalizing the mapping effort. (COMPLETE)
Ditesco will populate the map with current utility information. Any conflicting utility information will be
reviewed with COFC plant staff to clarify discrepancies.
The mapping effort will identify utility type and pipe size, when known.
The mapping effort will also include project survey control points.
As an option, Ditesco has provided an estimated cost to create the GIS attribute interface for future
attribute addition to the map. If this option is taken, this cost will be deducted from the future Phase 3.
Phase 3 – GIS Online (future phase)
• Ditesco staff will coordinate with Invision GIS to develop a GIS-based map of the Drake Water Reclamation
Facility utilities. This base map will be initially developed utilizing the Civil 3D mapping file.
• Ditesco staff will add attributes to all pipe systems through the GIS database as developed by Invision.
• The GIS mapping database will contain polygon layers, linking PDF record drawings to the GIS map, based
on the drawing area. These will not be linked individually to each attribute.
• Future deliverable for this phase is an online GIS integrated map with attributes.
Deliverables
Deliverables will include Civil 3D AutoCAD file containing all base map utility information.
Page 5 of 7
DocuSign Envelope ID: 32088731-9687-4D43-8B3E-39F28348FE62
Page 3 of 4
Schedule
The anticipated schedule for this scope of work is to have all items complete by June 2018.
Fee Estimate
We have based our fee estimate on the following assumptions of the project schedule.
• 2-month remaining project timeframe
Estimated Fee: $6,100.00
Estimated Reimbursable Expenses: $ 350.00
Subtotal: $6,450.00
Optional GIS Attribute Interface: $3,200.00
Total Fee: $9,650.00
Future GIS Online Phase: $27,023.00
The fee shown above is to be billed on a time and material not to exceed basis based on the rates shown in the table on page 4
of this proposal. All reimbursable expenses will be billed at direct cost.
Page 6 of 7
DocuSign Envelope ID: 32088731-9687-4D43-8B3E-39F28348FE62
City of Fort Collins - DWRF Mapping
March to June 2018 3/20/2018
Project Manager Project Engineer CAD / Design
(hrs) (hrs) (hrs)
$135 $110 $80
Phase 1: Data Collection $1,200
1.1 Coordination Meetings - 2 meetings with plant staff 0 4 0 $440
1.2 Review all Electronic Project Records 0 2 4 $540
1.3 Review all Hard Copy Project Records 0 2 0 $220
Phase 2: Mapping $4,900
2.1 Finalize base map with all electronic and hard copy records 2 4 12 $1,670
2.2 Reconcile utility data 0 4 16 $1,720
2.3 Input all survey data and control point information 0 0 2 $160
2.4 Quality Control Deliverables 2 4 8 $1,350
2.5 GIS Attribute interface creation (optional) 0 0 0 $3,200
Phase 3: GIS Online (future phase) $27,023
3.1 Create Polygon Layers for Base Drawings 0 12 4 $1,640
3.2 Add attributes to all pipe systems (Assumes 9 plan sets x 5hrs/set) 0 45 0 $4,950
3.3 Quality Control Deliverables (Assumes 9 plan sets x 2hrs/set) 2 18 0 $2,250
GIS Subconsultant Create GIS Database $18,183
Reimbursable Expenses
Reprographics: Scan 24"x36" hard copy files $250
Reprographics: Printing $100
Work Effort Subtotal 6 95 46 $6,100
Subtotal Reimbursable Items $350
Contract Subtotal $6,450
With GIS Attribute Interface (option) $3,200
Contract Total $9,650
Cost per labor category $810 $10,450 $3,680
Effort (days) 1 12 6
Effort (weeks) 0 2 1
Effort (hours per day) 1 1 1
Assumptions:
- 2 month project (8 weeks)
- Start Date - April 2018
- End Date - June 2018
Phase/Task Description Task Total
Classification
Page 4 of 4
Page 7 of 7
DocuSign Envelope ID: 32088731-9687-4D43-8B3E-39F28348FE62