HomeMy WebLinkAboutCORRESPONDENCE - BID - 8519 MAPLE HILL NEIGHBORHOOD PARK (4)301 Centennial Drive CHANGE ORDER REQUEST
Milliken, CO 80534 Owner
Office: (970)587-7200 Contractor
Fax: (970)352-6284 Architect
Other
PROJECT: Maple Hill Park CHANGE ORDER REQUEST #: 03
OWNER NAME: City of Fort Collins Parks & Development
Attn: Matt Day
215 N. Mason 3rd Floor
Fort Collins, CO 80522
DATE: 12/6/2017
THE CONTRACT IS CHANGED AS FOLLOWS:
Item Description Quantity Units Unit Price Extension
CI 01 1 LS $ 33,425.77 $ 33,425.77
CI 02 1 LS $ 2,110.25 $ 2,110.25
CI 03 1 LS $ 3,975.00 $ 3,975.00
CI 04 1 LS 5 Days
Add 5 Schedule
Days to Project
Schedule
TOTAL $ 39,511.02
Not Valid Until Signed by the Owner and Contractor
The original Contract Sum was . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $2,393,499.11
Net Change by previously authorized Change Orders . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ($17,964.00)
The Contract Sum prior to this Change Order was . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $2,375,535.11
The Contract Sum will be increased
by this Change Order in the amount of . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $39,511.02
The new Contract Sum including this Change Order will be. . . . . . . . . . . . . . . . . . . . . . . . . . $2,415,046.13
The Contract Time will be increased by 5 days
The date of Substantial Completion
1/13/2018
All change orders will be reviewed in an accumulated manner for both time and cost impact as they relate to the ongoing impacts
on the project. Accumulated time and cost impacts will then be forwarded under a separate change order.
City of Fort Collins Parks & Development Alms2S Hall-Irwin Corporation
215 N. Mason 3rd Floor 712 Whalers Way 301 Centennial Drive
Suite B-100
Fort Collins, CO 80522 Fort Collins, CO 80525 Milliken, CO 80543
By: ______________________________ By: __________________________ By: ________________________
Date: ____________________________ Date _________________________ Date: _______________________
Install 18" Boulder Edge Along Pond
Add power through the time clock for three
bench lights with in-ground boxes. Two
boxes in the dirt/gravel, and 1 to be poured
in concrete. Liquid tight flex whips to feed
benches.
Install a second circuit to the outlet on the
shelter, with a split outlet. Also add a
dedicated circuit to power a controller for
the door lonks, this includes the wiring for
the sensor touch push bar and locks.
as of the date of this Change Order therefore is:
Additional schedule days added to
complete electrical and boulder work
above