WORK ORDER
PURSUANT TO A MASTER AGREEMENT BETWEEN
THE CITY OF FORT COLLINS
AND
HDR ENGINEERING, INC.
WORK ORDER NUMBER: 5026410131
PROJECT TITLE: Zone 3 - Old Town Library Water and Wastewater
ORIGINAL BID/RFP NUMBER & NAME: 8073, Engineering Services for Water, WW
and Stormwater Facilities Capital
Improvements
MASTER AGREEMENT EFFECTIVE DATE: May 15, 2015
ARCHITECT/ENGINEER:
OWNER’S REPRESENTATIVE: Brian Mulligan
WORK ORDER COMMENCEMENT DATE: October 23, 2017
WORK ORDER COMPLETION DATE: February 23, 2018
MAXIMUM FEE: (time and reimbursable direct costs): $125,962.00
PROJECT DESCRIPTION/SCOPE OF SERVICES:
Work includes professional services in the conceptual design and scoping of the water and
wastewater repair and replacement in Zone 3-Old Town Library Park area. Work includes
identifying the pipelines to be repaired and replaced, project scope, determining the best
construction methods, and the project limits. See attached supporting documentations.
Service Provider agrees to perform the services identified above and on the attached forms in
accordance with the terms and conditions contained herein and in the Master Agreement
between the parties. In the event of a conflict between or ambiguity in the terms of the Master
Agreement and this Work Order (including the attached forms) the Master Agreement shall
control.
The attached forms consisting of seven (7) pages are hereby accepted and incorporated herein,
by this reference, and Notice to Proceed is hereby given after all parties have signed this
document.
SERVICE PROVIDER: HDR Engineering, Inc.
By: Date:
Name: Title:
DocuSign Envelope ID: AD6B112A-09F1-46A2-97BE-0763B2BAE619
R. Bradley Martin Senior Vice President
October 24, 2017
Utilities Work Order Form Official Purchasing Form
Last updated 10/2017
OWNER’S ACCEPTANCE & EXECUTION:
This Work Order and the attached Contract Documents are hereby accepted and incorporated
herein by this reference.
ACCEPTANCE: Date:
Brian Mulligan, Special Project Manager
REVIEWED: Date:
Pat Johnson, Senior Buyer
APPROVED AS TO FORM: Date:
Name,City Attorney's Title
(if greater than $1,000,000)
ACCEPTANCE: Date:
Owen Randal, Water Systems Engineering Division Manager
ACCEPTANCE: Date:
Matt Fater, Water Engineering & Field Services Operations Manager
ACCEPTANCE: Date:
Kevin Gertig, Utilities Executive Director
(if greater than $1,000,000)
ACCEPTANCE: Date:
Gerry Paul, Purchasing Director
(if greater than $60,000)
ACCEPTANCE: Date:
Darin Atteberry, City Manager
(if greater than $1,000,000)
ATTEST: Date:
City Clerk
(if greater than $1,000,000)
DocuSign Envelope ID: AD6B112A-09F1-46A2-97BE-0763B2BAE619
October 17, 2017
October 17, 2017
October 25, 2017
October 26, 2017
October 27, 2017
Utilities Work Order Form Official Purchasing Form
Last updated 10/2017
ATTACHMENT A
WORK ORDER SCOPE OF SERVICES
DocuSign Envelope ID: AD6B112A-09F1-46A2-97BE-0763B2BAE619
Fort Collins Utilities | Old Town Library Park Water and Sewer R&R
Scope of Work
Scope of Work
Date: Friday, August 25, 2017
Project: Old Town Library Park Water and Sewer Rehabilitation and Replacement
Project Understanding
The Old Town Library Park area was identified by the city as a high priority zone for
rehabilitation and reconstruction of water and sanitary sewer utilities. Water mains in the project
area range from 4-inch to 16-inch diameter with ages of 80- to greater than 100-years. The
existing sanitary sewer system is of similar age with pipe sizes ranging from 6-inch to 10-inch.
The city’s goal with this project is to rehab or replace water and sewer utilities, and potentially
local storm sewers and inlets, in the project area such that additional infrastructure work is not
required within the projected 50-year useful life of those utilities.
The approximate project area is shown below in Figure 1. It is anticipated the project area
boundary may change to accommodate connections to existing utilities and/or to meet available
project funds.
Figure 1 – Update after city provides GIS data
419 Canyon Avenue, Suite 316, Fort Collins, CO 80521-2679
hdrinc.com
1
DocuSign Envelope ID: AD6B112A-09F1-46A2-97BE-0763B2BAE619
Fort Collins Utilities | Old Town Library Park Water and Sewer R&R
Scope of Work
Predesign Phase
Objective: Identify key project issues and the resulting preferred rehab/replacement approach
and scope for water, sewer and local stormwater systems within the project area.
Task 1. Project Management, Coordination and QA/QC
Objective: Manage scope, schedule, and staff, coordinate project technical elements, and
provide quality reviews of work products.
TASK 1.1 PROJECT MANAGEMENT, ACCOUNTING AND QUALITY CONTROL
• Initiate project accounting, budget and resource management tools.
• Prepare a project guide that clearly identifies the project work elements, deliverables,
budget and schedule.
• Prepare monthly invoices and progress reports.
• Perform QA/QC reviews of calculations and supporting documents.
TASK 1.2 PROJECT COORDINATION MEETINGS
• Hold weekly and bi-weekly meetings as needed at City offices to discuss progress,
address technical issues, and review submittal comments. Approximately 20, 1-hr
progress meetings.
Key Assumptions:
• 7 month Work Order duration (predesign through issuance of construction documents)
Deliverables:
• Action item summary lists
• Monthly invoices
Task 2. Data Collection
Objective: Obtain and review data necessary for predesign and final design activities.
Task 2.1 Coordinate, Collect and Review City Utility Data
• Obtain city LIDAR data for use as project topography and aerial imagery for drawing
base plan reference.
• Review water system data:
o GIS data including pipe size, material, and water service locations.
o Coordinate with City Meter Shop for service line and meter improvement
requirements within the project area.
o Coordinate with FCU Consultant (Ditesco) for water model scenario of upsizing
4-inch mains and reducing size of existing 16-inch main.
• Review sewer system data:
o GIS data including manhole inspections, manhole inverts, pipe age, pipe
material, pipe condition/defects, sewer services, etc. to obtain a thorough
understanding of the sewer system.
o Identify data gaps including pipe invert elevations and coordinate with FCU
consultant (Ditesco) for data collection.
o Review CCTV data to validate pipe condition/defects, sewer profile, and service
locations.
• Review storm sewer data
419 Canyon Avenue, Suite 316, Fort Collins, CO 80521-2679
hdrinc.com
2
DocuSign Envelope ID: AD6B112A-09F1-46A2-97BE-0763B2BAE619
Fort Collins Utilities | Old Town Library Park Water and Sewer R&R
Scope of Work
o Review Oak Street Outfall drawings relative to water main/service line locations.
o Identify inlet types within the project area and coordinate with City Stormwater
group for potential improvements to address maintenance issues.
Task 2.2 Perform Utility survey
• Locate existing utilities and identify utility owner and contact information.
• Perform ground survey of marked utilities and surface utility elements including valves,
hydrants, curb stops, meter pits, sanitary manhole covers, storm manhole covers, storm
inlets, etc.
o Sanitary sewer invert and pipe data will be obtained from the city GIS.
o Storm sewer invert and pipe data will be added based on GIS and record
drawing data, if required.
• Prepare Existing Utility Plan incorporating:
o Ground survey of utilities.
o GIS-based property lines.
o Sanitary sewer invert and pipe size and material data obtained from the city GIS.
o Aerial imagery provided.
• Survey utility pothole locations (two separate occasions).
Task 2.3 Perform Geotechnical Investigations
• Review and incorporate existing geotechnical information from previous City of Fort
Collins pipeline projects along Oak Street and in the project vicinity to refine and
optimize proposed boring locations and laboratory testing program.
• Drill 4 borings to 25 feet along the proposed replacement and rehabilitation alignment(s).
o Samples will be collected in even intervals for classification and laboratory
testing.
o Borings will be backfilled in accordance with City standards.
• Submit samples for geotechnical testing to determine in place soil parameters and
characterization.
Key Assumptions:
• GIS and LIDAR data are sufficient for vertical design information
• Potholing locations will be identified in project progress meetings and the Contractor
partner (Connell Resources) will perform potholing.
Deliverables:
• Existing Utility Plan and associated AutoCAD files
• Geotechnical Engineering Report:
o Geotechnical pipeline design recommendations
o Analysis of alternative and feasible trenchless rehabilitation alternatives
o Construction considerations
o Trenchless specifications for pipe bursting and horizontal directional drilling
Task 3. Problem Characterization
Objective: Identify key project issues and opportunities to define the limits of the project area
and scope of the project.
419 Canyon Avenue, Suite 316, Fort Collins, CO 80521-2679
hdrinc.com
3
DocuSign Envelope ID: AD6B112A-09F1-46A2-97BE-0763B2BAE619
Fort Collins Utilities | Old Town Library Park Water and Sewer R&R
Scope of Work
Task 3.1 Prepare project basemap
• Compile utility survey, GIS data and LIDAR data within AutoCAD
• Validate LIDAR data with MH rim elevations and other similar utility survey ground shots.
• Perform plan-in-hand site review of utilities and base data.
Task 3.2 Identify Project Issues and Opportunities
• Assess project area boundary and available budget through coordination with contractor
and City.
• Assess sewer condition and determine extent and type of R&R needs.
• Identify sewer services and connections to mains requiring R&R.
• Evaluate water system replacement limits, services and temporary service
arrangements.
• Identify Old Town Library Park area stakeholders and potential construction issues
including:
o DDA/DBA, Library Park and other city events via discussions with the City Event
Coordinator.
o Residential and commercial parking and access.
o Library access.
o Pavement condition/age and material.
o Floodplain/floodway limits (Whedbee and Oak Streets).
o Etc.
• Prepare Project Characterization Mapping summarizing project scope, constraints and
opportunities. Review, update and refine during progress meetings.
• Prepare a Gantt chart or similar table outlining Old Town events that may be impacted
by construction activities.
Deliverables:
• Project Area and Utilities Base Map
• Project Issues and Opportunity Map
• Old Town Event Table/Gantt Chart
Task 4. Water and Sewer Rehab and Reconstruction Alternatives
Objective: Develop and evaluate alternative to identify the recommended plan that provides
rehab and reconstruction (R&R) of the water and sewer utilities.
Task 4.1 Develop and Evaluate Alternatives
• Collaborate and evaluate potential construction methods based on Project
Characterization Mapping, key project issues, R&R needs, geotechnical conditions,
construction sequencing, disturbance limits, etc.
• Develop pre-design level mapping to present alternatives, identify impacts, and
coordinate estimates of construction costs.
• Assess alternatives based on impact mitigation, schedule, risk, cost, etc. Summarize
pros/cons in tabular/fact sheet format.
419 Canyon Avenue, Suite 316, Fort Collins, CO 80521-2679
hdrinc.com
4
DocuSign Envelope ID: AD6B112A-09F1-46A2-97BE-0763B2BAE619
Fort Collins Utilities | Old Town Library Park Water and Sewer R&R
Scope of Work
Task 4.2 Identify and Summarize Recommended Plan
• Identify preferred alternatives for each system (water, sanitary, storm) and summarize
rationale for selection in brief memo.
• Identify sequencing options for design and construction activities of preferred alternative.
Deliverables:
• Alternative analysis memo with supporting alternatives and recommended plan mapping.
Final Design Phase (Not Included in this Work Order)
Objective: Refined the preferred alternative and develop final construction document
package(s).
419 Canyon Avenue, Suite 316, Fort Collins, CO 80521-2679
hdrinc.com
5
DocuSign Envelope ID: AD6B112A-09F1-46A2-97BE-0763B2BAE619
Utilities Work Order Form Official Purchasing Form
Last updated 10/2017
ATTACHMENT B
WORK ORDER COST DETAIL
DocuSign Envelope ID: AD6B112A-09F1-46A2-97BE-0763B2BAE619
9/7/2017
Exhibit B - Fee Proposal HDR Engineering
Rich Thornton
Contract and Senior
Project Manager
Technical Advisor /
QC Reviewer
Keith Bushdiecker
Senior Engineer III
Brandon Luster
Senior Engineer III
Sara Race
Project Engineer I
Mike Austin
CAD Designer
Project Accounting
and Administration
Clerical Assistant
Hours
Labor
Total Expenses
HDR Fee
Total Fee
$ 220 $ 225 $ 180 $ 175 $ 120 $ 115 $ 77 $ 67
Task Description
Task 1. Management, Coordination and QA/QC
1.1 Project Management, Accounting and Quality Control 24 24 48 $ 7,134 $ 571 $ 7,705 $ 7,705
1.2 Project Coordination Meetings 40 40 40 120 $ 20,800 $ 2,300 $ 23,100 $ 23,100
Sub-total 64 0 40 0 40 0 24 0 168 $ 27,934 $ 2,871 $ 30,805 $ - $ - $ 30,805
Task 2. Data Collection
Task 2.1 Coordinate, Collect and Review City Utility Data 4 8 16 12 40 $ 5,620 $ 450 $ 6,070 $ 6,070
Task 2.2 Perform Utility survey 1 4 8 8 2 23 $ 2,954 $ 236 $ 3,190 $ 11,545 $ 14,735
Task 2.3 Perform Geotechnical Investigations 1 4 4 2 2 13 $ 1,784 $ 143 $ 1,927 $ 17,600 $ 19,527
Sub-total 6 0 16 0 28 22 0 4 76 $ 10,358 $ 829 $ 11,186 $ 11,545 $ 17,600 $ 40,331
Task 3. Problem Characterization
Task 3.1 Prepare project basemap 4 6 16 16 4 46 $ 5,988 $ 479 $ 6,467 $ 6,467
Task 3.2 Identify Project Issues and Opportunities 12 2 16 4 32 16 82 $ 12,350 $ 1,306 $ 13,656 $ 13,656
Sub-total 16 2 22 4 48 32 0 4 128 $ 18,338 $ 1,785 $ 20,123 $ - $ - $ 20,123
Task 4. Water and Sewer Rehab and Reconstruction Alternatives
Task 4.1 Develop and Evaluate Alternatives 24 2 32 10 48 48 2 166 $ 24,654 $ 2,290 $ 26,944 $ 26,944
Task 4.2 Identify and Summarize Recommended Plan 10 2 2 4 24 4 2 48 $ 7,184 $ 575 $ 7,759 $ 7,759
Sub-total 34 4 34 14 72 52 0 4 214 $ 31,838 $ 2,865 $ 34,703 $ - $ - $ 34,703
Hours 120 6 112 18 188 106 24 12 586
Fee $26,400 $1,350 $20,160 $3,150 $22,560 $12,190 $1,854 $803 $ 88,467 8,349 $ 96,817 $ 11,545 $ 17,600 $ 125,962
City of Fort Collins Utilities
Old Town Library Park Water and Sewer
Rehab & Reconstruction
King Surveyors
Lithos
C:\Users\rthornto\Documents\01_Marketing\Fort Collins\OTLP W-WW R&R\OTLP - W San R&R Fee
DocuSign Envelope ID: AD6B112A-09F1-46A2-97BE-0763B2BAE619
Utilities Work Order Form Official Purchasing Form
Last updated 10/2017
ATTACHMENT C
SCHEDULE
DocuSign Envelope ID: AD6B112A-09F1-46A2-97BE-0763B2BAE619
ID Task
Mode
Task Name Duration Start Finish
1 Project Management and QC 120 days Mon 9/4/17Mon 3/5/18
2 Task 1.1 Project Management, Accounting and QC 120 days Mon 9/4/17 Mon 3/5/18
3 Task 1.2 Project Coordination Meetings 120 days Mon 9/4/17 Mon 3/5/18
4 Predesign Phase 65 days Mon 9/11/1Wed 12/13/
5 Task 2. Data Collection 20 days Mon 9/11/17 Fri 10/6/17
6 Task 2.1 Coordinate, Collect, and Review City Utility Da 20 days Mon 9/11/17 Fri 10/6/17
7 Task 2.2 Perform Utility Survey 20 days Mon 9/11/17 Fri 10/6/17
8 Task 2.3 Perform Geotechnical Investigations 20 days Mon 9/11/17 Fri 10/6/17
9 Task 3. Problem Characterization 15 days Mon 10/9/17 Fri 10/27/17
10 Task 3.1 Prepare Project Basemapping 5 days Mon 10/9/17 Fri 10/13/17
11 Task 3.2 Identify Project Issues & Opportunities 10 days Mon 10/16/17 Fri 10/27/17
12 Task 4. Water and Sewer R&R Alternatives 30 days Mon 10/30/17Wed 12/13/17
13 Task 4.1 Develop and Evaluate Alternatives 20 days Mon 10/30/17 Wed 11/29/17
14 Task 4.2 Identify and Summarize Rec Plan 10 days Thu 11/30/17 Wed 12/13/17
15 Final Design Phase (Future Work Order) 41 days Thu 12/14/ Tue 2/20/18
16 Develop drawings and specifications 30 days Thu 12/14/17 Mon 2/5/18
17 Submit Drawings for Cost Validation 1 day Tue 2/6/18 Tue 2/6/18
18 Cost Validation Process 10 days Wed 2/7/18 Tue 2/20/18
19 Construction Phase (Future Work Order) 11 days Wed 2/21/1Wed 3/7/18
20 Contracting (Connell/City) 10 days Wed 2/21/18 Tue 3/6/18
21 NTP 1 day Wed 3/7/18 Wed 3/7/18
2/6
3/7
Aug Sep Oct Nov Dec Jan Feb Mar Apr
Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration‐only
Manual Summary Rollup
Manual Summary
Start‐only
Finish‐only
Deadline
Progress
Page 1
Project: OTLP ‐ W San R&R Sched
Date: Thu 8/17/17
DocuSign Envelope ID: AD6B112A-09F1-46A2-97BE-0763B2BAE619