City of Fort Collins
SIP Migration
Statement of Work
Version 1.0
October 12th, 2017
ANM and Error! Unknown document property name. Confidential Page 2
Contents
Contents ............................................................................................................................... 2
About This Statement of Work .............................................................................................. 3
Omissions ......................................................................................................................................3
Confidentiality ...............................................................................................................................3
Executive Summary ............................................................................................................... 4
Project Deliverables............................................................................................................... 4
Project Tasks ......................................................................................................................... 5
Plan and Design Session .................................................................................................................5
Implementation .............................................................................................................................5
Project Timeline .................................................................................................................... 6
Customer Responsibilities ...................................................................................................... 6
Assumptions ......................................................................................................................... 7
Billing Milestones .................................................................................................................. 8
Appendix A - Operational Transition and Acceptance Criteria ................................................. 9
Operational Transition ...................................................................................................................9
Outstanding Issues – Severity Levels ...............................................................................................9
Acceptance Criteria ........................................................................................................................9
Appendix B – Change Management Process ......................................................................... 11
Change Request Process ............................................................................................................... 11
Appendix C – Project Management Office Overview ............................................................ 12
Project Review Meetings .............................................................................................................. 12
ANM Project Manager ........................................................................................................................ 12
ANM Solution Architect ...................................................................................................................... 13
ANM Consulting Engineer(s) ............................................................................................................... 13
Customer Key Staff Participation .................................................................................................. 13
Customer Project Sponsor(s) .............................................................................................................. 13
Customer Project Manager / Coordinator .......................................................................................... 13
Customer Technical Contact(s) ........................................................................................................... 14
ANM and Error! Unknown document property name. Confidential Page 3
About This Statement of Work
The purpose of this Statement of Work is to define tasks, deliverables, timeline, responsibilities and any
additional terms for this project for City and County of Denver (“Customer”) provided by Advanced
Network Management (“ANM”).
Change Authority Advanced Network Management
ANM Account Manager Brian Von der Heydt
ANM Solution Architect Garrick Barnett
ANM Engineering Approver James Arnold
Customer Project Sponsor
Table 1: Document History
Version Date Status Reason for Change
1.0 10/12/17 Draft Initial Version
2.0 10/13/17 Final Final
3.0 10/19/17 Revised Final Adjusted Assumption BVDH
Omissions
ANM reserves the right to correct any error or omission in this Statement of Work and will do so by
utilizing a Change Request process. The initial project kick-off meeting and design workshop (Customer
Requirements Validation) might uncover unforeseen items that impact this Statement of Work and will
be addressed (if necessary) by the Change Request process.
Confidentiality
This Statement of Work is confidential and must not be disclosed outside of ANM and Customer unless
agreed upon by both parties.
ANM and Error! Unknown document property name. Confidential Page 4
Executive Summary
City of Fort Collins (CoFC) are engaging ANM to assist with migrating away from legacy PSTN services to a
centralized SIP service. Currently they are using eight PRI’s to provide PSTN access. The current
environment is utilizing SIP as the primary protocol for communication back to the VoIP infrastructure.
ANM will work with the client to help design and implement a solution which will accommodate the
requirements, and aid in putting the SIP trunks into production.
Project Deliverables
Table 2: Project Deliverables
Name Customer Acceptance
Signatures Required
Project Plan Yes
Acceptance Test Plan Yes
Any other applicable documentation (e.g. sample config, diagram) Yes
Project Completion & Survey (Final Signoff) Yes
ANM and Error! Unknown document property name. Confidential Page 5
Project Tasks
Plan and Design Session
ANM will conduct a design session with Customer to discover, plan, design, and validate how the solution
will be configured and tested. The session will require few sessions to complete and the Customer
technical point of contact will need to be available throughout the process to the ANM Engineering team.
Some of the items that will be covered and documented include (but not limited to):
IP addresses
Call Routing & Dial plan
Test and Validation: (testing to include, but not be limited to)
o Inbound, Outbound
o Local, LD, International, Toll-Free
o Main numbers
o Standard Users
o Contact Center call-flows, numbers, and agents
Cutover and Transition strategy
Go-live support strategy
Implementation
The following applications and infrastructure components will be deployed, configured, and tested per
the agreed upon design between ANM and Customer:
The ANM engineer will deploy the agreed design and dial plan configuration items within the border
element, and the Communication Manager. Additionally, they will work within the agreed Change Control
process to implement all configuration items needed for SIP service.
CUBE Configuration and Validation:
Review existing configuration on the CUBE
Work with provider and client to make any changes necessary CUBE for SIP services
Update the dial plan and configure the CUBE to allow for new SIP services to be implemented
without impact to legacy environment, and allow for a full battery of testing as required prior to
rolling out into production.
Work with client and provider to schedule porting of existing numbers from PRI’s to SIP trunks.
ANM and Error! Unknown document property name. Confidential Page 6
Systems Acceptance:
Full testing of the SIP solution to ensure no issues will arise during the migration. Including but
not limited to:
o Emergency Services
o Toll-Free
o Local and Long Distance
o DTMF
o Inbound call center access
o Faxing
* The ANM team will work with the CoFC team to define the SAT plan. ANM has a standard SAT, but
there may be testing needed on applications or call flows that the client has more intimate knowledge.
Project Timeline
Table 3: Project Timeline
Phase Task
Phase 1 Plan and Design
Phase 2 Transition Planning and Implementation
Phase 3 Test and Validation
Phase 4 Solution Go-live and Day 2 Support
Customer Responsibilities
The following are responsibilities that will need to be performed/provided by Customer.
Provide onsite physical access to required systems and space to work
Provide remote access (VPN) or other agreed upon remote access solution
Provide any required hardware and/or software that was not procured by ANM
Provide diagrams of existing environment if required
Provider (coordination and meetings/planning porting, etc.)
WAN/LAN configuration and updates
Change Control coordination and process
Management and coordination of 3rd party for ordering of SIP services and Porting activity.
ANM and Error! Unknown document property name. Confidential Page 7
Provide an SFTP server in the event any IOS upgrades are needed
Ensure WAN bandwidth is adequate and devices have applicable QoS configurations
Maintain valid support contracts with all product manufacturers involved in the solution
Assumptions
The overall scope and related work estimates for this engagement were developed based on the following
assumptions. Material changes to these assumptions and exclusions may impact the estimated effort and
cost associated with completing the work and therefore would require a Change Request.
Customer has adequately met all of their responsibilities
Unless otherwise specified, the following services are not included:
o Network infrastructure (LAN, WAN, Wireless LAN, QoS)
o Security infrastructure (firewalls and other perimeter security)
o Environmental requirements: Electrical/Power & Air Conditioning services
o Network cabling services
During this project any software or hardware changes on systems and applications not covered
by this Statement of Work will have to be addressed with a Change Request Form.
Unless it is explicitly stated in this Statement of Work, Customer is responsible for installation,
configuration or re-configuration of any additional equipment not provided by ANM.
Any services provided in the reconfiguration or troubleshooting as a result of existing faulty
equipment, software compatibility or systems interoperability will be considered out of scope and
billed at the Time and Material rates provided in this Statement of Work.
Customer understands that any onsite delays due to support issues related to equipment
procured by Customer will be billed at the Time and Material rates provided in this Statement of
Work.
Customer will manage all oversight and communication with third party vendors not directly
contracted by ANM (for example, service providers, other equipment manufacturers, etc.).
All standard work to be completed during business hours. Live migration and porting activity to
be completed during associated change control windows, afterhours change window migrations
are expected and included.
ANM and Error! Unknown document property name. Confidential Page 8
Billing Milestones
Services for this project will be billed at a fixed fee. Below are the billing milestones for this project.
Table 4: Billing Milestones
Milestones Description Payment Percent
#1 Project Kick-off 10%
#2 SIP Turn-up and Testing completed 40%
#3 Project Completion 50%
Total Project Investment $29,520
ANM and Error! Unknown document property name. Confidential Page 9
Appendix A - Operational Transition and Acceptance
Criteria
ANM is committed to Customer’s long term success with the newly implemented solution. ANM is eager
to continue to support Custopmer and has a variety of support options available after the project
completion. Customer’s Account Manager can provide additional information.
Operational Transition
Operational Transition occurs when the solution has been fully deployed, Customer training has
occurred (if applicable), and the solution has been cutover/migrated to with an executed Acceptance
Test Plan. During the Operational Transition phase, any applicable as-built documentation will be
provided and ANM will attempt to resolve any outstanding issues.
Outstanding Issues – Severity Levels
ANM deploys thoroughly tested software and solutions for customers. But as with all complex
technology solutions, product issues can arise. During the project ANM will document such issues. The
following table describes the severity levels of issues.
Table 5: Outstanding Issues – Severity Levels
Severity Levels Description
1 These issues have an operational impact and no work-around. These issues might require
a rollback to the old system if necessary until a fix or work-around is determined.
2 These issues have an operational impact, but a work-around exists that allows the
solution to go live or be cutover. Production rollout or cut-overs can occur with
outstanding Severity 2 issues. The issues will be addressed on an individual basis and
resolution time frames will be specified at that time based on complexity of proposed
interim and final resolutions.
3 These issues have a minor operational impact. These issues are often cosmetic in nature
and do not prevent any functionality with the new system.
Acceptance Criteria
The project and Statement of Work will be deemed complete upon the following:
o Completion of all project deliverables and the project in Operational Transition
o Signing of the Project Completion & Survey, with the following caveats:
o No Severity 1 defects outstanding
o Severity 2 & 3 defects can be outstanding as long as ANM has made a reasonable
attempt to resolve the issues and the current status is pending a manufacturer’s
resolution to the issues (for example, bug fixes)
ANM and Error! Unknown document property name. Confidential Page 10
Note: until project completion and final signoff, it is expected that Customer will not make any changes
to the system without the consent/supervision of ANM.
ANM and Error! Unknown document property name. Confidential Page 11
Appendix B – Change Management Process
Change Request Process
A project Change Request Form (CRF) will be used to document and communicate any changes to this
Statement of Work. The CRF will describe the change, the reason for the change, and the impact that
the change will have on the project. The CRF will also specify any additional charges (if necessary).
Should changes be necessary or requested by Customer, ANM will investigate the effect of such changes
and determine an impact on price, schedule, and other terms and conditions. A completed CRF will be
the output and Customer and ANM must both sign it to authorize the changes. A change control log will
be maintained throughout the project to track all approved changes and record them (if applicable) in
the successive approved versions of the Project Plan. All versions will be tracked using a strict document
version control mechanism maintained by the Project Managers. For reference, an example CRF is
provided in Appendix A.
Table 6: Appendix B – Change Request Form (CRF)
CHANGE REQUEST FORM
For the use in the event of a change to the Scope or Time periods
contained in the Statement of Work between <Customer> and ANM.
Change Request No.
CRXXX
Date
1 - CHANGE REQUEST
From: (Name of Company)
To: (Name of Company)
Description and Objective of Proposed Change:
Cost Implications (fixed and/or recurring) Additional to the Initial Agreement:
Value (USD): Total cost to the project of $
Please note this will be fully invoiced upon delivery of the equipment and/or additional service, and is subject to the signed
Purchase Order between <Customer> and ANM.
Responsibilities for the Implementation of the Proposed Change:
Time Impact, Duration and key Milestones for the Proposed Change:
Change Request Proposed by:
Company:
Name:
Signature:
Date:
Note: This Change Request is not authorized for action until approval by the other party in Section 3 below.
2 – CHANGE REQUEST REFUSAL
Company:
Name:
Signature:
Date:
Reasons:
3 – CHANGE ORDER AUTHORIZATION
Company:
Name:
Signature:
Date:
Comments:
ANM and Error! Unknown document property name. Confidential Page 12
Appendix C – Project Management Office Overview
Project Review Meetings
A communication plan will be designed and agreed to at the project kick-off meeting along with a project
contact list of all stakeholders. The purpose of the communication plan and contact list is to ensure
relevant information is distributed to the appropriate parties in a timely manner.
The project review meetings will be undertaken on a reoccurring basis; to be attended by Customer
Project Manager, the ANM Project Manager and other project team members as required in order to
review the progress of work being undertaken, any issues experienced, scope and cost changes, and
future expected target dates for the completion of activities. The meetings will take the form of face-to-
face meetings or through a conference bridge, whichever is deemed appropriate.
During the project review meetings, ANM will provide:
Status Updates
Progress, Milestones Achieved, Issues Raised
Planned and Scheduled Activities
Review and update minutes
Agreed Actions ANM Key Staff Participation
ANM Project Manager
The Project Manager is the strategic contact at ANM and directs the service towards its aims and
ensures it meets or exceeds them. The Project Manager will manage the roles and responsibilities of the
people within ANM and liaise and report to the pertinent members of the Customer team. The Project
Manager will develop the project plan used to track progress against schedule and resources. ANM
standard practice is to meet at key milestones to review the project status. The progress information
from each meeting will be used to update the actual activity against the plan, enabling the Project
Manager to identify any issues or concerns and to take corrective action.
Provides a single point of contact for all issues relating to delivery of the project
Designates a backup contact when the ANM Project Manager is not available
Produces the Project Management Plan incorporating project schedules, dependencies, roles,
responsibilities and risk and issue management process
Manages the review process for all deliverables with Customer as they relate to project
Participates in regularly scheduled meetings with Customer to discuss the status of the
implementation
Reviews logical/physical schematics received from Customer
Reviews all pertinent site information received from Customer
ANM and Error! Unknown document property name. Confidential Page 13
ANM Solution Architect
The Solution Architect has responsibility for the quality assurance of all technical aspects of the solution.
This person will not necessarily be responsible for delivering technical aspects of the project, but will be
a point of reference for all technical engineers working on the project. This role is key to providing a
cohesive solution with consistent documentation and clear interfaces between different vendor
products.
ANM Consulting Engineer(s)
The Consulting Engineer has responsibility for deploying and configuring all technical aspects of the
solution. The Consulting Engineer is responsible for the following:
Configuration of the system in-line with the agreed approach as signed off in the Customer
Requirements Validation (CRV)
Execution of the Acceptance Test Plan in conjunction with Customer
Completion of as-built documentation (if applicable)
Customer Key Staff Participation
Customer will guarantee the participation of key personnel to ensure that requirements can be defined
expeditiously. Customer will provide access to technical and functional subject matter experts on a
timely basis to work in a collaborative manner with ANM engineering team. Key staff participation
includes the following:
Customer Project Sponsor(s)
The Project Sponsor(s) ensure funding is provided for the project. The individual(s) must be able to make
critical decisions in regards to budget and unknown risks that could impact the project.
A route for escalation (relating to project decisions, risks, issues, changes)
Advice, guidance and support to the Project Manager
Ensuring that the project remains in line with the business environment and needs
Customer Project Manager / Coordinator
Elicitation and specification of requirements from all end users and administration staff
Co-ordination of Customer staff to ensure 100% efficiency in delivery of the Project
Communication of accurate and complete system requirements
Liaison to all third parties
ANM and Error! Unknown document property name. Confidential Page 14
Customer Technical Contact(s)
Act as voice/data technical resources for the Customer
Retain technical ownership and responsibility for the configuration of the Customer voice/data
environment
Work with the ANM engineering team to ensure key requirements and dependencies are
understood and documented