WORK ORDER
PURSUANT TO A MASTER AGREEMENT BETWEEN
THE CITY OF FORT COLLINS
AND
HYDRO CONSTRUCTION, INC.
WORK ORDER NUMBER: H-WRF-2018-10
PROJECT TITLE: DWRF Sidestream Design Services
ORIGINAL BID/RFP NUMBER & NAME: 8286, Construction Contractor for Projects at
the Water and Wastewater Treatment
Facilities
MASTER AGREEMENT EFFECTIVE DATE: 06/20/2016
ARCHITECT/ENGINEER: NA
OWNER’S REPRESENTATIVE: Link Mueller
WORK ORDER COMMENCEMENT DATE: March 27, 2018
WORK ORDER COMPLETION DATE: March 30, 2019
MAXIMUM FEE: (time and reimbursable direct costs): $50,239.00
PROJECT DESCRIPTION/SCOPE OF SERVICES: Provide constructability, cost estimating,
scheduling, and independent cost estimating services for the Drake Water Reclamation Facility.
See the attached supporting documentation.
Service Provider agrees to perform the services identified above and on the attached forms in
accordance with the terms and conditions contained herein and in the Master Agreement between
the parties. In the event of a conflict between or ambiguity in the terms of the Master Agreement
and this Work Order (including the attached forms) the Master Agreement shall control.
The attached forms consisting of Four (4) pages are hereby accepted and incorporated herein,
by this reference, and Notice to Proceed is hereby given after all parties have signed this
document.
SERVICE PROVIDER: Hydro Construction, Inc.
By: Date:
Name: Title:
Page 1 of 9
DocuSign Envelope ID: 4CDEB4BE-7F2A-4674-8FFA-330603DF56F9
Stan Javernick
March 22, 2018
President
Utilities Work Order Form Official Purchasing Form
Last updated 10/2017
OWNER’S ACCEPTANCE & EXECUTION:
This Work Order and the attached Contract Documents are hereby accepted and incorporated
herein by this reference.
ACCEPTANCE: Date:
Link Mueller, Special Project Manager
REVIEWED: Date:
Pat Johnson, Senior Buyer
APPROVED AS TO FORM: Date:
Name,City Attorney's Title
(if greater than $1,000,000)
ACCEPTANCE: Date:
Jason Graham, Water Reclamation & Biosolids Manager
ACCEPTANCE: Date:
Owen Randall, Water Systems Engineering Division Manager
ACCEPTANCE: Date:
Carol Webb, Water Resources & Treatment Operations Manager
ACCEPTANCE: Date:
Kevin Gertig, Utilities Executive Director
(if greater than $1,000,000)
ACCEPTANCE: Date:
Gerry Paul, Purchasing Director
(if greater than $60,000)
ACCEPTANCE: Date:
Darin Atteberry, City Manager
(if greater than $1,000,000)
ATTEST: Date:
City Clerk
(if greater than $1,000,000)
Page 2 of 9
DocuSign Envelope ID: 4CDEB4BE-7F2A-4674-8FFA-330603DF56F9
March 22, 2018
March 22, 2018
March 28, 2018
March 23, 2018
April 2, 2018
Utilities Work Order Form Official Purchasing Form
Last updated 10/2017
ATTACHMENT A
WORK ORDER SCOPE OF SERVICES & COST DETAILS
Page 3 of 9
DocuSign Envelope ID: 4CDEB4BE-7F2A-4674-8FFA-330603DF56F9
Hydro Construction Company, Inc. DWRF - Sidestream-P Page 1
Design/Preconstruction Phase 2/27/2018 9:50 AM
Page 4 of 9
DocuSign Envelope ID: 4CDEB4BE-7F2A-4674-8FFA-330603DF56F9
Hydro Construction Company, Inc. DWRF - Sidestream-P Page 2
Design/Preconstruction Phase 2/27/2018 9:50 AM
Item Description Takeoff Qty
Labor
Amount
Material
Amount
Subcontract
Amount Name
Equipment
Amount
Other
Amount
Total
Amount
1000.000 GENERAL CONDITIONS
1100.100 Project Management
12 Coordination Meetings 16.00 ea 4,681 - 3,392 0 - 8,073
14 Design Review Workshops 3.00 ea 1,755 - 1,272 0 - 3,027
16 Cost Estimating 1.00 ls 6,679 - 2,120 0 - 8,799
Project Management 13,116 6,784 19,900
99.000 Labor hours
99.000 Equipment hours
1370.100 Scheduling
10 Scheduling 1.00 ls 4,388 0 1,760 - - 6,148
Scheduling 4,388 1,760 6,148
1400.100 Misc. Labor Expense
10 Estimate Reconciliation 3.00 day 3,511 2,544 - 6,055
Misc. Labor Expense 3,511 2,544 6,055
24.00 Labor hours
24.00 Equipment hours
GENERAL CONDITIONS 21,015 0 11,088 0 0 32,103
123.000 Labor hours
123.000 Equipment hours
2000.000 SITEWORK
2531.018 Utility Tie-Ins
10 Site Investigation 1.00 ls 4,416 500 - 2,685 806 8,407
Utility Tie-Ins 4,416 500 2,685 806 8,407
80.00 Labor hours
SITEWORK 4,416 500 0 2,685 806 8,407
80.00 Labor hours
16000.000 ELECTRICAL
16000.001 Electrical
-sub Electrical Site Investigation 1.00 ls - - 4,750 - - 4,750
Electrical 4,750 4,750
ELECTRICAL 0 0 4,750 0 0 4,750
Page 5 of 9
DocuSign Envelope ID: 4CDEB4BE-7F2A-4674-8FFA-330603DF56F9
Hydro Construction Company, Inc. DWRF - Sidestream-P Page 3
Design/Preconstruction Phase 2/27/2018 9:50 AM
Estimate Totals
Description Amount Totals Hours Rate Cost Basis Cost per Unit Percent of Total
Labor 25,431 203.000 hrs 50.62%
Material 500 1.00%
Subcontract 15,838 31.53%
Equipment 2,685 123.000 hrs 5.34%
Other 806 1.60%
45,260 45,260 90.09 90.09%
Profit & Overhead 4,979 11.000 % T 9.91%
4,979 50,239 9.91 100.00%
Total 50,239
Page 6 of 9
DocuSign Envelope ID: 4CDEB4BE-7F2A-4674-8FFA-330603DF56F9
Utilities Work Order Form Official Purchasing Form
Last updated 10/2017
ATTACHMENT B
WORK ORDER SCHEDULE OF SERVICES
Page 7 of 9
DocuSign Envelope ID: 4CDEB4BE-7F2A-4674-8FFA-330603DF56F9
City of Fort Collins - Sidestream-P Design
Carollo Design Activities and Schedule
last revised: 1/19/2017
DWRF Sidestream-P Project
Project Coordination
Bi-Weekly Coordination Meetings
Basis of Design/Alternative Evaluation/Conceptual Design
Define Design Parameters (flows/loads, treatment, redundancy)
Identify Process Options and Request Vendor Proposals
Vendor Proposal Development
Alternative Development and Evaluation
Confirm Cost Estimate (Hydro) and Select Vendor
Preliminary Analysis and Layout
Hydraulic Analysis
Engineering Report
Procurement Document Preparation
Sidestream-P Drawings and Specs (Draft)
Sidestream-P Drawings and Specs (review by FCU)
Sidestream-P Drawings and Specs (Final)
Design Development
Prepare 60% Design Documents (Drawings and Specs)
Submit 60% Design Drawings and Specs to City
City Review of 60% Design Documents + Carollo QA/QC
Design Review Workshop (60%)
Prepare 90% Design Documents (Drawings and Specs)
Carollo QA/QC + Comment Incorporation
Submit 90% Design Documents to City
City Review of 90% Design Documents
Design Review Workshop (90%)
Prepare Issued for Construction Documents
Submit IFC Documents to City
2018
oct nov dec 19-Jan 19-Feb 19-Mar
Alternative Analysis Workshop
Kickoff Meeting HYDRO ATTENDS ALL MEETINGS
feb mar apr may jun jul aug sep
Hydro ICE
Hydro Scheduling
Carollo Engineers, Inc. DWRF Sidestream-P Design Schedule__03-19-18.xlsx 3/20/2018
Page 8 of 9
DocuSign Envelope ID: 4CDEB4BE-7F2A-4674-8FFA-330603DF56F9
Utilities Work Order Form Official Purchasing Form
Last updated 10/2017
ATTACHMENT C
CERTIFICATE OF INSURANCE
CONTRACTOR shall submit Certificate of Insurance in compliance with the Contract Documents.
Page 9 of 9
DocuSign Envelope ID: 4CDEB4BE-7F2A-4674-8FFA-330603DF56F9
The ACORD name and logo are registered marks of ACORD
CERTIFICATE HOLDER
© 1988-2014 ACORD CORPORATION. All rights reserved.
ACORD 25 (2014/01)
AUTHORIZED REPRESENTATIVE
CANCELLATION
CERTIFICATE OF LIABILITY INSURANCE DATE (MM/DD/YYYY)
JECT LOC
PRO-
POLICY
GEN'L AGGREGATE LIMIT APPLIES PER:
CLAIMS-MADE OCCUR
COMMERCIAL GENERAL LIABILITY
PREMISES (Ea occurrence) $
DAMAGE TO RENTED
EACH OCCURRENCE $
MED EXP (Any one person) $
PERSONAL & ADV INJURY $
GENERAL AGGREGATE $
PRODUCTS - COMP/OP AGG $
DED RETENTION $
CLAIMS-MADE
OCCUR
$
AGGREGATE $
UMBRELLA LIAB EACH OCCURRENCE $
EXCESS LIAB
DESCRIPTION OF OPERATIONS / LOCATIONS / VEHICLES (ACORD 101, Additional Remarks Schedule, may be attached if more space is required)
INSR
LTR TYPE OF INSURANCE POLICY NUMBER
POLICY EFF
(MM/DD/YYYY)
POLICY EXP
(MM/DD/YYYY) LIMITS
PER
STATUTE
OTH-
ER
E.L. EACH ACCIDENT
E.L. DISEASE - EA EMPLOYEE
E.L. DISEASE - POLICY LIMIT
$
$
$
ANY PROPRIETOR/PARTNER/EXECUTIVE
If yes, describe under
DESCRIPTION OF OPERATIONS below
(Mandatory in NH)
OFFICER/MEMBER EXCLUDED?
WORKERS COMPENSATION
AND EMPLOYERS' LIABILITY Y / N
AUTOMOBILE LIABILITY
ANY AUTO
ALL OWNED SCHEDULED
HIRED AUTOS
NON-OWNED
AUTOS AUTOS
AUTOS
COMBINED SINGLE LIMIT
BODILY INJURY (Per person)
BODILY INJURY (Per accident)
PROPERTY DAMAGE $
$
$
$
THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD
INDICATED. NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS
CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS,
EXCLUSIONS AND CONDITIONS OF SUCH POLICIES. LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS.
INSD
ADDL
WVD
SUBR
N / A
$
$
(Ea accident)
(Per accident)
OTHER:
THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS
CERTIFICATE DOES NOT AFFIRMATIVELY OR NEGATIVELY AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES
BELOW. THIS CERTIFICATE OF INSURANCE DOES NOT CONSTITUTE A CONTRACT BETWEEN THE ISSUING INSURER(S), AUTHORIZED
REPRESENTATIVE OR PRODUCER, AND THE CERTIFICATE HOLDER.
IMPORTANT: If the certificate holder is an ADDITIONAL INSURED, the policy(ies) must be endorsed. If SUBROGATION IS WAIVED, subject to
the terms and conditions of the policy, certain policies may require an endorsement. A statement on this certificate does not confer rights to the
certificate holder in lieu of such endorsement(s).
COVERAGES CERTIFICATE NUMBER: REVISION NUMBER:
INSURED
PHONE
(A/C, No, Ext):
PRODUCER
ADDRESS:
E-MAIL
FAX
(A/C, No):
CONTACT
NAME:
NAIC #
INSURER A :
INSURER B :
INSURER C :
INSURER D :
INSURER E :
INSURER F :
INSURER(S) AFFORDING COVERAGE
SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE
THE EXPIRATION DATE THEREOF, NOTICE WILL BE DELIVERED IN
ACCORDANCE WITH THE POLICY PROVISIONS.
INS025 (201401)
3/21/2018
Flood and Peterson
PO Box 578
Greeley CO 80632
Dana Stewart, CIC, CISR
(970)266-7149 (970)506-6845
DStewart@floodpeterson.com
Hydro Construction Company Inc.
77 NW Frontage Road
Fort Collins CO 80524
Phoenix Insurance Company 25623
Travelers Indemnity Company 25658
Travelers Property Casualty Company 25674
Pinnacol Assurance 41190
CL17121120854
A
X
X
X
DTCO8G990899PHX17 4/1/2017 4/1/2018
1,000,000
300,000
10,000
1,000,000
2,000,000
2,000,000
B
X
X X
DT8108G990899IND17 4/1/2017 4/1/2018
1,000,000
C
X X
X 10,000 CUP-2J40080A-17-26
4/1/2017 4/1/2018
5,000,000
5,000,000
D 2091550 4/1/2017 4/1/2018
X
1,000,000
1,000,000
1,000,000
RE: 18-01-510 DWRF Sidestream Design Services
City of Fort Collins is included as Additional Insured on the General, Automobile, and Umbrella Liability
Policies if required by written contract or agreement and with respect to work performed by Insured
subject to the policy terms and conditions.