HomeMy WebLinkAboutCHANGE ORDER - RFP - 7220 WATER WW TREATMENT & SITE INFRASTRUCTURE DESIGN CONSTRUCTION CONTRACTOR (20)SECTION 00950
CHANGE ORDER NO. 4
PROJECT TITLE: WTF Chlorine Contact Basin Phase 3 Construction
CONTRACTOR: Hydro Construction
PROJECT NUMBER: PO NUMBER: PO9162138 and BU 5020331000
ORIGINAL BID/RFP NUMBER & NAME: 8286, Construction Contractor for Projects at the
Water and Wastewater Treatment Facilities
DESCRIPTION:
1. Reason for change: additional work identified in association with the construction and
operation of the CCB project
2. Description of Change: additional site work identified during valve installation for the CCB
project. When the new piping and valves were installed, the
existing valves did not operate and function correctly, they did
not completely “seat” and operated difficultly. With the CCB
installed and operating, these dysfunctional existing valves
impact the operation and maintenance of the CCB. Two new
valves, a new meter on the clearwell bypass, manholes for
actuator access, and the UTV for cleaning inside the CCB will
be purchased and installed.
3. Change in Contract Price: with three change orders, including this one at $362,636, the new
total for business unit 5020331000 amounts to $7,686,255.00.
The total contract cost for PO 9162138 is $8,055,006.00
4. Change in Contract Time: With these new work items, the master schedule for the
substantial completion is the CCB construct will change to
March 2018.
ORIGINAL CONTRACT PRICE $6,852,437.00
TOTAL APPROVED CHANGE ORDER $471,182.00
TOTAL PENDING CHANGE ORDER .00
TOTAL THIS CHANGE ORDER $362,636.00
TOTAL % OF THIS CHANGE ORDER 5.3%
TOTAL C.O.% OF ORIGINAL CONTRACT 12.2%
ADJUSTED CONTRACT COST $ 7,686,255.00
(Assuming all change orders approved)
DocuSign Envelope ID: 393918BF-2E36-4B59-8D50-6191078E1530
APPROVED BY: DATE:
Jim Eurich, Hydro Construction
REVIEWED BY: DATE:
Pat Johnson, Senior Buyer
SUBMITTED BY: DATE:
Sue Paquette, Special Project Manager
APPROVED BY: DATE:
Mark Kempton, Water Production Division Manager
APPROVED BY: DATE:
Owen Randall, Chief Engineer & Project Manager
APPROVED BY: DATE:
Carol Webb, Water Resources/Treatment
Operations Manager
APPROVED BY: DATE:
Gerry Paul, Purchasing Director (over $60,000)
DocuSign Envelope ID: 393918BF-2E36-4B59-8D50-6191078E1530
20/9/2017
22/9/2017
25/9/2017
25/9/2017
25/9/2017
25/9/2017
28/9/2017
WTF Large Finish Water Valve Installation or Replacement September 6, 2017
Hydro Construction Company, Inc. - Scope of Services.
36 inch valve (replaces YDV 911)
Provide personnel and equipment to assist in design, investigative potholing, excavation, removal of
existing pipe, reassembly of pipe and new valve (requiring 5 lineal feet of pipe and a Pratt valve
w/additional minor pipe appurtenances and no additional fittings) backfill of pipe and valve and
landscaping as required. Abandon YDV 911 opened and in place.
36 inch valve (replaces valve CE)
Provide personnel and equipment to assist in design, investigative potholing, excavation, removal of
existing pipe and flange to MJ adaptor, install new valve (requiring a welded steel flange and a Pratt
valve w/additional minor pipe appurtenances and no additional fittings) backfill of pipe and valve and
seeding as required.
36 inch flow meter installation
Provide personnel and equipment to assist in design, investigative potholing, excavation, removal
precast vault lid, removal of existing meter, reassembly of pipe with new meter, installation of new
precast vault lid and seeding as required.
Sitework
Provide personnel and equipment to load and haul City provided topsoil from stockpile site to the Water
Treatment plant and spread as necessary. Install 6 precast manholes and ladders on existing valve
actuators and purchase electric utility vehicle for access in the CCB.
DocuSign Envelope ID: 393918BF-2E36-4B59-8D50-6191078E1530
Standard Estimate Report Page 1
FCWTF 36 & 42 Valve Repla 9/6/2017 7:04 AM
Project name FCWTF 36 & 42 Valve Repla
Labor rate table Labor - Bare
Equipment rate table Equipment
Report format Sorted by 'Structure/Group phase'
'Detail' summary
Allocate addons
DocuSign Envelope ID: 393918BF-2E36-4B59-8D50-6191078E1530
Standard Estimate Report Page 2
FCWTF 36 & 42 Valve Repla 9/6/2017 7:04 AM
Item Description Takeoff Qty
Labor
Amount
Material
Amount
Subcontract
Amount Name
Equipment
Amount
Other
Amount
Total
Amount
01 Gen Cond
1000.000 GENERAL CONDITIONS
18 Bonds & Insurance 1.00 ls - - - 6,527 6,527
14 Project Manager 6.00 wk 6,984 - - 932 236 8,151
14 Superintendent 9.00 wk 23,572 - - 1,397 757 25,726
12 Office Supplies 2.00 mo - - - 1,066 1,066
12 Copier 2.00 mo - - - 311 311
18 Telephone Charges 2.00 mo - - - 135 135
20 Temporary Toilets 2.00 mo - - - 224 224
10 Safety 1.00 ls - 207 - 1,122 1,329
50 Temporary Protection 1.00 ls 509 - 78 56 643
12 Weekly Cleaning 9.00 wk 458 - - 505 963
10 Fuels - Gas 9.00 wk - - - 1,262 1,262
12 Fuels - Diesel 9.00 wk - - - 2,777 2,777
GENERAL CONDITIONS 31,523 207 2,717 14,668 49,115
1,120.00 Labor hours
600.00 Equipment hours
1900.000 OWNED EQUIPMENT
50 500 Gal. Fuel Tank 2.00 mo - - - 311 - 311
10 Total Station 2.00 mo - - - 1,387 - 1,387
OWNED EQUIPMENT 1,697 1,697
01 Gen Cond 31,523 0 207 4,414 14,668 50,813
1,120.00 Labor hours
600.00 Equipment hours
02 36 inch (Repl YDV 911)
1900.000 OWNED EQUIPMENT
45 Hydra Torque Wrench 0.50 mo - - - 311 - 311
10 20' Trench Box 0.50 mo - - - 518 - 518
20 Bedding Box 0.50 mo - - - 193 - 193
45 Connex Box 0.50 mo - - - 259 - 259
pt 3 Trash Pump 3" 0.50 mo - - - 123 - 123
10 938 Cat Loader 0.50 mo - - 1,974 - 1,974
20 ZX350 Hitachi Trackhoe 0.50 mo - - - 4,689 - 4,689
30 Compaction Wheel Trackhoe 0.50 mo - - - 129 - 129
10 Jobsite Truck 0.50 mo - - - 518 - 518
OWNED EQUIPMENT 8,712 8,712
2000.000 SITEWORK
50 Potholing 2.00 cd 1,862 120 - 1,573 168 3,724
40 Erosion Control 1.00 ls 757 0 - - 168 925
12 Trench Excav, Install Pipe & Valve 10.00 lf 6,518 815 - 3,623 168 11,125
n b 42 Pipe Steel 36 5.00 lf 116 4,337 2,070 - 140 6,664
24 Butterfly Valve 1.00 ea 116 23,207 - 729 24,053
DocuSign Envelope ID: 393918BF-2E36-4B59-8D50-6191078E1530
Standard Estimate Report Page 3
FCWTF 36 & 42 Valve Repla 9/6/2017 7:04 AM
Item Description Takeoff Qty
Labor
Amount
Material
Amount
Subcontract
Amount Name
Equipment
Amount
Other
Amount
Total
Amount
2000.000 SITEWORK
20 Manhole & Ladder 1.00 ea 116 4,022 - 160 - 4,299
n 6 Test Stations, Wire 1.00 ea 931 815 - 181 39 1,967
15 Seeding 3,000.00 sf - - 776 - - 776
SITEWORK 10,418 33,317 2,846 5,537 1,414 53,532
337.194 Labor hours
162.00 Equipment hours
02 36 inch (Repl YDV 911) 10,418 33,317 2,846 14,250 1,414 62,244
337.194 Labor hours
162.00 Equipment hours
03 36 inch (New CE)
1900.000 OWNED EQUIPMENT
45 Hydra Torque Wrench 0.60 mo - - - 373 - 373
10 20' Trench Box 0.60 mo - - - 621 - 621
20 Bedding Box 0.60 mo - - - 232 - 232
45 Connex Box 0.60 mo - - - 311 - 311
pt 3 Trash Pump 3" 0.60 mo - - - 147 - 147
10 938 Cat Loader 0.60 mo - - 2,369 - 2,369
20 ZX350 Hitachi Trackhoe 0.60 mo - - - 5,626 - 5,626
30 Compaction Wheel Trackhoe 0.60 mo - - - 155 - 155
10 Jobsite Truck 0.60 mo - - - 621 - 621
OWNED EQUIPMENT 10,455 10,455
2000.000 SITEWORK
50 Potholing 2.00 cd 2,175 120 - 1,573 168 4,036
40 Erosion Control 1.00 ls 883 - - 168 1,052
12 Trench Excav, Install Pipe & Valve 10.00 lf 7,611 815 - 4,230 168 12,825
n b 42 Pipe Steel 36 5.00 lf 136 4,337 2,070 - 140 6,683
n b 42 Steel Flange 1.00 ea 509 2,391 1,863 - 28 4,792
24 Butterfly Valve 1.00 ea 136 23,207 - 729 24,073
20 Manhole & Ladder 1.00 ea 136 4,022 - 187 - 4,345
n 6 Test Stations, Wire 1.00 ea 1,088 815 - 181 39 2,124
15 Seeding 3,000.00 sf - - 776 - - 776
SITEWORK 12,674 35,708 4,709 6,172 1,442 60,705
404.182 Labor hours
181.11 Equipment hours
03 36 inch (New CE) 12,674 35,708 4,709 16,627 1,442 71,160
404.182 Labor hours
181.11 Equipment hours
04 36 inch Flow Meter
1900.000 OWNED EQUIPMENT
45 Hydra Torque Wrench 0.60 mo - - - 373 - 373
10 20' Trench Box 0.60 mo - - - 621 - 621
DocuSign Envelope ID: 393918BF-2E36-4B59-8D50-6191078E1530
Standard Estimate Report Page 4
FCWTF 36 & 42 Valve Repla 9/6/2017 7:04 AM
Item Description Takeoff Qty
Labor
Amount
Material
Amount
Subcontract
Amount Name
Equipment
Amount
Other
Amount
Total
Amount
1900.000 OWNED EQUIPMENT
20 Bedding Box 0.60 mo - - - 232 - 232
45 Connex Box 0.60 mo - - - 311 - 311
pt 3 Trash Pump 3" 0.60 mo - - - 147 - 147
10 938 Cat Loader 0.60 mo - - 2,369 - 2,369
20 ZX350 Hitachi Trackhoe 0.60 mo - - - 5,626 - 5,626
30 Compaction Wheel Trackhoe 0.60 mo - - - 155 - 155
10 Jobsite Truck 0.60 mo - - - 621 - 621
OWNED EQUIPMENT 10,455 10,455
2000.000 SITEWORK
40 Erosion Control 1.00 ls 757 - - 281 1,037
12 Trench Excav 10.00 lf 4,656 815 - 2,588 168 8,227
n b 42 Pipe & Fittings 5.00 lf 2,829 5,353 2,070 - 140 10,393
20 Vault Top 1.00 ea 698 2,120 - 342 - 3,160
n 6 Test Stations, Wire 1.00 ea 931 815 - 181 39 1,967
15 Landscaping 2,500.00 sf 0 0 647 - - 647
SITEWORK 9,871 9,104 2,717 3,110 628 25,430
365.88 Labor hours
86.00 Equipment hours
13000.000 SPECIAL CONSTRUCTION
300 Meter 1.00 ea 1,804 27,175 4,865 - - 33,844
SPECIAL CONSTRUCTION 1,804 27,175 4,865 33,844
80.00 Labor hours
04 36 inch Flow Meter 11,676 36,279 7,582 13,565 628 69,729
445.88 Labor hours
86.00 Equipment hours
05 Sitework
2000.000 SITEWORK
19 Topsoil 1.50 cd 1,397 2,251 2,368 589 6,605
20 Manhole & Ladder 6.00 ea 9,312 24,131 - 12,835 - 46,278
SITEWORK 10,709 24,131 2,251 15,202 589 52,883
292.00 Labor hours
92.00 Equipment hours
11000.000 EQUIPMENT
n 100 Polaris EV 1.00 ea 0 14,104 - - - 14,104
EQUIPMENT 14,104 14,104
10.00 Labor hours
05 Sitework 10,709 38,235 2,251 15,202 589 66,987
302.00 Labor hours
92.00 Equipment hours
Estimate Totals
DocuSign Envelope ID: 393918BF-2E36-4B59-8D50-6191078E1530
Standard Estimate Report Page 5
FCWTF 36 & 42 Valve Repla 9/6/2017 7:04 AM
Estimate Totals
Description Amount Totals Hours Rate Cost Basis Cost per Unit Percent of Total
Labor 77,000 2,609.254 hrs 21.23%
Material 143,538 39.58%
Subcontract 17,596 4.85%
Equipment 64,058 1,121.106 hrs 17.66%
Other 18,741 5.17%
320,933 320,933 88.50 88.50%
Profit & Overhead 41,703 11.500 % T 11.50%
41,703 362,636 11.50 100.00%
Total 362,636