CHANGE ORDER NO. 01
PROJECT TITLE: Pine Street Water Main Replacement
CONTRACTOR: Connell Resources, Inc.
PROJECT NUMBER: 201709 PO NUMBER: 9175452
ORIGINAL BID/RFP NUMBER & NAME: 8106 Utility Infrastructure Construction Services for
Water, Wastewater, and Stormwater Facilities Capital Improvements
DESCRIPTION:
1. Reason for change: Construction Completed at Reduced Cost due to reduced footage of
water main and service connections required. This caused savings
across several interrelated bid items.
2. Description of Change: Reduction in Contract Cost
3. Change in Contract Price: ($73,140.65)
4. Change in Contract Time: None
ORIGINAL CONTRACT PRICE $228,230.00
TOTAL APPROVED CHANGE ORDER $0.00
TOTAL PENDING CHANGE ORDER $0.00
TOTAL THIS CHANGE ORDER ($73,140.65)
TOTAL % OF THIS CHANGE ORDER 32%
TOTAL C.O.% OF ORIGINAL CONTRACT 32%
ADJUSTED CONTRACT COST $155,062.35
(Assuming all change orders approved)
ACCEPTED BY: DATE:
Contractor's Representative
REVIEWED BY: DATE:
Pat Johnson, Senior Buyer
SUBMITTED BY: DATE:
Owen Randall, Chief Engineer & Project Manager
APPROVED BY: DATE:
Matt Fater, Water Engineering and Field Services
Manager
APPROVED BY: DATE: _________________
Gerry Paul, Purchasing Director (over $60,000)
DocuSign Envelope ID: 8C389253-5041-4F10-84D1-55D5386DC2FE