WORK ORDER
PURSUANT TO A MASTER AGREEMENT BETWEEN
THE CITY OF FORT COLLINS
AND
HYDRO CONSTRUCTION, INC.
WORK ORDER NUMBER: SCP-WTF-HydroWTF12918
PROJECT TITLE: WTF Pleasant Valley Presedimentation
Basin Repairs
ORIGINAL BID/RFP NUMBER & NAME: 8286, Construction Contractor for Projects
at the Water and Wastewater Treatment
Facilities
MASTER AGREEMENT EFFECTIVE DATE: June 20, 2016
ARCHITECT/ENGINEER: Hydro Construction, Inc.
OWNER’S REPRESENTATIVE: Sue Paquette
WORK ORDER COMMENCEMENT DATE: February 5, 2018
WORK ORDER COMPLETION DATE: April 30, 2018
MAXIMUM FEE: (time and reimbursable direct costs): $63,297.00
PROJECT DESCRIPTION/SCOPE OF SERVICES: Contractor to provide construction services
for the Pleasant Valley Presedimentation Basin Repairs for the Fort Collins Water Treatment
Facility. Services shall include construction and repairs through excavation, fill, fabric, liner, and
other repair and replacement work. See the attached supporting documentation.
Service Provider agrees to perform the services identified above and on the attached forms in
accordance with the terms and conditions contained herein and in the Master Agreement
between the parties. In the event of a conflict between or ambiguity in the terms of the Master
Agreement and this Work Order (including the attached forms) the Master Agreement shall
control.
The attached forms consisting of five (5) pages are hereby accepted and incorporated herein,
by this reference, and Notice to Proceed is hereby given after all parties have signed this
document.
SERVICE PROVIDER: Hydro Construction, Inc.
By: Date:
Name: Title:
Page 1 of 10
DocuSign Envelope ID: 06638CD2-13D5-463B-ACD2-0F5D14282B5C
January 31, 2018
Jim Eurich COO
Utilities Work Order Form Official Purchasing Form
Last updated 10/2017
OWNER’S ACCEPTANCE & EXECUTION:
This Work Order and the attached Contract Documents are hereby accepted and incorporated
herein by this reference.
ACCEPTANCE: Date:
Sue Paquette, Special Project Manager
REVIEWED: Date:
Pat Johnson, Senior Buyer
APPROVED AS TO FORM: Date:
Name,City Attorney's Title
(if greater than $1,000,000)
ACCEPTANCE: Date:
Mark Kempton, Water Production Division Manager
ACCEPTANCE: Date:
Owen L. Randall, Water Systems Engineering Division Manager
ACCEPTANCE: Date:
Carol Webb, Water Resources & Treatment Operations Manager
ACCEPTANCE: Date:
Kevin Gertig, Utilities Executive Director
(if greater than $1,000,000)
ACCEPTANCE: Date:
Gerry Paul, Purchasing Director
(if greater than $60,000)
ACCEPTANCE: Date:
Darin Atteberry, City Manager
(if greater than $1,000,000)
ATTEST: Date:
City Clerk
(if greater than $1,000,000)
Page 2 of 10
DocuSign Envelope ID: 06638CD2-13D5-463B-ACD2-0F5D14282B5C
January 31, 2018
January 31, 2018
January 31, 2018
January 31, 2018
February 1, 2018
February 5, 2018
Utilities Work Order Form Official Purchasing Form
Last updated 10/2017
ATTACHMENT A
WORK ORDER SCOPE OF SERVICES
Page 3 of 10
DocuSign Envelope ID: 06638CD2-13D5-463B-ACD2-0F5D14282B5C
January 26, 2018
Hydro Construction Company, Inc. - Scope of Services.
Pleasant Valley Presed Intake Structure
Provide personnel and equipment to remove existing fence, remove existing liner (as necessary) and
remove existing soil materials to wall footing elevation. Place flow fill and clay material as necessary,
install geotextile where needed and reinstall liner and fence.
Page 4 of 10
DocuSign Envelope ID: 06638CD2-13D5-463B-ACD2-0F5D14282B5C
Utilities Work Order Form Official Purchasing Form
Last updated 10/2017
ATTACHMENT B
WORK ORDER COST DETAIL
Page 5 of 10
DocuSign Envelope ID: 06638CD2-13D5-463B-ACD2-0F5D14282B5C
Standard Estimate Report Page 1
Pleasant Valley Presed Re 1/26/2018 9:52 AM
Project name Pleasant Valley Presed Re
Labor rate table Labor - Bare
Equipment rate table Equipment
Report format Sorted by 'Structure/Group phase'
'Detail' summary
Allocate addons
Page 6 of 10
DocuSign Envelope ID: 06638CD2-13D5-463B-ACD2-0F5D14282B5C
Standard Estimate Report Page 2
Pleasant Valley Presed Re 1/26/2018 9:52 AM
Item Description Takeoff Qty
Labor
Amount
Material
Amount
Subcontract
Amount Name
Equipment
Amount
Other
Amount
Total
Amount
02 Pleasant Valley Presed
1000.000 GENERAL CONDITIONS
10 Bonds 1.00 ls - - - 1,234 1,234
14 Project Manager 3.00 wk 2,130 - - 1,122 112 3,365
14 Superintendent 3.00 wk 6,390 - - 1,122 241 7,753
14 Electric Power 1.00 mo - - - 160 160
18 Telephone Charges 1.00 mo - - - 128 128
20 Temporary Toilets 1.00 mo - - - 128 128
10 Safety 1.00 ls 0 - 500 535 535 1,569
10 Fuels 1.00 ls - - - 1,069 1,069
GENERAL CONDITIONS 8,520 500 2,779 3,607 15,407
292.00 Labor hours
240.00 Equipment hours
1900.000 OWNED EQUIPMENT
45 Connex Box 1.00 mo - - - 535 - 535
10 938 Cat Loader 0.50 mo - - 2,039 - 2,039
20 ZX350 Hitachi Trackhoe 0.50 mo - - - 4,843 - 4,843
30 Compaction Wheel Trackhoe 0.50 mo - - - 134 - 134
10 Dump Truck 0.50 mo - - 1,347 - 1,347
OWNED EQUIPMENT 8,897 8,897
1.00 Labor hours
2000.000 SITEWORK
40 Site Exc 190.00 cy 660 - - 1,016 508 2,183
40 Site Fill 100.00 cy 711 0 - 535 267 1,513
40 Site Fill-Clay 190.00 cy 1,423 7,921 - 1,016 508 10,867
40 Flow Fill 20.00 cy 142 2,031 - 107 53 2,334
50 Filter Fabric 1.00 ls 772 2,673 - - - 3,445
50 Liner 1.00 ls 772 0 8,500 - - 9,272
2 Fence R & R 1.00 ls 97 - 2,500 - - 2,597
SITEWORK 4,577 12,625 11,000 2,673 1,336 32,211
188.17 Labor hours
02 Pleasant Valley Presed 13,097 12,625 11,500 14,349 4,944 56,514
481.17 Labor hours
240.00 Equipment hours
Estimate Totals
Description Amount Totals Hours Rate Cost Basis Cost per Unit Percent of Total
Labor 13,097 481.166 hrs 20.69%
Material 12,625 19.95%
Subcontract 11,500 18.17%
Equipment 14,349 240.000 hrs 22.67%
Other 4,944 7.81%
Page 7 of 10
DocuSign Envelope ID: 06638CD2-13D5-463B-ACD2-0F5D14282B5C
Standard Estimate Report Page 3
Pleasant Valley Presed Re 1/26/2018 9:52 AM
Estimate Totals
56,515 56,515 89.29
Profit & Overhead 6,782 12.000 % T 10.71%
Total 63,297
Page 8 of 10
DocuSign Envelope ID: 06638CD2-13D5-463B-ACD2-0F5D14282B5C
Utilities Work Order Form Official Purchasing Form
Last updated 10/2017
ATTACHMENT C
WORK ORDER SCHEDULE DETAIL
Page 9 of 10
DocuSign Envelope ID: 06638CD2-13D5-463B-ACD2-0F5D14282B5C
Project/Task
(week ending) 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12
Preconstruction
Issue City Work Order
Construction
Pleasant Valley Presed
Fence & Liner Demo
Excavation
Backfill & Flow Fill
Liner Replacement
Fence Replacement
by others
by Hydro
Jan Feb Mar Apr May
Page 10 of 10
DocuSign Envelope ID: 06638CD2-13D5-463B-ACD2-0F5D14282B5C
The ACORD name and logo are registered marks of ACORD
CERTIFICATE HOLDER
© 1988-2014 ACORD CORPORATION. All rights reserved.
ACORD 25 (2014/01)
AUTHORIZED REPRESENTATIVE
CANCELLATION
CERTIFICATE OF LIABILITY INSURANCE DATE (MM/DD/YYYY)
JECT LOC
POLICY PRO-
GEN'L AGGREGATE LIMIT APPLIES PER:
CLAIMS-MADE OCCUR
COMMERCIAL GENERAL LIABILITY
PREMISES (Ea occurrence) $
DAMAGE TO RENTED
EACH OCCURRENCE $
MED EXP (Any one person) $
PERSONAL & ADV INJURY $
GENERAL AGGREGATE $
PRODUCTS - COMP/OP AGG $
DED RETENTION $
CLAIMS-MADE
OCCUR
$
AGGREGATE $
UMBRELLA LIAB EACH OCCURRENCE $
EXCESS LIAB
DESCRIPTION OF OPERATIONS / LOCATIONS / VEHICLES (ACORD 101, Additional Remarks Schedule, may be attached if more space is required)
INSR
LTR TYPE OF INSURANCE POLICY NUMBER
POLICY EFF
(MM/DD/YYYY)
POLICY EXP
(MM/DD/YYYY) LIMITS
PER
STATUTE
OTH-
ER
E.L. EACH ACCIDENT
E.L. DISEASE - EA EMPLOYEE
E.L. DISEASE - POLICY LIMIT
$
$
$
ANY PROPRIETOR/PARTNER/EXECUTIVE
If yes, describe under
DESCRIPTION OF OPERATIONS below
(Mandatory in NH)
OFFICER/MEMBER EXCLUDED?
WORKERS COMPENSATION
AND EMPLOYERS' LIABILITY Y / N
AUTOMOBILE LIABILITY
ANY AUTO
ALL OWNED SCHEDULED
HIRED AUTOS
NON-OWNED
AUTOS AUTOS
AUTOS
COMBINED SINGLE LIMIT
BODILY INJURY (Per person)
BODILY INJURY (Per accident)
PROPERTY DAMAGE $
$
$
$
THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD
INDICATED. NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS
CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS,
EXCLUSIONS AND CONDITIONS OF SUCH POLICIES. LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS.
INSD
ADDL
WVD
SUBR
N / A
$
$
(Ea accident)
(Per accident)
OTHER:
THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS
CERTIFICATE DOES NOT AFFIRMATIVELY OR NEGATIVELY AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES
BELOW. THIS CERTIFICATE OF INSURANCE DOES NOT CONSTITUTE A CONTRACT BETWEEN THE ISSUING INSURER(S), AUTHORIZED
REPRESENTATIVE OR PRODUCER, AND THE CERTIFICATE HOLDER.
IMPORTANT: If the certificate holder is an ADDITIONAL INSURED, the policy(ies) must be endorsed. If SUBROGATION IS WAIVED, subject to
the terms and conditions of the policy, certain policies may require an endorsement. A statement on this certificate does not confer rights to the
certificate holder in lieu of such endorsement(s).
COVERAGES CERTIFICATE NUMBER: REVISION NUMBER:
INSURED
PHONE
(A/C, No, Ext):
PRODUCER
ADDRESS:
E-MAIL
FAX
(A/C, No):
CONTACT
NAME:
NAIC #
INSURER A :
INSURER B :
INSURER C :
INSURER D :
INSURER E :
INSURER F :
INSURER(S) AFFORDING COVERAGE
SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE
THE EXPIRATION DATE THEREOF, NOTICE WILL BE DELIVERED IN
ACCORDANCE WITH THE POLICY PROVISIONS.
INS025 (201401)
1/31/2018
Flood and Peterson
PO Box 578
Greeley CO 80632
Dana Stewart, CIC, CISR
(970)266-7149 (970)506-6845
DStewart@floodpeterson.com
Hydro Construction Company Inc.
77 NW Frontage Road
Fort Collins CO 80524
Phoenix Insurance Company 25623
Travelers Indemnity Company 25658
Travelers Property Casualty Company 25674
Pinnacol Assurance 41190
CL17121120854
A
X
X
X
DTCO8G990899PHX17 4/1/2017 4/1/2018
1,000,000
300,000
10,000
1,000,000
2,000,000
2,000,000
B X
X X
DT8108G990899IND17 4/1/2017 4/1/2018
1,000,000
C
X X
X 10,000 CUP-2J40080A-17-26 4/1/2017 4/1/2018
5,000,000
5,000,000
D 2091550 4/1/2017 4/1/2018
X
1,000,000
1,000,000
1,000,000
RE: 18-01-506 WTF Pleasant Valley Presedimentation Basin Repair
City of Fort Collins is included as Additional Insured on the General, Automobile, and Umbrella Liability
Policies if required by written contract or agreement and with respect to work performed by Insured
subject to the policy terms and conditions.