Loading...
HomeMy WebLinkAboutCHANGE ORDER - RFP - 8286 CONSTRUCTION CONTRACTOR FOR PROJECTS AT THE WATER & WASTEWATER TREATMENT FACILITIES (4)Change Order Form (for Work Orders) Official Purchasing Form Last updated 10/2017 CHANGE ORDER NO. 1 PROJECT TITLE: DWRF UV System Final Clarifier Covers CONTRACTOR: Hydro Construction, Inc. WORK ORDER NUMBER: H-WRF-2016-17 PO NUMBER: 9167118 DESCRIPTION: 1. Reason for Change: 1) Relocation of electrical conduit on two SPT clarifiers that were in conflict with covers. 2) Delay of installation of NPT clarifier covers until the completion of UV Construction Project. 2. Description of Change: 1) Demolition of existing conduits, installation of 4 – 60 foot conduits, replacing wiring to final clarifier drives. 2) Delayed taking NPT clarifiers off-line for construction until October 2017 which delayed Hydro’s construction schedule. 3. Change in Work Order Price: $6,299.36 4. Change in Work Order Time: February 9, 2018 ORIGINAL WORK ORDER PRICE $ 371,867.00 TOTAL APPROVED CHANGE ORDER 0.00 TOTAL PENDING CHANGE ORDER 0.00 TOTAL THIS CHANGE ORDER 6,299.36 TOTAL % OF THIS CHANGE ORDER 1.7% TOTAL C.O.% OF ORIGINAL WORK ORDER 1.7% ADJUSTED WORK ORDER COST $ 378,166.36 CONTRACTOR: Hydro Construction, Inc. By: Date: Name: Stanley A. Javernick III Title: Vice President of Operations ACCEPTANCE: Date: Link Mueller, Project Manager REVIEWED: Date: Pat Johnson, Senior Buyer ACCEPTANCE: Date: Jason Graham, Water Reclamation & Biosolids Manager Page 1 of 3 DocuSign Envelope ID: 22A12BE7-92C3-442E-B772-68C838B38F8E January 24, 2018 January 24, 2018 January 31, 2018 February 2, 2018 Change Order Form (for Work Orders) Official Purchasing Form Last updated 10/2017 ACCEPTANCE: Date: Owen L. Randall, Chief Engineer ACCEPTANCE: Date: Carol Webb, Water Resources/Treatment Operations Manager ACCEPTANCE: Date: Gerry Paul, Purchasing Director (if greater than $60,000) Page 2 of 3 DocuSign Envelope ID: 22A12BE7-92C3-442E-B772-68C838B38F8E January 31, 2018 February 2, 2018 Ph : (970) 225-2211 77 NW Frontage Rd. Fort Collins, CO 80524 Change Order Date: Project: Hydro Construction Co., Inc. 77 NW Frontage Rd. Fort Collins, CO 80524 16-03-419 DWRF - UV FINAL CLARIFIER Change Order: 1 12/21/17 To Contractor: FORT COLLINS, CO 80525 Architect's Project: 3036 ENVIRONMENTAL DRIVE The Contract is changed as follows: Conduit relocation and time extension 1 Conduit Relocation/Substantial completion to 1-31-18 $6,299.36 NOT VALID UNTIL SIGNED BY THE ARCHITECT, CONTRACT AND OWNER. ENGINEER CONTRACTOR OWNER Hydro Construction Co., Inc. The date of Substantial Completion as of the date of this Change Order therefore is The Contract Time will be increased by 150 days. $371,867.00 $378,166.36 The original Contract Amount was Net change by previously authorized Change Orders The Contract Amount prior to this Change Order was The Contract will be increased by this Change Order in the amount of The new Contract Amount including this Change Order will be $0.00 $371,867.00 $6,299.36 77 NW Frontage Rd. Fort Collins, CO 80524 (Signature) (Signature) Date Date Date By By By (Signature) Page 3 of 3 DocuSign Envelope ID: 22A12BE7-92C3-442E-B772-68C838B38F8E