HomeMy WebLinkAboutWORK ORDER - PURCHASE ORDER - 9180901Utilities Work Order Form Official Purchasing Form
Last updated 10/2017
WORK ORDER
PURSUANT TO A MASTER AGREEMENT BETWEEN
THE CITY OF FORT COLLINS
AND
CAROLLO ENGINEERS, INC.
WORK ORDER NUMBER: H-WRF-2018-04
PROJECT TITLE: Engineering Support during DWRF Dewater
& Sludge Strain Press Construction
ORIGINAL BID/RFP NUMBER & NAME: 8115, Engineering Services for Water
Reclamation and Biosolids Facility Design
and Construction Services
MASTER AGREEMENT EFFECTIVE DATE: September 21, 2015
ARCHITECT/ENGINEER: Carollo Engineers, Inc.
OWNER’S REPRESENTATIVE: Eileen Dornfest
WORK ORDER COMMENCEMENT DATE: January 31, 2018
WORK ORDER COMPLETION DATE: March 31, 2019
MAXIMUM FEE: (time and reimbursable direct costs): $421,212.00
PROJECT DESCRIPTION/SCOPE OF SERVICES: Engineering-related services during
construction of the dewatering and sludge strain press projects. See attached supporting
documentation.
Service Provider agrees to perform the services identified above and on the attached forms in
accordance with the terms and conditions contained herein and in the Master Agreement
between the parties. In the event of a conflict between or ambiguity in the terms of the Master
Agreement and this Work Order (including the attached forms) the Master Agreement shall
control.
The attached forms consisting of fourteen (14) pages are hereby accepted and incorporated
herein, by this reference, and Notice to Proceed is hereby given after all parties have signed this
document.
SERVICE PROVIDER: Carollo Engineers, Inc.
By: Date:
Name: Title:
Page 1 of 18
By: Date:
Name: Title:
DocuSign Envelope ID: 16B6E580-451E-4919-991B-1D3319F62498
Jason Garside
January 23, 2018
Vice President
January 24, 2018
Ron Burdick Vice President
Utilities Work Order Form Official Purchasing Form
Last updated 10/2017
OWNER’S ACCEPTANCE & EXECUTION:
This Work Order and the attached Contract Documents are hereby accepted and incorporated
herein by this reference.
ACCEPTANCE: Date:
Eileen Dornfest, Special Project Manager
REVIEWED: Date:
Pat Johnson, Senior Buyer
APPROVED AS TO FORM: Date:
Name,City Attorney's Title
(if greater than $1,000,000)
ACCEPTANCE: Date:
Jason Graham, Water Reclamation & Biosolids Division
ACCEPTANCE: Date:
Owen Randall, Water Systems Engineering Division Manager
ACCEPTANCE: Date:
Carol Webb, Water Resources & Treatment Operations Manager
ACCEPTANCE: Date:
Kevin Gertig, Utilities Executive Director
(if greater than $1,000,000)
ACCEPTANCE: Date:
Gerry Paul, Purchasing Director
(if greater than $60,000)
ACCEPTANCE: Date:
Darin Atteberry, City Manager
(if greater than $1,000,000)
ATTEST: Date:
City Clerk
(if greater than $1,000,000)
Page 2 of 18
DocuSign Envelope ID: 16B6E580-451E-4919-991B-1D3319F62498
January 23, 2018
January 24, 2018
January 30, 2018
January 30, 2018
January 30, 2018
January 30, 2018
Utilities Work Order Form Official Purchasing Form
Last updated 10/2017
ATTACHMENT A
WORK ORDER SCOPE OF SERVICES & COST DETAILS
Page 3 of 18
DocuSign Envelope ID: 16B6E580-451E-4919-991B-1D3319F62498
FINAL (01-16-18) pg. 1
Scope of Work – Dewatering and Strain Press Construction Services
FINAL 1-16-18
The City of Fort Collins (City) through assistance with Carollo Engineers (Consultant and
Engineer of Record), Ditesco (Resident Engineer), and Hydro Construction (Contractor) has
completed the design of the Dewatering and Strain Press Project.
The scope of work for the dewatering portion of the project includes demolition of existing
equipment, piping, supply and odor control duct, and appurtenances inside the existing belt filter
press room and conveyor room, and installation of two dewatering centrifuges, which were
procured under the DWRF Dewatering Centrifuge Procurement project. Appurtenances related
to the dewatering centrifuges will be installed, including piping, valves, power supplies,
instruments, and controls.
The scope of work for the stain press portion of the project includes demolition of existing
equipment, piping, and appurtenances inside the Headworks Facility, and installation of two new
strain presses, which were procured under the DWRF Strain Press Procurement project.
Appurtenances related to the sludge screens will be installed, including piping, valves, power
supplies, pneumatic equipment, instruments, and controls. The existing building will be modified
to increase the platform size and provide monorails and hoists for removal of the strain presses.
The purpose of this Work Order is to provide the engineering support and resident engineering
during the construction phase of the proposed Dewatering and Strain Press project (Project).
The construction phase of the Project is estimated to occur from February 2, 2018 to October
29, 2018 (approximately 9 month duration).
The scope of work is divided into the following tasks and subtasks, summarized below:
Task 1 - Project Coordination
Task 1.1 - Weekly Coordination Meetings
Prepare for and participate in thirty-six (36), 2-hour meetings (weekly over 9 month duration)
with the Project Team to coordinate construction activities. Consultants Project Manager will
participate in three (3) meetings per month via conference call and attend one (1) meeting per
month in person. Consultant's engineering discipline staff will be in attendance at the
coordination meetings based on the topics of discussion - it is assumed that one (1) discipline
staff member will be required to attend one (1) coordination meeting per month for a total of nine
(9), 2-hour meetings, and will also participate in one (1) coordination meeting per month via
conference call. It is assumed that the discipline engineer will participate in site
coordination/inspection activities following the monthly meeting for a duration of four (4) hours
per site visit.
Task 1.2 - Progress Reporting
Invoices will be submitted monthly in accordance with City payment protocols. Each invoice will
be submitted with a progress report detailing the work executed during the invoice period and
work remaining.
Page 4 of 18
DocuSign Envelope ID: 16B6E580-451E-4919-991B-1D3319F62498
FINAL (01-16-18) pg. 2
Task 2 - Resident Engineering
Task 2.1 - Resident Engineering
Resident Engineering services will be provided by Ditesco, a subconsultant to Consultant.
Ditesco's scope of services is attached.
Task 3 - Engineering Services during Construction
Task 3.1 - Shop Drawing Review
Consultant assumes reviews of up to ninety four (94) shop drawing submittals. Consultants
estimates that each shop drawing submittal will require an average of three (3) hours to receive,
process, review, verify, respond, document, and return.
Task 3.2 - Interpretations/Clarifications and Field Change Directives
Consultant assumes that up to twenty (20) interpretations and clarifications of contract
documents are required. Consultant estimates that each interpretation and clarification will
require up to four (4) hours to research, respond, and document. Consultant assumes providing
assistance with development of up to eight (8) field change directives. Consultant anticipates
that each change order will require eight (8) hours to research, prepare engineering, respond,
and document.
Task 3.3 - Start-Up/Commissioning Assistance
Consultant shall provide startup assistance to City and Contractor on critical process, systems,
and equipment installed under this project. Provide engineering support to assist in startup
planning and sequence review and check that proper operating parameters are being met,
suggest adjustments, review applicable performance data, and provide written confirmation that
specific process, system, or equipment is functioning as designed. Consultant assumes that
process engineer will be onsite for forty (40) hours during start-up/testing, an Electrical and
Instrumentation Engineer onsite for forty (40) hours; and an HVAC Engineer onsite for sixteen
(16) hours.
Task 3.4 - Record Drawings
Consultant shall develop Record Drawings based on the field hand markups. Record Drawings
will be compiled and delivered within thirty (30) calendar days following Substantial Completion.
Consultant shall provide a signed Colorado Department of Public Health and Environment
(CDPHE) Construction As-Approved Certification Form.
Task 3.5 - Update to Electrical System
Consultant shall provide updates to the City’s existing electrical system study. The updates will
include all modifications to the electrical distribution system as part of the Project as well as
updating Utility information as needed. Updates to the actual report will be coordinated with the
City and applied accordingly. New arc flash labels will be printed for all new equipment to be
applied by the Contractor.
Page 5 of 18
DocuSign Envelope ID: 16B6E580-451E-4919-991B-1D3319F62498
FINAL (01-16-18) pg. 3
Task 3.5 - Factory Acceptance Test
Consultant process engineer will attend and participate in factory acceptance testing of the
centrifuge and strain press equipment. The factory acceptance testing is assumed to occur in
the United States and consist of a total of four (4) days (2 days at factory + 2 days travel) for
each test.
Task 4 - Additional Design Services
Task 4.1 - Additional Design Services
Perform additional engineering analysis and design, and prepare drawings/specifications to
change from electric to pneumatic actuators for the following: centrifuge slop diverter gates and
screw conveyor knife gate valves.
ATTACHMENTS:
1. Labor Hours and Engineering Fee.
2. Ditesco's Scope of Services.
Page 6 of 18
DocuSign Envelope ID: 16B6E580-451E-4919-991B-1D3319F62498
FINAL - 01/16/18
DRAKE DEWATERING AND STRAIN PRESS PROJECT (CONSTRUCTION
PHASE)
LABOR HOURS AND ENGINEERING FEE
Senior Professional
Lead Project Professional
Project Professional
Professional (PE + Mech)
Disciplines (Structural+EIC)
Disciplines (HVAC)
Disciplines (staff engineers)
Senior Technician
Technician
Document
Processing/Clerical
Billing Rate $238 $219 $238 $171 $206 $171 $147 $162 $110 $96
Task 1 - Project Coordination 20 120 20 0 100 0 0 0 0 20 280 $58,320 $0 $2,520 $3,276 $64,116
Task 1.1 - Weekly Coordination Meetings 10 100 20 0 100 0 0 0 0 10 240 $50,600 $0 $2,520 $2,808 $55,928
Task 1.2 - Progress Reporting 10 20 0 0 0 0 0 0 0 10 40 $7,720 $0 $0 $468 $8,188
Task 2 - Resident Engineering 0 0 0 0 0 0 0 0 0 0 0 $0 $183,433 $0 $0 $183,433
Task 2.1 - Resident Engineering (Ditesco) 0 0 0 0 0 0 0 0 0 0 0 $0 $183,433 $0 $0 $183,433
Task 3 - Engineering Services During Construction 16 49 31 190 143 111 174 104 0 35 854 $148,826 $0 $4,180 $9,992 $162,997
Task 3.1 - Shop Drawing Review 6 14 14 51 56 56 71 0 0 14 282 $49,446 $0 $0 $3,299 $52,745
Task 3.2 - Interpretations/Clarifications and Field Change Directives 3 7 7 26 29 29 36 0 0 7 144 $25,249 $0 $0 $1,685 $26,934
Task 3.3 - Start-Up/Commissioning Assistance 2 8 0 40 40 16 0 0 0 0 106 $20,044 $0 $1,680 $1,240 $22,964
Task 3.4 - Record Drawings 4 20 10 10 10 10 20 104 0 10 196 $33,579 $0 $200 $2,293 $36,072
Task 3.5 - Update to Electrical System Studies 2 0 0 0 8 0 48 0 0 4 62 $9,564 $0 $0 $725 $10,289
Task 3.6 - Factory Acceptance Test 0 0 0 64 0 0 0 0 0 0 64 $10,944 $0 $2,300 $749 $13,993
Task 4 - Additional Design Services 0 4 0 16 16 0 0 8 16 0 60 $9,964 $0 $0 $702 $10,666
Task 4.1 - Additional Design Services 0 4 0 16 16 0 0 8 16 0 60 $9,964 $0 $0 $702 $10,666
PROJECT TOTALS - TASKS 1-4 36 173 51 206 259 111 174 112 16 55 1194 $217,110 $183,433 $6,700 $13,970 $421,212
TOTAL COST
LABOR HOURS PROJECT COSTS
Total Direct Labor Hours
Total Labor Cost
Ditesco
Other Direct Costs (ODCs)
PECE
Page 7 of 18
DocuSign Envelope ID: 16B6E580-451E-4919-991B-1D3319F62498
Page 2 of 6
Exhibit A
City of Fort Collins Utilities
Dewatering and Strain Press
Resident Engineering/Construction Management
Scope of Services
Project Understanding
The City of Fort Collins (COFC) Utilities Department is planning to replace the existing strain press (poo kiddy)
installation and add two centrifuges for enhanced digested sludge dewatering. The dewatering project includes
demolition of existing equipment, piping, supply and odor control duct, and appurtenances inside the existing belt
filter press room and conveyor room, and installation of two dewatering centrifuges, which were procured under the
Dewatering Centrifuge Equipment Procurement project. Appurtenances related to the dewatering centrifuges will be
installed, including piping, valves, power supplies, instruments, and controls. The scope of work also includes
installation of one sludge cake transfer conveyor and two truck load out conveyors and related appurtenances.
The stain press project includes demolition of existing equipment, piping, and appurtenances inside the Headworks
Facility, and installation of two new strain presses, which were procured under the Pressurized In-Line Sludge
Screen Equipment Procurement project. Appurtenances related to the sludge screens will be installed, including
piping, valves, power supplies, pneumatic equipment, instruments, and controls. The existing building will be
modified to increase the platform size and provide monorails and hoists for removal of the strain presses.
Phase: Pre-Construction (Task 1)
• During the pre-construction phase, Ditesco will photograph and/or video the existing project conditions
within the construction limits. These photographs and video will be stored by Ditesco for use (as needed)
during the closeout stage of the project.
• We will review and comment on the contractor’s overall project schedule prior to the pre-construction
meeting. We will ensure a logical, defined CPM schedule is established with an overall baseline for
progress measurement.
Phase: Construction (Task 2)
During this phase Ditesco will provide part time Resident Engineering services to assist in work coordination and
ensure compliance with contract documents/specifications.
• Our staff will coordinate, attend and document one pre-construction meeting.
• We will conduct weekly progress meetings on site with the general contractor and their subcontractors. We
will provide meeting minutes for all meetings.
• We will review and recommend approval of pay applications to the City of Fort Collins, review and manage
contract changes for approval by the City, generate and coordinate responses to RFIs and provide for
overall administration of the construction contract. Here, this work task includes review and monitoring of
overall job costs through the monthly variance report and pending issues log.
• Our staff will perform daily site inspections to ensure quality construction and conformity to the plans and
specifications. Inspections will include all specialty inspections required of the project including structural
steel and concrete, mechanical systems, pipe, concrete flatwork and duct bank. We will provide field
engineering support addressing field changes quickly to avoid construction delays. We will provide Carollo
and the City with monthly reports documenting the contractors work progress, contract times and other
pertinent information. We will also document daily work progress in the form of daily logs.
• Ditesco staff will review all material test reports. We will comment on reports not meeting specifications
and recommend remediation measures, if necessary. We will ensure the appropriate numbers of tests are
taken and that they are sampled according to industry standards and the project specifications. We will
Page 8 of 18
DocuSign Envelope ID: 16B6E580-451E-4919-991B-1D3319F62498
Page 3 of 6
coordinate all testing activities with the City’s on-call material testing contractor, CTL Thompson. Material
testing has not been included in our contract.
• We will maintain a photographic records of the project documenting pre-construction, construction and post
construction conditions. This work is completed as part of the daily log record and on Procore and will
include brief descriptions of the photograph with a time and date reference.
• We will maintain project records including contracts, schedules (overall job and three-week look-ahead),
progress meeting minutes, material test results, weekly reports, correspondence, pay applications, change
orders, routine photographs, submittals, RFIs, permits, commissioning records and post construction close-
out paperwork (punch lists, lien waivers, substantial completion/final acceptance). We will maintain this
documentation through Procore, our electronic document management system.
• We will conduct a final punch list walk through and start up sessions for various stages of the work. Formal
start up, testing and training work is anticipated to include all instrumentation, dewatering equipment
operation, chemical feed and pump operation testing. Our staff will assist with testing sequence
documentation created directly from loop/control descriptions provided by Carollo. Ditesco personnel will
coordinate on-site training with City Operations and Maintenance staff by each supplier/manufacturer.
• Ditesco personnel will ensure that an as-built plan set is maintained and transmitted to Carollo upon
completion of the project. This will be an electronic redlined drawing set maintained by our staff and will be
coordinated with plan changes that may be documented by the general contractor. We will also ensure
accurate O&M manuals are transmitted to the City upon completion of the project.
• Ditesco staff will also assist City personnel with overall construction management efforts including cost,
schedule and quality control. Here, we will prepare monthly reports that show project progress, key events
and costs incurred to date.
Phase: Post Construction (Task 3)
• During the Post Construction Phase Ditesco staff will compile all job records in both an electronic and
hardcopy (paper) format for submission to the City. We will also participate in an 11th and 23rd month
warranty walkthrough of the project.
Deliverables
• Deliverables will include full project documentation presented electronically via flash drive (or other form, if
requested): cost information, construction correspondence, pay applications, change orders, field orders,
work change directives, schedules, submittals, requests for information, transmittals, reports, photographs,
meeting notes, record drawings and other relevant information produced throughout the construction
phase.
Schedule
The anticipated schedule for construction is as follows:
Construction: February to November 2018
Fee Estimate
We have based our fee estimate on the following assumptions of the project schedule.
• 10 months total construction project timeframe
• Construction to begin February 2018 with completion by November 2018
• Office trailer and internet/phone service provided by Contractor or City
• Copier/scanner/printer provided by Contractor or City
Page 9 of 18
DocuSign Envelope ID: 16B6E580-451E-4919-991B-1D3319F62498
Page 4 of 6
Estimated Fee: $173,230.00
Estimated Reimbursable Expenses: $ 1,468.00
Total: $174,698.00
A detailed task breakdown is included. Please find this on page 6 of this scope of work proposal.
The fee shown above is to be billed on a time and material not to exceed basis based on the rates shown in the table on page 5
and 6 of this proposal. All reimbursable expenses will be billed at direct cost.
Page 10 of 18
DocuSign Envelope ID: 16B6E580-451E-4919-991B-1D3319F62498
Page 5 of 6
Ditesco
2015-2016 Wage Rate Schedule
Principal: $130.00 - $145.00 per hour
Project Manager: $100.00 - $140.00 per hour
Construction Manager/Resident Engineer: $110.00 - $130.00 per hour
Project Engineer $95.00 - $110.00 per hour
Engineer: $75.00 to 100.00 per hour
Administrative: $60.00 to $75.00 per hour
Mileage Reimbursement: $0.75 per mile
Subconsultant Markup: 5% of cost
All other costs at direct expense
Terms 30 days net
Page 11 of 18
DocuSign Envelope ID: 16B6E580-451E-4919-991B-1D3319F62498
City of Fort Collins - DWRF Dewatering and Strain Press Project
February 2018 to November 2018 10/20/2017
Principal Resident Engineer Administrative
Keith Meyer Jenna Beairsto Cassidy Hill
(hrs) (hrs) (hrs)
$135 $110 $65
Task 1: Preconstruction $685
1.6 Preconstruction Photographs and Video 0 4 0 $440
1.8 Schedule review 1 1 0 $245
Task 2: Construction $161,450
1.1 Review Construction Contracts 0 1 0 $110
1.2 Review Construction Plans and Specifications 2 6 0 $930
1.3 Create and compile job files 0 12 0 $1,320
1.7 Preconstruction Meeting (minutes, contact lists, etc.) 3 3 4 $995
1.9 Submittal/shop drawing coordination and record keeping 0 44 11 $5,555
1.10 Construction progress meetings (1 per week for 10 months) 66 66 132 $24,750
1.11 Monthly Reports 0 5 15 $1,525
1.12 Contract Management (pay applications, change orders, etc.) 5 10 0 $1,775
1.13 RFI Response 0 20 0 $2,200
1.14 Resident Engineering (RE: 4 Hours/Day) 0 880 0 $96,800
1.15 Daily Construction Logs 0 165 0 $18,150
1.16 Job Files (test reports, minutes, correspondence, photos, etc.) 0 11 22 $2,640
2.1 Start Up and Testing 10 20 0 $3,550
2.2 Commissioning 2 8 0 $1,150
Task 3: Post Construction $5,890
3.1 Punch list walk through 2 4 0 $710
3.2 Record Drawing Compilation 0 10 2 $1,230
3.3 Close out paperwork (substantial and final completion, etc.) 0 4 0 $440
3.4 Project Close Out (compilation of files, photos, job records, etc.) 0 20 10 $2,850
3.5 Warranty walkthrough (11th and 23rd months) 0 6 0 $660
Reimbursable Expenses
Mileage @ $0.54 per mile $968
Photocopies, project binders/files, etc. $500
Materials Testing - CTL Thompson (by city) $0
Work Effort Subtotal 91 1300 196 $173,230
Subtotal Reimbursable Items $1,468
Contract Total $174,698
Cost per labor category $12,285 $143,000 $12,740
Effort (days) 11 163 25
Effort (weeks) 2 33 5
Effort (hours per day) 0.41 5.91 0.89
FTE 0.05 0.74 0.11
Assumptions:
- 10 month construction phase
- Daily resident engineering effort (0.75 time)
- Construction start date - February 2018
- Construction end date - November 2018
Phase/Task Description Task Total
Page 6 of 6
Page 12 of 18
DocuSign Envelope ID: 16B6E580-451E-4919-991B-1D3319F62498
Utilities Work Order Form Official Purchasing Form
Last updated 10/2017
ATTACHMENT B
WORK ORDER SCHEDULE
Page 13 of 18
DocuSign Envelope ID: 16B6E580-451E-4919-991B-1D3319F62498
Activity ID Activity Name Original
Duration
Start Finish Total
Float
Predecessors Successors
DWRF - D Dewatering & Sludge Strain Press 436 01-Jan-17 A 29-Oct-18 41
Prelimina Preliminary Design 224 01-Jan-17 A 02-Jan-18 253
A1530 Release of 50% Funds for Dewatering & Sludge Strain 0 01-Jan-17 A A1000
A1000 Kickoff Meeting 1 26-Jan-17 A 26-Jan-17 A A1530 A1010, A103
A1690 Laser Scan 15 03-Mar-17 A 10-Mar-17 A A1030 A1090
A1010 Deliverable: Alternatives Memo 1 08-Mar-17 A 08-Mar-17 A A1000 A1030
A1680 Site Visits 15 09-Mar-17 A 20-Mar-17 A A1000 A1620
A1030 Meeting: Workshop #1 1 21-Mar-17 A 21-Mar-17 A A1000, A101 A1050, A169
A1790 Bi-Weekly Meeting #1 0 04-Apr-17 A A1030 A1800
A1550 Develop and Approve Final Design Contract 15 10-Apr-17 A 27-Apr-17 A A1000 A1090
A1040 Meeting: WEF Conference 3 15-Apr-17 A 18-Apr-17 A A1000 A1620
A1050 Deliverable: DRAFT Basis of Design 0 18-Apr-17 A A1030 A1060, A107
A1670 Bench Testing 10 18-Apr-17 A 02-May-17 A A1030 A1620
A1540 Draft Basis of Design Review 15 20-Apr-17 A 06-Jun-17 A A1050 A1090
A1800 Bi-Weekly Meeting #2 1 25-Apr-17 A 25-Apr-17 A A1790
A1060 Deliverable: Final Basis of Design 0 16-Jun-17 A A1050 A1090
A1780 Release of Remaining 50% Funds for Dewatering & Slu 0 02-Jan-18* 0 A1460
Design 164 01-May-17 A 18-Dec-17 43
A1090 30% Design Development & Specification T.O.C. 40 01-May-17 A 27-Jun-17 A A1540, A155 A1100, A1110
A1100 30% Design Review 5 28-Jun-17 A 30-Jun-17 A A1090 A1560
A1110 30% Design Estimate Generation 10 03-Jul-17 A 18-Jul-17 A A1090 A1140
A1120 60% Design Development 40 03-Jul-17 A 08-Sep-17 A A1560 A1130, A114
A1560 30% Design Workshop 0 22-Aug-17 A A1100 A1120
A1130 60% Design Review 10 08-Sep-17 A 26-Sep-17 A A1120 A1150, A250
A1140 60% Design Estimate Generation 10 08-Sep-17 A 10-Oct-17 A A1120, A111 A1170
A1570 60% Design Workshop 0 26-Sep-17 A A1120 A1150
A1150 90% Design Development 30 02-Oct-17 A 04-Dec-17 41 A1130, A157 A1170, A158
A1580 Carollo QA/QC 20 24-Oct-17 A 04-Dec-17 41 A1150 A1160
A1170 90% Design Estimate Generation 20 17-Nov-17 A 18-Dec-17 43 A1150, A114 A1420
A1160 90% Design Review 10 05-Dec-17 18-Dec-17 41 A1580 A1400
Permitting 362 25-Apr-17 A 02-Oct-18 60
A1070 Prepare CDPHE Site Application 10 25-Apr-17 A 08-May-17 A A1050 A1080
A1080 Submit Site Application to CDPHE 0 23-May-17 A A1070 A1590
A1590 CDPHE Site Application Review 40 24-May-17 A 16-Jun-17 A A1080 A1180, A181
A1180 Site Application Approval by CDPHE 0 16-Jun-17 A A1590 A1190
A1190 Prepare Process Design Report - DRAFT 15 19-Jun-17 A 31-Aug-17 A A1180, A109 A1200
A1200 Review of Process Design Report - DRAFT 10 31-Aug-17 A 07-Sep-17 A A1190 A1210
A1810 Coordination Meeting w/ CDPHE 0 31-Aug-17 A A1590
A1210 Prepare Process Design Report - FINAL 10 07-Sep-17 A 08-Sep-17 A A1200 A1220
A1220 Review of Process Design Report - FINAL 3 11-Sep-17 A 11-Sep-17 A A1210 A1230
A1230 Submit Process Design Report to CDPHE 0 11-Sep-17 A A1220 A1600
A1600 CDPHE Process Design Report Review 30 11-Sep-17 A 08-Nov-17 A A1230 A1240
A1240 Process Design Report Approval by CDPHE 0 08-Nov-17 A A1600 A1460
A1260 Notice to CDPHE of Construction Completion 1 12-Sep-18 12-Sep-18 73 A1760 A1330
A1330 Certification Letter to CDPHE 1 02-Oct-18 02-Oct-18 60 A1260, A176
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 2019
DWRF - Dewatering & Sludge Strain Press
Preliminary Design
Release of 50% Funds for Dewatering & Sludge Strain Press
Kickoff Meeting
Laser Scan
Deliverable: Alternatives Memo
Site Visits
Meeting: Workshop #1
Activity ID Activity Name Original
Duration
Start Finish Total
Float
Predecessors Successors
Procurem Procurement 287 09-May-17 A 29-Jun-18 125
A1400 Capstone Project Review 0 17-Nov-17 A A1160 A1410
A1410 Capstone Estimate Generation 10 20-Nov-17 A 18-Dec-17 41 A1400 A1420
A1420 Estimate Reconciliation 1 21-Dec-17 21-Dec-17 41 A1410, A117 A1430
A1430 Develop Construction Work Order 5 22-Dec-17 05-Jan-18 41 A1420 A1440
A1440 Procure Construction Bonds & Insurance 3 08-Jan-18 10-Jan-18 41 A1430 A1450
A1450 Execute Construction Work Order 15 11-Jan-18 31-Jan-18 41 A1440 A1460
A1460 Notice to Proceed 1 01-Feb-18 01-Feb-18 41 A1450, A124 A1840, A202
DDeewwaatteerriinngg Equipment Procurement 258 09-May-17 A 18-May-18 68
A1270 Develop Dewatering Equipment Specification 20 09-May-17 A 16-Jun-17 A A1090 A1610
A1610 Dewatering Equipment Specification Review 10 19-Jun-17 A 20-Jul-17 A A1270 A1280
A1280 Dewatering Equipment Procurement Estimate Generati 15 27-Jul-17 A 07-Aug-17 A A1610 A1620
A1620 Dewatering Equipment Best Value Selection 10 08-Aug-17 A 26-Sep-17 A A1280, A167 A1290, A182
A1290 Develop Dewatering Equipment Procurement Work Ord 5 28-Aug-17 A 29-Sep-17 A A1620 A1300
A1820 Issue Dewatering Equipment Letter of Intent 2 27-Sep-17 A 28-Sep-17 A A1620 A1630
A1300 Procure Payment Bond for Dewatering Equipment Work 3 02-Oct-17 A 06-Oct-17 A A1290 A1310
A1310 Execute Dewatering Equipment Procurement Work Ord 10 09-Oct-17 A 15-Nov-17 A A1300 A1320
A1320 Issue Dewatering Equipment Purchase Order 0 17-Nov-17 A A1310 A1470
A2890 Dewatering Factory Acceptance Testing 5 14-May-18 18-May-18 68 A1480 A1710
Sludge SludgeStra Strain Press Procurement 220 09-May-17 A 27-Mar-18 192
A1340 Develop Sludge Strain Press Specification 15 09-May-17 A 14-Jun-17 A A1090 A1640
A1640 Sludge Strain Press Specification Review 10 15-Jun-17 A 20-Jul-17 A A1340 A1350
A1350 Sludge Strain Press Procurement Estimate Generation 10 27-Jul-17 A 07-Sep-17 A A1640 A1650
A1650 Sludge Strain Press Best Value Selection 10 08-Sep-17 A 06-Oct-17 A A1350 A1360, A183
A1830 Issue Sludge Strain Press Letter of Intent 2 27-Sep-17 A 28-Sep-17 A A1650 A1660
A1360 Develop Sludge Strain Press Procurement Work Order 6 02-Oct-17 A 01-Nov-17 A A1650 A1370
A1370 Procure Payment Bond for Sludge Strain Press Work O 3 02-Nov-17 A 02-Nov-17 A A1360 A1380
A1380 Execute Sludge Strain Press Procurement Work Order 10 03-Nov-17 A 05-Dec-17 266 A1370 A1390
A1390 Issue Sludge Strain Press Purchase Order 0 06-Dec-17 266 A1380
A2880 Sludge Strain Factory Acceptance Testing 5 21-Mar-18 27-Mar-18 107 A1510 A2490
Electrical Procurement P 25 24-Oct-17 A 03-Jan-18 103
A2500 SSB and HVT Estimate Generation 14 24-Oct-17 A 29-Nov-17 103 A1130 A2560
A2560 Develop SSB & HVT Procurement Work Order 5 22-Nov-17 30-Nov-17 103 A2500 A2570
A2570 Procure Payment Bond for SSB & HVT Work Order 3 01-Dec-17 05-Dec-17 103 A2560 A2580
A2580 Execute SSB & HVT Work Order 15 06-Dec-17 03-Jan-18 103 A2570 A2510, A252
Submittal G Generation 76 24-Oct-17 A 15-Mar-18 143
A1630 Dewatering Equipment Pre-Submittal Meeting 0 24-Oct-17 A 24-Oct-17 A A1820 A1470
A1470 Dewatering Equipment Submittal Generation 30 25-Oct-17 A 07-Dec-17 68 A1630, A132 A1480
A1660 Sludge Strain Press Pre-Submittal Meeting 0 26-Oct-17 A 26-Oct-17 A A1830 A1500
A1500 Sludge Strain Press Equipment Submittal Generation 30 27-Oct-17 A 11-Dec-17 107 A1660 A1510
A2510 SSB1204 - Main Switchboard Submittal Generation 20 04-Jan-18 31-Jan-18 123 A2580 A2640
A2520 HVT1204 - High Voltage Transformer Submittal Genera 20 04-Jan-18 31-Jan-18 103 A2580 A2650
A2530 MCC1225 - Motor Control Center Submittal Generation 20 02-Feb-18 01-Mar-18 70 A1460 A2600
A2540 Light Fixture Submittal Generation 15 02-Feb-18 22-Feb-18 158 A1460 A2610
A2550 Screw Conveyor Submittal Generation 30 02-Feb-18 15-Mar-18 41 A1460 A2620
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 2019
Procurement
Capstone Project Review
Capstone Estimate Generation
Estimate Reconciliation
Develop Construction Work Order
Procure Construction Bonds & Insurance
Execute Construction Work Order
Notice to Proceed
Activity ID Activity Name Original
Duration
Start Finish Total
Float
Predecessors Successors
A2590 FRP HVAC Ductwork Submittal Generation 30 02-Feb-18 15-Mar-18 125 A1460 A2630
A2840 Overhead Bridge Crane Submittal Generation 30 02-Feb-18 15-Mar-18 120 A1460 A2850
Submittal R Review 74 08-Dec-17 29-Mar-18 143
A1480 Dewatering Equipment Submittal Review 20 08-Dec-17 12-Jan-18 68 A1470 A1490, A289
A1510 Sludge Strain Press Equipment Submittal Review 20 12-Dec-17 16-Jan-18 107 A1500 A1520, A288
A2640 SSB1204 - Main Switchboard Submittal Review 10 01-Feb-18 14-Feb-18 123 A2510 A2700
A2650 HVT1204 - High Voltage Transformer Submittal Review 10 01-Feb-18 14-Feb-18 103 A2520 A2710
A2610 Light Fixture Submittal Review 10 23-Feb-18 08-Mar-18 158 A2540 A2670
A2600 MCC1225 - Motor Control Center Submittal Review 10 02-Mar-18 15-Mar-18 70 A2530 A2660
A2620 Screw Conveyor Submittal Review 10 16-Mar-18 29-Mar-18 41 A2550 A2680
A2630 FRP HVAC Ductwork Submittal Review 10 16-Mar-18 29-Mar-18 125 A2590 A2690
A2850 Overhead Bridge Crane Submittal Review 10 16-Mar-18 29-Mar-18 120 A2840 A2860
FFaabbrriiccaattiioonn & Delivery 119 15-Jan-18 29-Jun-18 115
A1490 Dewatering Equipment Fabrication 90 15-Jan-18 18-May-18 73 A1480 A1710
A1520 Sludge Strain Press Equipment Fabrication 50 17-Jan-18 27-Mar-18 112 A1510 A2490
A2700 SSB1204 - Main Switchboard Fabrication 60 15-Feb-18 09-May-18 123 A2640 A2780
A2710 HVT1204 - High Voltage Transformer Fabrication 80 15-Feb-18 07-Jun-18 103 A2650 A2790
A2670 Light Fixture Fabrication 30 09-Mar-18 19-Apr-18 158 A2610 A2810
A2660 MCC1225 - Motor Control Center Fabrication 75 16-Mar-18 29-Jun-18 70 A2600 A2800
A2680 Screw Conveyor Fabrication 50 30-Mar-18 08-Jun-18 41 A2620 A2830
A2690 FRP HVAC Ductwork Fabrication 40 30-Mar-18 24-May-18 125 A2630 A2820
A2860 Overhead Bridge Crane Fabrication 60 30-Mar-18 22-Jun-18 120 A2850 A2200
Construc Construction 189 02-Feb-18 29-Oct-18 41
Sludge SludgeStra Strain Press 123 02-Feb-18 26-Jul-18 107
A1840 Relocate HWS & HWR lines 8 02-Feb-18 13-Feb-18 110 A1460 A1890
A1890 Erect Scaffolding for Monorail Install 7 14-Feb-18 22-Feb-18 110 A1840 A1900
A1900 Concrete GPR Scanning for Monorail Install 3 23-Feb-18 27-Feb-18 110 A1890 A1910
A1910 Install Monorail 15 28-Feb-18 20-Mar-18 110 A1900 A2010
A2010 Remove Scaffolding for Monorail 5 21-Mar-18 27-Mar-18 110 A1910 A2000, A197
A1970 Demo East Strain Press Raceways, Wire, and Equipme 3 28-Mar-18 30-Mar-18 176 A2010 A2720
A2000 Demo Existing East Sludge Strain Press 2 28-Mar-18 29-Mar-18 110 A2010 A1950
A2490 Sludge Strain Press Delivery 0 03-Apr-18 107 A1520, A288 A1950, A170
A1950 East Sludge Strain Press Install 2 04-Apr-18 05-Apr-18 107 A2000, A249 A1960, A272
A1960 Install East Sludge Strain Piping 5 06-Apr-18 12-Apr-18 107 A1950 A1930
A2720 Install East Strain Press Motor and Control Raceways 5 06-Apr-18 12-Apr-18 172 A1970, A195 A2730
A1930 Install Pneumatic Connections for East Strain Press 5 13-Apr-18 19-Apr-18 107 A1960 A1990, A185
A2730 East Strain Press Wire Pull & Terminations 2 13-Apr-18 16-Apr-18 172 A2720 A2740
A2740 Install East Strain Press Instruments 1 17-Apr-18 17-Apr-18 172 A2730 A1990
A1850 Demo Existing Handrail & Platform Section 3 20-Apr-18 24-Apr-18 107 A1930 A1860, A187
A1990 East Sludge Strain Press Start-up & Commissioning 5 20-Apr-18 26-Apr-18 170 A1930, A274
A1860 Install Temporary Handrail 1 24-Apr-18 24-Apr-18 172 A1850
A1870 Install Platform & Handrail Addition 10 25-Apr-18 08-May-18 107 A1850 A1880
A1880 Extend Existing Checker Plate 3 09-May-18 11-May-18 107 A1870 A1700
A1700 West Sludge Strain Press Install 2 14-May-18 15-May-18 107 A1880, A249 A1920, A194
A1940 Install Electrical & Controls for West Strain Press 10 14-May-18 25-May-18 109 A1700 A1720
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 2019
FRP HVAC Ductwork Submittal Generation
Overhead Bridge Crane Submittal Generation
Submittal Review
Dewatering Equipment Submittal Review
Sludge Strain Press Equipment Submittal Review
SSB1204 - Main Switchboard Submittal Review
HVT1204 - High Voltage Transformer Submittal Review
Light Fixture Submittal Review
Activity ID Activity Name Original
Duration
Start Finish Total
Float
Predecessors Successors
A1920 Install West Sludge Strain Piping 5 16-May-18 22-May-18 107 A1700 A1980
A2750 Install West Strain Press Motor and Controls Raceway 5 16-May-18 22-May-18 109 A1700 A2760
A1980 Install Pneumatic Connections for West Strain Press 5 23-May-18 30-May-18 107 A1920 A1720
A2760 West Strain Press Wire Pull and Terminations 2 23-May-18 24-May-18 109 A2750 A2770
A2770 Install West Strain Press Instruments 1 25-May-18 25-May-18 109 A2760 A1720
A1720 West Sludge Strain Press Start-up & Commissioning 10 31-May-18 13-Jun-18 107 A1940, A198 A1740
A1740 Sludge Strain Press Substantial Completion 0 14-Jun-18 107 A1720 A1750
A1750 Sludge Strain Press Final Completion 0 26-Jul-18 107 A1740
DDeewwaatteerriinngg 173 26-Feb-18 29-Oct-18 41
Belt Press Area 138 26-Feb-18 10-Sep-18 76
A2020 Remove Existing South Section of Glazing 1 26-Feb-18 26-Feb-18 145 A1460 A2030
A2030 Install Temp Wall and Gaurdrail (South Glazing Section) 3 27-Feb-18 01-Mar-18 145 A2020 A2040
A2040 Demo Existing Belt Press Conveyor 3 02-Mar-18 06-Mar-18 145 A2030 A2060
A2060 Demo Raised Concrete Floor 5 07-Mar-18 13-Mar-18 145 A2040 A2050, A207
A2050 Demo Existing Interior Misc. Piping 3 14-Mar-18 16-Mar-18 148 A2060 A2090
A2070 Demo Existing HVAC Ductwork 6 14-Mar-18 21-Mar-18 145 A2060 A2080, A218
A2080 Repair HVAC Wall Penetration 1 22-Mar-18 22-Mar-18 195 A2070
A2090 Demo Existing Monorail & Beams 2 22-Mar-18 23-Mar-18 145 A2070, A205 A2140, A287
A2100 Relocate HWS/HWR, Vent Lines & Unit Heaters 15 26-Mar-18 13-Apr-18 145 A2090 A2120
A2140 Sawcut Wall Openings (Conveyor & HVAC) 4 26-Mar-18 29-Mar-18 186 A2090 A2150
A2870 Demo Existing Lighting & Misc. Electrical 2 26-Mar-18 27-Mar-18 176 A2090 A2230
A2150 Repair Existing Conveyor Belt Opening - Masonry 2 30-Mar-18 02-Apr-18 186 A2140 A2160
A2120 Roof Decking Reinforcement 2 02-Apr-18 03-Apr-18 145 A2100 A2110
A2160 Repair Glazing - North Wall 2 03-Apr-18 04-Apr-18 186 A2150
A2110 Demo Roof Decking for Skylight 2 04-Apr-18 05-Apr-18 145 A2120 A2130, A221
A2130 Install Skylight 8 06-Apr-18 17-Apr-18 153 A2110 A2170, A219
A2210 Layout & Core Drill Drain Penetrations (Existing Floor) 3 06-Apr-18 10-Apr-18 145 A2110 A2290
A2290 Install Centrate & Slop Drain Lines 11 11-Apr-18 25-Apr-18 145 A2210 A2300
A2170 Install Coating for Walls and Roof 8 18-Apr-18 27-Apr-18 153 A2130 A2230
A2810 Light Fixture Delivery 0 20-Apr-18 158 A2670 A2230
A2300 Install 6" Centrifuge Feed Lines 10 26-Apr-18 09-May-18 145 A2290 A2310
A2230 Install New Lighting 6 30-Apr-18 07-May-18 153 A2170, A281 A2200
A2310 Install Conveyor Drain Line 8 10-May-18 21-May-18 145 A2300 A2320
A2320 Grind & Patch Floor Demo 8 22-May-18 01-Jun-18 145 A2310
A2180 Install HVAC Supply & Exhaust Ductwork 15 25-May-18 15-Jun-18 125 A2070, A282 A2190
A2820 FRP HVAC Ductwork Delivery 0 25-May-18 125 A2690 A2180
A1710 Dewatering Equipment Delivery 0 25-May-18 68 A1490, A289 A2420
A2190 Patch Roof Penetrations 10 18-Jun-18 29-Jun-18 125 A2130, A218
A2200 Install Overhead Bridge Crane 10 25-Jun-18 09-Jul-18 120 A2230, A286
A2410 Install New Conveyor (Centrifuges to Truck Bay) 8 25-Jun-18 05-Jul-18 41 A2340 A2420
A2800 MCC1225 Delivery 0 02-Jul-18 70 A2660 A3000
A3000 Demo Existing MCC1225 & Setup Temp Power 5 02-Jul-18 09-Jul-18 70 A2800 A3010
A2420 Install North Centrifuge Stand 2 06-Jul-18 09-Jul-18 41 A2410, A171 A2430
A2430 Install North Centrifuge onto Stand 3 10-Jul-18 12-Jul-18 41 A2420 A2440
A3010 Install MCC1225 and Terminations to Existing Loads 6 10-Jul-18 17-Jul-18 70 A3000 A2910
A2440 Complete Process Piping Connections to North Centrifu 10 13-Jul-18 26-Jul-18 41 A2430 A2450
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 2019
Install West Sludge Strain Piping
Install West Strain Press Motor and Controls Raceway
Install Pneumatic Connections for West Strain Press
West Strain Press Wire Pull and Terminations
Install West Strain Press Instruments
West Sludge Strain Press Start-up & Commissioning
Sludge Strain Press Substantial Completion
Activity ID Activity Name Original
Duration
Start Finish Total
Float
Predecessors Successors
A2450 Install South Centrifuge Stand 2 27-Jul-18 30-Jul-18 41 A2440 A2460
A2460 Install South Centrifuge onto Stand 3 31-Jul-18 02-Aug-18 41 A2450 A2470, A290
A2470 Complete Process Piping Connections to South Centrifu 10 03-Aug-18 16-Aug-18 92 A2460
A2900 Install Centrifuge Raceways 17 03-Aug-18 27-Aug-18 41 A2460 A2910
A2910 Centrifuge Wire Pulls 4 28-Aug-18 31-Aug-18 41 A2900, A301 A2920
A2920 Centrifuge Wire Terminations 5 04-Sep-18 10-Sep-18 41 A2910 A1730
Site SiteWork Work 38 10-May-18 03-Jul-18 123
A2780 SSB1204 Delivery 0 10-May-18 123 A2700 A2930
A2350 Demo Sidewalk and Landscaping 1 25-May-18 25-May-18 110 A1460 A2390
A2390 Excavate Electrical Duct Bank 2 29-May-18 30-May-18 110 A2350 A2250
A2250 Form & Place Electrical Duct Bank 6 31-May-18 07-Jun-18 110 A2390 A2260
A2790 HVT1204 Delivery 0 08-Jun-18 103 A2710 A2930
A2930 Demo Existing MCC1225 Feeds from SSB1204 2 08-Jun-18 11-Jun-18 103 A2780, A279 A2240
A2240 Demo SSB1204 & HVT1204 3 12-Jun-18 14-Jun-18 103 A2930 A2480
A2480 Demo Existing SSB/HVT Electrical Pad 2 15-Jun-18 18-Jun-18 103 A2240 A2260
A2260 Form & Place SSB/HVT Electrical Pad 3 19-Jun-18 21-Jun-18 103 A2250, A248 A2280
A2280 Install SSB1204 & HVT1204 3 22-Jun-18 26-Jun-18 103 A2260 A2270, A302
A2270 Repair Landscaping & Sidewalk 4 27-Jun-18 02-Jul-18 124 A2280
A3020 Feeder SFC 1225 from SSB1204 to MCC1225 3 27-Jun-18 29-Jun-18 103 A2280 A3030
A3030 Feeder HVT 1204 to SFB 1204 2 02-Jul-18 03-Jul-18 103 A3020 A1760
Truck Bay Conveyor Area 43 11-Jun-18 09-Aug-18 97
A2830 Screw Conveyor Delivery 0 11-Jun-18 41 A2680 A2330
A2330 Demo Existing South Conveyor 4 12-Jun-18 15-Jun-18 41 A2830 A2340
A2340 Install New South Conveyor 5 18-Jun-18 22-Jun-18 41 A2330 A2940, A241
A2940 Install South Screw Conveyor Raceways 4 25-Jun-18 28-Jun-18 97 A2340 A2950
A2950 Wire Pull for South Screw Conveyor 2 29-Jun-18 02-Jul-18 97 A2940 A2960
A2960 South Screw Conveyor Terminations 2 03-Jul-18 05-Jul-18 97 A2950 A2360
A2360 Start-up & Commissioning South Conveyor 5 06-Jul-18 12-Jul-18 97 A2960 A2370
A2370 Demo Existing North Screw Conveyor 4 13-Jul-18 18-Jul-18 97 A2360 A2380
A2380 Install New North Screw Conveyor 5 19-Jul-18 25-Jul-18 97 A2370 A2970
A2970 Install Raceways for North Screw Conveyor 4 26-Jul-18 31-Jul-18 97 A2380 A2980
A2980 Wire Pull for North Screw Conveyor 1 01-Aug-18 01-Aug-18 97 A2970 A2990
A2990 Terminations for North Screw Conveyor 1 02-Aug-18 02-Aug-18 97 A2980 A2400
A2400 Start-up & Commissioning North Conveyor 5 03-Aug-18 09-Aug-18 97 A2990
Start-up & Commissioning 35 11-Sep-18 29-Oct-18 41
A1730 Dewatering Start-up & Commissioning 15 11-Sep-18 01-Oct-18 41 A2920 A1760
A1760 Dewatering Substantial Completion 0 02-Oct-18 41 A1730, A303 A1770, A126
A1770 Dewatering Final Completion 0 29-Oct-18 41 A1760
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 2019
Install South Centrifuge Stand
Install South Centrifuge onto Stand
Complete Process Piping Connections to South Centrifuge
Install Centrifuge Raceways
Centrifuge Wire Pulls
Centrifuge Wire Terminations
Site Work
SSB1204 Delivery
Demo Sidewalk and Landscaping
Excavate Electrical Duct Bank
Form & Place Electrical Duct Bank
HVT1204 Delivery
Demo Existing MCC1225 Feeds from SSB1204
Demo SSB1204 & HVT1204
Demo Existing SSB/HVT Electrical Pad
Form & Place SSB/HVT Electrical Pad
Install SSB1204 & HVT1204
Repair Landscaping & Sidewalk
Feeder SFC 1225 from SSB1204 to MCC1225
Feeder HVT 1204 to SFB 1204
Truck Bay Conveyor Area
Screw Conveyor Delivery
Demo Existing South Conveyor
Install New South Conveyor
Install South Screw Conveyor Raceways
Wire Pull for South Screw Conveyor
South Screw Conveyor Terminations
Start-up & Commissioning South Conveyor
Demo Existing North Screw Conveyor
Install New North Screw Conveyor
Install Raceways for North Screw Conveyor
Wire Pull for North Screw Conveyor
Terminations for North Screw Conveyor
Start-up & Commissioning North Conveyor
Start-up & Commissioning
Dewatering Start-up & Commissioning
Dewatering Substantial Completion
Dewatering Final Completion
Data Date:20-Nov-17 DWRF - Dewatering Sludge Strain Press Current Date:27-Nov-17
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 5 of 5 TASK filter: All Activities
© Oracle Corporation
Page 18 of 18
DocuSign Envelope ID: 16B6E580-451E-4919-991B-1D3319F62498
Sludge Strain Press Final Completion
Dewatering
Belt Press Area
Remove Existing South Section of Glazing
Install Temp Wall and Gaurdrail (South Glazing Section)
Demo Existing Belt Press Conveyor
Demo Raised Concrete Floor
Demo Existing Interior Misc. Piping
Demo Existing HVAC Ductwork
Repair HVAC Wall Penetration
Demo Existing Monorail & Beams
Relocate HWS/HWR, Vent Lines & Unit Heaters
Sawcut Wall Openings (Conveyor & HVAC)
Demo Existing Lighting & Misc. Electrical
Repair Existing Conveyor Belt Opening - Masonry
Roof Decking Reinforcement
Repair Glazing - North Wall
Demo Roof Decking for Skylight
Install Skylight
Layout & Core Drill Drain Penetrations (Existing Floor)
Install Centrate & Slop Drain Lines
Install Coating for Walls and Roof
Light Fixture Delivery
Install 6" Centrifuge Feed Lines
Install New Lighting
Install Conveyor Drain Line
Grind & Patch Floor Demo
Install HVAC Supply & Exhaust Ductwork
FRP HVAC Ductwork Delivery
Dewatering Equipment Delivery
Patch Roof Penetrations
Install Overhead Bridge Crane
Install New Conveyor (Centrifuges to Truck Bay)
MCC1225 Delivery
Demo Existing MCC1225 & Setup Temp Power
Install North Centrifuge Stand
Install North Centrifuge onto Stand
Install MCC1225 and Terminations to Existing Loads
Complete Process Piping Connections to North Centrifuge
Data Date:20-Nov-17 DWRF - Dewatering Sludge Strain Press Current Date:27-Nov-17
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 4 of 5 TASK filter: All Activities
© Oracle Corporation
Page 17 of 18
DocuSign Envelope ID: 16B6E580-451E-4919-991B-1D3319F62498
MCC1225 - Motor Control Center Submittal Review
Screw Conveyor Submittal Review
FRP HVAC Ductwork Submittal Review
Overhead Bridge Crane Submittal Review
Fabrication & Delivery
Dewatering Equipment Fabrication
Sludge Strain Press Equipment Fabrication
SSB1204 - Main Switchboard Fabrication
HVT1204 - High Voltage Transformer Fabrication
Light Fixture Fabrication
MCC1225 - Motor Control Center Fabrication
Screw Conveyor Fabrication
FRP HVAC Ductwork Fabrication
Overhead Bridge Crane Fabrication
Construction
Sludge Strain Press
Relocate HWS & HWR lines
Erect Scaffolding for Monorail Install
Concrete GPR Scanning for Monorail Install
Install Monorail
Remove Scaffolding for Monorail
Demo East Strain Press Raceways, Wire, and Equipment
Demo Existing East Sludge Strain Press
Sludge Strain Press Delivery
East Sludge Strain Press Install
Install East Sludge Strain Piping
Install East Strain Press Motor and Control Raceways
Install Pneumatic Connections for East Strain Press
East Strain Press Wire Pull & Terminations
Install East Strain Press Instruments
Demo Existing Handrail & Platform Section
East Sludge Strain Press Start-up & Commissioning
Install Temporary Handrail
Install Platform & Handrail Addition
Extend Existing Checker Plate
West Sludge Strain Press Install
Install Electrical & Controls for West Strain Press
Data Date:20-Nov-17 DWRF - Dewatering Sludge Strain Press Current Date:27-Nov-17
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 3 of 5 TASK filter: All Activities
© Oracle Corporation
Page 16 of 18
DocuSign Envelope ID: 16B6E580-451E-4919-991B-1D3319F62498
Dewatering Equipment Procurement
Develop Dewatering Equipment Specification
Dewatering Equipment Specification Review
Dewatering Equipment Procurement Estimate Generation
Dewatering Equipment Best Value Selection
Develop Dewatering Equipment Procurement Work Order
Issue Dewatering Equipment Letter of Intent
Procure Payment Bond for Dewatering Equipment Work Order
Execute Dewatering Equipment Procurement Work Order
Issue Dewatering Equipment Purchase Order
Dewatering Factory Acceptance Testing
Sludge Strain Press Procurement
Develop Sludge Strain Press Specification
Sludge Strain Press Specification Review
Sludge Strain Press Procurement Estimate Generation
Sludge Strain Press Best Value Selection
Issue Sludge Strain Press Letter of Intent
Develop Sludge Strain Press Procurement Work Order
Procure Payment Bond for Sludge Strain Press Work Order
Execute Sludge Strain Press Procurement Work Order
Issue Sludge Strain Press Purchase Order
Sludge Strain Factory Acceptance Testing
Electrical Procurement
SSB and HVT Estimate Generation
Develop SSB & HVT Procurement Work Order
Procure Payment Bond for SSB & HVT Work Order
Execute SSB & HVT Work Order
Submittal Generation
Dewatering Equipment Pre-Submittal Meeting
Dewatering Equipment Submittal Generation
Sludge Strain Press Pre-Submittal Meeting
Sludge Strain Press Equipment Submittal Generation
SSB1204 - Main Switchboard Submittal Generation
HVT1204 - High Voltage Transformer Submittal Generation
MCC1225 - Motor Control Center Submittal Generation
Light Fixture Submittal Generation
Screw Conveyor Submittal Generation
Data Date:20-Nov-17 DWRF - Dewatering Sludge Strain Press Current Date:27-Nov-17
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 2 of 5 TASK filter: All Activities
© Oracle Corporation
Page 15 of 18
DocuSign Envelope ID: 16B6E580-451E-4919-991B-1D3319F62498
Bi-Weekly Meeting #1
Develop and Approve Final Design Contract
Meeting: WEF Conference
Deliverable: DRAFT Basis of Design
Bench Testing
Draft Basis of Design Review
Bi-Weekly Meeting #2
Deliverable: Final Basis of Design
Release of Remaining 50% Funds for Dewatering & Sludge Strain Press
Design
30% Design Development & Specification T.O.C.
30% Design Review
30% Design Estimate Generation
60% Design Development
30% Design Workshop
60% Design Review
60% Design Estimate Generation
60% Design Workshop
90% Design Development
Carollo QA/QC
90% Design Estimate Generation
90% Design Review
Permitting
Prepare CDPHE Site Application
Submit Site Application to CDPHE
CDPHE Site Application Review
Site Application Approval by CDPHE
Prepare Process Design Report - DRAFT
Review of Process Design Report - DRAFT
Coordination Meeting w/ CDPHE
Prepare Process Design Report - FINAL
Review of Process Design Report - FINAL
Submit Process Design Report to CDPHE
CDPHE Process Design Report Review
Process Design Report Approval by CDPHE
Notice to CDPHE of Construction Completion
Certification Letter to CDPHE
Data Date:20-Nov-17 DWRF - Dewatering Sludge Strain Press Current Date:27-Nov-17
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 1 of 5 TASK filter: All Activities