HomeMy WebLinkAboutWORK ORDER - PURCHASE ORDER - 9180899Utilities Work Order Form Official Purchasing Form
Last updated 10/2017
WORK ORDER
PURSUANT TO A MASTER AGREEMENT BETWEEN
THE CITY OF FORT COLLINS
AND
CAROLLO ENGINEERS, INC.
WORK ORDER NUMBER: H-WRF-2018-05
PROJECT TITLE: DWRF Digester 612 Lid Design
ORIGINAL BID/RFP NUMBER & NAME: 8115, Engineering Services for Water
Reclamation and Biosolids Facility Design
and Construction Services
MASTER AGREEMENT EFFECTIVE DATE: September 21, 2015
ARCHITECT/ENGINEER: Carollo Engineers, Inc.
OWNER’S REPRESENTATIVE: Eileen Dornfest
WORK ORDER COMMENCEMENT DATE: February 1, 2018
WORK ORDER COMPLETION DATE: September 30, 2018
MAXIMUM FEE: (time and reimbursable direct costs): $130,448.00
PROJECT DESCRIPTION/SCOPE OF SERVICES: Engineering and design services for the
design and procurement of a new lid for digester 612. See attached supporting documentation.
Service Provider agrees to perform the services identified above and on the attached forms in
accordance with the terms and conditions contained herein and in the Master Agreement
between the parties. In the event of a conflict between or ambiguity in the terms of the Master
Agreement and this Work Order (including the attached forms) the Master Agreement shall
control.
The attached forms consisting of Four (4) pages are hereby accepted and incorporated herein,
by this reference, and Notice to Proceed is hereby given after all parties have signed this
document.
SERVICE PROVIDER: Carollo Engineers, Inc.
By: Date:
Name: Title:
By: Date:
Name: Title:
Page 1 of 8
DocuSign Envelope ID: ACAB7483-2B75-459B-B9FC-A0F6FC4BD7C0
January 22, 2018
Jason Garside Vice President
January 23, 2018
Ron Burdick Vice President
Utilities Work Order Form Official Purchasing Form
Last updated 10/2017
OWNER’S ACCEPTANCE & EXECUTION:
This Work Order and the attached Contract Documents are hereby accepted and incorporated
herein by this reference.
ACCEPTANCE: Date:
Eileen Dornfest, Special Project Manager
REVIEWED: Date:
Pat Johnson, Senior Buyer
APPROVED AS TO FORM: Date:
Name,City Attorney's Title
(if greater than $1,000,000)
ACCEPTANCE: Date:
Jason Graham, Water Reclamation & Biosolids Division
ACCEPTANCE: Date:
Owen Randall, Water Systems Engineering Division Manager
ACCEPTANCE: Date:
Carol Webb, Water Resources & Treatment Operations Manager
ACCEPTANCE: Date:
Kevin Gertig, Utilities Executive Director
(if greater than $1,000,000)
ACCEPTANCE: Date:
Gerry Paul, Purchasing Director
(if greater than $60,000)
ACCEPTANCE: Date:
Darin Atteberry, City Manager
(if greater than $1,000,000)
ATTEST: Date:
City Clerk
(if greater than $1,000,000)
Page 2 of 8
DocuSign Envelope ID: ACAB7483-2B75-459B-B9FC-A0F6FC4BD7C0
January 22, 2018
January 22, 2018
January 30, 2018
January 23, 2018
January 30, 2018
January 30, 2018
Utilities Work Order Form Official Purchasing Form
Last updated 10/2017
ATTACHMENT A
WORK ORDER SCOPE OF SERVICES & COST DETAILS
Page 3 of 8
DocuSign Envelope ID: ACAB7483-2B75-459B-B9FC-A0F6FC4BD7C0
Scope of Work - Digester Lid (Cover) 612 Replacement Design
FINAL v2 1-12-18
The City of Fort Collins (City) intends to implement the replacement of Digester Cover 612 at
the Drake Water Reclamation Facility (DWRF). The Digester Cover 612 Replacement project
(Project) consists of demolition of the existing Digester 612 cover, installation of a new metal-
framed cover, potential concrete repair/coating of the existing digester walls (internal), and
potential minor modifications to piping internal to the digester. The Project will be designed by
Carollo Engineers, Inc. (Consultant) and constructed by Hydro Construction Company, Inc.
(Contractor).
The purpose of this Work Order is to provide technical analysis and engineering, and for the
preparation of drawings and specifications for the Project. The level of detail for drawings and
specifications will be similar to what was utilized for the Digester Cover 611 Replacement
project (MWH; June 2015). It is anticipated that this design work will proceed beginning January
15, 2018 and be completed by June 30, 2018. Construction-related services are not included in
this scope and the cost estimate attached.
The scope of work is divided into the following major tasks, summarized below:
Task 1 - Project Administration and Coordination
Task 1.1 - Project Team Coordination Meetings and Project Management Coordination
Meetings
Prepare for and participate in six (6), two (2) hour meetings with the Project Team to coordinate
the pre-design and design activities. Appropriate Consultant staff and subconsultants will be in
attendance based on the topics of discussion. Meeting agendas will be provided and a Decision
Log will be kept up to date over the course of the Project.
Consultant's Project Manager will participate in bi-weekly conference calls with the City's Project
Manager for project coordination purposes. A total of twelve (12), one (1) hour meetings are
assumed.
Task 1.2 - Quality Assurance/Quality Control (QA/QC)
Perform quality assurance and quality control of all deliverables prepared by Consultant in
accordance with Consultant's standard QA/QC policies and procedures.
Task 1.3 - Progress Reporting
Invoices will be submitted monthly in accordance with City payment protocols. Each invoice will
be submitted with a progress report detailing the work executed during the invoice period and
work remaining.
Task 2 - Facility Investigations and Existing Documentation Review
Task 2.1 - Facility Investigations
Conduct walkthrough of facilities with plant staff to develop understanding of existing conditions
and preferences for implementation of proposed improvements. Assume one (1), two (2) hour
walkthrough. Consultant's Project Manager (PM), Mechanical Engineer and Structural Engineer
will attend walkthrough.
Page 4 of 8
DocuSign Envelope ID: ACAB7483-2B75-459B-B9FC-A0F6FC4BD7C0
Perform structural and mechanical investigation of empty and cleaned digester to evaluate
structural integrity and piping configuration that can be determined through surface visual
inspection. Consultant will document observations and recommendations for structural repair
and/or coating in an email summary. Consultant will consider piping configuration for design of
any proposed piping modifications.
Task 2.2 - Existing Documentation Review
Consultant will review digester record drawings and specifications from Digester 611 Lid project.
City will provide record drawings. Contractor will perform as-built measurements of existing
Digester 612 for confirmation of dimensions included in drawings and specifications.
Task 3 - Design Development and Procurement Support
Task 3.1 - Engineering Analyses
Consultant will assist City and Contractor in confirming that cover manufacturer for Project will
be same cover manufacturer that supplied the Digester 611 cover. Consultant will meet with
Owner and digester cover manufacturer to understand design considerations specific to the
manufacturer's scope of supply. Design for a mixing system for Digester 612 is not included in
this scope but the possibility of a future mixer installation will be considered in the lid design.
Task 3.2 and Task 3.3 - Design Drawings and Specifications
Prepare design drawings and specifications to progress the design of Project to 30 and 90
percent completion levels. The 90 percent drawings and specifications will be reviewed by City
and revised by Consultant to produce the Issued for Construction documents. A proposed
drawings list is attached. Specifications are assumed for the following: Digester Cover; Misc.
Instrumentation and Controls specifications; Coatings; and Miscellaneous Metals.
Task 3.4 - Digester Cover Shop Drawing Submittal Review
Consultant will review Digester Cover shop drawing submitted by cover supplier, as part of early
procurement. Assume review of two submittals (1 original and 1 revision).
Page 5 of 8
DocuSign Envelope ID: ACAB7483-2B75-459B-B9FC-A0F6FC4BD7C0
FINAL v2 - 1/12/18
DWRF DIGESTER LID 612 REPLACEMENT
LABOR HOURS AND ENGINEERING FEE
Senior Professional (BL)
Project Manager (JG)
Lead Project Professional
Professional (PE)
Disciplines
(Structural+Arch) (MK)
Disciplines (EIC) (CH)
Disciplines (Civil, HVAC,
Mech)
Senior Technician
Technician
Document
Processing/Clerical
Billing Rate $238 $219 $219 $171 $206 $171 $147 $162 $110 $96
Task 1 - Project Administration and Coordination 22 50 4 28 28 0 0 0 0 1 133 $27,714 $0 $0 $0 $600 $1,556 $29,870
Task 1.1 - Project Team Coordination Mtgs and PM Coordination Mtgs 4 36 0 24 24 0 0 0 0 0 88 $17,884 $0 $0 $0 $600 $1,030 $19,514
Task 1.2 - Quality Assurance/Quality Control 16 8 4 4 4 0 0 0 0 0 36 $7,944 $0 $0 $0 $0 $421 $8,365
Task 1.3 - Progress Reporting 2 6 0 0 0 0 0 0 0 1 9 $1,886 $0 $0 $0 $0 $105 $1,991
Task 2 - Facility Investigations and Exist Doc Review 0 6 0 20 20 0 0 0 0 0 46 $8,854 $0 $0 $0 $200 $538 $9,592
Task 2.1 - Facility Investigations 0 4 0 8 8 0 0 0 0 0 20 $3,892 $0 $0 $0 $200 $234 $4,326
Task 2.2 - Existing Documentation Review 0 2 0 12 12 0 0 0 0 0 26 $4,962 $0 $0 $0 $0 $304 $5,266
Task 3 - Design Development 10 24 21 89 164 0 0 82 82 0 471 $83,374 $2,100 $0 $0 $0 $5,512 $90,986
Task 3.1 - Engineering Analyses 4 2 2 24 16 0 0 0 0 0 48 $9,228 $0 $0 $0 $0 $562 $9,790
Task 3.2 - Design Drawings 2 16 16 49 115 0 0 66 66 0 330 $57,564 $1,050 $0 $0 $0 $3,861 $62,475
Task 3.3 - Design Specifications 2 3 2 7 17 0 0 10 10 0 52 $9,219 $1,050 $0 $0 $0 $609 $10,877
Task 3.4 - Digester Lid Shop Drawing Submittal Review 2 2 0 8 16 0 0 7 7 0 41 $7,362 $0 $0 $0 $0 $481 $7,843
PROJECT TOTALS - TASKS 1-3 32 80 25 137 212 0 0 82 82 1 650 $119,942 $2,100 $0 $0 $800 $7,607 $130,448
TOTAL COST
LABOR HOURS PROJECT COSTS
Total Direct Labor Hours
Total Labor Cost
Ditesco
Lithos
King Surveying
Other Direct Costs (ODCs)
PECE
Page 6 of 8
DocuSign Envelope ID: ACAB7483-2B75-459B-B9FC-A0F6FC4BD7C0
Utilities Work Order Form Official Purchasing Form
Last updated 10/2017
ATTACHMENT B
WORK ORDER SCHEDULE
Page 7 of 8
DocuSign Envelope ID: ACAB7483-2B75-459B-B9FC-A0F6FC4BD7C0
City of Fort Collins - Digester Lid 612 Replacement Design
Carollo Design Activities and Schedule
last revised: 1/16/2018
DWRF Digester Lid 611 Project
Project Coordination
x 1/25
Coordination/Design Review Meetings x 2/22 x 3/30 x 5/30
Basis of Design
Digester Survey/Measurements (by Hydro) xx
Digester Inspection x Week of 2/6 (date TBD)
Existing Documentation Review x
Digester Structural Inspection x 2/7
Digester Survey (by Hydro) x 2/6
30% Design/Procurement Document Preparation
Prepare 30% Design Documents (includes Digester Lid Procurement Documents) xx xx xx xx
Carollo Internal QA/QC of 30% Design Documents x
30% Design Documents (Draft) to City/Hydro for Review x 3/30
Prepare Digester Lid Procurement Documents (Final) x
Design Development
Prepare 90% Design Documents xx xx xx
Carollo Internal QA/QC of 90% Design Documents x
90% Design Documents (Draft) to City/Hydro for Review x 5/30
Prepare Issued for Construction Documents xx
Issued for Construction Documents to City/Hydro x 6/15
Kickoff Meeting and Site Walkthrough
jan feb march april may
2018
june july
Page 8 of 8