HomeMy WebLinkAboutCHANGE ORDER - RFP - 9177073CHANGE ORDER
NO. 1
PROJECT TITLE: Zone 3 - Old Town Library Water and Wastewater
CONTRACTOR: HDR Engineering, Inc.
WORK ORDER NUMBER: 5026410131
PO NUMBER: 9177073
DESCRIPTION:
1. Reason for Change: Additional scope
2. Description of Change: See the attached supporting documentation
3. Change in Work Order Price: $78,737.00
4. Change in Work Order Time: May 31, 2018
ORIGINAL WORK ORDER PRICE $ 125,962.00
TOTAL APPROVED CHANGE ORDER $ 00.00
TOTAL PENDING CHANGE ORDER $ 00.00
TOTAL THIS CHANGE ORDER $ 78,737.00
TOTAL % OF THIS CHANGE ORDER 62.5%
TOTAL C.O.% OF ORIGINAL WORK ORDER 62.5%
ADJUSTED WORK ORDER COST $ 204,699.00
CONTRACTOR: HDR Engineering, Inc.
By: Date:
Name: Title:
ACCEPTANCE: Date:
Brian Mulligan, Special Project Manager
REVIEWED: Date:
Pat Johnson, Senior Buyer
ACCEPTANCE: Date:
Owen Randal, Water Engineering Division Manager
ACCEPTANCE: Date:
Matt Fater, Water Engineering & Field Services Operations Manager
Page 1 of 7
DocuSign Envelope ID: 2029E8A8-0583-4B96-985C-6CA6675350FC
January 23, 2018
January 24, 2018
January 25, 2018
R. Bradley Martin Senior Vice President
January 30, 2018
January 30, 2018
ACCEPTANCE: Date:
Gerry Paul, Purchasing Director
(if greater than $60,000)
Page 2 of 7
DocuSign Envelope ID: 2029E8A8-0583-4B96-985C-6CA6675350FC
January 30, 2018
Scope of Work
Date: Monday, December 11, 2017
Project: Old Town Library Park Water and Sewer Rehabilitation and Replacement
Project Understanding
The predesign phase for the Zone 3 water and sewer R&R area identified the scope of
improvements that can be accomplished within the current project funding (Figure 1). This limit
of the work defines the first phase of the Old Town Library Park (OTLP) Water and Sewer
Improvements. It is anticipated the OTLP Phase 1 project limits may extend slightly to optimize
connections with existing utilities and/or improve service connections.
Figure 1 – OTLP Phase 1 Project Area
Page 3 of 7
DocuSign Envelope ID: 2029E8A8-0583-4B96-985C-6CA6675350FC
Final Design Phase
Objective: Prepare drawings and technical specifications for the project area using the city’s
APDS process for construction by the city’s APDS Contractor.
Task 5 – Develop Construction Documents
Objective: Refine design developed in the preliminary design phase and develop additional
drawings to form the project construction documents.
TASK 5.1 FINALIZE CONSTRUCTION LIMITS AND METHODS
Refine basemapping to incorporate meter data and sewer services from predesign.
Develop plan view design drawings to identify improvements, construction methods, and
reconnections to existing utilities
Identify approach for water service and meter improvements
Identify temporary water service plan
Identify wastewater flow management plan
TASK 5.2 PREPARE 60% DRAWINGS FOR SUBMITTAL
Develop full drawing set for updating construction cost estimate and city review.
Anticipated sheet list is as follows:
o Cover sheet
o General notes, legend, and abbreviations
o Overall Utility Plan (1-sheets)
o Mathews Street 4” Waterline replacement (2-sheet)
o Oak Street 4” waterline replacement (3-sheets)
o Whedbee Street 4” waterline replacement (3-sheets)
o Olive Street 6” waterline replacement (2-sheet)
o North Alley Sewer 6” Replacement Plan and Profile (1-sheet)
o South Alley Sewer 6” Replacement Plan and Profile (2-sheet)
o Water and sewer standard details (2-sheets)
o Water meter relocation details (2-sheets)
o Civil details (1-sheet)
TASK 5.3 DEVELOP PROJECT SPECIFICATIONS
Select and edit City standard technical specifications for application to OTLP project
scope (Div 02 – Site Work, Div 03 – Concrete, and Div 05 – Metals).
Develop project specific technical specifications to address work elements not covered
within the City’s Master Specifications. Anticipated project specific technical
specifications are summarized below:
o Pipe bursting
o Ground monitoring
o Fuseable PVC pipe (or equal)
o Wastewater Flow Management Plan (Bypass Pumping Plan)
Submit specifications for review between project progress meetings
Page 4 of 7
DocuSign Envelope ID: 2029E8A8-0583-4B96-985C-6CA6675350FC
TASK 5.4 PREPARE 90% CONSTRUCTION DOCUMENTS FOR COST RECONCILIATION
Discuss and address City/Contractor review comments from 60% drawing submittal and
interim review of project specifications
Update 60% drawings and submit 90% for cost reconciliation process
Attend reconciliation meeting
TASK 5.5 PREPARE FINAL CONSTRUCTION DOCUMENTS
Finalize drawings based on City/Contractor comments during reconciliation process.
Submit Issue for Construction (IFC) drawings.
Key Assumptions:
Contractor will prepared dewatering permit as required
Floodplain use permit not required as scope does not alter surface grades and
materials/equipment will be stored outside the floodway.
Deliverables:
PDFs for 60% and 90% submittals
PDFs and 2 full sized drawing sets and hard copy specifications for IFC submittal
Page 5 of 7
DocuSign Envelope ID: 2029E8A8-0583-4B96-985C-6CA6675350FC
1/18/2018
Change Order #1 HDR Engineering
Rich Thornton
Contract and Senior
Project Manager
Technical Advisor /
QC Reviewer
Keith Bushdiecker
Senior Engineer III
Sara Race
Project Engineer I
Mike Austin
CAD Designer
Project Accounting
and Administration
Clerical Assistant
Hours
Labor
Total Expenses
HDR Fee
Total Fee
$ 225 $ 225 $ 185 $ 120 $ 120 $ 77 $ 67
Task 5. Final Design
Task 5.1 Finalize construction limits and methods 8 8 8 4 28 $ 4,549 $ 364 $ 4,913 $ 4,913
Task 5.2 Prepare 60% Drawings for submittal 16 4 16 140 40 2 218 $ 29,194 $ 2,336 $ 31,529 $ 2,000 $ 33,529
Task 5.3 Develop Project Specifications 8 2 8 24 2 44 $ 6,744 $ 540 $ 7,283 $ 7,283
Task 5.4 Prepare 90% Construction Documents for Cost Reconciliation16 4 8 80 32 4 144 $ 19,688 $ 1,575 $ 21,263 $ 21,263
Task 5.5 Prepare Final Construction Documents 12 2 4 40 16 4 78 $ 10,878 $ 870 $ 11,748 $ 11,748
Sub-total 60 12 44 292 88 4 12 512 $ 71,052 $ 5,684 $ 76,737 $ 2,000 $ 78,737
Hours 60 12 44 292 88 4 12 512
Fee $13,500 $2,700 $8,140 $35,040 $10,560 $309 $803 $ 71,052 5,684 $ 76,737 $ 2,000 $ 78,737
City of Fort Collins Utilities
Old Town Library Park Water and Sewer
Rehab & Reconstruction
King Surveyors
c:\pwworking\central01\d0512788\OTLP - W San R&R Fee - Final Design
Page 6 of 7
DocuSign Envelope ID: 2029E8A8-0583-4B96-985C-6CA6675350FC
ID Task
Mode
Task Name Duration Start Finish
1 Final Design Phase Milestones 75 days Fri 12/1/17 Tue 3/27/18
2 60% Design and Submittal 40 days Fri 12/1/17 Tue 2/6/18
3 60% Drawings (Draft) 20 days Fri 12/1/17 Tue 1/9/18
4 City Review of Phased Approach 5 days Wed 1/10/18 Tue 1/16/18
5 Update Construction Cost Estimate
and Assess Construction Methods
5 days Wed 1/17/18 Tue 1/23/18
6 Update 60% Drawings for
Construction Methods
5 days Wed 1/24/18 Tue 1/30/18
7 Outline Specs 3 days Wed 1/24/18 Fri 1/26/18
8 60% Submittal and Review 5 days Wed 1/31/18 Tue 2/6/18
9 90% Design and Submittal 15 days Wed 2/7/18 Tue 2/27/18
10 Project Specifications 10 days Wed 2/7/18 Tue 2/20/18
11 90% Drawings 15 days Wed 2/7/18 Tue 2/27/18
12 Independent Cost Estimate 10 days Wed 2/28/18 Tue 3/13/18
13 Review of 90% Submittal 10 days Wed 2/28/18 Tue 3/13/18
14 IFC and Submittal 10 days Wed 3/14/18 Tue 3/27/18
15 Purchasing/Contract Award 21 days Wed 3/28/18 Wed 4/25/18
16 Contracting 20 days Wed 3/28/18 Tue 4/24/18
17 Notice to Proceed 1 day Wed 4/25/18 Wed 4/25/18 4/25
26 3 10172431 7 142128 4 111825 4 111825 1 8 152229 6
Dec '17 Jan '18 Feb '18 Mar '18 Apr '18 May '18
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 1