HomeMy WebLinkAboutWORK ORDER - PURCHASE ORDER - 9180746Utilities Work Order Form Official Purchasing Form
Last updated 10/2017
WORK ORDER
PURSUANT TO A MASTER AGREEMENT BETWEEN
THE CITY OF FORT COLLINS
AND
CH2M HILL ENGINEERS, INC.
WORK ORDER NUMBER: WTF–Lime-011818
PROJECT TITLE: WTF Post Treatment Lime Solution
Application Point Relocation Assistance
ORIGINAL BID/RFP NUMBER & NAME: 7575, Consulting Engineering Services for
Water Treatment Facility Design &
Construction Services
MASTER AGREEMENT EFFECTIVE DATE: February 24, 2014
ARCHITECT/ENGINEER: CH2M HILL Engineers, Inc.
OWNER’S REPRESENTATIVE: Sue Paquette
WORK ORDER COMMENCEMENT DATE: January 22, 2018
WORK ORDER COMPLETION DATE: June 30, 2018
MAXIMUM FEE: (time and reimbursable direct costs): $24,722.00
PROJECT DESCRIPTION/SCOPE OF SERVICES: Professional engineering services for
process assistance at the Water Treatment Facility (WTF).
Service Provider agrees to perform the services identified above and on the attached forms in
accordance with the terms and conditions contained herein and in the Master Agreement
between the parties. In the event of a conflict between or ambiguity in the terms of the Master
Agreement and this Work Order (including the attached forms) the Master Agreement shall
control.
The attached forms consisting of three (3) pages are hereby accepted and incorporated herein,
by this reference, and Notice to Proceed is hereby given after all parties have signed this
document.
SERVICE PROVIDER: CH2M HILL Engineers, Inc.
By: Date:
Name: Title:
Page 1 of 7
DocuSign Envelope ID: 1CB93061-B189-4B52-81C5-18FC166F47CA
January 19, 2018
Kevin Heffernan Vice President
Utilities Work Order Form Official Purchasing Form
Last updated 10/2017
OWNER’S ACCEPTANCE & EXECUTION:
This Work Order and the attached Contract Documents are hereby accepted and incorporated
herein by this reference.
ACCEPTANCE: Date:
Sue Paquette, Special Project Manager
REVIEWED: Date:
Pat Johnson, Senior Buyer
APPROVED AS TO FORM: Date:
Name,City Attorney's Title
(if greater than $1,000,000)
ACCEPTANCE: Date:
Owen Randall, Water Systems Engineering Division Manager
ACCEPTANCE: Date:
Mark Kempton, Water Production Division Manager
ACCEPTANCE: Date:
Carol Webb, Water Resources & Treatment Operations Manager
ACCEPTANCE: Date:
Kevin Gertig, Utilities Executive Director
(if greater than $1,000,000)
ACCEPTANCE: Date:
Gerry Paul, Purchasing Director
(if greater than $60,000)
ACCEPTANCE: Date:
Darin Atteberry, City Manager
(if greater than $1,000,000)
ATTEST: Date:
City Clerk
(if greater than $1,000,000)
Page 2 of 7
DocuSign Envelope ID: 1CB93061-B189-4B52-81C5-18FC166F47CA
January 19, 2018
January 22, 2018
January 22, 2018
January 22, 2018
January 23, 2018
Utilities Work Order Form Official Purchasing Form
Last updated 10/2017
ATTACHMENT A
WORK ORDER SCOPE OF SERVICES
Page 3 of 7
DocuSign Envelope ID: 1CB93061-B189-4B52-81C5-18FC166F47CA
Exhibit A - Scope of Services
Exhibit A to the AGREEMENT between the City of Fort Collins, Colorado, a Municipal Corporation,
hereinafter referred to as the City, and CH2M HILL Engineers, Inc., hereinafter referred to as the
Professional, for a project generally described as
Professional Services for consulting input on WTF Post Treatment Lime Solution Application
Point Relocation Assistance located at the Fort Collins Water Treatment Facility.
The Professional’s services for the project are detailed hereinafter.
Project Objective: To provide treatment process consultation to the City for Lime Application point
relocation and related assistance.
It is understood the City will designate Ms. Sue Paquette as the City Project Manager (PM) and
primary points of contact with respect to the work performed under this AGREEMENT, with authority to
transmit instructions, receive information, and interpret and define City policies and decisions relative
to elements pertinent to the work covered by this AGREEMENT.
Task 1 – Lime Solution Application Point Relocation Engineering Assistance
Professional will provide engineering and design assistance for lime solution application point
engineering assistance.
• Provide 3rd Party input on the “CFE Turbidity Spike After Action Review” document.
• Provide a brief Technical Memorandum (TM) outlining potential lime relocation points within the
clearwell along with alternative advantages and disadvantages. Review online alkalinity data
provided by the City to determine differences between Combined Filter Effluent (CFE) Sample
Station, Sample Station #1 and Sample Station #2.
• Update flow schematic to include chemical dose locations sample points for regulatory analysis
(normal and clearwell bypass conditions).
• Assist in coordination with the Colorado Department of Health and Environment (CDPHE) for trial
relocation of the lime application point.
• Provide process assistance during the lime application point relocation trial and related work.
Professional’s Project Manager (PM) shall prepare, implement, monitor, and update the project
execution plan throughout the project. Professional’s PM will prepare and submit to the City’s PM, on a
monthly basis, a brief cost and schedule status report. The report will include a narrative description of
progress to-date, actual costs for each item, estimates of percent complete, and potential cost
variances.
Deliverables:
The following deliverables will be prepared for this task:
• Letter with response to City after action review,
• Engineering Technical Memorandum with Exhibits, and
• Monthly project cost and schedule status reports and invoices.
Assumptions Used in Developing this Scope of Services
The Professional’s estimate of engineering costs for the project is based on the elements included in
task descriptions above, and the following assumptions:
1. City will examine information submitted by Professional and render in writing or otherwise provide
Page 4 of 7
DocuSign Envelope ID: 1CB93061-B189-4B52-81C5-18FC166F47CA
decisions within two weeks.
2. City will give prompt notice to Professional whenever City observes or becomes aware of any
development that affects the scope or timing of Professional’s services, or of any defect in the
work of Professional.
3. Professional will provide the City with deliverables as defined respectively in this scope of work.
4. All deliverables will be distributed electronically via email (pdf format).
5. Meetings with the City will be held at the City’s service center office or water treatment facility.
6. APDS Contractor will provide conceptual construction cost estimates to assist with evaluations of
alternatives when applicable. Final pricing construction work will be performed by APDS
contractor.
Page 5 of 7
DocuSign Envelope ID: 1CB93061-B189-4B52-81C5-18FC166F47CA
Utilities Work Order Form Official Purchasing Form
Last updated 10/2017
ATTACHMENT B
WORK ORDER COST DETAIL
Page 6 of 7
DocuSign Envelope ID: 1CB93061-B189-4B52-81C5-18FC166F47CA
Exhibit B – Compensation
Brock McEwen
Senior Technologist
Al Paquet
Principal Project Manager
Brad Schutt
Engineer Specialist
Janelle Prange
Project Engineer
Skylor Flaska
Technician 3
Craig Van Horn
Corrosion Engineer
Gretchen Sage
Contracts
Administration/
Accounting
Labor
Hours Labor Expense Total Cost
Per Diem Code/Classification 02 03 05 8 13 06 04 19
2018 Labor Rates $275 $238 $188 $130 $125 $162 $205 $94
Task 1 Lime Solution Application Point Relocation Engineering Assistan 4 32 48 30 8 2 12 136 $24,092 $630 $24,722
Total 4 32 48 30 8 2 0 12 136 $24,092 $630 $24,722
Page 7 of 7
DocuSign Envelope ID: 1CB93061-B189-4B52-81C5-18FC166F47CA