00950-1
SECTION 00950
CHANGE ORDER NO. 1
PROJECT TITLE: WTF Replacement Project – High Service Pump Station Electrical Procurement
CONTRACTOR: Hydro Construction Company, Inc.
PROJECT NUMBER: Business Unit 5026310066.535010.6, PO 9175340
ORIGINAL BID/RFP NUMBER & NAME: 8286, Construction Contractor for Projects at Water and
Wastewater Treatment Facilities
DESCRIPTION:
1. Reason for change: Additional time needed for procurement of items; submittal approval
process required additional time and delayed the ordering of materials.
2. Description of Change: Extension of contract time.
3. Change in Contract Cost: $0.00
4. Change in Contract Time: Substantial completion date is revised from February 1, 2018 to April
30, 2018. Final Acceptance date is revised from April 1, 2018 to May 31, 2018.
ORIGINAL CONTRACT COST $ 268,845.00
TOTAL APPROVED CHANGE ORDERS $0.00
TOTAL PENDING CHANGE ORDERS $0.00
TOTAL THIS CHANGE ORDER $0.00
TOTAL % OF THIS CHANGE ORDER 0.0.%
TOTAL C.O.% OF ORIGINAL CONTRACT 0.0%
ADJUSTED CONTRACT COST $ 268,845.00
(Assuming all change orders approved)
ACCEPTED BY: DATE:
Contractor's Representative
ACCEPTED BY: DATE:
Special Projects Manager
REVIEWED BY: DATE:
Chief Engineer & Project Manager
APPROVED BY: DATE:
Water Production Division Manager
APPROVED BY: DATE:
Water Resources/Treatment Ops Manager
APPROVED BY: DATE:
Purchasing Agent over $60,000
DocuSign Envelope ID: E68B31C3-062B-48EC-BC5B-67833CFE916E
1/4/2018
1/4/2018
1/4/2018
1/4/2018
1/4/2018