HomeMy WebLinkAboutCHANGE ORDER - RFP - 8127 ENGINEERING SERVICES FOR ELECTRIC FACILITIES CAPITAL IMPROVEMENTS (3)SECTION 00950 CHANGE ORDER NO. 01 PROJECT TITLE: Linden St. Duct Bank PO NUMBER: TBD CONTRACTOR: Exponential Engineering Company PROJECT NUMBER: 5010082692 DESCRIPTION: 1. Reason for change: Proposed new location for 10x10 concrete vault 2. Description of Change: Additional design services and construction staking 3. Change in Contract Cost: $6,010.00 4. Change in Contract Time: 1 Month ORIGINAL CONTRACT COST $ 31,950.00 TOTAL APPROVED CHANGE ORDER 0.00 TOTAL PENDING CHANGE ORDER 0.00 TOTAL THIS CHANGE ORDER 6,010.00 TOTAL % OF THIS CHANGE ORDER % TOTAL C.O.% OF ORIGINAL CONTRACT % ADJUSTED CONTRACT COST $ 37,960.00 (Assuming all change orders approved) REVIEWED BY: __________________________________ DATE: _________________ Pat Johnson, Senior Buyer ACCEPTED BY: DATE: Contractor's Representative SUBMITTED BY: _________________________________ DATE: _________________ Robert Irish, Project Manager APPROVED BY: _________________________________ DATE: _________________ Tim McCullough, L&P Operations Manger APPROVED BY: _________________________________ DATE: _________________ Gerry Paul, Purchasing Director (over $60,000) 8/11/2017 8/16/2017 8/16/2017 8/16/2017 Page 1 of 2 August 11, 2017 Mr. Robert Irish Electrical Project Manager City of Fort Collins 700 Wood Street Fort Collins, CO 80522 Re: Linden Duct Bank – Change Order 1 Dear Mr. Irish: Exponential Engineering Company (EEC) is requesting a change order to provide the City of Fort Collins with additional professional engineering services for the Linden Duct Bank project. EEC proposes the following not to exceed price agreement for the scope listed herein as follows: Not-to-Exceed Linden Duct Bank: Change Order 1 $6,010 The price provided is for the work scope outlined in this letter only. Any work outside of this scope will be considered extra and negotiated with the City of Fort Collins. Scope of Work: 1. Base Map Survey: Lat40 will survey utility locates, pothole locations, and elevation information necessary for the modified vault location and duct bank routing. EEC will coordinate potholing and pothole survey. 2. Base Map Profile Drawings: Lat40 will extend the profile drawings approximately 70 feet north of the vault location within Vine Drive to the modified vault location north of the intersection at Linden Street and Vine Drive. EEC will update the profile drawings for vault relocation and associated duct bank. 3. Construction Staking: EEC will perform construction staking consisting of one site trip to stake the centerline and offsets for for one vault and 70 linear feet of duct bank. Page 2 of 2 LINDEN DUCT BANK: CHANGE ORDER 1 Linden Duct Bank Items Not Included in Scope of Work: 1. Utility locates for potholing and construction will be ordered by Colorado Boring Company. 2. Colorado Boring Company will provide potholing services. Please call me at (970) 207-9648 x180 if you have any questions or need additional information. EEC looks forward to working with you on this project. Sincerely, Tyler Swaney, P.E. EXPONENTIAL ENGINEERING COMPANY Electrical Engineer ESTIMATE OF ENGINEERING SERVICES COSTS PROJECT: FTCL-1603 PROJECT TITLE: Linden Duct Bank - Change Order 1 DATE: 8/1/2017 PROJECT MANAGER: T. Swaney PROJECT ENGINEER: T. Swaney BILLING GROUP: TASK DESCRIPTION # OF DWGS Engineer I-2 Engineer II-2 Senior Designer Project Controls Manager (Select One) (Select One) (Select One) Engineer II-2 Engineer II-2 TOTAL HOURS TOTAL LABOR COSTS $132.00 $155.00 $100.00 $125.00 $0.00 $0.00 $0.00 $155.00 $155.00 HOURS HOURS HOURS HOURS HOURS HOURS HOURS HOURS HOURS Coordinate Potholing & Survey 31 116.0 $900.00 Base Map Profile Drawings 6121 1121.0 $2,565.00 Construction Staking 41 005.0 $745.00 000.0 $0.00 000.0 $0.00 000.0 $0.00 000.0 $0.00 000.0 $0.00 000.0 $0.00 000.0 $0.00 000.0 $0.00 000.0 $0.00 000.0 $0.00 000.0 $0.00 000.0 $0.00 TOTAL HOURS 0 13 12 3 0 0 0 2 2 TOTAL LABOR COSTS $0.00 $2,015.00 $1,200.00 $375.00 $0.00 $0.00 $0.00 $310.00 $310.00 TOTAL HOURS AND LABOR COSTS: 32 $4,210.00 TOTAL HOURS AND ROUNDED LABOR COSTS (TO BE USED IN PROPOSAL): 32 $4,210.00 AVERAGE BILLING GROUP RATE: $0.00 REIMBURSABLE EXPENSES RATE QTY COST REIMBURSABLE TRIP EXPENSES - TRIP 1 Prints and Plots (22" X 34") BW $1.20 $0.00 Trip 1 Name: Prints (22" x 34") COLOR $10.00 $0.00 EXPENSE RATE QTY # PEOPLE # OF TRIPS COST Labor Costs $4,210.00 Copies (11" x 17") $0.20 $0.00 Mileage $0.775 $0.00 Reimbursable Expenses $0.00 Copies (11" x 17") COLOR $0.50 $0.00 Airfare $750.00 $0.00 Outside Services $1,800.00 Copies (8.5" x 11") $0.10 $0.00 Per Diem (per day) $46.00 $0.00 Trip 1 $0.00 Copies (8.5" x 11") COLOR $0.25 $0.00 Lodging (per night) $125.00 $0.00 Trip 2 $0.00 High Level Design and Analysis Software $12.50 $0.00 Car Rental (per day) $50.00 $0.00 Billing Group Total $6,010.00 PSS/E Power Systems Analysis Software $100.00 $0.00 Parking and Tolls (total) $15.00 $0.00 GPS Survey Grade Equipment (per week) $1,500.00 $0.00 (Other) $0.00 GPS Survey Grade Equipment (per day) $500.00 $0.00 (Other) $0.00 Arc Flash Labels (each) $1.50 $0.00 (Other) $0.00 (Other) $0.00 TOTAL "TRIP 1" REIMBURSABLE EXPENSES: $0.00 (Other) $0.00 TOTAL ROUNDED "TRIP 1" REIMBURSABLE EXPENSES $0.00 (Other) $0.00 (Other) $0.00 REIMBURSABLE TRIP EXPENSES - TRIP 2 TOTAL REIMBURSABLE EXPENSES: $0.00 Trip 2 Name: TOTAL ROUNDED REIMBURSABLE EXPENSES $0.00 EXPENSE RATE QTY # PEOPLE # OF TRIPS COST Mileage (per mile) $0.775 $0.00 OUTSIDE SERVICES (SUB'S, ETC.) RATE QTY COST Airfare $750.00 $0.00 Lat40 Pothole Survey $1,800.00 1 $1,800.00 Per Diem (per day) $46.00 $0.00 $0.00 Lodging (per night) $125.00 $0.00 $0.00 Car Rental (per day) $50.00 $0.00 $0.00 Parking and Tolls (total) $15.00 $0.00 $0.00 (Other) $0.00 TOTAL OUTSIDE SERVICES: $1,800.00 (Other) $0.00 0% Markup $0.00 (Other) $0.00 TOTAL OUTSIDE SERVICES WITH MARKUP: $1,800.00 TOTAL "TRIP 2" REIMBURSABLE EXPENSES: $0.00 TOTAL ROUNDED OUTSIDE SERVICES $1,800.00 TOTAL ROUNDED "TRIP 2" REIMBURSABLE EXPENSES $0.00 COST SUMMARY 002 - DESIGN SERVICES