HomeMy WebLinkAboutBID - 8396 MAX BRT DIRECTIONAL BORING FOR NEW TRAFFIC SIGNALSADDENDUM NO. 1
SPECIFICATIONS AND CONTRACT DOCUMENTS
Description of BID 8396: MAX BRT Directional Boring for New Traffic Signals
OPENING DATE: 3:00 PM (Our Clock) October 24, 2016
To all prospective bidders under the specifications and contract documents described above,
the following changes/additions are hereby made and detailed in the following sections of this
addendum:
1. Questions & Answer
Question: Does the conduit need to be encased in metal under the railroad tracks?
Answer: Per the attached Utility Accommodation Policy, the installation is considered
a wireline (as opposed to pipeline). Electric power lines must be encased completely
across the Railroad right-of-way with a rigid conduit. The conduit can be metal or
high-density pol-ethylene (HDPE). All underground utility crossings must be
designed to carry Cooper’s E-80 Railroad live loading. Historically, schedule 80
HDPE has been used.
2. Additional Information
BNSF Utility Accommodation Policy (attached)
Please contact Elliot Dale, Buyer at (970) 221-6777 with any questions regarding this
addendum.
RECEIPT OF THIS ADDENDUM MUST BE ACKNOWLEDGED BY A WRITTEN STATEMENT
ENCLOSED WITH THE BID/QUOTE STATING THAT THIS ADDENDUM HAS BEEN
RECEIVED.
Financial Services
Purchasing Division
215 N. Mason St. 2nd Floor
PO Box 580
Fort Collins, CO 80522
970.221.6775
970.221.6707
fcgov.com/purchasing
Burlington Northern Santa Fe
UTILITY ACCOMMODATION
POLICY
Engineering Services
4515 Kansas Avenue
Kansas City, KS 66106
May 18, 2011
TABLE OF CONTENTS
PART 1 - GENERAL POLICY
A. Policy Application 1-1
B. Utility License Agreement Requirements 1-3
C. Safety 1-5
D. Maintenance and Servicing Utilities 1-6
E. Preservation, Restoration and Cleanup 1-7
F. Protection of Vegetation 1-7
PART 2 - UTILITIES PARALLELING RAILROAD PROPERTY
A. General Provisions 2-1
B. Overhead Installations 2-1
C. Underground Installations 2-2
D. Attachment to Bridges and Other Structures 2-3
E. Drains for Steep Slopes (Tight Lines) 2-3
PART 3 - UTILITIES CROSSING RAILROAD PROPERTY
A. General Provisions 3-1
B. Overhead Installations 3-1
C. Underground Installations 3-2
PART 4 - PLANS, APPROVALS AND PROCEDURES
A. Plans and Approvals 4-1
B. License Procedures 4-2
C. Construction 4-2
PART 5 - APPENDIX
Application for Pipelines A-1
Application for Wirelines A-2
Application for Environmental Access A-4
Application to Conduct Seismic Survey A-5
Applicant’s Pipeline Crossing Checklist A-6
Underground Cable Locate Form A-7
Horizontal Directional Drilling Standard A-8
Retirement of Pipeline A-9
Drains for Steep Slopes (Tight Lines) A-10
Definition of Terms A-11
References A-14
************************************
PART 1
GENERAL POLICY
************************************
May 18, 2011
Page 1-1
PART 1 - GENERAL POLICY
A. Policy Application
1. Purpose
This policy is to prescribe the accommodation, location and method of installation,
adjustments, removal, relocation and maintenance of utility facilities within the property of
Burlington Northern & Santa Fe Railway Company, referred to hereafter as BNSF. The
policy was developed in the interest of safety, protection, utilization, and future development
of BNSF with due consideration given to public and private service afforded by adequate and
economical utility installations.
2. Application
The policy concerning utility accommodations shall apply to all:
a. New utility installations.
b. Additions to existing utility installations.
c. Adjustment and relocation of utilities.
d. Existing or planned utility installations for which agreements with BNSF were entered
prior to the date of the adoption of this policy.
e. Existing utility installations that do not meet the license requirements may remain at the
discretion of BNSF.
Various types of utility lines not specifically discussed herein shall be considered within the
provisions of this policy. It shall be the general practice to consider all lines carrying caustic,
flammable or explosive materials under the provisions for high-pressure gas and liquid fuel
lines.
3. Scope
Utilities include lines, facilities and systems for producing, transmitting or distributing
communications, power, electricity, light, heat, gas, oil, crude products, water, steam, waste,
storm water and other similar commodities which are privately, publicly or cooperatively
owned and which serve directly or indirectly the public or any part thereof.
A Utility Agreement License allowing a Utility Owner the privilege of placing its facilities in
or on railroad property does not constitute permanent right for such usage. Any removal,
remodeling, maintenance or relocation of the facilities, whether or not required by BNSF,
will be accomplished promptly by the Utility Owner at no cost to BNSF.
May 18, 2011
Page 1-2
4. Exceptions
Exceptions to any design, location or methods of installation provisions contained in this
policy must be authorized by BNSF. Requests for exceptions will be considered only where
it is shown that extreme hardship and/or unusual conditions provide justification and where
alternate measures can be prescribed in keeping with the intent of this policy. All requests
for exceptions shall be fully documented including design data, cost comparisons and other
pertinent information.
5. Liability
The Utility Owner, it successor, or assigns shall assume all risk and liability for accidents
and damages that may occur to persons or property on account of this work, and shall
indemnify and hold BNSF harmless from any and all costs, liabilities, expenses, suits,
judgments or damages to persons or property or claims of any nature whatsoever arising out
of or in connection with the permit, or the operation and performance thereunder by the
utility, its agents, employees or subcontractors. In this regard, it is further understood and
agreed that the utility may be required to obtain insurance coverage as determined by BNSF.
The Utility Owner agrees that if liability insurance is required, it will file with the designated
office, prior to granting of the license, “Certificates of Insurance” or other evidence to show
that the appropriate insurance is carried.
Insurance as may be required shall be maintained in force until the final release of the Utility
Owner by BNSF from all obligations under the terms of the license. The insurance contract
shall cover claims for such length of time as law permits said claims. The insurance
document shall include a clause requiring the insurer to notify BNSF ten (10) days in
advance of any cancellation or change in insurance contacts.
The Utility Owner is responsible for any subcontractor to be knowledgeable of the policy and
to require all work to be in compliance with this policy. Subcontractors must carry a liability
insurance policy unless the subcontractor is covered by the Utility Owner’s insurance.
6. Replacement of Facility
Replacement of existing facility with the same facilities or facilities of a different type, or
design, is to be considered as a new utility installation and all work shall adhere to this
policy.
May 18, 2011
Page 1-3
7. Change in Ownership
It is the Utility Owner’s responsibility to inform BNSF, in writing, of any name, ownership
or address changes.
8. Noncompliance
Noncompliance with any terms of this Utility Accommodation Policy or Utility License
Agreements may be considered as cause for discontinuance of construction or operations
until compliance is assured. Continued noncompliance will result in the revocation of the
license. The cost of any work required by BNSF in the removal of non-complying
construction will be assessed against the Utility Owner.
9. Discharge of Waste Material
Applications for a Utility License Agreement for the installation of utility facilities which
will discharge materials into the nation’s waters, must comply with all applicable
requirements of Corps of Engineers, and other federal, state or local environmental
protection agencies. Identification of applicable requirements and administration of
compliance procedures are the responsibility of the Utility Owner.
B. Utility License Agreement Requirements
1. General
Utility License Agreements are required when utility facilities are installed, relocated,
removed or maintained along or across all BNSF property.
If liability insurance is required, then evidence of adequate liability insurance is to be on file
with BNSF for each agreement.
2. Applications
Approved requests to install, maintain, relocate or remove a utility within the property of
BNSF shall be authorized by a Utility License Agreement. The applications for utility
license agreements along with plans for the proposed installation shall be submitted to BNSF
and approved before construction has commenced (see blank forms in appendix).
3. Location
a. Utility lines shall be located to avoid or minimize the need for adjustments for future
railroad improvements and to permit access to the utility lines for their maintenance with
minimum interference to railroad traffic.
May 18, 2011
Page 1-4
b. Pipelines shall be installed under tracks by boring, jacking, or in some cases, open-
trenching. WATER JETTING IS NOT PERMITTED.
c. Where practical, pipelines carrying liquefied petroleum gas shall cross the railway where
the tracks are carried on an embankment.
d. All high-pressure pipelines (greater than 60-psi internal pressure), except those in public
roads, shall be prominently marked at the property line (on both sides of the track for
under crossings) by signs which state the size of the line and its depth.
Example:
CAUTION: 30-inch diameter high-pressure Gas main 7 feet deep.
4. Design Considerations
a. The design of any utility installation will be the responsibility of the Utility Owner. An
installation within the railroad property must be reviewed and approved by the railroad
with regard to location and the manner of adjustment. This includes the measures to be
taken to preserve the safety and flow of rail traffic, structural integrity of the roadway or
structure, ease of maintenance and the integrity of the utility facility. Utility installations,
on, over or under BNSF property shall conform with requirements contained herein
and/or as a minimum, the appropriate requirements outlined in the following:
1) Safety Rules for the Installation and Maintenance of Electric Supply and
Communication Lines-National Electric Safety Code.
2) Title 49 C.F.R. Part 192, Transportation of Natural and Other Gas by Pipeline:
Minimum Federal Safety Standards and Amendments.
3) Title 49 C.F.R. Part 195, Transportation of Liquids by Pipelines and Amendments.
4) American Society for Testing and Materials (ASTM) Specifications - latest edition.
5) Manual on Uniform Traffic Control Devices - with revisions.
6) Rules and Regulations for Public Water Systems - latest edition, published by the
appropriate State Health Department.
b. All utility installations on, over or under BNSF property shall be of durable materials
designed for long service life and relatively free from routine servicing and maintenance.
Conformance with current applicable material specifications and codes is mandatory.
c. References given to any manual, publication or specification are intended to be the most
current edition. If a conflict occurs between any publication and this manual, the most
restrictive specification will be used.
May 18, 2011
Page 1-5
d. For all boring and jacking installations under main and passing tracks, greater than 26
inches in diameter, and at a depth of between 5.5 and 10.0 feet below top of tie, a
geotechnical study will need to be performed to determine the presence of granular
material and/or high water table elevation, at the sole expense of the Permittee. The study
will include recommendations and a plan for a procedure to prevent failure and a collapse
of the bore. Generally, core samples are to be taken near the ends of tie at the proposed
location, at least as deep as the bottom of the proposed horizontal bore. Test results must
be reviewed and approved by BNSF, or its agent, prior to boring activities commencing.
BNSF reserves the rights, based on test results, to require the Permittee to select an
alternate location, or to require additional engineering specifications be implemented, at
the sole expense of the Permittee, in order to utilize existing location.
C. Safety
1. A safety orientation course will be completed by all workers prior to entering BNSF
property. It is the contractor’s responsibility to conduct the safety training and
implementation of a safety program for its employees. Training materials are available on
the web site: www.contractororientation.com. The contractor must comply with all federal,
state and local safety regulations.
2. Flagging
When work is performed within twenty-five (25) feet of the centerline of the track, railroad
flagging will be required.
a. Railroad flagging will be required:
1) During the period of construction when it is necessary for the Contractor to operate
equipment in the vicinity of, or over, BNSF property which may endanger railroad
operations, or
2) Two or more railroad flagmen may be required at other times that the Railway
Company Roadmaster’s sole discretion shall deem necessary.
b. Flagging services shall be performed by BNSF employees and the total cost borne by the
Utility Owner.
c. The Utility Owner will be billed monthly at a rate to be determined by BNSF to include
labor and payroll associated costs plus any expenses incurred by BNSF for flagging
services.
d. A written request for flagging services will be required at least 72 hours prior to the time
when such services are needed. This request is made to the BNSF Roadmaster, as noted
in agreement.
May 18, 2011
Page 1-6
3. Material Storage
Storage of materials, parking of equipment and vehicles when not used in actual utility work
will not be permitted on railroad property.
4. Call Before You Dig! Call 1-800-533-2891 to arrange for a BNSF underground cable
locate. BNSF form “Underground Cable Location & Acknowledge” will be completed by a
BNSF representative and copy provided to the contractor. The contractor must have this
completed form in possession at the job site at all times.
D. Maintenance and Servicing Utilities
1. Utility Owner’s Responsibility
a. Maintenance of the utility is the responsibility of the Utility Owner.
b. Maintenance must be performed to keep the facility in an as-constructed condition, and in
a good state of repair in accordance with the requirements of Federal, State and Local
laws, regulatory standards and utility codes.
c. It is the Utility Owner’s responsibility to replace and stabilize all earth cover and
vegetation when it has eroded over an underground utility facility where such erosion is
due to, or caused by, the placement or existence of the underground utility facility.
d. The Utility Owner shall be responsible for any settlement of backfill, fills, and
embankments that may occur.
2. Emergency Maintenance
a. Emergency maintenance of utilities located on railroad property is permissible without
obtaining a Utility License Agreement if an emergency exists that is dangerous to the
life, safety or welfare of the public and which requires immediate repair. The Utility
Owner shall take all necessary and reasonable safety measures to protect the public and
the railroad.
b. The Utility Owner, in such an event, will advise the Railway Company’s Roadmaster as
soon as possible. Damage to the right-of-way and facilities will be restored to its original
condition. A Utility License Agreement should be requested by the Utility Owner within
the second working day provided the work is not covered under any previously granted
license. Flagging requirements described earlier apply in all situations.
May 18, 2011
Page 1-7
E. Preservation, Restoration and Cleanup
1. Disturbed Areas
a. Areas of railroad property, disturbed by the installation, maintenance, removal and
relocation of utilities shall be kept to a minimum.
b. Disturbed areas shall be returned to normal grade and elevation, with compaction of
backfill material, and all excess or undesirable material removed by the Utility Owner.
The Utility Owner shall replace destroyed vegetation by sodding, or seeding, fertilizing
and mulching, or a combination thereof.
c. The Utility Owner shall provide protection against erosion in disturbed areas that are
subject to erosion. Such protection may be in the form of rock riprap, wash checks, hay
or straw cover, or other material that is approved and does not interfere with railroad
maintenance.
2. Drainage Facilities
Care shall be taken to avoid disturbing existing drainage facilities. Underground utility
facilities shall be bedded with pervious material and outlets provided for entrapped water.
Underdrains should be provided where necessary.
3. Cleanup
Unused material or debris shall be removed from the work site area. At the end of every
construction day, construction equipment and materials shall be removed as far from the
operating railroad tracks as possible (minimum 25 feet from centerline). All machines will
be disabled when not in use to prevent unauthorized operation.
F. Protection of Vegetation
1. Trimming, Clearing or Removal of Vegetation
a. Consistent with the preservation of planted vegetation, consideration will be given to
Utility Owners for the necessary trimming, clearing or removal of vegetation to provide
adequate clearance of overhead wires. Such work will be done in accordance with
established practices and standards; however, approval will not be granted for wasteful or
wanton trimming, or removal in order to provide easy solutions to a difficult situation.
b. No trees, shrubs, bushes, vines or ground cover on railroad property shall be sprayed,
trimmed, cut down, rooted up, removed or mutilated in any manner unless a permit is
granted by BNSF to do such work.
May 18, 2011
Page 1-8
2. Chemical Brush Control
a. Spraying brush and seedling tree growth to prevent re-sprouting may be permitted, and
when permitted, shall be carried out with extreme caution and careful performance. The
Utility Owner shall be responsible for the performance of their employees or contractors
in the application of brush control and approved by BNSF Environmental Department.
b. All spraying shall be done by a herbicide applicator that is licensed in the state where the
work is to be performed.
c. Permit applications for spraying shall list the kinds of chemical weed and brush killers
that will be used. When liability insurance is required, it shall be provided by the
herbicide applicator, or be insured under the liability insurance of the Utility Owner.
d. Plants over five (5) feet in height should not be sprayed for control. Brush over five (5)
feet in height, which is to be removed, should be cut and the stumps treated to prevent
growth. Shrubbery type growth such as dogwood, sumac, redbud, plum, etc., should not
be sprayed as a general rule. Steep slopes, where brushy growth is a major factor in
preventing erosion, should not be sprayed.
3. Tree Pruning
a. Tree pruning on railroad property for utility lines will utilize the best horticultural
practices. All cut branches, dead limbs, etc., shall be removed. Such materials shall not
be burned or disposed of on railroad property unless permission is granted by Utility
License Agreement.
b. Should burning be permitted, the Utility Owner will be held liable for any damage to
grass, crops, native shrubs and trees arising from careless burning of such brush.
c. Any and all limbs trimmed shall be removed with a clean cut and all limb scars over one
(1) inch in diameter shall be treated with appropriate tree paint.
************************************
PART 2
UTILITIES PARALLELING
RAILROAD PROPERTY
************************************
May 18, 2011
Page 2-1
PART 2 - UTILITIES PARALLELING RAILROAD PROPERTY
A. General Provisions
This section of the policy applies to all public and private utilities, including electric power,
telephone (including fiber optics), telegraph, cable television, water, gas, oil, petroleum
products, steam, chemicals, sewage, drainage, irrigation and similar lines that are located,
adjusted or relocated within the property under the jurisdiction of BNSF. Such utilities may
involve underground, surface or overhead facilities.
Any utility line greater than five hundred (500) feet in length will be considered a parallel line
and is to be located on uniform alignment, within ten (10) feet or less of the property line so as to
provide a safe environment and to preserve space for future railroad improvements or other
utility installations. BNSF Engineering must approve any installation over one mile.
Utilities will be located so as to provide a safe environment and shall conform to the current
“National Electrical Safety Code,” “American Waterworks Association Specifications,” Federal
Pipeline Safety Regulations,” and “The American Railway Engineering and Maintenance
Association Specifications.” Where laws or orders of public authority prescribe a higher degree
of protection, then the higher degree of protection prescribed shall supersede the provisions of
this manual.
B. Overhead Installations
1. Minimum four feet clearance required above signal and communication lines.
2. Poles must be located 50 feet out from the centerline of railroad main, branch and running
tracks, CTC sidings, and heavy tonnage spurs. Pole location adjacent to industry tracks; must
provide at least a 10-foot clearance from the centerline of track, when measured at right
angles. If located adjacent to curved track, then said clearance must be increased at a rate of
1-½ inches per degree of curved track.
3. Regardless of the voltage, unguyed poles shall be located a minimum distance from the
centerline of any track, equal to the height of the pole above the ground-line plus 10 feet. If
guying is required, the guys shall be placed in such a manner as to keep the pole from
leaning/falling in the direction of the tracks.
4. Poles (including steel poles) must be located a minimum distance from the railroad signal
and communication line equal to the height of the pole above the ground-line or else be
guyed at right angles to the lines. High voltage towers (34.5 kV and higher) must be located
off railroad right of way.
May 18, 2011
Page 2-2
5. For proposed electrical lines paralleling tracks, BNSF may request that an inductive
coordination study be performed at the expense of the utility owner. Inductive interference
from certain lines has the potential to disrupt the signal system in the track causing failures in
the track signals and highway grade crossing warning devices. Generally, if the proposed
electrical line exceeds 12.5 kV and runs parallel to the track for at least 1,000 feet, a study
will be required. A study will be required if a new sub-station is to be located within 1,000
feet of the track. The General Director of Signals will determine the need for a study on a
case-by-case basis.
C. Underground Installations
1. Underground utility installations should be located on top of the back slope at the outer limits
of the railroad property.
2. If the pipeline is located forty (40) feet or less from centerline of track, the pipeline shall be
encased in a steel pipe subject to approval from BNSF. No pipe may be placed closer than
twenty-five (25) feet from centerline of track. Pipe must be buried with a minimum cover of
three (3) feet.
a. If less than minimum depth is necessary because of existing utilities, water table,
ordinance or similar reasons, the line shall be rerouted.
b. Locations where it will be difficult to attain minimum depth due to wet or rocky terrain
shall be avoided. Any location change from plan must be approved by BNSF.
3. The use of plastic carrier pipe for sewer, water, natural gas and other liquids is acceptable
under specific circumstances. The use of plastic pipe is satisfactory if the pipe is designed to
meet AREMA and all applicable federal and state codes, and if the carrier pipe is properly
encased with a steel casing pipe for the entire length on BNSF right of way.
4. Manholes shall be limited to those necessary for installation and maintenance of underground
lines. Manholes vary as to size and shape depending on the type of utility they serve. To
conserve space, their dimensions should be minimally acceptable by good engineering and
safety standards. In general, the only equipment to be installed in manholes located on
railroad property is that which is essential to the normal flow of the utility, such as circuit
reclosers, cable splices, relays, valves and regulators. Other equipment should be located
outside the limits of the railroad property. Manholes shall not protrude above the
surrounding ground nor be located in the shoulder, shoulder slope, ditch, backslope, or
within twenty-five (25) feet of the centerline of track without approval of BNSF.
5. Electric Power Lines
a. A minimum depth of 3.0 feet below natural grade (BNG) will be maintained for 750 volts
and less, and 4.0 feet BNG for greater than 750 volts.
May 18, 2011
Page 2-3
b. A 6-inch wide warning tape will be installed, 1.0 foot BNG directly over the underground
power line where located on Railroad right-of-way outside the track ballast sections.
6. Fiber Optic Lines
a. A minimum depth of 4.0 feet BNG for fiber optic cable wirelines.
b. Whenever feasible, all cable should be laid within 5 feet from property lines.
c. A 6-inch wide warning tape will be installed, 1.0 foot BNG directly over the underground
fiber optic line where located on Railroad right-of-way outside the track ballast sections.
7. Abandonment/Removal of Facilities
a. Upon termination of license the pipeline needs to be removed from BNSF property
except for the portion under the track embankment.
D. Attachment to Bridges and Other Structures
The Utility Owner will not be permitted to attach to BNSF bridges or route facilities through
drainage structures or cattle passes. Utilities are not to be attached to other railroad
structures without the written approval of BNSF Engineering. As a general rule, overhead
power, communication and cable television line crossings at bridges must be avoided.
Pipelines laid longitudinally on railroad property shall be located as far as practical from any
tracks or other important structures. If located within forty (40) feet of the centerline of any
track, the carrier pipe shall be encased or be of special design as approved by BNSF
Engineering.
E. Drains for Steep Slopes (Tight Lines)
Drainage onto BNSF property from adjacent land that is significantly higher than the track
elevation should be directed through a pipe anchored into the steep slope. The pipe needs to
be designed to withstand the weight of the water in the pipe. The drainage system will
include a diffuser at the bottom to prevent erosion on BNSF property (see appendix page A-
10 for an example).
In some instances a concrete vault with a strike plate and bolted manhole cover may be
required. The volume and velocity of discharge will determine the type of pipe or structure
to convey the water across BNSF property. BNSF Engineering will review and approve the
plan prior to execution of the license agreement.
************************************
PART 3
UTILITIES CROSSING
RAILROAD PROPERTY
************************************
May 18, 2011
Page 3-1
PART 3 - UTILITIES CROSSING RAILROAD PROPERTY
A. General Provisions
This section of the policy applies to all public and private utilities, including electric power,
telephone (including fiber optics), telegraph, cable television, water, gas, oil, petroleum
products, steam, chemicals, sewage, drainage, irrigation and similar lines that are located,
adjusted or relocated within the property under the jurisdiction of BNSF. Such utilities may
involve underground, surface or overhead facilities.
Installations crossing the property of the railroad, to the extent feasible and practical, are to be
perpendicular to the railroad alignment and preferably at not less than forty-five (45) degrees to
the centerline of the track. Utilities shall not be placed within culverts or under railroad bridges,
buildings or other important structures.
Utilities will be located so as to provide a safe environment and shall conform to the current
“National Electrical Safety Code,” “American Waterworks Association Specifications,” Federal
Pipeline Safety Regulations,” and “The American Railway Engineering and Maintenance
Association Specifications.” Where laws or orders of public authority prescribe a higher degree
of protection, then the higher degree of protection prescribed shall supersede the provisions of
this manual.
B. Overhead Installations
1. Minimum four feet clearance required above signal and communication lines.
2. Poles must be located 50 feet out from the centerline of railroad main, branch and running
tracks, CTC sidings, and heavy tonnage spurs. Pole location adjacent to industry tracks; must
provide at least a 10-foot clearance from the centerline of track, when measured at right
angles. If located adjacent to curved track, then said clearance must be increased at a rate of
1-½ inches per degree of curved track.
3. Regardless of the voltage, unguyed poles shall be located a minimum distance from the
centerline of any track, equal to the height of the pole above the ground-line plus 10 feet. If
guying is required, the guys shall be placed in such a manner as to keep the pole from
leaning/falling in the direction of the tracks.
4. Poles (including steel poles) must be located a minimum distance from the railroad signal
and communication line equal to the height of the pole above the ground-line or else be
guyed at right angles to the lines. High voltage towers (34.5 kV and higher) must be located
off railroad right of way.
5. Crossings must not be installed under or within 500 feet of the end of any railroad bridge, or
300 feet from the centerline of any culvert or switch area.
May 18, 2011
Page 3-2
6. Complete spanning of the property is encouraged with supportive structures and
appurtenances located outside railroad property. For electric supply lines, normally the
crossing span shall not exceed 150 feet with adjacent span not exceeding 1-1/2 times the
crossing span length. For communication lines, the crossing span shall not exceed 100 feet
in heavy loading districts, 125 feet in medium loading districts, and 150 feet in light loading
districts; and the adjacent span shall not exceed 1-1/2 times the crossing span length. For
heavier type construction, longer spans will be considered.
7. Joint-use construction is encouraged at locations where more than one utility or type of
facility is involved. However, electricity and petroleum, natural gas or flammable materials
shall not be combined. Pipe truss design and layout will need to be reviewed and approved
by BNSF Engineering.
8. To ensure that overhead wire crossings are clear from contact with any equipment passing
under such wires, communication lines shall be constructed with a minimum clearance above
top of rail of twenty-four (24) feet, and electric lines with a minimum clearance of twenty-six
and one-half (26 1/2) feet or greater above top of rail when required by the “National Electric
Safety Code” or state and local regulations. Electric lines must have a florescent ball marker
on low wire over centerline of track.
9. The utility owner will label the posts closest to the crossing with the owner’s name and
telephone number for emergency contact.
10. All overhead flammable and hazardous material lines will need BNSF Engineering approval,
but should be avoided if possible.
11. For proposed electrical lines crossing tracks, BNSF may request that an inductive
coordination study be performed at the expense of the utility owner. Inductive interference
from certain lines have the potential to disrupt the signal system in the track causing failures
in the track signals and highway grade crossing warning devices. The General Director of
Signals will determine the need for a study on a case-by-case basis.
C. Underground Installations
1. General
a. All underground utility crossings of railroad trackage shall be designed to carry Cooper’s
E-80 Railroad live loading with diesel impact (AREMA Cooper’s loading Section 8-2-8).
This 80,000-lb. axle load may be distributed laterally a distance of three (3) feet, plus a
distance equal to the depth from structure grade line to base of rail, on each side of
centerline of single tracks, or centerline of outer track where multiple tracks are to be
crossed. In no case shall railroad loading design extend less than ten (10) feet laterally
from centerline of track. Longitudinally, the load may be distributed between the five-
foot axle spacing of the Cooper configuration. Railroad loading criteria will also apply
May 18, 2011
Page 3-3
where future tracks on BNSF are contemplated, to the extent this information is
available.
b. All utility crossings under ditches and railroad trackage should have a minimum depth of
cover of three (3) feet below the flow line of the ditch or ground surface and five and
one-half (5-1/2) feet from base of rail. In fill sections, the natural ground line at the toe
of slope will be considered as ditch grade. The depth of cover shall not be less than that
meeting applicable industry standards.
c. For all boring and jacking installations under main and passing tracks, greater than 26
inches in diameter, and at a depth of between 5.5 and 10.0 feet below top of tie, a
geotechnical study will need to be performed to determine the presence of granular
material and/or high water table elevation, at the sole expense of the Permittee. The study
will include recommendations and a plan for a procedure to prevent failure and a collapse
of the bore. Generally, core samples are to be taken near the ends of tie at the proposed
location, at least as deep as the bottom of the proposed horizontal bore. Test results must
be reviewed and approved by BNSF, or its agent, prior to boring activities commencing.
BNSF reserves the rights, based on test results, to require the Permittee to select an
alternate location, or to require additional engineering specifications be implemented, at
the sole expense of the Permittee, in order to utilize existing location.
d. The use of plastic carrier pipe for sewer, water, natural gas and other liquids is acceptable
under specific circumstances. The use of plastic pipe is satisfactory if the pipe is
designed to meet all applicable federal and state codes, and if the carrier pipe is properly
encased within a steel casing pipe per AREMA standards. This casing must extend the
full width of the right of way. Casing may be omitted only for gaseous products if the
carrier pipe is steel and is placed ten (10) feet minimum below the base of rail per
AREMA standards.
2. General Design and Construction Requirements
a. If the minimum depth is not attainable because of existing utilities, water table,
ordinances, or similar reasons, the line shall be rerouted.
b. Locations that are considered unsuitable or undesirable are to be avoided. These include
deep cuts and in wet or rocky terrain or where it will be difficult to obtain minimum
depth.
c. Underground installations may be made by open-trenching from the property line to the
toe of the fill slope in fill sections and to the toe of the shoulder slope in cut sections but
to no closer than thirty (30) feet of the centerline of track. The remainder will be
tunneled, augured, jacked or directional-bored through the roadbed. Refer to the
following sections for required encasement of utilities and boring requirements.
d. Manholes should be located outside railroad property, when possible. No manhole will
be located in the shoulder, shoulder slope, ditch or backslope, or within twenty-five (25)
May 18, 2011
Page 3-4
feet of the centerline of track, and shall not protrude above the surrounding ground
without approval of BNSF.
e. Utilities will not be attached to or routed through drainage structures or cattle passes.
Utilities are not to be attached to other railroad structures without written approval of the
BNSF Structures Department.
f. Jacking/boring pits shall be located a minimum of thirty (30) feet from the centerline of
track, and kept to the minimum size necessary.
g. Under-track bores shall be located greater than 150 feet from the nearest bridge, culvert,
track switch, building or other major structure.
3. Pipeline Requirements
a. Pipeline designs are to specify the type and class of material, maximum working
pressures and test and design pressure. Pipelines which are not constructed, operated and
maintained under regulations established under US Department of Transportation
Hazardous Materials Regulations Board, shall upon revisions in the class of material or
an increase in the maximum operating pressure, must obtain BNSF Engineering approval.
b. Pipelines carrying oil, liquefied petroleum gas, natural or manufactured gas and other
flammable products shall conform to the requirements of the current AREMA,
ANSI/ASME B 31.4 Code for pressure piping - Liquid Petroleum Transportation Piping
Systems; ANSI B 31.8 Code for pressure piping - Gas Transmission and Distribution
Piping Systems; other applicable ANSI codes and 49 C.F.R. Part 192 or Part 195 -
Transportation of Hazardous Liquids by Pipeline, except that the maximum allowable
stress of design of steel pipe shall not exceed the following percentages of the specified
minimum yield strength (multiplied by longitudinal joint factor) of the pipe as defined in
the ANSI codes.
c. Pipelines under railroad tracks and across railroad property shall be encased in a larger
pipe or conduit called “casings.” Generally, casings shall extend from right-of-way line
to right-of-way line, unless otherwise approved.
d. Pipelines and casing pipes shall be suitably insulated from underground conduits carrying
electric wires on railroad property.
e. Reinforced concrete pipe will need to be encased for a distance as wide as the
embankment at the utility crossing. This is to protect against track failure due to joint
separation.
4. Encasement of Utilities
a. Casings are oversized load-bearing conduits or ducts through which a utility is inserted:
May 18, 2011
Page 3-5
1) To protect the railroad from damages and to provide for repair, removal and
replacement of the utility without interference to railway traffic.
2) To protect the carrier pipe from external loads or shock, either during or after
construction.
3) To convey leaking fluids or gases away from the area directly beneath the railroad
trackage to a point of venting at the railroad property line.
b. Casings may be omitted for gaseous products only under the following circumstances:
1) Carrier pipe must be steel and the wall thickness must conform to E-80 loading for
casing pipe shown in the tables as included in the AREMA manual Chapter 1, Part 5
for Pipeline Crossings. The length of thicker-walled pipe shall extend from railroad
right-of-way line to right-of-way line. This will generally result in thicker-walled
pipe on railroad right-of-way.
2) All steel pipe shall be coated and cathodically protected.
3) The depth from base of rail to top of pipe shall not be less than ten (10) feet below
base of rail. The depth from ditches or other low points on railroad right-of-way shall
not be less than six (6) feet from ground line to top of pipe.
c. In circumstances where it is not feasible to install encasement from right-of-way line to
right-of-way line, casing pipe under railroad tracks and across railroad property shall
extend to the greater of the following distances, measured at right angles to the centerline
of track:
1) Two (2) feet beyond toe of slope.
2) Three (3) feet beyond ditch line.
3) Twenty-five (25) feet from centerline of outside track when casing is sealed at both
ends.
4) Forty-five (45) feet from centerline of outside track when casing is open at both ends.
5) If additional track is planned for future construction, casing must extend far enough
to meet above distances given the additional track requirement.
d. Pipelines and casing pipe shall be suitably insulated from underground conduits carrying
electric wires on railroad property.
e. Casing pipe and joints shall be made of metal, and of leakproof construction. Casings
shall be capable of withstanding the railroad loadings and other loads superimposed upon
them.
May 18, 2011
Page 3-6
f. Wall thickness designations for steel casing pipe for E-80 loading (including impact) are:
Nominal Diameter, Min. Thickness for Non Coated
(Inches) Coated (Inches) (Inches)
14 and Under 0.188 0.188
16 0.219 0.281
18 0.250 0.312
20 and 22 0.281 0.344
24 0.312 0.375
26 0.344 0.406
28 0.375 0.438
30 0.406 0.469
32 0.438 0.500
34 and 36 0.469 0.531
38, 40 and 42 0.500 0.563
44 and 46 0.531 0.594
48 0.563 0.625
50 0.594 0.656
52 0.625 0.688
54 0.656 0.719
56 and 58 0.688 0.750
60 0.719 0.781
62 0.750 0.813
64 0.718 0.844
66 and 68 0.813 0.875
70 0.844 0.906
72 0.875 0.938
1) Steel pipe shall have minimum yield strength of 35,000 pounds per square inch.
2) All metallic casing pipes are to be designed for effective corrosion control, long
service life and relatively free from routine servicing and maintenance. Corrosion
control measures for metallic carrier piping must include cathodic protection.
3) Cast iron may be used for casing. It shall conform to ANSI A21. The pipe shall be
connected with mechanical-type joints. Plain-end pipe shall be connected with
compression-type couplings. The strength of the cast iron pipe to sustain external
loads shall be computed in accordance with the most current ANSI A21.1 “Manual
for the Computation of Strength and Thickness of Cast Iron Pipe.”
g. The inside diameter of the casing pipe shall be such that the carrier pipe can be removed
without disturbing the casing. All joints or couplings, supports, insulators or centering
devices for the carrier pipe shall be considered in the selection of the casing diameter.
May 18, 2011
Page 3-7
h. For flexible casing pipe, a minimum vertical deflection clearance of the casing pipe shall
be three percent (3%) of its diameter plus one-half (1/2) inch so that no loads from the
roadbed, track, railroad traffic or casing pipe are transmitted to the carrier pipe. When
insulators are used on the carrier pipe, the relationship of the casing size to the size of the
carrier pipe is:
Inside Dia. of Casing Pipe Equals
Diameter of Carrier Pipe Outside Dia. of Carrier Pipe Plus
0” - 8” 2”
10” - 16” 3-1/4”
Over 16” 4-1/2”
5. Casing and Pipeline Installation
a. Casing and pipeline installations should be accomplished by directional boring (see
appendix page A-8), jack-and-bore, tunneling or other approved methods. Tunneling
construction under tracks will be permitted only under direct supervision of a BNSF
Engineer. Tunneling procedures and equipment, as well as structural design, must have
BNSF Engineering approval prior to starting any work on BNSF property. Generally,
tunneling shall not be considered where less than six (6) feet of cover exists, or where
excessively sandy, loose or rocky soils are anticipated.
Rail elevations over the work must be monitored at intervals prescribed by BNSF to
detect any track movement. Movements of over one-quarter (1/4) inch vertically shall be
immediately reported to the BNSF Roadmaster. Due to the danger to rail traffic that is
caused by only small amounts of track movement, BNSF forces may have to be called to
surface the track several times.
The following requirements shall apply to these construction methods:
1) The use of water under pressure jetting or puddling will not be permitted to facilitate
boring, pushing or jacking operations. Some boring may require water to lubricate
cutter and pipe, and under such conditions, is considered dry boring.
2) Where unstable soil conditions exist, boring or tunneling operations shall be
conducted in such a manner as not to be detrimental to the railroad being crossed.
3) If excessive voids or too large a bored hole is produced during casing or pipeline
installations, or if it is necessary to abandon a bored or tunneled hole, prompt
remedial action should be taken by the Utility Owner.
4) All voids or abandoned holes caused by boring or jacking are to be filled by pressure
grouting. The grout material should be sand cement slurry with a minimum of two
(2) sacks of cement per cubic yard and a minimum of water to assure satisfactory
placement.
May 18, 2011
Page 3-8
5) The hole diameter resulting from bored or tunneled installations shall not exceed the
outside diameter of the utility pipe, cable or casing (including coating) by more than
one and one-half (1-1/2) inches for pipes with an inside diameter of twelve (12)
inches or less, or two (2) inches on pipes with an inside diameter greater than twelve
(12) inches.
6) Pits for boring, tunneling or jacking will not be permitted within thirty (30) feet of the
centerline of track; or closer to the track than the toe of fill slopes in fill sections, or
toe of shoulder slopes in ditch sections when pipes are allowed on the railroad
property.
c. Vents. In casing pipe installations, vents are appurtenances by which fluids or gases
between carrier and casing may be inspected, sampled, exhausted or evacuated.
1) Vents shall be located at the high end of short casings and at both ends of casing
longer than one hundred fifty (150) feet.
2) Vent standpipes shall be located and constructed so as not to interfere with
maintenance of the railroad or to be concealed by vegetation. Where possible, they
shall be marked and located at the property line. The markers shall give the name and
address of the owner, and a phone number to contact in case of emergency.
3) Casing pipe, when sealed, shall be properly vented. Vent pipes shall be of sufficient
diameter, but in no case less than two (2) inches in diameter and shall be attached
near each end of casing, projecting through ground surface at property lines.
4) Vent pipes shall extend not less than four (4) feet above ground surface. Top of vent
pipes shall be fitted with a down-turned elbow, properly screened; or a relief valve.
5) For pipelines carrying flammable materials, vent pipes on casings shall be at least 16
feet (vertically) from aerial electric wires. Casings shall be suitably insulated from
underground conduits carrying electric wires on Railroad right-of-way.
d. Shut-Off Valves
1) The Utility Owner shall install accessible emergency shut-off valves within effective
distances on each side of the railroad. Where pipelines are provided with automatic
control stations, no additional valves will be required.
2) Locating a shut-off valve on railroad property should be avoided. If approval is
acquired, a guardrail must protect the shut-off valve.
3) When a guardrail is required, its height shall be four (4) feet above the ground line.
All four corner posts shall be driven to a minimum depth of four (4) feet below
ground line. There shall be a minimum clearance of two (2) feet from the valve to the
May 18, 2011
Page 3-9
guardrail. The steel pipes for the four corner posts and guardrail shall have a
minimum diameter of four (4) inches. All joints will be welded with a one-quarter
(1/4) inch fillet weld all around.
6. Water Lines
a. Where casing pipe is used, venting is not required; however, sealing will be required if
the ends of the casing are not above high water.
b. Where non-metallic pipe is permitted and installed, steel casings are required from right
of way line to right of way line.
c. Manholes should be located outside the railroad property. Manholes shall not be located
within twenty-five (25) feet of railroad trackage, in the shoulder, shoulder slope, ditch or
backslope; and shall not protrude above the surrounding ground without the approval of
BNSF Engineering.
d. The Utility Owner shall place a readily identifiable and suitable marker at each railroad
property line where it is crossed by a water line.
7. Sewer Lines
a. New and relocated sewer lines shall be constructed with satisfactory joints, materials and
designs which will provide protection and resistance to damage from sulfide gases and
other corrosive elements to which they may be exposed.
b. Where casing pipe is used, venting and sealing of casing will be required on pressurized
lines.
c. Where non-metallic pipe is permitted and installed, a durable metal wire shall be
concurrently installed; or other means shall be provided for detection purposes.
d. Manholes should be located outside the railroad property. Manholes shall not be located
within twenty-five (25) feet of railroad trackage, in the shoulder, shoulder slope, ditch or
backslope; and shall not protrude above the surrounding ground without the approval of
BNSF Engineering.
8. Electric Power Lines
a. A minimum depth of 5.5 feet below the base of rail (BBR) will be maintained.
b. A minimum depth of 3.0 feet below natural grade (BNG) will be maintained for 750 volts
and less, and 4.0 feet BNG for greater than 750 volts.
c. The wireline must be encased completely across the Railroad right-of-way with a rigid
conduit. The conduit can be metal or high-density poly-ethylene (HDPE).
May 18, 2011
Page 3-10
d. Crossings shall not be installed under or within 50 feet of the end of any Railroad bridge,
centerline of any culvert or switch area.
e. A BNSF signal representative must be present during installation if railroad signals are in
the vicinity of wireline crossings unless signal representative authorizes otherwise.
f. Markers that identify the Utility Owner shall be placed at both property lines for utilities
crossing the railroad property. For parallel lines markers shall be placed above the cable
at intervals no less than 300’ apart. The markers should identify the owner, type of cable
and emergency telephone number. A 6-inch wide warning tape will be installed, 1.0 foot
BNG directly over the underground power line where located on Railroad right-of-way
outside the track ballast sections.
g. Above-ground utility appurtenances installed as a part of an underground installation
shall be located at or near the railroad property line and shall not be any closer than
twenty-five (25) feet to the centerline of track.
9. Fiber Optic Lines.
a. The same requirements for electric power line crossings will apply for fiber optic line
crossings except for the following:
b. A minimum depth of 4.0 feet BNG for fiber optic cable wirelines.
c. BNSF Engineering must approve any specialized equipment used to install cable. No rail
plow will be allowed for installation purposes.
d. Schedule 80 HDPE pipe is acceptable (with no casing pipe) for use when housing fiber
optic lines. A metallic ribbon or wire must be included in the pipe to allow for radio
locating at a later date.
10. Abandonment/Removal of Facilities
a. Upon termination of license the pipeline needs to be removed from BNSF property
except for the portion under the track embankment. For pipelines crossing under the
tracks the pipe and casing will be cut just short of the toe of embankment slope, purged
and filled with a flowable grout (see appendix page A-9).
************************************
PART 4
PLANS, APPROVALS AND
PROCEDURES
************************************
May 18, 2011
Page 4-2
PART 4 - PLANS, APPROVALS AND PROCEDURES
A. Plans and Approvals
1. Design
a. The design of all utility installations will be the responsibility of the Utility Owner.
b. The plans for the proposed installation shall be submitted with the application and have
BNSF approval before construction is initiated.
c. Plans shall be drawn to scale showing the relationship of the proposed utility line to the
railroad tracks, the angle of crossing, location of valves and vents, the railroad mile post
and engineering station, railroad property lines and general layout of tracks and other
railroad facilities. The plans should include a cross-section (or sections) from the field
survey that will show utility placement in relation to actual profile of ground and tracks.
If tunneling is proposed, method of supporting tracks or driving of tunnel shall be shown.
The geotechnical study, when required, should be included.
d. The plans should contain the following data for carrier pipe and casing pipe:
Contents to be carried
Inside diameter
Pipe material
Specifications and grade of material
Wall thickness
Actual working pressure
Type of joints
Longitudinal joint factor
Coating
Method of installation
Vents-Number, Size, Height above ground
Seals-Both ends, One end
Cover (top of tie to top of pipe or casing)
Cover (other than under tracks)
Cover (at ditches)
Cathodic protection
Type, Size and Spacing of insulators or supports
e. When a geotechnical study is required, the findings and protection plan shall be prepared
by a licensed civil engineer and included with the plans. The geotechnical crew will need
to be properly permitted to enter BNSF right-of-way and a BNSF flagman will be
required when working within 25 feet of the track.
May 18, 2011
Page 4-3
2. Approvals
a. Approval of plans and application forms is required for all installations of utilities prior
to initiation of work on railroad property.
b. If surveying is necessary for the completion of an application, a “Right of Entry” or
“Temporary Occupancy Permit” must be executed and referenced.
B. License Procedures
1. Submit applications to:
Jones Lang LaSalle
4300 Amon Carter Blvd, Suite 100
Fort Worth, TX 76155
2. Upon receipt of the application, a letter will be forwarded acknowledging receipt and
advising of the Permit & Contract file reference number that has been assigned and the
person who should be contacted for further inquiries.
3. Office Hours: 8:00 A.M. to 5:00 P.M. Monday through Friday, CT
Phone Number: (toll free) 866-498-6647. Fax: 817-306-8265
4. Agreements will be required for all encroachments on railroad property.
5. Generally, agreement-processing time will be thirty to sixty days. Please allow sufficient
lead-time for document handling prior to desired construction date. Before construction
begins, agreements must be executed by Utility Owner and returned. Verbal authorizations
will not be granted or permitted. A minimum of seventy-two (72) hours advance notice after
execution of an agreement will be required prior to initiation of construction.
6. License fees must be submitted at the time the agreement is executed and returned.
7. Applications are to be made on the standard application form including an Exhibit “A.”
C. Construction
1. The execution of the work on railroad property shall be subject to the inspection and
direction of the BNSF Roadmaster or his representative.
2. A representative of BNSF Signal Department must be present during installation if railroad
signals are in the vicinity of the proposed construction.
************************************
APPENDIX
************************************
D:\Office\Dgn\hdd.dgn 10/16/2008 2:54:47 PM
A-8
A-9
A-10
DEFINITION OF TERMS
The terminology used in this Policy strives for conventional meaning and to insure uniform
interpretation. To this end, the following definitions apply:
ACCESS CONTROL: Restriction of access to and from abutting lands to railroad property.
AREMA: American Railroad Engineering and Maintenance of Way Association.
ANSI: American National Standard Institute.
ASTM: American Society for Testing and Materials.
BACKFILL: Replacement of soil around and over an underground utility facility.
BORING: Piercing a hole under the surface of the ground without disturbing the earth surrounding the
hole. Boring may be accomplished by any approved manner. Water jetting or puddling will not be
permitted. Holes may be mechanically bored and cased using a cutting head and continuous auger
mounted inside of the casing. Small diameter holes may be augured and the casing or utility facility
pushed in later.
BNSF: Burlington Northern and Santa Fe Railway Company.
BURY: Placement of the utility facility below grade of roadway, ditch or natural ground to a specified
depth.
CARRIER: Pipe directly enclosing a transmitted fluid (liquid or gas).
CASING: A larger pipe enclosing a carrier.
CFR: Code of Federal Regulations.
COATING: Material applied to or wrapped around a pipe.
COMMUNICATION LINE: Fiber optic, telephone cable and similar lines, not exceeding four hundred
(400) volts to ground or seven hundred fifty (750) volts between any two (2) points of the circuit, the
transmittal power of which does not exceed one hundred fifty (150) watts.
CONDUIT OR DUCT: An enclosed tubular runway for protecting wires or cables.
COVER: The depth of material placed over a utility. Depth of cover is measured from top of utility casing
or carrier pipe (if no casing is required) to the natural ground line or construction line above the utility.
DIRECT BURIAL: Installing a utility underground without encasement, by plowing or trenching. No rail
plows will be permitted.
ELECTRIC SUPPLY: Electric light, power supply, and trolley lines, irrespective of voltage used for
transmitting a supply of electrical energy.
A-11
ENCASEMENT: Structural element surrounding a pipe or cable.
FLEXIBLE PIPE: A plastic, fiberglass, or metallic pipe having a large ratio of diameter to wall thickness
that can be deformed without undue stress. Copper or aluminum pipe shall be considered as flexible
pipe.
GROUNDED: Connected to the earth or to some extended conducting bodies which intentionally or
accidentally is connected with the earth.
GROUT: A cement mortar or slurry of fine sand or clay as conditions govern.
HORIZONTAL DIRECTIONAL DRILLING: A steerable trenchless method of installing underground
pipes, conduits and cables in a shallow arc along a prescribed bore path by using a surface launched
drilling rig, with minimal impact on the surrounding area.
JACK-AND-BORE: The installation method whereby the leading edge of the jacked pipe is well ahead of
the cutting face of the auger bit. The auger is removing waste from inside the pipe as it is being jacked.
This method greatly reduces the likelihood of subsidence of granular material during installation.
JACKING: The installation of small pipes by the use of hydraulic jacks or rams to push the pipe under the
traveled surface of a road, railroad roadbed, or other facility.
LICENSE:
UTILITY LICENSE AGREEMENTS are executed for all utility facilities located on railroad
property.
MANHOLE: An opening to an underground utility system which workmen or other may enter for the
purpose of maintaining, inspecting, or making installations.
NATURAL GAS PIPELINES:
DISTRIBUTION SYSTEM - A pipeline other than a gathering or transmission line.
SERVICE LINE - A distribution line that transports gas from a common source of supply to a customer
meter.
TRANSMISSION SYSTEM - A pipeline other than a gathering line that transports gas from a
gathering line or storage facility to a distribution center or storage facility. It operates at a hoop stress of
twenty percent (20%) or more of the Specified Minimum Yield Strength.
NORMAL: Crossing at a right angle.
PERMITS:
PERMIT TO BE ON BNSF PROPERTY FOR UTILITY SURVEY is to be executed prior to all
survey work on railroad property.
PIPE: A tubular product made as a production item for sale as such. Cylinders formed from plate in the
course of fabrication of auxiliary equipment are not pipes as defined here.
PRESSURE: Relative internal pressure in PSI (pounds per square inch) gauge.
A-12
PRIVATE LINES: Any privately owned facilities which convey or transmit the commodities outlined
under the definition for Utilities but are devoted exclusively to private use.
PUBLIC LINES: Those facilities which convey or transmit the commodities outlined under the definition
for Utilities and directly or indirectly serve the public or any part thereof.
RIGHT OF WAY: A general term denoting land, property of interest therein, usually in a strip, acquired
for or devoted to railroad transportation purposes.
SEAL: A material placed between the carrier pipe and casing to prevent the intrusion of water, where ends
of casing are below the ground surface.
SHOULDER: That portion of the roadbed outside the ballast.
TRENCHED: Installed in a narrow excavation.
TUNNELING: Excavating the earth ahead of a large diameter pipe by one or more of the following
processes: 1) The earth ahead of the pipe will be excavated by men using hand tools while the pipe is
pushed through the holes by means of jacks, rams or other mechanical devices, 2) The excavation is
carried on simultaneously with the installation of tunnel liner plates, and/or 3) The tunnel liner plates are
installed immediately behind the excavation as it progresses and are assembled completely away from
the inside.
UTILITY OWNER: All privately, publicly or cooperatively owned lines, facilities and systems for
producing, transmitting or distributing communications, power, electricity, light, heat, gas, oil, crude
products, water, steam, waste, storm water and other similar commodities, including fire and police
signal systems and street lighting systems which directly or indirectly serve the public.
A-13