ADDENDUM NO. 1
SPECIFICATIONS AND CONTRACT DOCUMENTS
Description of BID 8484: Asphalt Supply
OPENING DATE: 3:00 PM (Our Clock) March 17, 2017
To all prospective bidders under the specifications and contract documents described above,
the following changes/additions are hereby made and detailed in the following sections of this
addendum:
Exhibit 1 – Revised Bid Schedule
Exhibit 2 – Questions & Answers
Please contact Elliot Dale, Buyer at (970) 221-6777 with any questions regarding this
addendum.
RECEIPT OF THIS ADDENDUM MUST BE ACKNOWLEDGED BY A WRITTEN STATEMENT
ENCLOSED WITH THE BID/QUOTE STATING THAT THIS ADDENDUM HAS BEEN
RECEIVED.
Financial Services
Purchasing Division
215 N. Mason St. 2nd Floor
PO Box 580
Fort Collins, CO 80522
970.221.6775
970.221.6707
fcgov.com/purchasing
EXHIBIT 1 – REVISED BID SCHEDULE
Addendum 1 - Page 2 of 3
BID SCHEDULE
8484 ASPHALT SUPPLY
Hot Mix Asphalt Pricing (FOB Plant)
ITEM ITEM ESTIMATED UNIT
NO. DESCRIPTION QUANTITY PRICE
403.10 HMA GR SX (PG 58-28) 20% RAP 2,000 tons $______________ /ton
403.15 HMA GR SX (PG 64-22) 20% RAP 2,000 tons $______________ /ton
403.20 HMA GR SX (PG 64-28) 20% RAP 2,000 tons $______________ /ton
403.25 HMA GR S (PG 58-28) 20% RAP 2,000 tons $______________ /ton
403.30 HMA GR S (PG 64-22) 20% RAP 30,000 tons $______________ /ton
403.35 HMA GR S (PG 64-28) 20% RAP 2,000 tons $______________ /ton
403.40 HMA GR SG (PG 64-22) 20% RAP 1,000 tons $______________ /ton
Note: The quantities listed above are estimates only. The City of Fort Collins reserves the right to
modify the quantities for any or all items listed.
IN ADDITION TO THE BID SCHEDULE PRICES FOR EACH MIX DESIGN LISTED ABOVE, VENDORS
MUST SUBMIT THE FOLLING LIQUID ASPHALT COSTS FOR THE 2017 SEASON. THESE COSTS ARE
NOT TO BE ADJUSTED FOR THE ENTIRETY OF THE 2017 SUPPLY CONTRACT. THESE COSTS ARE
INTENDED TO BE LOCKED IN FOR THE LENGTH OF THE CONTRACT FROM DATE SIGNED TO THE
SAME DATE IN THE FOLLOWING YEAR.
Asphalt Cement (PG 58-28) $________________ /ton
Asphalt Cement (PG 64-22) $________________ /ton
Asphalt Cement (PG 64-28) $________________ /ton
NIGHT OR WEEKEND UP-CHARGE (OPTIONAL) $________________ /ton
FIRM NAME
Are you a Corporation, Partnership, DBA, LLC, or PC
SIGNATURE PRINT NAME
ADDRESS
PHONE CELL PHONE
EMAIL
EXHIBIT 2 – QUESTIONS & ANSWERS
Addendum 1 - Page 3 of 3
1. How will the COFC determine which plant they select to purchase from for each project they
do? For example will the total delivered price to the project be used or will the asphalt price
alone govern the selection?
The City of Fort Collins will select which plant to use based on vicinity to the
scheduled project, the quality of mix, etc.; however the price of the mix shall be
the main driver of the selection. The City utilizes internal and external forces and
trucks for their jobs, so calculating the delivered price is not an accurate
representation of our needs.
2. Is there a list of streets available?
This supply will be utilized by all of the Streets crews. The mix will be used with
misc. patching efforts as well as full repaving of roadways and unexpected
circumstances that may arise. The scheduled streets for repaving can be
provided as it is currently scheduled after bid opening, but they are subject to
change.
3. Will the COFC accept a qualification for night and weekend purchases?
See attached Revised Bid Schedule, which includes pricing for optional night and
weekend up-charge.