HomeMy WebLinkAboutPrebid - BID - 8358 PITKIN STREET BIKEWAY8/26/2016
1
1
Pitkin Bikeway Project
Federal Aid Project No. TAP M455-120
PRE-BID CONFERENCE
Friday August 26, 2016
10:30 AM – 11:30 AM
215 N. Mason Street
Training Room 2E
City of Fort Collins
2
INTRODUCTIONS
• Engineering Capital Projects:
• Dan Woodward – Project Manager 416-4203
• Craig Farver – Construction Inspector 222-0854
• Purchasing:
• Elliot Dale – Buyer 221-6777
8/26/2016
2
3
IMPORTANT BID DATES
• Please be sure to register
• Questions deadline
• September 1, 5:00 PM
• Bid Opening
• When: September 9, 3:00 PM SHARP
• Where: Purchasing Department; 215 N.
Mason Street
• All items on BID FORM must be completed for bid
to be accepted
• All bid documents and addendum posted at
www.rockymountainbidsystem.com
4
CDOT LOCAL AGENCY PROJECT
UDBE goal for this project: 10%
Bid proposal must include:
– CDOT 606 Anti-Collusion Affidavit
– CDOT 1413 Bidder’s List
– CDOT 1414 Anticipated DBE Participation Plan
– Buy America and Certification Regarding Lobbying
Bids will not be accepted if they do not have these forms
Low bidder to receive:
Form 605, Form 621, Form 1415 and Form 1416 (if DBE goal is not met)
These forms must be returned by 4:00 pm the following day
Monthly payments will not be processed until all documentation required by
CDOT for federally funded projects has been submitted to the City
8/26/2016
3
5
SUMMARY OF WORK
• New signal installations at arterial streets (City performed,
contractor installs caissons)
• Removals (curb, concrete, asphalt)
• Clearing and grubbing and Tree removal (Shields)
• Concrete sidewalk (includes curb ramps) and median work – bike
medians
• Curb and gutter
• Asphalt paving
• Construction traffic control
• Striping (sharrows along route)
• Utility coordination
6
SUMMARY OF WORK (by others)
Construction Staking
Provided by the City of Fort Collins
48 Hours (Minimum) Required for Notification
Testing
Paid for by the City of Fort Collins thru CTL Thompson
Concrete and asphalt
Contractor will schedule Testing as required
Signal installations
Performed by City of Fort Collins Traffic Department
Contractor required to coordinate timing
8/26/2016
4
7
SUMMARY OF WORK
8
VICINITY MAP
• TAP Funding
• Facilitates bicycle/ped crossing of major arterials
• Work primarily at Taft Hill, Shields and Lemay
• Striping work at College
8/26/2016
5
9
IMPORTANT CONTRACT DATES
• Award Contract
• Pre-construction Meeting
• Mandatory meeting prior to start of construction
• Date to be determined, end of Sept
• Notice to Proceed with CDOT concurrence to award
• Substantial Completion
• Fifty (50) calendar days
• Final Completion
• Ten (10) calendar days
10
PROJECT OVERVIEW
• Coordination with other utilities (Centurylink OH line at
Shields), City Departments and CSU (light poles at Shields)
• Contractor responsible to acquire all appropriate permits
and submit required documentation
– SWMP – permit and inspections
– CDOT Form 205 for each subcontractor
– TCS Diaries, Payrolls
• All required CDOT documentation prior to progress
payments (Buy America, EEO, etc.)
• No designated staging area provided
8/26/2016
6
11
PROJECT OVERVIEW
• Traffic Control
– All Traffic Control Plans (MHTs) approved through City Traffic
Department, submitted at least 48 hours in advance
– Lane rental spec for arterial roadways
– Minor street closures may be allowed
– Contractor responsible for submitting all MHTs
– Access to local businesses and residents required
– Coordination with CSU events/construction near Shields and
College
12
HIGHLIGHTS FROM SPECIFICATIONS
• Section 104 – Lane Rental Fee
– 5 days allowed on major arterials, Taft, Shields and Lemay
– Additional days shall be $1200/lane day
– Lane day measured as any day that thru lane or left turn lane
closed to traffic
– Lane days from 7 AM to 3:30 PM
– Minor streets do not have Lane Rental Fee
8/26/2016
7
13
• Section 108 – Prosecution and Progress
– 60 total calendar days for completion of project
– Liquidated Damages assessed for failure to complete work on
time
• $800/day in accordance with Section 108.09
– Standard hours of operations
• 7 AM thru 6 PM M-F
• Extended hours and weekend work may be requested
HIGHLIGHTS FROM SPECIFICATIONS
14
• Section 108 – Prosecution and Progress
– Notice to Proceed, plan to issue by Sept 30 2016
• If not issued by then, Contractor may request to postpone
work until Spring of 2017 due to weather limitations, must
hold unit prices
• Contractor may request to postpone entire project, or work
until weather limits operations and postpone remaining
work
• Contractor shall be required to maintain job site in an
acceptable condition during winter shutdown
• It is City’s preference that the work be completed Fall of
2016
HIGHLIGHTS FROM SPECIFICATIONS
8/26/2016
8
15
• Project Meetings
− Once a week at the construction office, time to be determined.
− Agree to quantities weekly
− Monthly payments confirm acceptance of quantities by the Contractor.
ALL quantity disputes MUST be resolved prior to monthly progress
payments.
• Progress and Schedule Revisions
− Prior to construction, initial schedule must be submitted and approved
− Schedules shall be updated weekly
• The Contractor may be required to submit additional schedules
depending on the progress of the project.
• Record Drawing Plan Set
− Contractor will be required to keep record drawings
HIGHLIGHTS FROM SPECIFICATIONS
16
• Haul Routes
− Arterial and Collector streets only. Contractor will not be
allowed to use residential streets to access the site with
trucks hauling materials.
− The City reserves the right to dictate haul routes to
protect pavement and other material per Section 106
• Site Clean-up
− The construction work shall be kept and accomplished in
a neat, clean and orderly fashion
− Tracking pads and street sweeping may need to be used
in order to minimize tracking and meet EPA storm water
quality requirements
− Dust control as required – City has dust control policy
and manual
HIGHLIGHTS FROM SPECIFICATIONS
8/26/2016
9
17
PAY ITEMS
18
SECTION 201 – CLEARING AND GRUBBING
• Clearing and Grubbing – LS
• Includes removal of the following
– Bushes and shrubs as identified by Engineer
or Assistant City Forester (Ralph Zentz)
– Material along Shields to facilitate sidewalk
installation
– Abandoned utilities above ground
• All removed debris becomes the property of
Contractor
• Debris to be removed from project site, not buried
on-site
8/26/2016
10
19
SECTION 202 - REMOVALS
- Removal of Concrete – Includes all ramps and sidewalks
- Removal of Tree (Less than 8” Diameter) – EA
- Removal of Tree (Greater than 8” Diameter) – EA
- Removal of Curb and Gutter - Concrete
- Removal of Asphalt
20
SECTION 203
• Laborer – HOUR
• Backhoe – HOUR
• Potholing – HOUR
– Investigative potholing for traffic caissons
• Excavation – Along Shields for sidewalk installation,
150 CUYD, will add this pay item with addendum
8/26/2016
11
21
SECTION 208 – EROSION CONTROL
• Erosion Control – LS
– Includes work identified in preliminary erosion control
plan
– Work required to maintain clean job site, sweeping,
washout, etc.
– Other protections identified in order to meet stormwater
BMP’s
22
SECTION 403 – HOT MIX ASPHALT
• Hot Mix Asphalt (Grading S) (100) (PG 64-22) – TON
• Match existing pavement section
8/26/2016
12
23
SECTIONS 503, 608, 609 – CONCRETE
• 503 – Drilled Caisson (18 Inch) - LF
• 503 – Drilled Caisson (36 Inch) - LF
• 608 – Concrete Sidewalk (includes ramps and pedestrian curb) - SY
• 608 – Detectible Warnings - EA
• 609 – Modified Curb and Gutter (4” Rolled Curb, Match Existing) - LF
• 609 – Curb Type 2 (Section B) - LF
24
SECTIONS 610 – CONCRETE
• 610 – Concrete Bike Median (6” Thick) - SY
• 610 – Concrete Median Cover (6” Thick) - SY
8/26/2016
13
25
SECTION 613 - ELECTRICAL
• 2 Inch Electrical Conduit (Bored) – LF
• 2 Inch Electrical Conduit – LF
• 3 Inch Electrical Conduit (Bored) – LF
• 3 Inch Electrical Conduit – LF
• Pull Box (13”x24”x18”) – EACH
• Pull Box (18”x30”x18”) – EACH
26
SECTION 623 – IRRIGATION
• 623 – Irrigation Restoration – LS
– Impacted irrigation systems, Shields and Pitkin
– Existing irrigation heads at back of walk
– Includes all work required to restore the impacts to the systems
and make fully operational
• Anticipated replacement of irrigation heads
• Minor irrigation line repairs
• Controller reprogramming
• Tying into CSU’s system in Pitkin median
• 623 – 2.5” Irrigation Line – Bored
– To tie into CSU irrigation in median
8/26/2016
14
27
SECTIONS 626, 627
• 626 – Mobilization – LS
• 627 – Epoxy Pavement Marking – GAL
• 627 – Thermoplastic Pavement Marking (Word-Symbol) – SF
• 627 – Thermoplastic Pavement Marking (Xwalk-Stop Line) – SF
28
SECTION 630 – TRAFFIC
• 630 – Construction Zone Traffic Control – LS
– Covers all traffic control items necessary for the project except
for Flagging
– Plans developed by Contractor
– Approved by City of Fort Collins
• 630 – Flagging – HOUR
• 630 – Traffic Control Inspection – DAY
• 630 – Traffic Control Management – DAY
8/26/2016
15
29
TRAFFIC CONTROL
• All plans for work must be submitted at least 48 hours in advance
• Maintain pedestrian and bicycle traffic – TCP to account for these
movements
• Emergency vehicle access into and through construction site
• Provide and maintain continuous temporary access for businesses
and residences
• Maintain 11 foot lanes throughout the project
30
TRAFFIC SIGNAL COORDINATION
• City will install all new traffic signal equipment and
wiring, contractor to install conduit and pull boxes
• City Traffic Signal Contact:
Britney Sorenson
970-222-5533
bsorenson@fcgov.com
8/26/2016
16
31
TRAFFIC SIGNAL COORDINATION
• Contractor shall coordinate with City Traffic
Department to meet the following goals
– Traffic Department work is expedited
– Duplication of work is minimized
– Impacts to traffic are minimized
32
PAVEMENT MARKINGS AND SIGNAGE
• Permanent pavement markings to be installed by the Contractor
• Permanent signage to be installed by City
• Coordinate with City Traffic Department
• Signing and Striping Contact:
Rich Brewbaker
970-221-6792
rbrewbaker@fcgov.com
8/26/2016
17
33
UTILITIES
• The following utilities are known to be within the project limit:
Utility/Agency Contact Phone
City Sanitary/Storm Sewer Andrew Gingerich 970-221-6232
City Water Andrew Gingerich 970-221-6232
City Forester Ralph Zentz 970-221-6302
City Light & Power Tyler Siegmund 970-416-2772
CenturyLink Bill Johnson 970-490-7501
Xcel Stephanie Rich 970-225-7828
City Traffic Britney Sorenson 970-416-2268
Comcast (Cable TV) Don Kapperman 970-484-7166
CSU Light Poles Laura Bentley 970-492-4161
34
UTILITIES
The following utility work will be performed by Utility Company
or their agent:
• CenturyLink – Relocate OH lines at Shields and Pitkin
– Work may need to be coordinated by contractor at
beginning of project
• CSU – Relocate existing light poles at Shields and Pitkin
– Work needs to be coordinated by contractor and
scheduled
• City Traffic – Install all signal poles and wiring
– Timing and work needs to be coordinated by contractor
8/26/2016
18
35
QUESTIONS?
Thanks for attending!