WORK ORDER NUMBER CH-2016-03
CHANGE ORDER NO. 1
PROJECT TITLE: 2016 WTF Minor Capital Projects - Electrical
CONSULTANT: CH2M HILL Engineers, Inc.
PROJECT NUMBER: PO# 9165822
DESCRIPTION: Professional engineering services for providing support to the City for various electrical
minor capital improvement projects at the Water Treatment Facility and related facilities.
1. Reason for change: Contract completion date change. Longer construction period than
anticipated.
2. Description of Change: The current contract completion date of June 30, 2017, will be
exceeded; thus a contract completion date is required and recommended.
3. Change in Contract Cost: No change in contract cost.
4. Change in Contract Time: Change contract completion date to October 31, 2017
ORIGINAL CONTRACT COST $173,998.00
TOTAL APPROVED CHANGE ORDERS 0.00
TOTAL PENDING CHANGE ORDERS 0.00
TOTAL THIS CHANGE ORDER 0.00
TOTAL % OF THIS CHANGE ORDER 0%
TOTAL C.O.% OF ORIGINAL CONTRACT 0%
ADJUSTED CONTRACT COST $173,998.00
(Assuming all change orders approved)
ACCEPTED BY: DATE:
Consultant’s Representative
ACCEPTED BY: DATE:
Special Projects Manager
REVIEWED BY: DATE:
Chief Engineer
APPROVED BY: DATE:
Water Production Manager
APPROVED BY: DATE:
Water Resources & Treatment Ops Manager
APPROVED BY: DATE:
Purchasing Agent over $60,000
DocuSign Envelope ID: C7F336BB-8F99-4F38-A8FC-603DD6A2153C
6/20/2017
6/22/2017
6/22/2017
6/22/2017
6/22/2017
WORK ORDER NUMBER CH-2016-03 Minor Electrical Change Order No. 1
Purchasing
DocuSign Envelope ID: C7F336BB-8F99-4F38-A8FC-603DD6A2153C