HomeMy WebLinkAbout109420 HYDRO CONSTRUCTION CO INC - CONTRACT - RFP - 8286 CONSTRUCTION CONTRACTOR FOR PROJECTS AT THE W (10)CONTRACT DOCUMENTS FOR
24inch Poudre Pipeline Rehab Assessment Phase 1 Procurement-
Procurement of the materials and pre-construction requirements
Pertaining to the 24 inch Poudre Pipeline Rehabilitation Assessment
Phase 1 Scope of Services-
Construction personnel to provide input on constructability, value engineering, scheduling and cost
estimating pertaining to investigation and inspection efforts related to the 24 inch Poudre Pipeline
Rehabilitation. Additionally, material will be pre-procured due to the critical path, long lead time
materials. These consist of pipe closure materials, pipe couplings and inner seals. Services will
also include preconstruction efforts related to highway access permits, pre-pipeline inspections, and
construction erosion control.
June 5, 2017
3325 South Timberline Rd
Suite 150,
Fort Collins, CO 80525
Fort Collins Utilities
700 Wood Street
Fort Collins CO 80521
Hydro Construction Company, Inc.
301 East Lincoln Avenue
Fort Collins CO 80524
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Agre
June 2017
00500-1
SECTION 00500
AGREEMENT FORMS
00525 Work Order, Notice of Award, and Bid Schedule 00525-1
00530 Notice to Proceed 00530-1
00600 Bonds and Certificates 00600-1
00610 Performance Bond 00610-1 – 00610-2
00615 Payment Bond 00615-1 – 00615-2
00630 Certificate of Insurance 00630-1
00635 Certificate of Substantial Completion 00635-1
00640 Certificate of Final Acceptance 00640-1
00650 Lien Waiver Release (CONTRACTOR) 00650-1 – 00650-2
00651 Lien Waiver Release (SUBCONTRACTOR) 00651-1 – 00651-2
00660 Consent of Surety 00660-1
00670 Application for Exemption Certificate 00670-1 – 00670-2
CONDITIONS OF THE CONTRACT
00800 Supplementary Conditions 00800-1 – 00800-4
00900 Addenda, Modifications and Payment 00900
00950 Work Order Change Order 00950-1
00960 Application for Payment 00960-1
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment 00525-1 Work Order, Notice of Award and
June 2017 Bid Schedule
SECTION 00525
WORK ORDER, NOTICE OF AWARD AND BID SCHEDULE
TO: UHydro Construction
W. O. No. U BPM-WTF-PPR-5-05-17 U
PURCHASE ORDER:
TITLE: U24” Poudre Pipeline Rehabilitation Assessment – Phase 1 Procurement
OWNER’S REPRESENTATIVE: UBrian Mulligan
Original Bid/RFP Number & Name: RFP 8286, Construction Contractor for Projects at the Water and Wastewater
Treatment Facilities
Commencement Date: June 5, 2017
OWNER: UCITY OF FORT COLLINSU (hereinafter referred to as OWNER)
1. WORK. You are hereby notified that your bid dated UMay 4, 2017U, for the above Work Order has been
considered. Pursuant to your AGREEMENT with OWNER dated UJune 20, 2016U, you have been awarded a Work
Order for this Work Order Description:
A. See Section 01100 – Summary of Work.
2. CONTRACT PRICE, BONDS, AND CERTIFICATES. The price of your Work Order is UTwo Hundred and
Fifty Four Thousand One Hundred Eighty Eight Dollars ($254,188.00).U Pursuant to the AGREEMENT and the
Contract Documents, Performance and Payment Bonds and insurance are required.
3. CONTRACT TIMES. Pursuant to the AGREEMENT and the Contract Documents, the date for Substantial
Completion of this Work Order is UNov 6, 2017U, and after Substantial Completion, the number of days for Final
Payment and Acceptance is U60U Calendar days.
4. LIQUIDATED DAMAGES. OWNER and CONTRACTOR recognize that time is of the essence of this
Agreement and that OWNER will suffer financial loss if the Work is not completed within the times specified in
paragraph 3 above, plus any extensions thereof allowed in accordance with Article 12 of the General Conditions.
They also recognize the delays, expenses and difficulties involved in proving in a legal proceeding the actual loss
suffered by OWNER if the Work is not completed on time. Accordingly instead of requiring any such proof,
OWNER and CONTRACTOR agree that as liquidated damages for delay (but not as penalty) CONTRACTOR
shall pay OWNER the amounts set forth hereafter.
1) Substantial Completion: UFive Hundred Dollars ($500.00)U for each calendar day or fraction
thereof that expires after UNov 6, 2017U until the work is Substantially Complete.
2) Final Acceptance: After Substantial Completion UTwo Hundred Dollars ($200.00)U for each
calendar day or fraction thereof that expires after the 60 calendar day period for Final Payment
and Acceptance until the Work is ready for Final Payment and Acceptance.
5. EXECUTION. One electronic copy of this proposed Work Order & Notice of Award, and accompanying
amendments or supplements to the Contract Documents (except any applicable Drawings) incorporated
herein, are provided. Sets of any applicable Drawings will be delivered separately or otherwise made
available to you immediately. You must comply with the following conditions precedent within fifteen (fifteen)
days of the date of this Notice of Award, that is, by UJune 19, 2017.
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment 00525-2 Work Order, Notice of Award and
June 2017 Bid Schedule
A. You must deliver to OWNER one fully-executed electronic counterpart of this Work Order,
including all amendments or supplements to the Contract Documents incorporated herein. The
electronic Work Order must bear your signature as provided.
B. You must deliver with the executed Work Order the Contract Security (Bonds) and insurance, as
specified in the Agreement.
Failure to comply with these conditions within the time specified will entitle OWNER to consider your Bid
abandoned and to annul this Work Order & Notice of Award. Within ten (10) days after you comply with those
conditions, OWNER will return to you one (1) fully-signed electronic counterpart of this Work Order with any
amendments or supplements to the Contract Documents attached.
UCONTRACTOR’S NOTICE OF AWARD REPRESENTATION & EXECUTIONU:
CONTRACTOR agrees to perform the services identified above, in accordance with the terms and conditions
contained herein and in the AGREEMENT dated June 20, 2016 and the NOTICE OF AWARD dated June 5, 2017
U U
between the parties. In the event of a conflict between or ambiguity in the terms of the AGREEMENT or specific
Work Orders, the AGREEMENT shall control.
CONTRACTOR: UHydro Construction
By: Date:
Name: Title:
OWNER’S ACCEPTANCE & EXECUTION:
This Work Order and the attached Contract Documents are hereby accepted and incorporated herein by this
reference and the attached Notice to Proceed is hereby given.
Submitted: Date:
Brian Mulligan, Special Projects Manager
Reviewed By: Date:
Pat Johnson, Senior Buyer, Purchasing
Reviewed By: Date:
Mark Kempton, Water Production Manager
Reviewed By: Date:
Owen L. Randall, Chief Engineer
Reviewed By: Date:
Carol Webb, Water Resources and
Treatment Operations Manager
Acceptance: Date:
Gerry Paul, Director of Purchasing
(over $60,000)
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
5/15/2017
5/16/2017
5/17/2017
5/17/2017
5/17/2017
5/22/2017
5/22/2017
24” Poudre Pipeline Rehab Assessment 00525-3 Work Order, Notice of Award and
June 2017 Bid Schedule
Acceptance: Date:
Kevin R. Gertig, Utilities Executive Director
(over $1,000,000)
APPROVED AS TO FORM
Acceptance: Date:
City Attorney’s Office
(over $1,000,000)
Acceptance: Date:
Darin Atteberry, City Manager
(over $1,000,000)
ATTEST:
_____________________
City Clerk
(over $1,000,000)
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
Standard Estimate Report Page 1
Poudre Pipline 24 Line In 5/4/2017 7:02 AM
Item Description Takeoff Qty
Labor
Amount
Material
Amount
Subcontract
Amount Name
Equipment
Amount
Other
Amount
Total
Amount
01 Preconstruction/Procure
1000.000 GENERAL CONDITIONS
10 Bonds 1.00 ls - - - 5,300 5,300
14 Project Manager, Design/Preconstruction 14.00 wk 23,082 - - 4,542 636 28,260
14 Superintendent 4.00 wk 9,892 - - 1,817 389 12,098
10 Pipe Staging 1.00 ea 1,072 - 1,843 1,947 324 5,186
GENERAL CONDITIONS 34,046 1,843 8,305 6,650 50,844
720.00 Labor hours
720.00 Equipment hours
2000.000 SITEWORK
20 Temp Erosion Control 1.00 ls 1,081 0 - 227 649 1,957
20 Temp Erosion Control 1.00 ls 1,081 - 227 649 1,957
20 Temp Erosion Control 1.00 ls 1,081 - 227 649 1,957
20 Temp Erosion Control 1.00 ls 1,081 - 227 649 1,957
20 Temp Erosion Control 1.00 ls 1,081 - 227 649 1,957
20 Temp Erosion Control 1.00 ls 1,081 - 227 649 1,957
20 Temp Erosion Control 1.00 ls 1,081 - 227 649 1,957
n c 24 Closure Materials 1.00 ls 1,532 5,450 - - - 6,982
n c 24 Inner Seals 1.00 ls 1,532 6,229 - - - 7,761
n c 24 Closure Materials 1.00 ls 1,532 5,450 - - - 6,982
n c 24 Closure Materials 1.00 ls 3,064 13,237 - - - 16,301
n c 24 Inner Seals 1.00 ls 1,532 6,229 - - - 7,761
n c 24 Closure Materials 1.00 ls 3,064 13,237 - - - 16,301
n c 24 Inner Seals 1.00 ls 1,532 6,229 - - - 7,761
n c 24 Closure Materials 1.00 ls 3,064 13,237 - - - 16,301
n c 24 Inner Seals 1.00 ls 1,532 6,229 - - - 7,761
n c 24 Closure Materials 1.00 ls 1,532 5,450 - - - 6,982
n c 24 Closure Materials 1.00 ls 1,532 5,450 - - - 6,982
n c 24 Closure Materials 1.00 ls 3,064 26,473 - - - 29,537
n c 24 Inner Seals 1.00 ls 1,532 12,458 - - - 13,990
607 Camera Pipe 1.00 ls 1,531 3,932 - - 5,463
607 Camera Pipe 1.00 ls 1,531 3,932 - - 5,463
607 Camera Pipe 1.00 ls 1,531 3,932 - - 5,463
607 Camera Pipe 1.00 ls 1,531 3,932 - - 5,463
607 Camera Pipe 1.00 ls 1,531 3,932 - - 5,463
607 Camera Pipe 1.00 ls 1,531 3,932 - - 5,463
607 Camera Pipe 1.00 ls 1,531 3,932 - - 5,463
SITEWORK 44,331 125,358 27,523 1,590 4,542 203,344
1,079.362 Labor hours
01 Preconstruction/Procure 78,377 125,358 29,366 9,895 11,192 254,188
1,799.362 Labor hours
720.00 Equipment hours
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Notice to Proceed
June 2017 00530-1
SECTION 00530
WORK ORDER NOTICE TO PROCEED
Description of Work: U24” Poudre Pipeline Rehabilitation Assessment – Phase 1 Procurement
To: U Hydro Construction
This notice is to advise you:
That the contract covering the above described Work has been fully executed by the CONTRACTOR
and the OWNER.
That the required CONTRACTOR's Performance Bond and Payment Bond have been received by the
OWNER.
That the OWNER has approved the said Contract Documents.
Therefore, as the CONTRACTOR for the above described Work, you are hereby authorized and
directed to proceed within fifteen (15) calendar days from receipt of this notice as required by the
Agreement.
Dated this UJune 5, 2017.
The dates for Substantial Completion and Final Acceptance shall be UNov 6, 2017U and UDecember 6,
2017U, respectively.
UCity of Fort Collins
OWNER
By:
Brian Mulligan
Title USpecial Projects Manager
ACKNOWLEDGMENT OF NOTICE
Receipt of the above Notice to Proceed is hereby acknowledged this ___ day of U____________U,
U__________U.
UHydro Construction________________
CONTRACTOR
By: U____________________________
Title:
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Bonds and Certificates
June 2017 00600-1
SECTION 00600
BONDS AND CERTIFICATES
00610 Performance Bond
00615 Payment Bond
00630 Certificate of Insurance
00635 Certificate of Substantial Completion
00640 Certificate of Final Acceptance
00650 Lien Waiver Release (CONTRACTOR)
00651 Lien Waiver Release (SUBCONTRACTOR)
00660 Consent of Surety
00670 Application for Exemption Certificate
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Performance Bond
January 2017 00610-1
SECTION 00610
PERFORMANCE BOND
Bond No.
KNOW ALL MEN BY THESE PRESENTS: that
(Firm)U Hydro Construction
(Address) U___________________________________
(an Individual), (a Partnership), (a Corporation), hereinafter referred to as the "Principal" and
(Firm) U______________________________________
(Address) U_____________________________________
hereinafter referred to as "the Surety", are held and firmly bound unto UCity of Fort Collins, 300 Laporte
Ave, Fort Collins, Colorado 80522U a (Municipal Corporation) hereinafter referred to as the "OWNER", in
the penal sum of UTwo Hundred and Fifty Four Thousand One Hundred Eighty Eight Dollars
($254,188.00)U, in lawful money of the United States, for the payment of which sum well and truly to be
made, we bind ourselves, successors and assigns, jointly and severally, firmly by these presents.
THE CONDITIONS OF THIS OBLIGATION are such that whereas the Principal entered into a certain
Agreement with the OWNER, dated UJune 20, 2016U, a copy of which is hereto attached and made a part
hereof for the performance of The City of Fort Collins project, U24inch Poudre Pipeline Rehabilitation
Assessment – Phase 1 Procurement.
NOW, THEREFORE, if the Principal shall well, truly and faithfully perform its duties, all the
undertakings, covenants, terms, conditions and agreements of said Agreement during the original term
thereof, and any extensions thereof which may be granted by the OWNER, with or without Notice to the
Surety and during the life of the guaranty period, and if the Principal shall satisfy all claims and
demands incurred under such Agreement, and shall fully indemnify and save harmless the OWNER
from all cost and damages which it may suffer by reason of failure to do so, and shall reimburse and
repay the OWNER all outlay and expense which the OWNER may incur in making good any default
then this obligation shall be void; otherwise to remain in full force and effect.
PROVIDED, FURTHER, that the said Surety, for value received, hereby stipulates and agrees that no
change, extension of time, alteration or addition to the terms of the Agreement or to the Work to be
performed thereunder or the Specifications accompanying the same shall in any way affect its
obligation on this bond; and it does hereby waive notice of any such change, extension of time,
alteration or addition to the terms of the Agreement or to the Work or to the Specifications.
PROVIDED, FURTHER, that no final settlement between the OWNER and the CONTRACTOR shall
abridge the right of any beneficiary hereunder, whose claim may be unsatisfied.
PROVIDED, FURTHER, that the Surety Company must be authorized to transact business in the State
of Colorado and be acceptable to the OWNER.
IN WITNESS WHEREOF, this instrument is executed in three (3) counterparts, each one of which shall
be deemed an original, this U____U day of U________________U.
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Performance Bond
January 2017 00610-2
IN PRESENCE OF: Principal
By:
Title
Address
(Corporate Seal)
IN PRESENCE OF: Other Partners
By:
By:
IN PRESENCE OF: Surety
By:
Attorney-in-Fact
By:
Address
(Surety Seal)
NOTE: Date of Bond must UnotU be prior to date of Agreement. If CONTRACTOR is Partnership, all
partners should execute Bond.
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Performance Bond
June 2017 00615-1
SECTION 00615
PAYMENT BOND
Bond No.
KNOW ALL MEN BY THESE PRESENTS: that
(Firm)U Hydro Construction
(Address) U__________________________________
(an Individual), (a Partnership), (a Corporation), hereinafter referred to as the "Principal" and
(Firm) U______________________________________
(Address) U___________________________________
hereinafter referred to as "the Surety", are held and firmly bound unto Uthe City of Fort Collins, 300
Laporte Ave., Fort Collins, Colorado 80522U a (Municipal Corporation) hereinafter referred to as "the
OWNER", in the penal sum of UTwo Hundred and Fifty Four Thousand One Hundred Eighty Eight
Dollars ($254,188.00),U in lawful money of the United States, for the payment of which sum well and
truly to be made, we bind ourselves, successors and assigns, jointly and severally, firmly by these
presents.
THE CONDITIONS OF THIS OBLIGATION are such that whereas the Principal entered into a certain
Agreement with the OWNER, dated UJune 20, 2016U, a copy of which is hereto attached and made a part
hereof for the performance of The City of Fort Collins project, U24inch Poudre Pipeline Rehabilitation
Assessment – Phase 1 Procurement.
NOW, THEREFORE, if the Principal shall make payment to all persons, firms, subcontractors, and
corporations furnishing materials for or performing labor in the prosecution of the Work provided for in
such Agreement and any authorized extension or modification thereof, including all amounts due for
materials, lubricants, repairs on machinery, equipment and tools, consumed, rented or used in
connection with the construction of such Work, and all insurance premiums on said Work, and for all
labor, performed in such Work whether by subcontractor or otherwise, then this obligation shall be void;
otherwise to remain in full force and effect.
PROVIDED, FURTHER, that the said Surety, for value received, hereby stipulates and agrees that no
change, extension of time, alteration or addition to the terms of the Agreement or to the Work to be
performed thereunder or the Specifications accompanying the same shall in any way affect its
obligation on this bond; and it does hereby waive notice of any such change, extension of time,
alteration or addition to the terms of the Agreement or to the Work or to the Specifications.
PROVIDED, FURTHER, that no final settlement between the OWNER and the CONTRACTOR shall
abridge the right of any beneficiary hereunder, whose claim may be unsatisfied.
PROVIDED, FURTHER, that the Surety Company must be authorized to transact business in the State
of Colorado and be acceptable to the OWNER.
IN WITNESS WHEREOF, this instrument is executed in three (3) counterparts, each one of which shall
be deemed an original, this U____U day of U_________________U.
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Performance Bond
June 2017 00615-2
IN PRESENCE OF: Principal
By:
Title
Address
(Corporate Seal)
IN PRESENCE OF: Other Partners
By:
By:
IN PRESENCE OF: Surety
By:
Attorney-in-Fact
By:
Address
(Surety Seal)
NOTE: Date of Bond must UnotU be prior to date of Agreement. If CONTRACTOR is Partnership, all
partners should execute Bond.
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Certificate of Insurance
June 2017 00630-1
SECTION 00630
CERTIFICATE OF INSURANCE
CONTRACTOR shall insert his own standard form for Certificate of Insurance.
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Certificate of Substantial Completion
June 2017 00635-1
SECTION 00635
CERTIFICATE OF SUBSTANTIAL COMPLETION
TO: UCity of Fort Collins U
PROJECT TITLE: U24 inch Poudre Pipeline Rehabilitation Assessment – Phase 1 Procurement
Date of Substantial Completion: LOCATION: UFort Collins, Colorado
OWNER: U City of Fort Collins
Project or Specified Part Shall Include: CONTRACTOR: UHydro Construction
CONTRACT DATE:U ___________
Work performed under this contract has been inspected by authorized representatives of the OWNER,
CONTRACTOR, and the ENGINEER and the project (or specified part of the project, as indicated
above) is hereby declared to be substantially completed on the above date.
A tentative list of items to be completed or corrected is appended hereto. This list may not be
exhaustive, and the failure to include an item on it does not alter the responsibility of the
CONTRACTOR to complete all the Work in accordance with the Contract Documents.
By:
ENGINEER Authorized Representative Date
The CONTRACTOR accepts the above Certificate of Substantial Completion and agrees to complete
and correct the items on the tentative list within the time indicated.
By:
CONTRACTOR Authorized Representative Date
The OWNER accepts the project or specified area of the project as substantially complete and will
assume full possession of the project or specified area of the project at 12:01 a.m., on . The
responsibility for heat, utilities, security, and insurance under the Contract Documents shall be as set
forth under "Remarks" below.
UCITY OF FORT COLLINS, COLORADO U By:
OWNER Authorized Representative Date
REMARKS:
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Certificate of Final Acceptance
June 2017 00640-1
SECTION 00640
CERTIFICATE OF FINAL ACCEPTANCE
U,2017U
TO:
Gentlemen:
You are hereby notified that on the day of , U2017U the City of Fort
Collins, Colorado, has accepted the Work completed by UHydro ConstructionU for the City of Fort Collins
project, U24 inch Poudre Pipeline Rehabilitation Assessment – Phase 1 Procurement.
A check has been issued in the amount of $ as Final Payment for all Work done,
subject to the terms of the Contract Documents which are dated .
In conformance with the Contract Documents for this project, your obligations and guarantees will
continue for the specified time from the following date: .
Sincerely,
OWNER: UCity of Fort Collins
By:
Title:
ATTEST:
By:
Title:
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment
June 2017 00650-1
SECTION 00650
LIEN WAIVER RELEASE
(Contractor)
TO: UCity of Fort Collins, Colorado U
(OWNER)
FROM: UHydro Construction
(CONTRACTOR)
PROJECT: UWTF Replacement
1. The CONTRACTOR acknowledges having received payment, except retainage from the
OWNER for all work, labor, skill and material furnished, delivered and performed by the
CONTRACTOR for the OWNER or for anyone in the construction, design, improvement,
alteration, addition or repair of the above described project.
2. In consideration of such payment and other good and valuable consideration, the receipt and
adequacy of which are hereby acknowledged, the CONTRACTOR voluntarily waives all rights,
claims and liens, including but not limited to, mechanic's liens, Miller Act claims (40 U.S.C.A.
270 a and b), stop notices, equitable liens and labor and material bond rights which the
CONTRACTOR may now or may afterward have, claim or assert for all and any work, labor,
skill or materials furnished, delivered or performed for the construction, design, improvement,
alteration, addition or repair of the above described project, against the OWNER or its officers,
agents, employees or assigns, against any fund of or in the possession or control of the
OWNER, against the project or against all land and the buildings on and appurtenances to the
land improved by the project.
3. The CONTRACTOR affirms that all work, labor and materials, furnished, delivered or performed
to or for the construction, design, improvement, alteration, addition or repair of the project were
furnished, delivered or performed by the CONTRACTOR or its agents, employees, and
servants, or by and through the CONTRACTOR by various Subcontractors or materialmen or
their agents, employees and servants and further affirms the same have been paid in full and
have released in full any and all existing or possible future mechanic's liens or rights or claims
against the project or any funds in the OWNER'S possession or control concerning the project
or against the OWNER or its officers, agents, employees or assigns arising out of the project.
4. The CONTRACTOR agrees to defend and hold harmless the OWNER, the lender, if any, and
the Surety on the project against and from any claim hereinafter made by the CONTRACTOR'S
Subcontractors, materialmen, employees, servants, agents or assigns against the project or
against the OWNER or its officers, employees, agents or assigns arising out of the project for all
loss, damage and costs, including reasonable attorneys fees, incurred as a result of such
claims.
5. The parties acknowledge that the description of the project set forth above constitutes an
adequate description of the property and improvements to which this Lien Waiver Release
pertains. It is further acknowledged that this Lien Waiver Release is for the benefit of and may
be relied upon by the OWNER, the lender, if any, and Surety on any labor and material bonds
for the project.
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment
June 2017 00650-2
Signed this day of , U20
CONTRACTOR
By:
Title:
ATTEST:
Secretary
STATE OF COLORADO )
)ss.
COUNTY OF LARIMER )
Subscribed and sworn to before me this day of , 20 ,
By
Witness my hand and official seal.
My Commission Expires:
Notary Public
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment
June 2017 00651-1
SECTION 00651
LIEN WAIVER RELEASE
(Subcontractor)
TO: UHydro Construction. U (CONTRACTOR)
FROM: (Subcontractor)
PROJECT: UWTF Replacement
1. The Subcontractor acknowledges having received payment, except retainage, from the
CONTRACTOR for all work, labor, skill and material furnished, delivered and performed by the
Subcontractor for the CONTRACTOR or for anyone in the construction, design, improvement,
alteration, addition or repair of the above described project.
2. In consideration of such payment and other good and valuable consideration, the receipt and
adequacy of which are hereby acknowledged, the Subcontractor voluntarily waives all rights, claims
and liens, including but not limited to, mechanic's liens, Miller Act claims (40 U.S.C.A. 270 a and b),
stop notices, equitable liens and labor and material bond rights which the Subcontractor may now or
may afterward have, claim or assert for all and any work, labor, skill or materials furnished, delivered
or performed for the construction, design, improvement, alteration, addition or repair of the above
described project, against the CONTRACTOR or its officers, agents, employees or assigns, against
the project or against all land and the buildings on and appurtenances to the land improved by the
project.
3. The Subcontractor affirms that all work, labor and materials, furnished, delivered or performed to or
for the construction, design, improvement, alteration, addition or repair of the project were furnished,
delivered or performed by the Subcontractor or its' agents, employees, and servants, or by and
through the Subcontractor by various sub-subcontractors or materialmen or their agents, employees
and servants and further affirms the same have been paid in full and have released in full any and
all existing or possible future mechanic's liens or rights or claims against the project or against the
CONTRACTOR or its officers, agents, employees or assigns arising out of the project.
4. The Subcontractor agrees to defend and hold harmless the CONTRACTOR, the lender, if any, and
the Surety on the project against and from any claim hereinafter made by the Subcontractor's sub-
subcontractors, materialmen, employees, servants agents or assigns against the project or against
the CONTRACTOR or OWNER, lender or Surety or their officers, employees, agents or assigns
arising out of the project for all loss, damage and costs, including reasonable attorneys fees,
incurred as a result of such claims.
5. The parties acknowledge that the description of the project set forth above constitutes an adequate
description of the property and improvements to which this Lien Waiver Release pertains. It is
further acknowledged that this Lien Waiver Release is for the benefit of and may be relied upon by
the CONTRACTOR, OWNER, the lender, if any, and Surety on any labor and material bonds for the
project.
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment
June 2017 00651-2
Signed this day of , U20
SUBCONTRACTOR:
By:
Title:
ATTEST:
Secretary
STATE OF COLORADO )
)ss.
COUNTY OF LARIMER )
Subscribed and sworn to before me this day ofU , 20 U,
By
Witness my hand and official seal.
My Commission Expires:
Notary Public
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Consent of Surety
June 2017 00660-1
SECTION 00660
CONSENT OF SURETY
TO: UCity of Fort Collins, Colorado
(hereinafter referred to as the "OWNER")
CONTRACTOR: UHydro Construction
PROJECT: UWTF Replacement
CONTRACT DATE:
In accordance with the provisions of the Contract between the OWNER and the CONTRACTOR as
indicated above, for
bond of (Surety)
hereby approves of the Final Payment to the CONTRACTOR, and agrees that Final Payment to the
CONTRACTOR shall not relieve the Surety Company of any of its obligations to the OWNER, as set
forth in the said Surety Company's Bond.
IN WITNESS WHEREOF, the Surety Company has hereunto set its hand this day of
, U20 U.
(Surety Company)
By:
ATTACH: Power of Attorney and Certificate of Authority of Attorney(s)-in-Fact.
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Contractor Application for Tax Exemption Certificate
June 2017 00670
DR 0172 (12/98)
COLORADO DEPARTMENT OF REVENUE
DENVER CO 80261
(303) 232-2416
DO NOT WRITE IN THIS SPACE
The exemption certificate for which you are applying must be used only for the purpose of purchasing construction and building
materials for the exempt project described below. This exemption does not include or apply to the purchase or rental of equipment,
supplies, and materials which are purchased, rented, or consumed by the contractor and which do not become part of the structure,
highway, road, street, or other public works owned and used by the exempt organization.
Any unauthorized use of the exemption certificate will result in revocation of your exemption certificate and other penalties provided by
law.
A separate certificate is required for each contract.
Subcontractors will not be issued Certificates of Exemption by the Department of Revenue. It is the responsibility of the prime
contractor to issue certificates to each of the subcontractors. (See reverse side).
FAILURE TO ACCURATELY COMPLETE ALL BOXES WILL CAUSE THE APPLICATION TO BE DENIED.
0BRegistration/Account No. (to be assigned by DOR)
89 -
1BPeriod
2B0170-750 (999) $0.00
3BCONTRACTOR INFORMATION
Trade name/DBA: Owner, partner, or corporate name:
Mailing address (City, State, Zip): Contact Person
E-Mail address: Federal Employer’s Identification Number: Bid amount for your contract:
$
Fax Number:
( )
Business telephone number:
( )
Colorado withholding tax account number:
4BEXEMPTION INFORMATION Copies of contract or agreement pages (1) identifying the contracting parties
and (2) containing signatures of contracting parties must be attached.
Name of exempt organization (as shown on contract):
Exempt organization’s number:
98 -
Address of exempt organization (City, State, Zip):
Principal contact at exempt organization: Principal contact’s telephone number:
Physical location of project site (give actual address when applicable and Cities and/or County (ies) where project is located)
Scheduled
construction start date:
Month Day Year Estimated
completion date:
Month Day Year
I declare under penalty of perjury in the second degree that the statements made in this application are true and
complete to the best of my knowledge.
Signature of owner, partner or corporate officer: Title of corporate officer: Date:
5BDO NOT WRITE BELOW THIS LINE
CONTRACTOR APPLICATION
FOR
EXEMPTION CERTIFICATE
Pursuant to Statute
Section 39-26.114(1)(a)(XIX)
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22 6
24” Poudre Pipeline Rehab Assessment Contractor Application for Tax Exemption Certificate
June 2017 00670
Special Notice
Contractors who have completed this application in the past, please note the following changes in procedure:
The Department will no longer issue individual Certificates of exemption to subcontractors. Only prime contrac-
tors will receive a Contractor’s Exemption Certificate on exempt projects.
Upon receipt of the Certificate, the prime contractor should make a copy for each subcontractor involved in the
project and complete it by filling in the subcontractor’s name and address and signing it.
The original Certificate should always be retained by the prime contractor. Copies of all Certificates that the
prime contractor issued to subcontractors should be kept at the prime contractor’s place of business for a
minimum of three years and be available for inspection in the event of an audit.
Once an 89# has been assigned to you, please use the next five numbers following it for any applications
submitted for future projects. This should be your permanent number. For instance, if you were assigned 89-
12345-0001, every application submitted thereafter should contain 89-12345 on the application. The succeed-
ing numbers will be issued by the Department of Revenue. DO NOT enter what you believe to be the next in
sequence as this may delay processing of your application.
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Supplementary Conditions
June 2017
00800-1
SECTION 00800
SUPPLEMENTARY CONDITIONS
Conditions of the Contract
These Supplementary Conditions amend or supplement the General Conditions of the Construction
Contract (EJCDC General Conditions 1910-8, 1990 edition with City of Fort Collins modifications
(rev. 9/99)) and other provisions of the Contract Documents executed under the RFP #8286,
Construction Contractor for Projects at the Water and Wastewater Treatment Facilities Master
Contract dated June 20, 2016.
All work performed under this work order shall be conducted in accordance with the technical
specifications, U2016 City of Fort Collins Technical Specifications, dated March 1, 2016.
SC-1 DEFINITIONS
USC-1.38U. Add the following language to the conclusion of paragraph 1.38 of the General
Conditions:
1.38. Substantial Completion. … Substantial Completion is further defined as that
degree of completion of the operating facilities or systems of the Project defined in the Work
Order sufficient to provide the OWNER the full time, uninterrupted, continuous, beneficial
operation of the modifications, and all inspections required have been completed and
identified deficiencies corrected.
USC-1.43.AU Add the following new paragraph immediately after paragraph 1.43 of the General
Conditions:
1.43.A. Work Order – A written document executed by OWNER and CONTRACTOR that
provides for the construction of a portion of the Work, pursuant to the Agreement and all as
required by the Contract Documents, and that becomes a Contract Document when
executed.
SC-2 PRELIMINARY MATTERS
USC-2.8.U Delete paragraph 2.8 of the General Conditions entirely and replace it with the following
paragraph:
2.8 Preconstruction Conference. Within ten days after the Contract Times for a Work
Order start to run, but before any Work at the site is started, a conference attended by
CONTRACTOR, ENGINEER and others as appropriate will be held to establish a working
relationship among the parties as to the Work and to discuss the schedules referred to in
paragraph 2.6, procedures for handling Shop Drawing and other submittals, processing
Applications for Payment, and maintaining required records.
USC-2.10,U Add the following new paragraph immediately after paragraph 2.9 of the General
Conditions:
2.10 Work Order Required for All Work. References to the Agreement in this Article 2
and in the General and Supplementary Conditions and Contract Documents
notwithstanding, no Work shall be initiated or performed until CONTRACTOR has received a
signed and executed Work Order, incorporating the Notice to Proceed, from OWNER; and
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Supplementary Conditions
June 2017
00800-2
no provision of the Article 2 or of the General and Supplementary Conditions and Contract
Documents shall permit or require any action of CONTRACTOR in the absence of a signed
and executed Work Order. All provisions of this Article 2 and of the General and
Supplementary Conditions and Contract Documents referencing the Agreement or other
parts of the Contract Documents, or permitting or requiring any action of CONTRACTOR,
shall be read as referencing and, as appropriate, requiring a signed and executed Work
Order.
SC-4 AVAILABILITY OF LANDS; SUBSURFACE AND PHYSICAL CONDITIONS;
REFERENCE POINTS
USC-4.2.1.2.U Add the following new paragraph immediately following paragraph 4.2.1.2 of the
General Conditions:
4.2.1.2.1 No drawing of physical conditions in or relating to existing surface or
subsurface structures (except Underground Facilities referred to in Paragraph 4.3) which are
at or contiguous to the site have been utilized by the Engineer in preparation of the Contract
Documents, except the following:
1. None
Contractor may rely upon the accuracy of the technical data contained in the documents, but
not upon non-technical data, interpretations or opinions contained therein or upon the
completeness of any information in the report.
SC-5 BONDS AND INSURANCE
USC-5.4.7.U Include the following parties or entities as additional Insureds, as provided in
paragraph 5.4.7 of the General Conditions:
5.4.7.1.The City of Fort Collins, Colorado, 4316 LaPorte Avenue, Fort Collins, Colorado
80522
USC-5.4.8.1.U Add the following new paragraph immediately following paragraph 5.4.8 of the
General Conditions:
5.4.8.1.1. Limits of Liability. The limits of liability for the insurance required by the paragraph
numbers of the General Conditions listed below are as follows:
5.4.1 and 5.4.2
Coverage A - Statutory Limits
Coverage B - $100,000 / $100,000 / $500,000.
5.4.3 and 5.4.5 Commercial General Liability policy will have limits of $1,000,000 combined
single limits (CSL). This policy will include coverage for Explosion, Collapse, and
Underground coverage unless waived by the OWNER.
5.4.6: The Comprehensive Automobile Liability Insurance policy will have limits of $1,000,000
combined single limits (CSL).
5.4.9. This policy will include completed operations coverage / product liability coverage with
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Supplementary Conditions
June 2017
00800-3
limits of $1,000,000 combined single limits (CSL). This policy shall also include an Umbrella
Excess Liability as follows: General liability and automobile liability insurance in an amount not
less than $1,000,000 per occurrence in excess of the above stated primary limits.
SC-6 CONTRACTOR’S RESPONSIBILITIES
USC-6.14.3.U Add the following new paragraph immediately following paragraph 6.14.2 of the
General Conditions:
6.14.3.1. The following Laws or Regulations are included in the Contract Documents
as mandated by statute or for the convenience of the CONTRACTOR. Other Laws
and Regulations apply which are not included herein, and are within the
CONTRACTOR’S duty and responsibility for compliance thereto:
6.14.3.2. Notice to owners of Underground Facilities is required prior to excavations in
the vicinity of such facilities.
6.14.3.2. Unless otherwise decided by reason of the amount of the Contract Price
involved, or other good reason, before or at the time that the contract is awarded to a
corporation outside the State of Colorado, such corporation must carry out the
proper procedure to become authorized to do business in the State of Colorado,
designate a place of business therein, and appoint an agent for service of process.
Such corporation must furnish the OWNER with a certificate from the Secretary of
State of Colorado, has been issued by its office and there shall also be procured
from the Colorado Secretary of State a photostatic or certified copy of the designated
place of business and appointment of agent for service of process, or a letter from
the Colorado Secretary of State that such designation of place of business and
agent for service of process have been made.
6.14.3.3 The CONTRACTOR must conform to the rules and regulations of the
Industrial Commission of Colorado. Particular reference is made to rules and
regulations governing excavation Work adopted by the Industrial Commission of
Colorado.
SC-11 CHANGE OF CONTRACT PRICE
USC-11.6.2.7.U Add the following new paragraph to paragraph 11.6.2 of the General Conditions.
11.6.2.7. Cost of the Work. Allowances for profit, overhead and mark-up prescribed
by Article 4 of the Agreement shall be used in lieu of any CONTRACTOR’S fee,
overhead, profit or mark-up allowances as prescribed in paragraphs 11.6.2.1,
11.6.2.2 and 11.6.2.3.
SC-12 CHANGE OF CONTRACT TIMES
USC-12.3.U Add the following language to the end of paragraph 12.3 of the General Conditions.
12.3 … Lost days due to abnormal weather conditions will be allocated as required.
SC-14 PAYMENTS TO CONTRACTOR AND COMPLETION
USC- 14.1.U Add the following language to the end of paragraph 14.1 of the General Conditions.
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Supplementary Conditions
June 2017
00800-4
14.1. Schedule of values … Progress payments on the negotiated not-to-exceed fee
shall be based on a time and materials basis.
END OF SECTION
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Addenda, Modifications, & Payment
June 2017 00900-1 Table of Contents
SECTION 00900
ADDENDA, MODIFICATIONS, AND PAYMENT
00950 Contract Change Order
00960 Application for Payment
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Contract Change Order
June 2017 00950-1
SECTION 00950
CHANGE ORDER NO.
PROJECT TITLE: WTF Replacement
CONTRACTOR: Hydro Construction
PROJECT NUMBER:
DESCRIPTION:
1. Reason for change:
2. Description of Change:
3. Change in Contract Cost:
4. Change in Contract Time:
ORIGINAL CONTRACT COST $ 0.00
TOTAL APPROVED CHANGE ORDERS 0.00
TOTAL PENDING CHANGE ORDERS 0.00
TOTAL THIS CHANGE ORDER U0.00U
TOTAL % OF THIS CHANGE ORDER 0%
TOTAL C.O.% OF ORIGINAL CONTRACT 0%
ADJUSTED CONTRACT COST $ 0.00
U(Assuming all change orders approved)
ACCEPTED BY: DATE:
Contractor's Representative
ACCEPTED BY: DATE:
Special Projects Manager
REVIEWED BY: DATE:
Senior Engineer
APPROVED BY: DATE:
Water Production Manager
APPROVED BY: DATE:
Purchasing Agent over $60,000
cc: Project File
Contractor
Purchasing
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
Page 1 of 4
PROJECT: 24 inch Poudre Pipeline Rehabilitation Assessment, Phase 1 - Procure
OWNER: City of Fort Collins Utilities CONTRACTOR: Hydro Construction APPLICATION NUMBER:
700 Wood Street APPLICATION DATE:
Fort Collins, CO 80522 PERIOD BEGINNING:
PERIOD ENDING:
ENGINEERS:
PROJECT NUMBER:
CHANGE ORDERS: PAY APPLICATION:
NUMBER DATE AMOUNT Application is made for Payment as shown below in connection with the Contract.
The present status of the account for this Contract is as follows.
Original Contract Amount:
Net Change by Change Order: $ -
Revised Current Contract Amount: $0.00
Total Work Completed to Date:
Total Change Order Work to Date:
Total Stored to Date:
Total Completed and Stored Materials to Date: $0.00
Less Previous Payments:
Amount due this Pay Application (before retainage): $0.00
Less Retainage: $ -
Net Change by Change Order: $ - AMOUNT DUE THIS APPLICATION: $0.00
Change Order %: 0.00%
CERTIFICATION:
The undersigned CONTRACTOR certifies that all obligations of CONTRACTOR incurred in connection with
the WORK have been satisfied as required in paragraph 14.3 of the General Conditions of the Contract.
The above Amount Due this Application is requested by the CONTRACTOR's Project Manager.
Date: By:
Payment of the above Amount Due This Application has been reviewed by the OWNER'S Project Manager.
Date: By:
Brian Mulligan, Special Projects Manager
Payment of the above Amount Due This Application is approved by the OWNER.
Date: By:
Owen L. Randall, Chief Engineer
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
Page 2 of 4
24 inch Poudre Pipeline Rehabilitation Assessment, Phase 1 - Procure
Pay Request
Period Ending:
Contract Summary Cost Percent
Item # Description Quantity UOM Unit Price Total Quantity Total Quantity Total Quantity Total Remaining Complete
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
18a
19
20
21
22
23
24
25
25a
26
27
28
Combined:
Total Contract Amount
Total This Period $ -
Previous Billings
Total Completed to Date
Balance Remaining $ -
Percent Complete
Crosscheck $ - $ -
Contract Summary:
Original Contract Amount
Change Orders To Date (see attached)
Adjusted Contract Amount
Total Completed to Date
Total Materials Remaining @ Site
Total Change Order Work to Date (see attached)
Value of Work in Place
Percent Complete Including Stored Materials
Less Retention @ 10% up to 50% complete, 5% beyond 50% of Adjusted Contract
Total to Date Less Retention
Less Previous Billings
Total Due
This Period Previous Total to Date
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24 inch Poudre Pipeline Rehabilitation Assessment, Phase 1 - Procure 5/8/2017
Page 3 of 4
Change Change Order Summary This Period Previous Total to Date Cost Percent
Order # Description Quantity UOM Unit Price Total Amount Quantity Amount Quantity Amount Quantity Amount Remaining Complete
1
Total Amount of Change Orders $ -
Total This Period $ -
Previous Billings $ -
Total Completed to Date $ -
Balance Remaining $ -
Percent Complete #DIV/0!
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24 inch Poudre Pipeline Rehabilitation Assessment, Phase 1 - Procure 5/8/2017
Page 4 of 4
Bid Vendor Invoice Invoiced Item Amount This Month Previous Total Placed Previous Left on Hand
Item Pay Request # Description Invoice # Date Quantity UOM Unit Price Total Amount Quantity Amount Quantity Amount To Date Quantity Amount Quantity Amount Quantity Amount
Pipe Materials Claimed This Period:
Item Reference Date
- lf - - - - - - - - - - - -
- lf - - - - - - - - - - - -
- lf - - - - - - - - - - - -
- lf - - - - - - - - - - - -
- lf - - - - - - - - - - - -
- lf - - - - - - - - - - - -
- lf - - - - - - - - - - - -
- lf - - - - - - - - - - - -
- lf - - - - - - - - - - - -
- lf - - - - - - - - - - - -
- lf - - - - - - - - - - - -
- lf - - - - - - - - - - - -
- lf - - - - - - - - - - - -
Subtotal - - - - - - - - - -
Total Materials Procured as Stored Materials $ - $ - $ - $ -
Materials Installed This Period $ -
Materials Installed Previous $ -
Total Materials Remaining @ Site $ -
Place This Month
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Division 1 Table of Contents
June 2017 Division 1 TOC - 1
UDIVISION 1 - GENERAL REQUIREMENTS
SECTION 01110 SUMMARY OF WORK
SECTION 01140 CONTRACTOR’S USE OF PREMISES
SECTION 01180 UTILITY SOURCES
SECTION 01270 MEASUREMENT AND PAYMENT
SECTION 01310 PROJECT MEETINGS
SECTION 01320 CONSTRUCTION SCHEDULES
SECTION 01330 SUBMITTALS
SECTION 01425 STANDARD REFERENCES
SECTION 01450 MATERIALS TESTING\
SECTION 01535 TEMPORARY UTILITY SUPPORT
SECTION 01635 SUBSTITUTIONS AND PRODUCT OPTIONS
SECTION 01650 MATERIAL DELIVERY, STORAGE, AND HANDLING
SECTION 01710 SITE CONDITIONS
SECTION 01715 TREE, LANDSCAPE, VEGETATION, AND WETLAND PROTECTION
SECTION 01720 FIELD ENGINEERING AND SURVEYING
SECTION 01745 ENVIRONMENTAL CONTROLS
SECTION 01780 CONTRACT CLOSE-OUT
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Summary of Work
June 2017 01110-1
SECTION 01110
SUMMARY OF WORK
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Site location and description.
B. Project description.
C. Scope of work and work sequence.
D. Underground utilities.
1.02 SITE LOCATION AND DESCRIPTION
A. Poudre Canyon – Approxmiately 2 miles West of the intersection of Hwy 14 and Hwy 287 to
the Gateway Park (approximately 3.5 miles northwest in the Poudre Canyon.
The work is located in the Poudre River Canyon, approximately 4 miles northwest of the mouth of the
canyon. The nearest major intersection is Hwy 287 and Hwy 14. The project involves the
procurement of critical path equipment consisting of pipe, pipe closure materials, couplings, and inner
seals. Services will also include preconstruction efforst in the form of design construction, scheduling,
and permitting.
Construction Schedule is dependent on WTF operation and water rights associated with the different
pipelines and source of supplies.
1.03 PROJECT DESCRIPTION
A. General Conditions - Provide:
1. Mobilization & Field Overhead
2. Traffic Control (By CoFC)
B. Stormwater Management - Provide:
1. Erosion & Settlement Control Allowance
2. SWMP Inspections
1.04 WORK SEQUENCE
A. The Work Sequence is to be submitted as part of the construction schedule required in
Section 01320 (Construction Schedules) and Section 01330 (Submittals). Construction
of the project shall begin within seven (7) calendar days of the date of Notice to
Proceed. Please see the City of Fort Collins Master Specifications for these and other
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Summary of Work
June 2017 01110-2
Division section requirements, including Division 1 – General Requirements and Division
2 - Site Work.
1.05 UNDERGROUND UTILITIES
A. It shall be the responsibility of the CONTRACTOR to verify the existence and location of
all underground utilities along the route of the work and to coordinate the construction
schedules with these utility owners. See Section 01180 for a list of Utility Sources.
B. Known utilities and structures adjacent to or encountered in the work are shown on the
Drawings. The locations shown are taken from existing records and the best
information available from existing utility plans, however, there may be some
discrepancies and omissions in the locations and quantities of utilities and structures
shown. Those shown are for the convenience of the CONTRACTOR only, and no
responsibility is assumed by either the OWNER or the ENGINEER for their accuracy or
completeness.
C. The CONTRACTOR shall field verify all utilities and coordinate construction with utility
owners prior to starting construction. The CONTRACTOR shall be responsible for
protecting utilities during construction and scheduling utility adjustments to eliminate
conflict with progress of the work. Any damage to existing utilities shall be repaired at
no additional cost to the OWNER.
D. The CONTRACTOR shall notify the ENGINEER immediately of any field condition not
consistent with the contract documents.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
END OF SECTION
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Contractor’s Use of Premises
June 2017 01140-1
SECTION 01140
CONTRACTOR’S USE OF PREMISES
PART 1 GENERAL
1.01 SECTION INCLUDES
A. The CONTRACTOR may use the OWNER’s property designated within the construction
limits shown on the Drawings for equipment and materials as long as he confines his
operations to those permitted by local laws, ordinance and permits and meets the
following requirements:
1. Do not unreasonably encumber site with materials or equipment.
2. Assume full responsibility for protection and safekeeping of products stored on
premised.
3. Move any stored products which interfere with operations of the OWNER.
4. Obtain and pay for use of additional storage or work areas needed for
operations.
1.02 LIMITS OF CONSTRUCTION
A. The CONTRACTOR must maintain all construction activities within the OWNER’s
property and/or construction easements and limits of the project, or other stated areas,
unless permits and/or written permission are obtained by the CONTRACTOR, from
appropriate authorities or private property owners, outside of these areas. Contractor
shall fence all easements and work areas. Fences shall be substantial in size and type
to prevent injury to persons and animals and prevent domestic animals (i.e. horses,
cattle, livestock, etc.) from entering in or across the construction site. The temporary
permits must be secured and paid for by the CONTRACTOR at no extra cost to the
OWNER. Any temporary permits secured must be in writing and a copy of same
provided to the ENGINEER.
1.03 SECURITY
A. The CONTRACTOR shall at all times be responsible for the security of his facilities and
equipment. The OWNER will not take responsibility for missing or damaged equipment,
tools, or personal belongings of the CONTRACTOR.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
END OF SECTION
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Utility Sources
June 2017 01180-1
SECTION 01180
UTILITY SOURCES
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Names and telephone numbers of affected agencies and utilities in the area are listed
below for the CONTRACTOR’s convenience. The CONTRACTOR assumes all
responsibility of contacting these agencies and verification of telephone numbers.
1. Water Fort Collins Utilities (970) 221-6700
2. Sanitary Sewer Fort Collins Utilities (970) 221-6700
3. Stormwater Fort Collins Utilities (970) 221-6700
4. Electrical Fort Collins Utilities (970) 221-6700
6. Engineering City of Fort Collins (970) 221-6605
7. Traffic City of Fort Collins (970) 221-6615
8. Gas Xcel Energy (800) 895-2999
9. Telephone Qwest (800) 573-1311
10. Cable TV Comcast (800) 266-2278
11. One-Call Utility Locates (800) 922-1987
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
END OF SECTION
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Measurement and Payment
June 2017 01270 -1
SECTION 01270
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.01 SECTION INCLUDES
A. The work performed under this Agreement shall be paid for on a Time and Materials
basis. The quantities provided on the Bid Schedule are only estimates of the actual
quantities of the work to be performed, and are only included for purposes of making the
award and establishing a basis for estimating the probable cost of the Work. The actual
amounts of work performed and materials furnished may differ from the estimated
quantities. The basis of payment for work and materials bid as time and materials will
be the actual amount of approved work done and materials furnished. The
CONTRACTOR agrees that he will make no claim for damages, anticipated profits, or
otherwise on account of any difference between the amounts of work actually performed
and materials actually furnished and the estimated amount for bid items.
Payment shall be made only for those items included in the Bid Schedule. All costs
incurred shall comply with the provisions of these Specifications and shall be included in
the price bid for the associated items in the Bid Schedule. Except as may be otherwise
stipulated, the OWNER will furnish no material, labor or equipment. The quantity of
work, which will be considered for payment, is the actual cost of the work plus
CONTRACTOR’S markups in accordance with all relative Specifications and
Agreements.
END OF SECTION
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Project Meetings
June 2017 01310-1
SECTION 01310
PROJECT MEETINGS
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Pre-Construction Conference: A Pre-Construction Conference will be held after Notice
of Award and before the Notice to Proceed, the date, time and location will be
determined after Notice of Award.
The conference shall be attended by:
1. CONTRACTOR and CONTRACTOR’s Superintendent
2. CONTRACTOR’s Surveyor and Subcontractors
2. ENGINEER
3. OWNER
4. Others as requested by the CONTRACTOR, OWNER, or ENGINEER.
Unless previously submitted to the OWNER, the CONTRACTOR shall bring to the
conference a tentative schedule of the construction project, include in the schedule shop
drawings and other submittals.
The purpose of the conference is to designate responsible personnel and establish a
working relationship. Matters requiring coordination will be discussed and procedures
for handling such matters established. The agenda will include:
1. CONTRACTOR’s tentative Schedule
2. Permit applications and submittals, including 402 Permit, SWMP, and Traffic
Control Plan
3. Transmittal, review and distribution of CONTRACTOR’s submittals
4. Processing applications for payment
5. Maintaining record documents
6. Critical work sequencing
7. Field decision and change orders
8. Use of premises, office and storage areas, staging area, security, housekeeping,
and OWNER’s needs
9. CONTRACTOR’s assignment of safety and first aid
B. Construction Progress Meetings: Progress meetings will be conducted weekly or at
some other frequency, if approved by the OWNER, ENGINEER and CONTRACTOR.
These meetings shall be attended by the OWNER, the ENGINEER, the
CONTRACTOR’s representative and any others invited by these people.
The meeting will be conducted by the ENGINEER and the ENGINEER will arrange for
keeping the minutes and distributing the minutes to all persons in attendance.
The agenda of these project meetings will include construction progress, the status of
submittal reviews, status of information requests, critical work sequencing, review of
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Project Meetings
June 2017 01310-2
strategies for connections into existing facilities, status of field orders and change orders,
and any general business.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
END OF SECTION
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Construction Schedules
June 2017 01320-1
SECTION 01320
CONSTRUCTION SCHEDULES
1.01 SECTION INCLUDES
A. Prepare detailed schedule of all construction operations and procurements to be reviewed
by parties attending the preconstruction conference.
Schedule shall be approved by the OWNER and ENGINEER prior to Notice to Proceed.
1.02 FORMAT AND SUBMISSIONS
A. Prepare construction and procurement schedules in a graphic format suitable for displaying
scheduled and actual progress.
B. Submit four (4) copies of each schedule to the OWNER and ENGINEER for review.
The ENGINEER will return one copy to the CONTRACTOR with revisions suggested or
necessary for coordination of the Work with the needs of the OWNER or others.
1.03 CONTENT
A. Construction Progress Schedule
1. Show the complete work sequence of construction by activity and location.
2. Show the dates for the beginning and completion of major task items. At a minimum,
show the following items for 2015 Cathodic Protection Work Along the Anheuser
Busch water line:
• Landscaping
• Miscellaneous Work Items & Allowances
Show projected percentage of completion for each item as of the first day of the
month.
B. Report of delivery of equipment and materials.
1. Show delivery status of critical and major items of equipment and materials.
2. Include a schedule which includes the critical path for Shop Drawings, tests, and
other submittal requirements for equipment and materials.
1.04 PROGRESS REVISIONS
A. Submit revised schedules and reports when changes are foreseen, when requested by
OWNER or ENGINEER, and with each application for progress payment.
B. Show changes occurring since previous submission.
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Construction Schedules
June 2017 01320-2
1. Actual progress of each item to date.
2. Revised projections of progress and completion.
1.05 OWNER'S RESPONSIBILITY
A. OWNER's review is only for the purpose of checking conformity with the Contract
Documents and assisting CONTRACTOR in coordinating the Work with the needs of the
Project.
B. It is not to be construed as relieving CONTRACTOR from any responsibility to determine the
means, methods, techniques, sequences and procedures of construction as provided in the
General Conditions.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
END OF SECTION
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Submittals
June 2017 01330-1
SECTION 01330
SUBMITTALS
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Requirements:
1. Where required by the Specifications, the CONTRACTOR shall submit
descriptive information that will enable the ENGINEER to determine whether the
CONTRACTOR’s proposed materials, equipment, methods of work are in
general conformance to the design concept and in accordance with the Drawings
and Specifications. The information submitted may consist of drawings,
specifications, descriptive data, certificates, samples, test results, product data,
and such other information, all as specifically required in the Specifications. In
some instances, specified submittal information describes some, but not all
features of the material, equipment, or method of work.
2. The CONTRACTOR shall be responsible for the accuracy and completeness of
the information contained in each submittal and shall assure that the material,
equipment, or method of work shall be as described in the submittal. The
CONTRACTOR shall verify that all features of all products conform to the
requirements of the Drawings and Specifications. The CONTRACTOR shall
ensure that there is no conflict with other submittals and notify the ENGINEER in
each case where its submittal may affect the work of another CONTRACTOR or
the OWNER. The CONTRACTOR shall ensure coordination of submittals
among the related crafts and subcontractors.
3. Submittals will be reviewed for overall design intent and returned to
CONTRACTOR with action to be indicated by the ENGINEER. It shall be the
CONTRACTOR’s responsibility to assure that previously accepted documents
are destroyed when they are superseded by a resubmittal as such.
4. It shall be the CONTRACTOR’s responsibility to ensure that required items are
corrected and resubmitted. Any work done before approval shall be at the
CONTRACTOR’s own risk.
B. Submittal Procedure:
1. Unless a different number is called for in the individual sections, six (6) copies of
each submittal and sample are required, four (4) of which will be retained by the
ENGINEER. The CONTRACTOR shall receive two (2) copies in return. Faxed
submittals will not be accepted. As an alternate, submittals may be posted on a
“share site” such as Sharepoint, for review by the ENGINEER or OWNER. All
other requirements of this section shall apply.
2. Submittals that are related to or affect each other shall be forwarded
simultaneously as a package to facilitate coordinated review. Uncoordinated
submittals will be rejected.
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Submittals
June 2017 01330-2
3. If the items or system proposed are acceptable but the major part of the
individual drawings or documents are incomplete or require revision, the
submittal will be returned with requirements for completion.
4. The right is reserved for the ENGINEER to require submittals in addition to those
called for in individual sections.
5. Submittals regarding material and equipment shall be submitted directly to the
ENGINEER and will be accompanied by a transmittal form. A separate form
shall be used for each specific item, class of material, equipment, and items
specified in separate discrete sections for which the submittal is required.
Submittals for various items shall be made with a single form when the items
taken together constitute a manufacturer’s package or are so functionally related
that expediency indicates checking or review of the group or package as a whole.
6. A unique number, sequentially assigned, shall be noted on the transmittal form
accompanying each item submitted. Original submittal numbers shall have the
following format: “XXX-Y;” where “XXX” is the originally assigned submittal
number and “Y” is a sequential letter assigned for resubmittals (i.e., A, B, or C
being the first, second and third resubmittals, respectively). Submittal 25B, for
example, is the second resubmittal of Submittal 25.
7. If the CONTRACTOR proposes to provide material, equipment, or method of
work that deviates from the Contract Documents, it shall indicate so under
“deviations” on the transmittal form accompanying the submittal copies.
8. Submittals that do not have all the information required to be submitted, including
deviations, are not acceptable and will be returned without review.
C. Review Procedure:
1. Submittals are specified for those features and characteristics of materials,
equipment, and methods of operation that can be selected based on the
CONTRACTOR’s judgment of their conformance to the requirements of the
Drawing and Specifications. Other features and characteristics are specified in a
matter that enables the CONTRACTOR to determine acceptable options without
submittals. The review procedure is based on the CONTRACTOR’s guarantee
that all features and characteristics not requiring submittals conform to the
Drawings and Specifications. Review shall not extend to means, methods,
techniques, sequences, or procedures of construction or to verifying quantities,
dimensions, weights or gages, or fabrication processes (except where
specifically indicated or required by the Specifications) of separate items, and as
such, will not indicate approval of the assembly in which the item functions.
2. Unless otherwise specified, within twenty-one (21) calendar days after receipt of
the submittal, the ENGINEER will review the submittal and return copies. The
returned submittal will indicate one of the following actions:
a. If the review indicates that the material, equipment, or work method
complies with the Specifications, submittal copies will be marked “NO
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Submittals
June 2017 01330-3
EXCEPTIONS TAKEN”. In this event, the CONTRACTOR may begin to
implement the work method or incorporate the material or equipment
covered by the submittal.
b. If the review indicates limited corrections are required, copies will be
marked “FURNISH AS NOTED”. The CONTRACTOR may begin
implementing the work method or incorporating the material and
equipment covered by the submittal in accordance with the noted
corrections. Where submittal information will be incorporated in
Operation and Maintenance data, a corrected copy shall be provided.
c. If the review indicates that the submittal is insufficient or contains
incorrect data, copies will be marked “REVISE AND RESUBMIT”. Except
at its own risk, the CONTRACTOR shall not undertake work covered by
this submittal until it has been revised, resubmitted and returned marked
either “NO EXCEPTIONS TAKEN” or “FURNISH AS NOTED”.
d. If the review indicates that the material, equipment, or work method do
not comply with the Specifications, copies of the submittal will be marked
“REJECTED”. Submittals with deviations that have not been identified
clearly may be rejected. Except at its own risk, the CONTRACTOR shall
not undertake the work covered by such submittals until a new submittal
is made and returned marked either ”NO EXCEPTIONS TAKEN” or
“FURNISH AS NOTED”.
D. Drawing:
1. The term “shop drawings” includes drawings, diagrams, layouts, schematic,
descriptive literature, illustrations schedules performance and test data, and
similar materials furnished by CONTRACTOR to explain in detail specific
portions of the work required by the Contract.
2. CONTRACTOR shall coordinate all such drawings, and review them for legibility,
accuracy, completeness and compliance with contract requirements and shall
indicate this approval thereon as evidence of such coordination and review.
Shop drawing submitted to the ENGINEER without evidence of CONTRACTOR’s
approval will be returned for resubmission.
3. Shop drawing shall be clearly identified with the name and project number of this
contract, and references to applicable specification paragraphs and contract
drawings. When catalog pages are submitted, applicable items shall be clearly
identified.
4. CONTRACTOR shall stamp his approval on shop drawings prior to submission to
the ENGINEER as indication of his checking and verification of dimensions and
coordination with interrelated items. Stamp shall read:
“(CONTRACTOR’s Name) represents that we have determined and
verified all field dimensions and measurements, field construction criteria,
materials, catalog numbers and similar data, and that we have checked
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Submittals
June 2017 01330-4
with the requirements of the Specifications and Drawings, the Contract
Documents, and General Conditions”.
Marks on drawings by CONTRACTOR shall not be in red. Any marks by
CONTRACTOR shall be duplicated on all copies submitted.
5. If shop drawings show variations from contract requirements, CONTRACTOR
shall describe such variations in writing, separate from the drawings, at time of
submission. All such variations must be approved by the ENGINEER. If
ENGINEER approves any such variations, he shall issue an appropriate contract
modification, except that, if the variation is minor and does not involve a change
in price or in time of performance, a modification need not be issued.
6. Should the CONTRACTOR propose any item on his shop drawings or
incorporate an item into the work, and that item should subsequently prove to be
defective or otherwise unsatisfactory, (regardless of the ENGINEER’s preliminary
review), the CONTRACTOR shall, at his own expense, replace the item with
another item that will perform satisfactorily.
E. Certificates:
For those items called for in individual sections, furnish six (6) certificates of compliance
from manufacturers or suppliers certifying that materials or equipment being furnished
under the Contract comply with the requirements of these Specifications.
F. Samples:
Samples shall be sufficient in size to clearly illustrate functional characteristics and full
range of color, texture, and pattern.
G. Effect of Review of CONTRACTOR’s Submittals:
Review of drawings, data, methods of work, or information regarding materials or
equipment the CONTRACTOR proposes to provide, shall not relieve the contractor of its
responsibility for errors therein and shall not be regarded as an assumption of risks or
liability by the ENGINEER or the OWNER, or by any officer or employee thereof, and the
CONTRACTOR shall have no claim under the Contract on account of the failure or
partial failure, of the method of work, material, or equipment so reviewed. A mark of “NO
EXCEPTIONS TAKEN” or “FURNISH AS NOTED” shall mean that the OWNER has no
objection to the CONTRACTOR, upon its own responsibility, using the plan or method of
work proposed, or providing the materials or equipment proposed.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
END OF SECTION
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Standard References
June 2017 01425-1
SECTION 01425
STANDARD REFERENCES
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Reference to standards, specifications, manuals, or codes of any technical society,
organization, or association, or to the laws or regulations of any governmental authority,
whether such reference be specific or by implication, shall mean the latest standard
specification, manual, code, or laws or regulations in effect at the time of opening of
Bids, except as may be otherwise specifically stated. However, no provision of any
referenced standard, specifications manual or code (whether or not specially
incorporated by reference in the Contact Documents) shall be effective to change the
duties and responsibilities of OWNER, CONTRACTOR, or ENGINEER, or any of their
consultants, agents or employees from those set forth in the Contract Documents, nor
shall it be effective to assign to ENGINEER, or any of ENGINEER’s Consultants, agents,
or employees, any duty or authority to supervise or direct the furnishing or performance
of the Work.
Whenever used in the Contract Documents, the following abbreviations will have the
meanings listed:
AASHTO American Association of State Highway and Transportation Officials
444 North Capital Street, N.W., Suite 225
Washington, DC 20001
ACI American Concrete Institute
P. O. Box 19150
Detroit, MI
ACPA American Concrete Pipe Association
AISC American Iron and Steel Institute
150 East 42nd Street
New York, NY 10017
AISI American Iron and Steel Institute
150 East 42nd Street
New York, NY 10017
ANSI American National Standards Institute, Inc.
1430 Broadway
New York, NY 10017
AREMA American Railway Engineering and Maintenance-of-Way Association
8201 Corporate Drive, Suite 1125
Landover, MD 20785
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Standard References
June 2017 01425-2
ASCE American Society of Civil Engineers
345 East 47th Street
New York, NY 10017
ASTM American Society of Testing and Materials
1916 Race Street
Philadelphia, PA 19103
ATSSA American Traffic Safety Services Association
BOCA Building Officials and Code Administrators
17926 Halstead
Homewood, IL 60430
CCA Colorado Contractors Association
CISPI Cast Iron Soil Pipe Institute
CRSI Concrete Reinforcing Steel Institute
180 North LaSalle Street
Chicago, IL 60601
CSI Construction Specifications Institute
DIPRA Ductile Iron Pipe Research Associations
EPA Environmental Protection Agency
FEDSPEC Federal Specifications
General Services Administration Specification
and Consumer Information Distribution Branch
Washington Navy Yard, Building 197
Washington, DC 20407
FEDSTDS Federal Standards (see FEDSPEC)
ICBO International Conference of Building Officials
5360 South Workman Mill Road
Whittier, CA 90601
MILSPEC Military Specifications
Naval Publications and Forms Center
5801 Tabor Avenue
Philadelphia, PA 19120
NIST National Institute of Standards and Technology
NPC National Plumbing Code
NSC National Safety Council
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Standard References
June 2017 01425-3
OSHA Occupational Safety and Health Act
U.S. Department of Labor
Occupational and Health Administration
San Francisco Regional Office
450 Golden Gate Avenue, Box 30617
PCA Portland Cement Association
PCI Prestressed Concrete Institute
PS Products Standards Section - U.S. Depart. of Commerce
SSPC Steel Structures Painting Council
SSPWC Standard Specifications for Public Works Construction
Building News, Inc.
3055 Overhead Avenue
Los Angeles, CA 90034
TCA Title Council of America
UBC Uniform Building Code
Published by ICBO
UL Underwriter’s Laboratory
207 East Ohio Street
Chicago, IL 60611
UMC Uniform Mechanical Code
Published by ICBO
UPC Uniform Plumbing Code
Published by IAPMO
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
END OF SECTION
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Materials Testing
June 2017 01450-1
SECTION 01450
MATERIALS TESTING
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Provide such equipment and facilities as are required for conducting field tests and for
collecting and forwarding samples. Do not use any materials or equipment represented
by samples until tests, if required, have been made and the materials or equipment
found to be acceptable. Any product which becomes unfit for use after approval thereof
shall not be incorporated into the work.
B. Tests shall be made by an accredited testing laboratory selected by the OWNER.
Except as otherwise provided, sampling and testing of all materials and the laboratory
methods and testing equipment shall be in accordance with the latest standards and
tentative methods of the American Society for Testing Materials (ASTM), and the
American Association of Highway and Transportation Officials (AASHTO).
C. Where additional or specific information concerning testing methods, sample sizes, etc.,
is required, such information is included under the applicable sections of the
Specifications. Any modification of, or elaboration on, these test procedures which may
be included for specific materials under their respective sections in the Specifications
shall take precedence over these procedures.
1.02 OWNER’S RESPONSIBILITIES
A. The OWNER shall be responsible for and shall pay all costs in connection with the
following testing:
1. Soils compaction tests
2. Trench backfill
3. Pipe and structural bedding
4. Tests not called for by the Specifications of materials delivered to the site
5. Concrete tests
6. Pavement tests
1.03 CONTRACTOR’S RESPONSIBILITIES
A. In addition to those inspections and tests called for in the General Conditions,
CONTRACTOR shall also be responsible for and shall pay all costs in connection with
testing required for the following:
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Materials Testing
June 2017 01450-2
1. Concrete materials and mix designs.
2. Design of asphalt mixtures.
3. Gradation tests for embankment, fill and backfill materials.
4. All performance and field testing specifically called for by the Specifications.
5. All retesting for work or materials found defective or unsatisfactory, including
tests covered under 1.02 above.
6. Water quality testing required by discharge permits.
1.04 TRANSMITTAL OF TEST REPORTS
Written reports of tests and engineering data furnished by CONTRACTOR for ENGINEER’s
review of materials and equipment proposed to be used in the work shall be submitted as
specified for Shop Drawings.
The testing laboratory retained by the OWNER will furnish six (6) copies of a written report of
each test performed by laboratory personnel in the field or laboratory. Three (3) copies of each
test report will be transmitted to the ENGINEER, one (1) copy to the CONTRACTOR, and two
(2) copies to the OWNER within seven (7) days after each test is completed. Results of tests
performed on site will be relayed to the ENGINEER and CONTRACTOR before the testing
firm’s personnel leave the work site.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
END OF SECTION
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Temporary Utility Support
June 2017 01535-1
SECTION 01535
TEMPORARY UTILITY SUPPORT
PART 1 GENERAL
1.01 SECTION INCLUDES
A. The CONTRACTOR shall submit a plan and drawings, stamped by a registered
Professional ENGINEER in the State of Colorado, indicating the means of
temporary construction support for any crossing of a utility or structure requiring
support to remain in service.
1.02 RELATED SECTIONS
A. Section 01330 – Submittals
B. Section 02315 – Excavation and Embankment
C. Section 02321 – Controlled Low Strength Material Backfill (Flo-Fill)
1.03 QUALITY STANDARDS
A. American Concrete Institute (ACI) 318 - Building Code Requirements for
Structural Concrete (latest edition).
B. American Institute of Steel Construction (AISC) - Specification for the Design,
Fabrication and Erection of Structural Steel for Buildings (latest edition)
1.04 SUBMITTALS
A. The CONTRACTOR shall submit a written plan including the proposed
construction sequence, design calculations and drawings to show the proposed
means for temporarily supporting any crossing of a utility or structure requiring
support to remain in service.
B. The plans and structural calculations shall be stamped by a Professional
Engineer registered in the State of Colorado.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION
3.01 TEMPORARY SUPPORT DESIGN
A. The utility or structure support design shall be such that the following criteria are met:
1. The design shall account for all dead and live loads including differential
settlement of supports, snow, wind and construction loads.
2. Stresses in duct bank concrete and reinforcing steel shall be limited to
those allowed by ACI. Cracking of the concrete duct bank greater than
0.013 inches in width will not be permitted.
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Temporary Utility Support
June 2017 01535-2
3. Electric duct banks should be supported at a maximum of three-foot
centers.
4. Stresses in steel casing pipe shall be limited to those allowed by AISC.
5. Deflection of steel casing pipe under its own weight shall not exceed
1/360 of the unsupported length.
3.02 EXCAVATION
A. Care should be taken in excavation to avoid damaging the utility or structure.
3.03 MAINTENANCE
A. The temporary support system shall be maintained during construction and
removed only after the utility or structure has been crossed and backfilling has
progressed to the point the utility or structure will be supported by the backfill
material. Precautions should be made to avoid damaging the support system by
such means as excavating too close to support bases, flooding support base
areas, striking supports or electric lines with construction equipment, etc.
B. No part of the support system shall be permitted to remain without prior approval
by the ENGINEER.
3.04 BACKFILL
A. Backfill around existing utilities or structures shall be in accordance with Sections
02225 Trenching, Bedding and Backfill and 02321 Controlled Low Strength
Material Backfill. Use of Controlled Low Strength Material (flo-fill) may be
required to ensure no voids are present under the existing utilities or structures.
END OF SECTION
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Substitutions and Product Options
June 2017 01635-1
SECTION 01635
SUBSTITUTIONS AND PRODUCT OPTIONS
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Description:
1. This section describes the procedure required by the CONTRACTOR for
product substitutions.
2. Requests for Substitution:
a. Base all bids on materials, equipment and procedures specified.
b. Certain types of equipment and kinds of material are described in
specifications by means of trade names and catalog numbers,
and/or manufacturer’s names. Where this occurs, it is not
intended to exclude from consideration such types of equipment
and kinds of material bearing other trade names, catalog numbers
and/or manufacturer’s names, capable of accomplishing purpose
of types of equipment or kinds of material specifically indicated.
c. Other types of equipment and kinds of material may be acceptable
to the OWNER and ENGINEER.
d. Types of equipment, kinds of material and methods of
construction, if not specifically indicated must be approved in
writing by ENGINEER and the OWNER.
3. Submission of Requests for Substitution:
a. After Notice to Proceed, the OWNER/ENGINEER will consider
written requests for substitutions of products, materials, systems
or other items.
b. The ENGINEER reserves the right to require substitute items to
comply color and pattern-wise with base specified items, if
necessary to secure “design intent”.
c. Submit six (6) copies of request for substitution. Include in
request:
1) Complete data substantiating compliance of proposed
substitute with Contract Documents.
2) For products:
i. Product identification, including manufacturer’s
name.
ii. Manufacturer’s literature, marked to indicate
specific model, type, size, and options to be considered:
Product description; performance and test data; reference
standards; difference in power demand; dimensional
differences for specified unit.
iii. Name and address of similar projects on which
product was used, date of installation, and field
performance data.
3) For construction methods:
i. Detailed description of proposed method.
ii. Drawings illustrating methods.
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Substitutions and Product Options
June 2017 01635-2
4) Itemized comparison of proposed substitution with product
or method specified.
5) Data relating to changes in construction schedule.
6) Relation to separate contracts.
7) Accurate cost data on proposed substitution in comparison
with product or method specified.
d. In making request for substitution, or in using an approved
substitute item, Supplier/Manufacturer represents:
1) He has personally investigated proposed product or
method, and has determined that it is equal or superior in
all respects to that specified and that it will perform function
for which it is intended.
2) He will provide same guarantee for substitute item as for
product or method specified.
3) He will coordinate installation of accepted substitution into
work, to include building modifications if necessary, making
such changes as may be required for work to be complete
in all aspects.
4) He waives all claims for additional costs related to
substitution which subsequently become apparent.
4. Substitutions:
a. Request sufficiently in advance to avoid delay in construction.
5. CONTRACTOR’s Option:
a. For products specified only by reference standards, select any
product meeting standards by any manufacturer, indicate selected
type in submission.
b. For products specified by naming several products or
manufacturers, select any product and manufacturer named,
indicate selected type in submission.
c. For products specified by naming one or more products, but
indicating option of selecting equivalent products by stating “or
equivalent” after specified product, CONTRACTOR must submit
request, as required for substitution, for any product not
specifically named.
6. Rejection of Substitution or Optional Item:
a. Substitutions and/or options will not be considered if:
1) They are indicated or implied on shop drawings, or project
data submittals, without formal request submitted in
accordance with this section.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
END OF SECTION
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Material Delivery, Storage, and Handling
June 2017 01650-1
SECTION 01650
MATERIAL DELIVERY, STORAGE AND HANDLING
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Equipment, products and materials shall be shipped, handled, stored, and
installed in ways which will prevent damage to the items. Damaged items will not
be permitted as part of the work except in cases of minor damage that have been
satisfactorily repaired and are acceptable to the ENGINEER.
B. Pipe: Pipe and appurtenances shall be handled, stored, and installed as
recommended by the manufacturer. Pipes with paint, tape coatings,
linings or the like shall be stored to protect the coating or lining from
physical damage or other deterioration. Pipe shipped with interior bracing
shall have the bracing removed only when recommended by the pipe
manufacturer.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
END OF SECTION
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment 01710-1 Site Conditions
June 2017
SECTION 01710
SITE CONDITIONS
PART 1 GENERAL
1.01 SECTION INCLUDES
A. General:
1. The CONTRACTOR acknowledges that he has satisfied himself as to the
nature and location of the work, the general and local conditions, particularly
those bearing upon access to the site; handling, storage, and disposal of
materials; availability of water, electricity and roads; uncertainties of weather,
river stages, or similar physical conditions at the site; the conformation and
conditions of the ground; the equipment and facilities needed preliminary to
and during the execution of the work; and all other matters which can in any
way affect the work or the cost thereof under this Contract.
2. The CONTRACTOR further acknowledges that he has satisfied himself as to
the character, quality and quantity of surface and subsurface materials to be
encountered from his inspection of the site and from reviewing any available
records of exploratory work furnished by the OWNER or included in these
Documents. Failure by the CONTRACTOR to acquaint himself with the
physical conditions of the site and all the available information will not relieve
him from responsibility for properly estimating the difficulty or cost of
successfully performing the work.
3. The CONTRACTOR warrants that as a result of his examination and
investigation of all the aforesaid data that he can perform the work in a good
and workmanlike manner and to the satisfaction of the OWNER. The
OWNER assumes no responsibility for any representations made by any of
its officers or agents during or prior to the execution of this Contract, unless
(1) such representations are expressly stated in the Contract, and (2) the
Contract expressly provides that the responsibility therefore is assumed by
the OWNER.
PART 2 PRODUCTS
2.01 INFORMATION ON SITE CONDITIONS
A. Any information obtained by the ENGINEER regarding site conditions, subsurface
information, groundwater elevations, existing construction of site facilities, and
similar data will be available for inspection, as applicable, at the office of the
ENGINEER upon request. Such information is offered as supplementary information
only. Neither the ENGINEER nor the OWNER assumes any responsibility for the
completeness or interpretation of such supplementary information.
1. Differing Subsurface Conditions:
a. In the event that the subsurface or latent physical conditions are
found materially different from those indicated in these Documents,
and differing materially from those ordinarily encountered and
generally recognized as inherent in the character of work covered in
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment 01710-2 Site Conditions
June 2017
these Contract Documents, the CONTRACTOR shall promptly, and
before such conditions are disturbed, notify the ENGINEER in writing
of such changed conditions.
b. The ENGINEER will investigate such conditions promptly and
following this investigation, the CONTRACTOR shall proceed with
the work, unless otherwise instructed by the ENGINEER. If the
ENGINEER finds that such conditions do so materially differ and
cause an increase or decrease in the cost of or in the time required
for performing the work, the ENGINEER will recommend to the
OWNER the amount of adjustment in cost and time he considers
reasonable. The OWNER will make the final decision on all Change
Orders to the Contract regarding any adjustment in cost or time for
completion.
2. Underground Utilities:
a. Known utilities and structures adjacent to or encountered in the work
are shown on the Drawings. The locations shown are taken from
existing records and the best information available from existing utility
plans, however, it is expected that there may be some discrepancies
and omissions in the locations and quantities of utilities and
structures shown. Those shown are for the convenience of the
CONTRACTOR only, and no responsibility is assumed by either the
OWNER or the ENGINEER for their accuracy or completeness.
PART 3 EXECUTION
3.01 GENERAL
A. Where the CONTRACTOR's operations could cause damage or inconvenience to
railway, telegraph, telephone, television, oil, gas, electricity, water, sewer, or irrigation
systems, the operations shall be suspended until all arrangements necessary for the
protection of these utilities and services have been made by the CONTRACTOR.
B. Notify all utility offices which are affected by the construction operation at least 48
hours in advance. Under no circumstances expose any utility without first obtaining
permission from the appropriate agency. Once permission has been granted, locate,
expose, and provide temporary support for all existing underground utilities.
C. The CONTRACTOR shall protect all utility poles from damage. If interfering power
poles, telephone poles, guy wires, or anchors are encountered, notify the
ENGINEER and the appropriate utility company at least 48 hours in advance of
construction operations to permit the necessary arrangements for protection or
relocation of the interfering structure.
D. The CONTRACTOR shall be solely and directly responsible to the owner and
operators of such properties for any damage, injury, expense, loss, inconvenience,
delay, suits, actions, or claims of any character brought because of any injuries or
damage which may result from the construction operations under this Contract.
E. Neither the OWNER nor its officers or agents shall be responsible to the
CONTRACTOR for damages as a result of the CONTRACTOR's failure to protect
utilities encountered in the work.
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment 01710-3 Site Conditions
June 2017
F. If the CONTRACTOR while performing the Contract discovers utility facilities not
identified in the Drawings or Specifications, he shall immediately notify the OWNER,
utility, and the ENGINEER in writing.
G. In the event of interruption to domestic water, sewer, storm drain, or other utility
services as a result of accidental breakage due to construction operations, promptly
notify the proper authority. Cooperate with said authority in the restoration of service
as promptly as possible and bear all costs of repair.
H. The CONTRACTOR shall replace, at his own expense, any and all other existing
utilities or structures removed or damaged during construction, unless otherwise
provided for in these Contract Documents or ordered by the ENGINEER.
3.02 INTERFERING STRUCTURES
A. The CONTRACTOR shall take necessary precautions to prevent damage to existing
structures whether on the surface, aboveground, or underground. An attempt has
been made to show major structures on the Drawings. The completeness and
accuracy cannot be guaranteed, and it is presented simply as a guide to avoid
known possible difficulties.
3.03 FIELD RELOCATION
A. During the progress of construction, it is expected that minor relocations of the work
will be necessary. Such relocations shall be made only by direction of the
ENGINEER. If existing structures are encountered that prevent the construction,
and that are not properly shown on the Drawings, notify the ENGINEER before
continuing with the construction in order that the ENGINEER may make such field
revision as necessary to avoid conflict with the existing structures. If the
CONTRACTOR shall fail to so notify the ENGINEER when an existing structure is
encountered, and shall proceed with the construction despite the interference, he
shall do so at his own risk.
3.04 EASEMENTS
A. Where portions of the work are located on public or private property, easements and
permits will be obtained by the OWNER. Easements will provide for the use of the
property for construction purposes to the extent indicated on the easements. Copies
of these easements and permits are available upon request to the OWNER. It shall
be the CONTRACTOR's responsibility to determine the adequacy of the easement
obtained in every case and to abide by all requirements and provisions of the
easement. The CONTRACTOR shall confine his construction operations to within
the easement limits or make special arrangements with the property owners or
appropriate public agency for the additional area required. Any damage to property,
either inside or outside the limits of the easements provided by the OWNER, shall be
the responsibility of the CONTRACTOR as specified herein. The CONTRACTOR
shall remove, protect, and replace all fences or other items encountered on public or
private property. Before final payment will be authorized by the ENGINEER, the
CONTRACTOR will be required to furnish the OWNER with written releases from
property owners or public agencies where side agreements or special easements
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment 01710-4 Site Conditions
June 2017
have been made by the CONTRACTOR or where the CONTRACTOR's operations,
for any reason, have not been kept within the construction right-of-way obtained by
the OWNER.
B. It is anticipated that the required easements and permits will be obtained before
construction is started. However, should the procurement of any easement or permit
be delayed, the CONTRACTOR shall schedule and perform the work around these
areas until such a time as the easement or permit has been secured.
3.05 LAND MONUMENTS
A. The CONTRACTOR shall notify the ENGINEER of any existing Federal, State,
Town, County, and private land monuments encountered. Private monuments shall
be preserved, or replaced by a licensed surveyor at the CONTRACTOR's expense.
When Government monuments are encountered, the CONTRACTOR shall notify the
ENGINEER at least two (2) weeks in advance of the proposed construction in order
that the ENGINEER will have ample opportunity to notify the proper authority and
reference these monuments for later replacement.
END OF SECTION
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Tree, Landscape, Vegetation, and Wetland Protection
June 2017 01715-1
SECTION 01715
TREE, LANDSCAPE, VEGETATION, AND WETLAND PROTECTION
PART 1 GENERAL
1.01 SECTION INCLUDES
A. The work for this section consists of protecting existing trees, landscape, wetlands and
adjacent vegetation. The CONTRACTOR must take special care to avoid damaging existing
trees and vegetation in areas that do not need to be disturbed to complete construction.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION
3.01 SUBMITTAL REQUIREMENTS
A. The CONTRACTOR shall submit a plan for on-site haul of materials prior to construction.
The plans shall include points of access to and from the site and shall show a workable
system of on-site haul routes that protect existing landscaped and wetland areas. This plan
shall be submitted to the ENGINEER for his review and comment prior to the
commencement of any work. The plan will be discussed with the CONTRACTOR to insure
protection of existing vegetation, but the ENGINEER shall not dictate haul routes or
construction methods to the CONTRACTOR.
3.02 CONSTRUCTION REQUIREMENTS
A. Protected areas will be marked in the field, one time, by the OWNER and ENGINEER. No
access of construction vehicles or workers on foot is permitted through protected areas. No
material shall be stockpiled; no equipment shall be parked or repaired within these areas.
B. Trees and vegetation to be saved that do not fall within the limits of protected areas shall be
marked one time in the field by the OWNER and ENGINEER. The CONTRACTOR shall
erect fencing if there is risk of damage caused by construction operations. Vehicular and
pedestrian traffic shall be limited to performing work in areas marked. Through traffic, and
stock piling of equipment and materials are not permitted within marked areas.
C. No construction roads are to be created within the drop lines of any trees or other vegetation
designated to be saved without approval of the ENGINEER.
D. All trees which will be preserved, but are within the limits of construction, must be protected
from all damage associated with construction. A sturdy, physical barrier (florescent orange
in color) must be fixed in place around each tree for the duration of construction. This
barrier will be placed no closer than 6 feet from the trunk, or the drip line, whichever is
greater. The barrier itself must be fixed so it cannot be moved easily, but the material can
be flexible, such as orange snow fence attached to T-posts driven into the ground, and must
act as an effective deterrent to deliberate or accidental damage of each tree. Actual
materials and location of barrier must be approved by the OWNER’s representatives (i.e.
Utilities and City Forrester) and ENGINEER.
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Tree, Landscape, Vegetation, and Wetland Protection
June 2017 01715-2
E. The movement or storage of equipment, material, debris, or fill within these required
protective barriers is completely prohibited.
F. Any trees damaged during construction shall be immediately repaired by an approved tree
surgeon. Any tree judged by the ENGINEER to be damaged beyond repair shall be
removed at the CONTRACTOR’s expense. For each tree erroneously removed or damaged
beyond repair, an assessment shall be immediately withheld from the CONTRACTOR’s
progress payments. This assessment shall be equal to the value of the tree prior to
damage. This assessment shall be determined by a tree appraiser, selected by the
OWNER and paid for by the CONTRACTOR. The cost for hiring the appraiser shall also be
withheld from the CONTRACTOR’s progress payments.
In addition to the paying of the assessment, the CONTRACTOR shall replace each
damaged tree per OWNER’S standards for tree mitigation.
G. The CONTRACTOR shall pay an assessment if he disturbs any grasses, shrubs and/or
cattails located within the protected areas. The assessment shall not exceed one dollar
($1.00) per square foot of disturbance, and will be immediately withheld from the
CONTRACTOR’s progress payments.
In addition to the paying of the assessment, the damaged vegetation shall be replaced with
an equal value per square foot of damage. Replacements shall be planted in accordance
with the provisions outlined in these Specifications. Damaged wetland areas shall be
replaced and then seeded with a wetland seed mix in accordance with these Specifications
or as directed by the ENGINEER.
END OF SECTION
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Field Engineering and Surveying
June 2017 01720-1
SECTION 01720
FIELD ENGINEERING AND SURVEYING
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Surveying: It shall be the responsibility of the CONTRACTOR to provide
construction staking for horizontal and vertical alignment of the centerline,
grading, and all appurtenant features of the work including all offset lines
necessary for construction. The CONTRACTOR shall be responsible for staking
the limits of construction.
All construction surveying provided by the CONTRACTOR shall be completed
under the supervision of a Colorado Registered Land Surveyor.
The ENGINEER will provide the elevations and descriptions of the original and
temporary project benchmarks. The ENGINEER will also provide two (2)
additional benchmarks in a location within the limits of construction at the request
of the CONTRACTOR.
B. Supervision: The CONTRACTOR shall have supervision, knowledge of the
project requirements and proper installation, and construction procedures,
available in the field at all times that work is progressing.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
END OF SECTION
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Environmental Controls
June 2017 01745-1
SECTION 01745
ENVIRONMENTAL CONTROLS
PART 1 GENERAL
1.01 SECTION INCLUDES
A. The work of this section consists of obtaining permits and providing
environmental controls consistent with regulatory permits through the
duration of the work required under this project.
PART 2 PRODUCTS
2.01 MATERIALS
A. Dust Control: Dust control agents may be necessary in addition to
wetting down with water. Dust control agents may be used only after
prior approval by the OWNER.
PART 3 EXECUTION
3.01 Dust Control Application:
A. The CONTRACTOR shall execute work by methods to minimize raising
dust from construction operations.
B. The CONTRACTOR shall provide and apply dust control at all times,
including evenings, holidays and weekends, as required to abate dust
nuisance on and about the site that is a direct result of construction
activities. The use of non-approved chemicals, oil, or similar palliatives
will not be allowed. Dust control agents may be used only after prior
approval of the OWNER. The CONTRACTOR shall be required to
provide sufficient quantities of equipment and personnel for dust control
sufficient to prevent dust nuisance on and about the site.
C. The OWNER will have authority to order dust control work whenever in its
opinion it is required, and there shall be no additional cost to the OWNER.
The CONTRACTOR shall be expected to maintain dust control measures
effectively whether the OWNER or ENGINEER specifically orders such
Work.
3.02 PRESERVATION OF NATURAL FEATURES
A. Confine operations as much as possible. Exercise special care to
maintain natural surroundings in an undamaged condition. Within the
work limits, barricade trees, rock outcroppings, and natural features to be
preserved.
3.03 HOUSEKEEPING
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Environmental Controls
June 2017 01745-2
A. Keep project neat, orderly, and in a safe condition at all times. Store and
use equipment, tools, and materials in a manner that does not present a
hazard. Immediately remove all rubbish. Do not allow rubbish to
accumulate. Provide on-site containers for collection of rubbish and
dispose of it at frequent intervals during progress of work.
3.04 DISPOSAL
A. Disposal of Waste (Unsuitable) Materials: All material determined by the
ENGINEER to be waste will be disposed of in approved landfill in a
manner meeting all regulations. Dispose of waste materials, legally, at
public or private dumping areas. Do not bury wastes inside of the limits of
construction. All costs for dump fees, permits, etc., to be borne by the
CONTRACTOR.
B. Disposal of Garbage and Other Construction Materials: Provide sanitary
containers/dumpsters and haul away contents such that no overflow
exists.
C. Excess excavation shall become the property of the CONTRACTOR and
shall be legally disposed of by him outside the limits of construction to an
approved disposal site. Excess excavated material suitable for backfill
shall not be disposed of until all backfill operations are complete.
D. The CONTRACTOR is to immediately inform ENGINEER of any
hazardous materials encountered during construction. Dispose of waste
materials legally at private or public facilities.
3.05 BURNING
A. No burning of debris will be permitted.
3.06 WATER CONTROL
A. The project work is located within a natural drainage course is subject to
periodic flooding due to rainfall and snowmelt, flows for adjacent
developed areas and storm water pipes and ground water flows from
saturated soils or other ground water sources. Refer to Section 02240 for
Water Control and Dewatering requirements.
3.07 NOISE CONTROL
A. All mechanical equipment shall be equipped with the best available
mufflers to reduce noise. The CONTRACTOR shall be responsible for
obtaining any necessary permits and shall limit noise to the permitted
levels. Noise level monitoring shall be performed by the CONTRACTOR
as necessary to show that the permitted levels are not being exceeded.
3.08 PERMITS
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Environmental Controls
June 2017 01745-3
A. All work must be performed in accordance with all applicable regulatory
permits.
It shall be the responsibility of the CONTRACTOR to obtain a
Groundwater Discharge (402) Permit from the Colorado Department of
Public Health and Environment for any dewatering operations that will be
discharged into any drainageways, open channels, or irrigation ditches.
The CONTRACTOR shall be responsible for any testing required under
the 402 Permit.
B. The OWNER will obtain the following permits:
1. None
C. It shall be the responsibility of the CONTRACTOR to prepare and
maintain a Stormwater Management Plan (SWMP). The CONTRACTOR
must obtain all other applicable permits.
END OF SECTION
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Contract Closeout
June 2017 01780-1
SECTION 01780
CONTRACT CLOSEOUT
PART 1 GENERAL
1.01 SECTION INCLUDES
A. The following project closeout procedure defines the responsibilities of the
CONTRACTOR, OWNER, and ENGINEER in closing the project:
Step 1: CONTRACTOR advises the ENGINEER in writing that he has reached
"Substantial Completion" and provides a list of items to be completed or
corrected.
Closeout may be conducted by areas or portions of the work if requested by the
OWNER.
Step 2: ENGINEER inspects the work to determine if it is substantially complete,
and issues a Certificate of Substantial Completion plus a "Punch List" of items to
be completed or corrected.
Step 3: CONTRACTOR completes and/or corrects all punch list items and
notifies the ENGINEER in writing that his work is ready for final inspection. At
this time, a final application for payment is submitted.
Step 4: ENGINEER makes final inspection. When the work is found to be
acceptable under the Contract Documents, and the Contract fully performed, the
ENGINEER will issue a final Certificate of Final Completion.
B. Final Paperwork:
Prior to Final Payment and Acceptance, the CONTRACTOR shall deliver the
following items to the ENGINEER:
1. CONTRACTOR's Two-Year Guarantee of Materials and Workmanship
2. All Guarantees, Warranties and Submittals, as specified
3. Receipts for Extra Materials Delivered to the OWNER
4. Final Application for Payment
5. Consent of Surety to Final Payment
6. CONTRACTOR's Lien Waiver
7. SUBCONTRACTOR’s Lien Waivers
8. Releases from Property Owners for Special Easements
9. Project Record Documents
10. Red-lined as-built drawings (a.k.a. “Drawings of Record” or “Record
Drawings”)
C. Definition for Substantial Completion
1. See General Conditions
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22
24” Poudre Pipeline Rehab Assessment Contract Closeout
June 2017 01780-2
D. Definition for Final Completion
1. All Work must be complete for Final Completion.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
END OF SECTION
DocuSign Envelope ID: 6474B9F5-C525-49D3-A747-8BF7F9256D22