HomeMy WebLinkAboutCHANGE ORDER - RFP - 7546 DIRECTIONAL BORING & TRENCHING SERVICES (4)SECTION 00950
CHANGE ORDER NO. 1
PROJECT TITLE: Prospect/Timberline
PO NUMBER: 9172964
CONTRACTOR: Colorado Boring
PROJECT NUMBER: 1630-2672
DESCRIPTION:
1. Reason for change: Additional traffic control needed. Poor soil conditions that created extra
work. Had to grout the sleeve which was an add. Concrete removal
and re-poured the concrete.
2. Description of Change: Extra services for a directional bore
3. Change in Contract Cost: $12,906
4. Change in Contract Time: none
ORIGINAL CONTRACT COST $ 167,088.00
TOTAL APPROVED CHANGE ORDER .00
TOTAL PENDING CHANGE ORDER .00
TOTAL THIS CHANGE ORDER 12,906.00
TOTAL % OF THIS CHANGE ORDER 7.73%
TOTAL C.O.% OF ORIGINAL CONTRACT 7.73%
ADJUSTED CONTRACT COST $ 179,994.00
(Assuming all change orders approved)
ACCEPTED BY: DATE:
Contractor's Representative
REVIEWED BY: DATE:
Project Manager
APPROVED BY: DATE:
Buyer
APPROVED BY: DATE:
Title: Light & Power Operations MGR
APPROVED BY: DATE:
Purchasing Director (over $60,000)
DocuSign Envelope ID: 3788B5A1-A636-4958-BD3E-7CE73EA49903
180828
Req# 56776
Heather
5/17/17
cc: City Clerk Contractor Engineer