HomeMy WebLinkAboutWORK ORDER - RFP - 7515 CONSULTING ENGINEERING SERVICES FOR FUTURE WATER WW & SW FACILITIES CAPITAL IMPROVEMENTS (12)WORK ORDER
PURSUANT TO AN AGREEMENT BETWEEN
THE CITY OF FORT COLLINS
AND
Ditesco
DATED: 7/22/2013
Work Order Number: Necco-Ditesco-1
Purchase Order Number:
Project Title: Northeast College Corridor Outfall (NECCO)
Original Bid/RFP Number & Name: 7515-Consulting Engineering Services for future W/WW &
Stormwater Facilities Capital Improvements
Commencement Date: May 2017
Completion Date: December 2017
Maximum Fee: (time and reimbursable direct costs):$66,479.00
Project Description: See attached Exhibit A
Scope of Services: See attached Exhibit A
Professional agrees to perform the services
identified above and on the attached forms in
accordance with the terms and conditions
contained herein and in the Professional Services
Agreement between the parties. In the event of a
conflict between or ambiguity in the terms of the
Professional Services Agreement and this work
order (including the attached forms) the
Professional Services Agreement shall control.
The attached forms consisting of 9 (nine) pages
are hereby accepted and incorporated herein, by
this reference, and Notice to Proceed is hereby
given.
PROFESSIONAL
By:_______________________________
Date:_____________________________
CITY OF FORT COLLINS
Submitted By: _________________________
Linsey R. Chalfant, Special Project
Manager
Date: _________________________
Reviewed by: _________________________
Pat Johnson, Senior Buyer
Reviewed by: _________________________
Owen L. Randall, Chief Engineer
Date: _________________________
Approved by: _________________________
Jon Haukaas, Water Engineering & Field
Services Operations Manager or Carol
Webb, Water Resources/Treatment Operations Manager
Date: ________________________
Approved by: _________________________
Kevin Gertig, Utilities Executive Director
Date: ________________________
Approved by: _________________________
Gerry Paul, Purchasing Director (if over
$60,000)
Date: _______________________
5/6/2017
5/6/2017
5/6/2017
5/9/2017
5/9/2017
5/9/2017
Page 1 of 5
2133 South Timberline, Suite 110
Fort Collins, CO 80525
ditescoservices.com
Delivery by email to:
lchalfant@fcgov.com
April 28, 2017
Ms. Linsey R. Chalfant, PE
Special Projects Manager
City of Fort Collins Utilities
212 W. Mountain Avenue
Fort Collins, CO 80524
RE: Northeast College Corridor Outfall (NECCO)
Engineering Design Proposal and Scope of Work
Dear Linsey:
This letter and scope of work proposal follows on our recent meetings regarding the referenced project. The
attached scope of work has been configured to allow Jaclyn Michaelsen the ability to provide uninterrupted services
to the City on this project as she transitions employment to Ditesco. As such, the attached represents a partial
scope of services as a continuation of remaining work tasks to complete the 2017 work plan prior to initiating a new
work order in 2018 to complete the project.
Thank you again for giving Ditesco the opportunity to provide engineering services for this project. We hope you
will find the services outlined herein seamless and value driven.
We look forward to working with you and delivering another successful project for Fort Collins Utilities!
Please let me know if you have any questions or require further information regarding this proposal, I can be
reached by phone at 970.988.8605 and email keith.meyer@ditescoservices.com.
Sincerely,
Keith Meyer, P.E.
Enc. scope of services
Cc: file
Page 2 of 5
Exhibit A
Northeast College Corridor Outfall (NECCO)
Engineering Design and Construction Administration
Scope of Services
Project Understanding
The City of Fort Collins Utilities desires to continue uninterrupted services on the NECCO project related to
engineering and construction phase support. As such, scope of work covers the remaining work plan for 2017 for
the NECCO Ponds and Backbone project. A detailed task description is provided below. In addition, our services
include subconsultants Andy Herb who is tasked with wetland mitigation observation and construction, and BHA for
landscaping and irrigation design.
This project is being delivered using the Utilities Alternative Project Delivery System (APDS). Design plans and
specifications have been previously developed by Ayres Associates, Inc. The City will be utilizing Connell
Resources, Inc. throughout the design and construction process.
Task 1: Construction
• Ditesco staff will continue support of the construction phase attending and documenting meetings
associated with the landscaping design and construction. We will prepare and distribute meeting
minutes for these meetings. As a subconsultant to Ditesco, BHA will continue to provide landscaping
design services for the regional detention ponds according to their original base scope of services (see
attached).
• Final Design As-Built Report. Ditesco staff will update the NECCO Final Design Report to reflect as-
built conditions based upon record construction information. We will update the report, meet with City
staff and address any comments to the report. Upon receipt of final comments, we will issue a final
electronic version of the report.
• As-Built Drawings. Ditesco staff will develop record drawings based upon field collected information
from both our staff and the Contractor. We will update these plans and make review copies available
to the City. Upon receipt of final comments, we will provide a final version of the record drawings in
electronic (PDF), CAD and mylar formats (as the City may desire).
• Vine Pond Coordination: This task allows time for Ditesco staff to attend meetings regarding the Vine
pond design. We will perform minor modifications and adjustments to the hydraulic model to determine
feasibility of continuing the project without the construction of the Vine Regional Detention Pond.
Task 2: Landscaping Phase
• Landscape Construction Observation. This task includes construction observation and direction by
Alpine for the vegetative measures being constructed in the wetland mitigation site. Ditesco staff will
provide oversight and coordination as these activities are implemented in the field.
• Landscape Planting and Seeding. This task provides the cost for Alpine to provide the wetland
mitigation plant materials and seeding of the wetland mitigation site south of Vine Drive. Our scope of
work assumes that Connell Resources will hire a separate seeding contractor to seed all of the
disturbed areas along the road right of way. The deposit that the City has paid for plant materials has
been subtracted from this cost. Please note that the remainder of the deposit the City has paid will be
applied to wetland mitigation that will be constructed with the ponds portion of the project. This does
not include services for Phase II (2018) work.
Page 3 of 5
Deliverables:
• Expected Deliverables and Format:
o Record Drawings in both PDF format and digital (AutoCAD Civil 3D ver. 2015)
o Updated hydraulic model
o Final “as-built” design report in PDF format
o Weekly Meetings: Agendas, Meeting Minutes, both in PDF format
Schedule
The anticipated schedule for the remainder of the NECCO project is as follows.
Construction: April through December 2017 (landscaping)
Construction (phase 2): 2018
Fee Estimate
We have based our fee estimate on the following assumptions of the project schedule.
• 9 month delivery
• Record drawing information provided by others
Total Estimated Fee: $66,479.00
A detailed task breakdown is included. Please find this on page 5 of this scope of work proposal.
The fee shown above is to be billed on a time and material basis based on the rates shown in the table on page 4 and 5 of this
proposal. All reimbursable expenses will be billed at direct cost.
Page 4 of 5
Ditesco
City of Fort Collins Utilities
Consulting Engineering Services – Water, Wastewater, Stormwater
2014 Wage Rate Schedule
Principal: $115.00 - $125.00 per hour
Project Manager: $95.00 - $100.00 per hour
Engineer: $92.00 - $110.00 per hour
Construction Manager/Resident Engineer: $91.00 - $94.00 per hour
CAD Design $65.00 per hour
Administrative: $55.00 per hour
Mileage Reimbursement: $0.75 per mile
Subconsultant Markup 5% of cost
All other costs at direct expense
Terms 30 days net
City of Fort Collins Utilities
NECCO Project 4/28/2017
Keith Meyer Jackie Michaelsen Rhonda Bunner Cassidy Hill
Principal Project Manager CAD Design Administrative
(hrs) (hrs) (hrs) (hrs)
$125 $100 $65 $55
Task 1 - Construction Phase $54,170
PM 1.1 - Contract Management (Invoicing and Budget Management) 9 0 0 5 $1,400
PM 1.2 - Meetings/Correspondence (Progress Meetings) 18 36 0 0 $5,850
PE 1.1 - Design $0
- Landscaping (BHA) $ 29,090.11 $29,090
- Final Design Report 6 44 20 8 $6,890
- Record Drawings 4 16 32 0 $4,180
- Vine Pond Coordination and Modeling 4 60 4 0 $6,760
Task 2 - Landscaping Phase $11,005
CM1.14 Resident Engineering
- Landscaping Observation and Records (Alpine) 4 18 2 2 $ 8,000.00 $10,540
- Landscape Planting and Seeding (Alpine) 0 4 1 0 $465
Other direct costs at 2.0% (mileage, reproduction, etc) $1,304
Work Effort Subtotal 45 178 59 15 $65,175
ODCs $1,304
Cost per labor category $5,625.00 $17,800.00 $3,835.00 $825.00
Effort (days) 6 22 7 2
Effort (weeks) 1 4 1 0
Hours per day 0.2 0.8 0.3 0.1
Total Contract Value: $66,479
Assumptions:
- 9 month project duration
- Contract Start - April 2017
- Project End - December 2017
Phase/Task Description
Classification
Sub Consultants Task Total
Page 5 of 5
ID Task
Mode
Task Name Duration Start Finish
1 NECCO Design and Construction Administration 120 days Mon 5/1/17 Fri 10/13/17
2 Start NECCO Schedule 0 days Mon 5/1/17 Mon 5/1/17
3 Construction 120 days Mon 5/1/17 Fri 10/13/17
4 Meetings/Correspondence (Progress Meetings) 120 days Mon 5/1/17 Fri 10/13/17
5 Design 120 days Mon 5/1/17 Fri 10/13/17
6 As-Built Drawings 10 days Mon 5/1/17 Fri 5/12/17
7 City Review and Comment 10 days Mon 5/15/17 Fri 5/26/17
8 Complete As-Built Drawings 5 days Mon 5/29/17 Fri 6/2/17
9 As-Built Design Report 30 days Mon 6/5/17 Fri 7/14/17
10 Landscape Design 66 days Mon 5/1/17 Mon 7/31/17
11 Funding Approval 0 days Mon 7/31/17 Mon 7/31/17
12 Vine Pond Coordination 120 days Mon 5/1/17 Fri 10/13/17
13 Landscaping Phase 65 days Mon 5/1/17 Fri 7/28/17
14 Landscape Construction Observation 65 days Mon 5/1/17 Fri 7/28/17
15 Landscape Planting and Seeding 65 days Mon 5/1/17 Fri 7/28/17
16 Completion of Phase 1A and B 0 days Fri 10/13/17 Fri 10/13/17
0%
5/1
0%
0%
0%
0%
0%
0%
0%
0%
7/31
0%
0%
0%
0%
10/13
Apr May Jun Jul Aug Sep Oct Nov
2nd Half
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
NECCO Pond - Remaining Design Services for NECCO Regional Pond and Vine Regional Pond
ATTACHMENT B -SCHEDULE OF FEES
BHA Design, Inc. Task Task
Task Description Name Extension Name Extension Name Extension Name Extension Extension Hours Amount
Name Principal PM LA ADMIN
Rate $147.00 $105.00 $80.00 $80.00
Project Start-Up
Negotiate Scope Contract with Client 1 $147.00 1 $105.00 $0.00 $0.00 $0.00 2 $252.00
Acquire/Format digital survey and grading from Client $0.00 $0.00 $0.00 $0.00 $0.00 0 $0.00
Visit project site to review existing conditions 2 $294.00 3 $315.00 3 $240.00 $0.00 $0.00 8 $849.00
Conceptual Design and Review
Prepare site analysis, opportunities and constraints $0.00 2 $210.00 4 $320.00 $0.00 $0.00 6 $530.00
Prepare landscape and grading concept 1.5 $220.50 8 $840.00 30 $2,400.00 $0.00 $0.00 39.5 $3,460.50
Prepare plant list and seed mixes $0.00 1 $105.00 2 $160.00 $0.00 $0.00 3 $265.00
Details for Features and Amenities $0.00 4 $420.00 8 $640.00 $0.00 $0.00 12 $1,060.00
Revise landscape, and grading concepts 1 $147.00 5 $525.00 10 $800.00 $0.00 $0.00 16 $1,472.00
Build SketchUp model for digital rendering $0.00 3 $315.00 10 $800.00 $0.00 $0.00 13 $1,115.00
In-House Quality Assurance Review/Revisions 2 $294.00 3 $315.00 8 $640.00 $0.00 $0.00 13 $1,249.00
Render conceptual design plan $0.00 1 $105.00 6 $480.00 $0.00 $0.00 7 $585.00
Final Design and Construction Documents
CD Landscape Plans 3 $441.00 8 $840.00 20 $1,600.00 $0.00 $0.00 31 $2,881.00
Details for Features and Amenities $0.00 3 $315.00 8 $640.00 $0.00 $0.00 11 $955.00
Technical Specifications - Landscape 2 $294.00 6 $630.00 $0.00 $0.00 $0.00 8 $924.00
In-House Quality Assurance Review/Revisions 4 $588.00 8 $840.00 16 $1,280.00 $0.00 $0.00 28 $2,708.00
Final Revisions and Submittal of CD's $0.00 3 $315.00 10 $800.00 $0.00 $0.00 13 $1,115.00
Meetings and Project Management
Team Meetings $0.00 15 $1,575.00 10 $800.00 $0.00 $0.00 25 $2,375.00
Coordination outside of meetings $0.00 16 $1,680.00 $0.00 $0.00 $0.00 16 $1,680.00
Project Management 4 $588.00 20 $2,100.00 $0.00 16 $1,280.00 $0.00 40 $3,968.00
Total Hours 20.5 110 145 16 0 291.5
Total Amount $3,013.50 $11,550.00 $11,600.00 $1,280.00 $0.00 $27,443.50
Estimate of Expenses $1,647
Assumptions Total Fees $29,090.11
1 Structural design and geotechnical services are not included.
2 Trail design is not included in scope.
3 Irrigation will be design-build by contractor if necessary. Irrigation design is not included in scope.
4 Services do not include typical City development review process, planning coordination, presentations.
5 Public Outreach & Public Hearings are excluded.
6 Electrical/Lighting Design Services are not included but may be required for irrigation controllers.
7 Horizontal control plans are not part of this contract.
8 Sign design services are not part of this contract.
9 Meeting(s) with Natural Resources will occur as part of team meeting(s) if applicable.
10 Grading concepts prepared by Ayres will be the basis for grading concepts. Ayres is responsible for preparing final grading plans.
11 Sketchup terrain and flood models will focus on the ponds and the areas immediately abutting the ponds. Sketchup models for residential areas between ponds are not included.
12 Contour data of existing and initial planning will be provided to BHA by others. Contours received shall include accurate Z coordinate elevations.
13 Bid Package and Project Manual are being compiled by others.
14 Wetland Mitigation Plan will be by others
15 Perspective hand renderings are not included in this contract. Digital renderings form sketchup are included.
16 Features and amenities may include: fences, railings, trails, headwall improvements.
17 Restrooms, Parking Lots, Outdoor Classrooms, Kiosks, and Interpretive Signs are not included.
18 Construction observation shall be by separate contract
19 Project cost estimating is not included in scope.
Project Area:
4/19/2017
NECCO POND:
VINE POND:
Deadline
NECCO
Page 1
Mon 5/1/17
12:09 PM