HomeMy WebLinkAboutCORRESPONDENCE - RFP - 8106 UTILITY INFRASTRUCTURE CONSTRUCTION SERVICES FOR WATER, WASTEWATER, AND STORMWATER FACILITIES CAPITAL IMPROVEMENTS (6)Requisition Form
Vendor: Garney Construction Today's Date: May 1, 2017 Requisition No.:
Ship To: Date Entered:
Date Required: ASAP Date Approved:
Special Instructions: Date Denied:
Item # Quantity Unit Description Unit Price Total Charge Numbers
1 1 EA $24,855.00 $24,855.00 5040100004.535010.3
Requested By: Approved By:
Linsey R. Chalfant Date Jon Haukaas Date
Magnolia Street Outfall-Design and Estimating
I\ENG\FORMS\GarneyMagReq.xls
DocuSign Envelope ID: 2CE7A54E-49F8-4421-B970-CE9110A89A58
5/1/2017
5/1/2017
5/1/2017
DocuSign Envelope ID: 855300C9-29C3-4358-94CF-51CA79F07D50
WORK ORDER
PURSUANT TO AN AGREEMENT BETWEEN
THE CITY OF FORT COLLINS
AND
Garney Construction
DATED: August 17, 2015
Work Order Number: Mag-Garney-1
Purchase Order Number:
Project Title: Magnolia Street Outfall
Original Bid/RFP Number & Name: 8106 Utility Infrastructure Construction Services for Water,
Wastewater and Stormwater Facilities Capital Improvements
Commencement Date: May 2017
Completion Date: December 2017
Maximum Fee: (time and reimbursable direct costs):$24,855 (see attached Exhibit A)
Project Description: Design and estimating services related to the Magnolia Street Outfall-Conceptual
Scope of Services: (See Attached letter and fee)
Contractor agrees to perform the services
identified above and on the attached forms in
accordance with the terms and conditions
contained herein and in the Construction Work
Order Agreement between the parties. In the
event of a conflict between or ambiguity in the
terms of the Construction Work Order Agreement
and this work order (including the attached forms)
the Construction Work Order Agreement shall
control.
The attached forms consisting of 3 (three) pages
are hereby accepted and incorporated herein, by
this reference, and Notice to Proceed is hereby
given upon full execution of this document.
CONTRACTOR
By:_______________________________
Date:_____________________________
CITY OF FORT COLLINS
Submitted By: _________________________
Linsey R. Chalfant, PE, Special Project
Manager
Date: _________________________
Reviewed by: _________________________
Pat Johnson, Senior Buyer
Reviewed by: _________________________
Owen L. Randall, Chief Engineer
Date: _________________________
Approved by: _________________________
Jon Haukaas, Water Engineering & Field
Services Operations Manager
Date: ________________________
Approved by: _________________________
Kevin Gertig, Utilities Executive Director
Date: ________________________
Approved by: _________________________
Gerry Paul, Purchasing Director (if over
$60,000)
Date: _______________________
DocuSign Envelope ID: 855300C9-29C3-4358-94CF-51CA79F07D50
5/1/2017
5/1/2017
5/1/2017
5/3/2017
5/3/2017
7911 Shaffer Parkway, Littleton, CO 80127
Phone: 303.791.3600
Fax: 303.791.1801
www.garney.com
April 28, 2017
Ms. Linsey Chalfant
Mr. Matt Fater
City of Fort Collins Utilities
P.O. Box 580
700 Wood Street
Fort Collins, CO 80522-0580
RE: Magnolia Street Outfall Design Assistance Proposal
Dear Linsey & Matt,
We are pleased to offer our design assistance proposal for the Magnolia Street Outfall.
Attached is a fee schedule which is based on attending and following up on Design Meetings and
providing two Budget Level Estimates in 2017. Also attached is a Design Schedule that defines the
Design Meetings and Budget Level Estimating tasks.
We look forward to working with you on this exciting and challenging project.
If you have any questions or concerns, please contact me at (970) 217-1934 or jmoore@garney.com.
Sincerely,
GARNEY COMPANIES, INC.
Jeffrey J. Moore
Senior Project Manager
DocuSign Envelope ID: 855300C9-29C3-4358-94CF-51CA79F07D50
Magnolia Street Outfall Design Assistance Proposal
04/28/17
Design Meetings Jeff Moore Pickup Rich Trimble Pickup Zac Fry Vehicle Total
03/30/17 Attend 2 2 - - - - $ 210
04/13/17 Prepare/Attend/Follow-up 3 3 - - - - $ 315
04/27/17 Prepare/Attend/Follow-up 3 3 - - - - $ 315
05/11/17 Prepare/Attend/Follow-up 3 3 - - - - $ 315
05/25/17 Prepare/Attend/Follow-up 3 3 - - - - $ 315
06/08/17 Prepare/Attend/Follow-up 3 3 - - 2 2 $ 433
06/22/17 Prepare/Attend/Follow-up 3 3 - - - - $ 315
07/06/17 Prepare/Attend/Follow-up 3 3 - - - - $ 315
07/20/17 Prepare/Attend/Follow-up 3 3 - - 2 2 $ 433
08/03/17 Prepare/Attend/Follow-up 3 3 - - - - $ 315
08/17/17 Prepare/Attend/Follow-up 3 3 - - - - $ 315
08/31/17 Prepare/Attend/Follow-up 3 3 - - 2 2 $ 433
09/14/17 Prepare/Attend/Follow-up 3 3 - - - - $ 315
09/28/17 Prepare/Attend/Follow-up 3 3 - - - - $ 315
10/12/17 Prepare/Attend/Follow-up 3 3 - - 2 2 $ 433
10/26/17 Prepare/Attend/Follow-up 3 3 - - - - $ 315
11/09/17 Prepare/Attend/Follow-up 3 3 - - - - $ 315
11/23/17 Prepare/Attend/Follow-up 3 3 - - 2 2 $ 433
12/07/17 Prepare/Attend/Follow-up 3 3 - - - - $ 315
12/21/17 Prepare/Attend/Follow-up 3 3 - - - - $ 315
Construction Cost Estimating
Initial Budget Estimate 80 - 20 - 80 - $ 12,700
Finalize Budget Estimate 40 - 10 - 20 - $ 5,370
Total Hours 179 59 30 - 110 10
Hourly Rate $ 91 $ 14 $ 75 $ 14 $ 49 $ 10
Total Cost $ 16,289 $ 826 $ 2,250 $ - $ 5,390 $ 100 $ 24,855
Total Cost for Design Assistance Scope $ 24,855
PM/Estimator Superintendent PE/Estimator
DocuSign Envelope ID: 855300C9-29C3-4358-94CF-51CA79F07D50
ID Task Name Duration Start
1 Magnolia Street Outfall Design Schedule
2 Design Meetings 191 days Thu 3/30/17
3 Design Meeting #1 1 day Thu 3/30/17
4 Design Meeting #2 1 day Thu 4/13/17
5 Design Meeting #3 1 day Thu 4/27/17
6 Design Meeting #4 1 day Thu 5/11/17
7 Design Meeting #5 1 day Thu 5/25/17
8 Design Meeting #6 1 day Thu 6/8/17
9 Design Meeting #7 1 day Thu 6/22/17
10 Design Meeting #8 1 day Thu 7/6/17
11 Design Meeting #9 1 day Thu 7/20/17
12 Design Meeting #10 1 day Thu 8/3/17
13 Design Meeting #11 1 day Thu 8/17/17
14 Design Meeting #12 1 day Thu 8/31/17
15 Design Meeting #13 1 day Thu 9/14/17
16 Design Meeting #14 1 day Thu 9/28/17
17 Design Meeting #15 1 day Thu 10/12/17
18 Design Meeting #16 1 day Thu 10/26/17
19 Design Meeting #17 1 day Thu 11/9/17
20 Design Meeting #18 1 day Thu 11/23/17
21 Design Meeting #19 1 day Thu 12/7/17
22 Design Meeting #20 1 day Thu 12/21/17
23 Budget Level Estimate 111 days Mon 7/17/17
24 Initial Budget Level Estimate 11 days Mon 7/17/17
25 Final Budget Level Estimate 11 days Mon 12/4/17
Design Meetings
Design Meeting #1
Design Meeting #2
Design Meeting #3
Design Meeting #4
Design Meeting #5
Design Meeting #6
Design Meeting #7
Design Meeting #8
Design Meeting #9
Design Meeting #10
Design Meeting #11
Design Meeting #12
Design Meeting #13
Design Meeting #14
Design Meeting #15
Design Meeting #
Design Meeting
Design Meetin
Design Meeti
Design Mee
Budget Level Estimate
Initial Budget Level Estimate
Final Budget Level Estimate
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
2017 2018
Design Schedule