HomeMy WebLinkAboutCHANGE ORDER - RFP - 8286 CONSTRUCTION CONTRACTOR FOR PROJECTS AT THE WATER & WASTEWATER TREATMENT FACILITIESCHANGE ORDER NO. 1
PROJECT TITLE: DWRF Digester North Stairs
CONTRACTOR: Hydro Construction Company, Inc.
P.0. NUMBER: 9168183
VENDOR NUMBER: 109420
CHARGE NUMBER: 503334000.562020.6
DESCRIPTION
In preparing change orders show in order as separate numbered paragraphs the
following:
1. Reason for change. 2. Description of change.
3. Change in contract cost. 4. Change in contract time
1. Extend schedule to avoid construction conflicts with the Cogen project
2. Extend schedule to July 31, 2017
3. None
4. 3 months
(Attach additional sheets as required)
ORIGINAL CONTRACT COST $49,326.00
TOTAL APPROVED CHANGE ORDERS $0.00
TOTAL PENDING CHANGE ORDERS $0.00
TOTAL THIS CHANGE ORDER $0.00
TOTAL % OF ORIGINAL CONTRACT, THIS CO: 0.00%
TOTAL % OF ORIGINAL CONTRACT, ALL CO'S: 0.00%
ADJUSTED CONTRACT COST $49,326.00
(Assuming all change orders approved)
ACCEPTED BY: ___________________________________________ DATE: ________________
Stan Javernick, VP of Operations - Hydro Construction
REVIEWED BY: ___________________________________________ DATE: ________________
Eileen Dornfest, Project Manager
REVIEWED BY: ___________________________________________ DATE: ________________
Jason Graham, Water Reclamation & Biosolids Manager
APPROVED BY: ___________________________________________ DATE: ________________
Owen L. Randall, Chief Engineer
APPROVED BY: ___________________________________________ DATE: ________________
Carol Webb, Water Resources & Treatment Operations Manager
DocuSign Envelope ID: DE980B08-4816-4857-9C4A-B4FF2374E4E3
4/7/2017
4/7/2017
4/7/2017
4/7/2017
4/7/2017