HomeMy WebLinkAboutCHANGE ORDER - RFP - 8106 UTILITY INFRASTRUCTURE CONSTRUCTION SERVICES FOR WATER, WASTEWATER, AND STORMWATER FACILITIES CAPITAL IMPROVEMENTSMichigan Ditch Tunnel Contract Change Order
May 2016 00950-1
SECTION 00950
CHANGE ORDER NO. 1
PROJECT TITLE: Michigan Ditch Tunnel
CONTRACTOR: Hydro Construction Company, Inc.
PROJECT NUMBER: PO9163360
DESCRIPTION:
1. Reason for change: Not all items could be competed due to weather.
2. Description of Change: Time Extension
3. Change in Contract Cost: $0.00
4. Change in Contract Time: New completion date; October 31, 2017.
ORIGINAL CONTRACT COST $1,211,020.00
TOTAL APPROVED CHANGE ORDERS $0.00
TOTAL PENDING CHANGE ORDERS $0.00
TOTAL THIS CHANGE ORDER $0.00
TOTAL % OF THIS CHANGE ORDER 0.0%
TOTAL C.O.% OF ORIGINAL CONTRACT 0.0%
ADJUSTED CONTRACT COST $1,211,020.00
(Assuming all change orders approved)
ACCEPTED BY: DATE: 1/31/17
Contractor's Representative
ACCEPTED BY: DATE:
Special Projects Manager
REVIEWED BY: DATE:
Senior Engineer
APPROVED BY: DATE:
Water Production Manager
APPROVED BY: DATE:
Purchasing Agent over $60,000
cc: Project File
Contractor
Purchasing
NA
DocuSign Envelope ID: FBC4A839-AA5E-4057-8697-906742453E12
2/15/2017
2/15/2017
2/16/2017