SCOPE OF CHANGE:
1. Reason and Description for Change: Colorado Boring had to expand their bore length to
meet depth requirements and avoid a storm drain
2. Change in Contract Cost: $8,951.00
3. Change in Contract Time: N/A
ORIGINAL CONTRACT COST $ 87502.00
TOTAL APPROVED CHANGE ORDER(s) $ 8951.00
$TOTAL THIS CHANGE ORDER $ 96453.00
TOTAL % OF THIS CHANGE ORDER 10.2%
TOTAL C.O.(s)% OF ORIGINAL CONTRACT %
ADJUSTED CONTRACT COST $ 8951.00
ACCEPTED BY: DATE: