HomeMy WebLinkAboutCORRESPONDENCE - AGREEMENT MISC - EMPIRE CARPENTRY LLC (2)Nix Farm Education House Work: Date: 8/24/16 General Notes: - Contractor will be required to pull all necessary State/City of Fort Collins permits at the contractor’s expense. - Contractor will be required to coordinate all necessary State/City of Fort Collins building inspections and upon completion of the job will issue to the City of Fort Collins a Letter of Completion before final payment will be issued. - Contractor to fill out owner provided Waste Management Plan forms. o Please reference the specifications for these forms. o Contractor will not receive final payment until this has been provided, filled out with back-up. o Any material with a recycle value MUST be recycled. - All work to meet City of Fort Collins Design Standards at the following link: http://www.fcgov.com/opserv/design-standards.php - All work to be done during normal business hours and to abide by the City’s noise ordinance through Neighborhood Services. Night work will not be allowed on this project. - General contractor will be required to provide their own portable toilets. Location to be coordinated with the City of Fort Collins at the construction pre-con. meeting. - Coordination of dumpster locations to be coordinated with the City of Fort Collins at pre-con. meeting. - The City of Fort Collins has smoking restrictions in certain areas. Smoking on the premises is prohibited. If smoking is necessary, employees can smoke in their personal vehicles. Please go to: fcgov.com/smokefree for more information. Education House: Window Restoration - All windows in the house need to be restored, upper & lower, (approx. 20 windows) o Only use replacement if wood is deteriorated beyond restoration.  Contractor would need to gain State approval on a window by window basis. • State staff to work with: o Michelle Chichester  Replacement might need to be entire window or just remanufactured parts.  Contractor would need to gain State approval on a window by window basis. • State staff to work with: o Korben Pugh o Abatement of lead and/or asbestos will be required before removing the windows. Depending upon the condition of the window.  Please follow the attached abatement scope of work.  Hot material labeled caulking on the windows is really a glazing material. o Remove existing window sashes and jambs as necessary to complete the work. o Install temporary coverings to minimize air and moisture infiltration. o Restore existing window sashes, jambs, glass, & glazing as necessary. o Install window package once complete. o Any painting required will be handled by another vendor. - Front Door Replacement o The front door is not the original door and is not a historically appropriate replacement. o Look at using the existing door located in the utility entry located on the east side of the building. o Contractor would need to gain State approval on the use of the existing door.  State staff to work with: • Korben Pugh - Removal of the Shed-roof Utility Room Addition o Deconstruct the shed roof - utility room addition, it is in very poor condition and has no foundation. o The door to the shed-roof addition may have been the front door to this house and could be used to replace the front door. • Exterior Painting: o Touch-up paint work will be done by the City of Fort Collins once the refurbished windows and siding have been installed. - Environmental Testing: o Asbestos has been identified on the site. Please reference the attached: “Letter of Findings”. - Contractor to ensure a clean and safe work site at all times. - All OSHA regulations to be followed at all times. BID SCHEDULE: 1. Cost to provide full scope of work. $___31,__675.___00 ______ lump sum NOTE: RCRA disposal of hazardous materials is not included in lump sum price, The additional cost of RCRA disposal if required will be billed at cost + 20% ADD/ALTERNATES: AWARD OF THE CONTRACT IS BASED ON THE BASE BID OR AT THE CITY’S SOLE OPTION IN THE EVENT THE CITY ELECTS TO INCLUDE ANY OF THE ALTERNATES LISTED BELOW TO THE LOWEST QUALIFIED RESPONSIVE AND RESPONSIBLE BIDDER BASED ON THE CUMULATIVE TOTAL OF THE BASE BID AND ALL SELECTED ALTERNATES. 1. Provide a square foot cost to abate existing siding & lead paint, remove existing siding, furnish, and install siding as needed. Siding to match existing in profile and size. This work does not include painting the siding but priming of the siding is required. Paint to be handled by others. $____40.__00 __/ _SF _____ s.f. Recieved Addendum #1 Terry Schmitz Estimator Empire Carpentry llc 09/29/16 Rev 1/1/14 Community Development & Neighborhood Services 281 N. College Ave. Fort Collins, CO 80522; Voice: 970-221-6760 FAX: 970-224-6134 CONSTRUCTION WASTE MANAGEMENT PLAN and DOCUMENTATION Note: Environmental Services staff is able to assist with questions about getting a recycle program implemented, and will also provide education and site visits upon request (call Caroline Mitchell at (970) 221-6288). PROJECT INFORMATION Address_______________________________________________Date_____________________________ Permit No._____________________________________________________________________________ General Contractor & Contact Info: __________________________________________________________ ______________________________________________________________________________________ Material1 Vendor hauling the material2 Facility recycling the material3 Total volume or weight of material4 Concrete/Masonry Wood/Lumber Metals Cardboard Trash N/A Other (describe) Required Documentation4: Provide signed documentation from the hauling company that the volumes & weights listed above are accurate. If you hauled the materials yourself, attach tickets from locations receiving the recyclables. Documentation is required in order to receive final project approval from the City. I and my City-licensed hauler certify that the above materials from my construction site were recycled in the volume / weight described and were taken to the facilities described. ______________________________________________ ____________ Signature (Contractor or Owner) Date ______________________________________________ _____________ Signature (Licensed Hauler) Date 1 At minimum, the four listed materials must be recycled. 2 Enter vendor name and phone number. If the applicant will haul the material themselves, state such. 3 Where will applicant or vendor take the material for recycling? Enter facility name and address. 4 To be completed at the end of the project. Please re-submit this form at end of project withWKHVH sectionV completed.