HomeMy WebLinkAboutCHANGE ORDER - RFP - 7421 CITY ARCHITECTURAL l& ENGINEERING WORK ORDER CONTRACTSECTION 00950
CHANGE ORDER NO. 2
PROJECT TITLE: Graves Camp Historic Structure Assessment
CONTRACTOR: RB+B
PROJECT NUMBER: PO 9154839
DESCRIPTION:
1. Reason for change:
Additional funding has been requested to support the work of sub-consultants (Larsen and
Wattle and Daub) and to enable RB+B to bring the report through completion and final
approval with the State Historic Fund. Larsen’s scope shifted as they gained a more
detailed understanding of the requirements of the Historic Structure Assessment, and
expectations of the Natural Areas Department. Wattle and Daub are being engaged to fill a
skills gap and complete the cost estimating section of the HSA.
2. Description of Change:
Now-October 1, 2016
• Coordination of contributing disciplines and integration of their work into the Historic
Structure Assessment draft (this includes the remaining pricing contribution from Wattle
+ Daub)
• Edits to the draft based on feedback from the internal team (City + sub-consultants)
• Submittal of the internally-approved HSA draft to the State Historic Fund for review
• Payment of $7,953 [50% of the Change Order] will be made upon successful submittal
of the HSA draft to the State Historical Fund
October 1-December 31, 2016
• Coordination of contributing disciplines and edits to the submitted draft, and any
subsequent drafts, based on feedback from the State Historic Fund
• Resubmittal of revised drafts to occur no later than 15 calendar days after receipt of
comments from the State
• Submittals and subsequent resubmittals shall be completed no later than December 31st,
2016
• Digital delivery of all State approved submittals to the Natural Areas department (both in
PDF and original file formats: e.g. CAD, InDesign, Word, etc.) All Work produced shall
become the property of the City of Fort Collins
• Final Payment of the remaining change order amount shall be withheld until final
approval is secured by the State and all approved submittals have been received by the
Natural Areas Department.
• In the event that the State Historical Fund does not approve the plan by December 31,
2016 due to circumstances beyond RB+B’s reasonable control, the City shall pay RB+B
$6,362.40 [40% of the Change Order]
3. Change in Contract Cost: $15,906 (See attached)
4. Change in Contract Time: December 31, 2016
ORIGINAL CONTRACT COST $ 20,980.00
TOTAL APPROVED CHANGE ORDER 16,550.00
TOTAL PENDING CHANGE ORDER .00
TOTAL THIS CHANGE ORDER 15,906.00
TOTAL % OF THIS CHANGE ORDER 76%
TOTAL C.O.% OF ORIGINAL CONTRACT 155%
ADJUSTED CONTRACT COST $ 53,436.00
(Assuming all change orders approved)
ACCEPTED BY: DATE:
Contractor's Representative
REVIEWED BY: _________________________________ DATE: _________________
Project Manager
APPROVED BY: DATE:
Director of Purchasing & Risk Management
(over $60,000)
September 9, 2016
To: Stephanie Kopplin, Project Manager
City of Fort Collins
Natural Areas Department
1745 Hoffman Road
Fort Collins, CO 80524
Re: Graves Camp Historic Structure Assessment
Subject: Additional services
Dear Stephanie,
Thank you for allowing us to present our proposal for additional services for the important work that the
City of Fort Collins is doing at the Graves Camp site.
Per our recent conversations, we feel that this request will provide the funding needed to complete this
project (reports):
Wattle & Daub for cost estimating: $ 6,220
Larsen Engineering for structural recommendations: $ 7,004
RB+B for additional consultant coordination, meetings, etc.: $ 1,812
Total Request: $15,906
Please let me know if there are any questions.
Sincerely,
Corky Bradley, AIA, LEED AP
Principal
PROPOSAL FOR STRUCTURAL ENGINEERING SERVICES
Date: 23 August 2016
Client: City of Fort Collins Natural Areas Dept
Project Name: Graves Camp
Project GENERAL Location: SCOPE OF Larimer PROJECT: County, Colorado
Structural investigation and analysis of the structures at the Graves Camp. An investigative report will
be generated and will be based on the following:
The foundations, floor framing, roof framing, and wall framing of each structure will be
analyzed to determine the structures theoretical capacities to withstand current building code
prescribed loading with respective to gravity and lateral forces.
Design of reinforcing for inadequate structure will be completed and conveyed in written form
in the report. No drawings will be produced.
The format of an example report will followed closely.
SCOPE OF STRUCTURAL SERVICES:
Perform multiple site visits to document the existing foundation, floor framing, roof framing,
wall framing, and sheathing/decking of the building and investigate the current structural
condition of these items.
This investigation will be a “limited observation”. No load or destructive testing will be
performed and we will only comment on those items which are readily visible or made evident
by surface characteristics. Unseen defects may exist in the building structures that are not
apparent due to them being concealed by the building’s finishes (drywall, siding, etc).
Perform an analysis to verify the adequacy of the structural components of each building. The
currently adopted building code by Larimer County will be used to determine the loads/forces
that the structures are required to resist.
Provide a report compiling the findings of the site investigation, the results of the analysis, and
a recommended action to be taken for each structure.
The Base Fee includes reimbursables for mileage, copies, and normal printing. Printing above
normal coordination and express delivery services will be billed at actual cost without markup.
BASE FEE: $10,200
Breakdown:
Fees previously invoiced and paid by RB+B = $3,196