Exhibit A
Transfort Bus Pads Upgrades 2016
1. GENERAL
A. This project includes improvements, and additions to bus pad locations throughout Fort Collins, see
attached drawings for specific locations. The Work includes demo and haul off of existing concrete
pavement and existing curb and gutter, grading and re-compaction of existing subgrade, and placement of
new concrete bus pads. In addition to the bus pads, several locations include adjacent concrete
replacement, including concrete sidewalk, curb and gutter, and ADA accessible handicap ramps as noted
on the attached drawings.
B. The Service Provider must provide all labor, materials and equipment, including traffic control and
barricading to accomplish the work in accordance with City standard specifications. Replacement of curb,
gutter and sidewalk shall match existing, i.e., vertical curb shall be replaced with vertical curb, etc., or as
directed by Engineer or Project Manager.
C. Concrete bus pads shown on the plan must be constructed in accordance with current Transfort Bus
Stop Design Standards & Guidelines, and LCUASS Standards.
D. Handicap ramp layout and design shall be coordinated in the field with the Project Engineer. All ramps
shall conform to current ADA and LCUASS Standards.
2. COMPLIANCE STANDARDS
A. Service Provider must refer to the Larimer County Urban Area Street Standards (LCUASS) latest
edition. These documents are available on the internet at www.larimer.org.
B. The Service Provider must submit concrete mix designs for approval by the City Streets Department
prior to starting work, with the exception of City of Fort Collins Streets Department pre-approved concrete
mix designs.
3. WORK ORDER PROCEDURE
A. A bid schedule is attached which utilizes pricing established in the Agreement.
B. Service Provider will invoice for all jobs completed on a unit price basis with the prices established in
the Bid Schedule section.
C. Work order number must be included on the billing invoices.
D. All jobs must begin within a ten (10) day period following issue of a work order. Each work order shall be
signed and returned to the issuing department within 48 hours. If the low responsive, responsible Service
Provider cannot meet this performance specification, the City has the right to offer the project to the next
lowest responsive, responsible Service Provider according to prices listed from their submitted bid
schedule. Exceptions to this policy will be made for inclement weather preventing a timely response by the
Service Provider (a one-day extension for each day of bad weather will be given), or a previous
understanding between the Service Provider and the City's departmental representative allowing more
flexibility with regard to the individual project. It will be the Service Provider's responsibility to make these
arrangements with the City's Representative.
4. PATCHING REQUIREMENT
A. Not used
5. INSPECTION
Page 3 of 4
A. It shall be the Service Provider's responsibility to notify the City Engineer, or their representative, that the
work is ready for inspection. Every request for inspection shall be made at least twenty-four (24) hours
before inspection is desired. Any work completed by the Service Provider and not inspected and accepted
by the City engineer's office shall be removed and replaced at the Service Provider's expense.
6. AWARD AND PAYMENT TERMS
A. Prices bid shall be based upon Project Specifications and it shall be each Service Provider's
responsibility to familiarize themselves with the complexities involved for all work.
B. Service Provider shall submit invoices to the City monthly. Payment will be processed by City
Departments upon the presentation of invoicing and work order.
7. TRAFFIC CONTROL
A. All traffic control, work zone protection, and/or parking control and permits shall be the responsibility of
the Service Provider, and provided in accordance with the latest revisions of the “Manual on Uniform Traffic
Control Devices for Streets and Highways” (MUTCD), the City of Fort Collins “Work Area Traffic Control
Handbook”, and the attached revisions of Sections 104 and 630, Traffic and Parking Control and Traffic
Control Devices respectively.
B. The work described in this work order will be performed entirely on City of Fort Collins property at the
Transfort Bus Pad locations. Coordinate with Transfort and Ditesco operations and provide advance
notification before disrupting normal traffic flow through the facility.
8. WARRANTY
A. Warranty will be for 24 months for all work from date of acceptance by the City.
Page 4 of 4
BID SCHEDULE
CITY OF FORT COLLINS-
TRANSFORT BUS PAD UPGRADES 2016
Work Order No. 02
Purchase Order No. _________________
BID SCHEDULE
Stop Location
Size of
Pad (SF)
Contract
Quantity
Unit Unit Price Extended Price
13A Elizabeth and Azuro - EB: Adjacent - 1 LS $ 10,525.42 $ 10,525.42
13B Elizabeth and Azuro - EB: Bus Pad 435 1 LS $ 6,289.55 $ 6,289.55
20A Shields and Raintree- SB - 1 LS - -
20B Shields and Raintree- SB: Bus Pad 570 1 LS $ 6,096.27 $ 6,096.27
27A Elizabeth and Bryan - WB: Adjacent - 1 LS - -
27B Elizabeth and Bryan - WB: Bus Pad 450 1 LS $ 9,000.00 $ 9,000.00
28A
Harmony and Shields (FRCC) - EB:
Adjacent - 1 LS - -
28B
Harmony and Shields (FRCC) - EB: Bus
Pad 300 1 LS $ 4,082.32 $ 4,082.32
Contingency 1 $2,879.48 $ 2,879.48
Total $ 38,873.04
COMPANY NAME: BANNER CONCRETE LLC
CONTRACTOR’S SIGNATURE: __________________________________________ DATE: ________________
Estimate
Date
7/29/2016
Estimate #
219
Name / Address
Ditesco
BANNER CONCRETE LLC
715 Peterson Street
Fort Collins, CO 80524
bannerconcrete@gmail.com
Accounting:970-219-1026
Project
Customer Signature
Total
Description Qty Cost Total
Bus Stop # 13 Elizabeth and Azuro Eastbound
Excavation-General less than 50 cu yd 20 98.71 1,974.20
Flatwork--6" per sq ft 800 3.84 3,072.00
Aggregate base course/Recycled base >5 tons 25 38.39 959.75
Stormwater protection-Recycled rubber filled wattle per lf 20 8.77 175.40
Traffic Control 15% 1,500.00 1,500.00
Dump fee per ton 20 21.94 438.80
Remove concrete sidewalk per sq ft 500 3.57 1,785.00
_____________________________________
$9,905.15
435 1,670.40
300 1,071.00
$6,289.55
INCLUDED ON THE NEXT PAGE
Estimate
Date
7/29/2016
Estimate #
211
Name / Address
Ditesco
BANNER CONCRETE LLC
715 Peterson Street
Fort Collins, CO 80524
bannerconcrete@gmail.com
Accounting:970-219-1026
Project
Customer Signature
Total
Description Qty Cost Total
Bus Stop #13: Elizabeth/Azuro Adjacent Work
Remove concrete sidewalk per sq ft 2,400 3.57 8,568.00
Excavation-General less than 50 cu yd 35 98.71 3,454.85
Flatwork--6" per sq ft 2,300 3.84 8,832.00
Aggregate base course/Recycled base >5 tons 30 38.39 1,151.70
Dump fee per ton 30 21.94 658.20
Truncated dome panel per sq ft 20 32.90 658.00
Pedestrian access ramp per sq ft 100 6.04 604.00
Irrigation sleeve per lf 50 10.97 548.50
Stormwater protection-Recycled rubber filled wattle per lf 50 8.77 438.50
Traffic Control 15% of job 3,800.00 3,800.00
_____________________________________
$28,713.75
200
30
200
4
4
4
714.00
394.84
153.56
87.76
987.00
1208.00
2,193.26 2,193.26
$10,525.42
Estimate
Date
7/29/2016
Estimate #
224
Name / Address
Ditesco
BANNER CONCRETE LLC
715 Peterson Street
Fort Collins, CO 80524
bannerconcrete@gmail.com
Accounting:970-219-1026
Project
Customer Signature
Total
Description Qty Cost Total
Bus Stop # 20 Shields and Raintree Southbound
Excavation-General less than 50 cu yd 15 98.71 1,480.65
Flatwork--6" per sq ft 400 3.84 1,536.00
Aggregate base course/Recycled base >5 tons 8 38.39 307.12
Stormwater protection-Recycled rubber filled wattle per lf 20 8.77 175.40
Traffic Control 1,500.00 1,500.00
Dump fee per ton 15 21.94 329.10
_____________________________________
$5,328.27
600 2,304.00
$6,096.27
Estimate
Date
8/11/2016
Estimate #
253
Name / Address
Ditesco
BANNER CONCRETE LLC
715 Peterson Street
Fort Collins, CO 80524
bannerconcrete@gmail.com
Accounting:970-219-1026
Project
Customer Signature
Total
Description Qty Cost Total
Elizabeth And Bryan St. Bus Stop
Remove concrete sidewalk per sq ft 350 3.57 1,249.50
Excavation-General less than 50 cu yd 11 98.71 1,085.81
Flatwork--6" per sq ft 645 3.84 2,476.80
Aggregate base course/Recycled base >5 tons 15 38.39 575.85
Dump fee per ton 11 21.94 241.34
Barrier curb--6" x 18" per lf 30 25.23 756.90
Reinforcing steel per pound 140 2.19 306.60
Stormwater protection-Rock filled wattle per lf 20 6.58 131.60
Irrigation sleeve per lf 40 10.97 438.80
Traffic Control 15% 1 1,100.00 1,100.00
_____________________________________
$$9,8,000.363.20 00
Estimate
Date
8/11/2016
Estimate #
254
Name / Address
Ditesco
BANNER CONCRETE LLC
715 Peterson Street
Fort Collins, CO 80524
bannerconcrete@gmail.com
Accounting:970-219-1026
Project
Customer Signature
Total
Description Qty Cost Total
FRCC Bus Stop
Excavation-General less than 50 cu yd 9 98.71 888.39
Aggregate base course/Recycled concrete base <5 tons 4 42.77 171.08
Dump fee per ton 9 21.94 197.46
Barrier curb--6" x 18" per lf 40 25.23 1,009.20
Flatwork--6" per sq ft 150 3.84 576.00
Stormwater protection-Rock filled wattle per lf 15 6.58 98.70
Traffic Control 700.00 700.00
_____________________________________
$$4082.3,640.32 83
30'-0"
14'-6"
STOP 13
ELIZABETH AND AZURO- EASTBOUND
REPLACE ADA RAMPS AS
MARKED IN THE FIELD.
COORDINATE WITH DITESCO
IN THE FIELD FOR LAYOUT.
30'-0"
21'-0"
10'-0"
STOP 20
SHIELDS AND RAINTREE - SOUTHBOUND
30'-0"
15'-0"
STOP 27
ELIZABETH AND BRYAN - WESTBOUND
5'-0"
30'-0"
STOP 28
HARMONY AND SHIELDS (FRCC) - EASTBOUND