Address: 222 LaPorte Avenue, Fort Collins, CO. 80522 DATE: July 20, 2016
FOR: UAB Construction
ITEM AMOUNT
COR 085 PR 03, Additional cost to incorporate APP into retaining Walls along Laporte Ave. 8,287.00
COR 088 6,462.00
COR 099 PR 51, Add Fertigation system and installation for the Living Wall 7,818.00
COR 101 CCA 001 - Rough-ins for Cable 14 in Training Room 112 2,377.00
COR 113 PR 57, Add chair rail to walls of Training room 112 1,389.00
COR 114 3,117.00
COR 120 0.00
COR 121 RFI 156, Change irrigation controller to Weather Trac Flow 3, model WTF3-150 (922.00)
COR 123 Apply graffiti/water repellent on first 12'-0" of building and seal re-used brick - Use -----------
$9,005 of Contractor contingency to complete this scope of work. 0.00
COR 124 Mud Room 105, Add FRP and Wader hanging shelves - $2,938 of const. contingency 0.00
COR 126 4,201.00
COR 130 5,472.00
COR 131 3,127.00
COR 132 PR 59R1, Change at Entry Column to incorporate APP on Column 1,777.00
COR 133 RFI 181, Change HWDR set #22 to Restroom function in lieu of passage set. 852.00
COR 134 RFI 182, install colored concrete in lieu of asphalt patch at north end of alley 2,608.00
COR 137 2,662.00
COR 141 5,704.00
TOTAL $ 54,931.00
This attachment becomes part of the City Change Order Form
Exchange floor adhesive to mitigate floor moisture issues.
RFI 195, Modify sealing of interior window jambs to prevent condensation issues
PR 60, Install enclosure, raceways and wires for metering requirements
Install expansion joint materials at mechanical yard using option 3 presented
RFI 166, Paint exterior window mullion snap caps to match fiberglass windows
Construction Change Order 007
RFI 119, Added spray foam at cut-outs for wall panel structural supports
DESCRIPTION
Unforseen Steel work associated w/ Syntheon panels - $38,447 Const. contingency
April, May and June project weather conditions
Change Order Request
BLOCK 32 UAB CONST PHASE Project # 7106.00
222 LAPORTE AVE, FORT COLLINS, CO 80522 Tel: Fax:
Change Order Request: 085 Date: 6/27/2016
To: Brian Hergott From: Rick Ritter
CITY OF FORT COLLINS ADOLFSON & PETERSON, INC.
Change Order Request Description Proposed Amount Days Req
Art Wall PR 03 $8,287 0
COR Reference Reason Required By Status
Design Change 5/31/2016 BIC - Owner
COR Notes
PCO Description Proposed Amount
Potential Change Order Details
086 - Three Brothers Quote # 4956 dated 5 10 2016 -PR# 3 $5,765
SITE WORK INCLUDES:
75 ADDITIONAL HRS TO REINFORCE FORMS FOR RETAINING WALL
AFTER
KNOWING THAT CHEVO STUDIO DOESN'T ALLOW TIES ON LINER,
CHANGE OF
MIX. APPROXIMATELY 25 HRS PER SECTION (X3 SECTIONS)
4,125.00
8 LF OF 4' RETAINING WALL FOR 2ND MOCK UP 640.00
10 LF OF 5'10" RETAINING WALL FOR 3RD MOCK UP 1,000.00
10 LF OF 5'10" RETAINING WALL FOR 4TH MOCK UP
086 - AP Material Cost - City Form Dated 5 24 2016 $2,148
086 - 0.65% Performance Bond $51
086 - 1.00% General Liability Ins $80
086 - 1.25% Subguard Insurance $101
086 - 1.75% Fee $143
Total for PCO 086 $8,287
Approved By:
Signature
Printed Name
Date
Change Order Request
BLOCK 32 UAB CONST PHASE Project # 7106.00
222 LAPORTE AVE, FORT COLLINS, CO 80522 Tel: Fax:
Change Order Request: 088 Date: 5/20/2016
To: Brian Hergott From: Rick Ritter
CITY OF FORT COLLINS ADOLFSON & PETERSON, INC.
Change Order Request Description Proposed Amount Days Req
RFI # 119 SPRAY FOAM T&M for Syntheon Wall Panel Cut $6,462 0
COR Reference Reason Required By Status
Field Condition Field Condition BIC - A&P
COR Notes
- Per Brian H. Email Dated 3 10 2016-
"We only get one chance to do it correct. We would like you to proceed with this scope and do it on a T&M basis. If we
can try to schedule them to do it in one trip would be best to help minimize the cost."
"Proceed and coordinate this work."
Thanks,
Brian Hergott, CCCA, LEED AP BD+C
PCO Description Proposed Amount
Potential Change Order Details
125 - Mato Insulation Proposal 3 10 2016 - Spray Foam insulation to infill areas. $6,170
125 - 0.65% Performance Bond $40
125 - 1.00% General Liability Ins $62
125 - 1.25% Subguard Insurance $78
125 - 1.75% Fee $111
Total for PCO 125 $6,462
Approved By:
Signature
Printed Name
Date
Change Order Request
BLOCK 32 UAB CONST PHASE Project # 7106.00
222 LAPORTE AVE, FORT COLLINS, CO 80522 Tel: Fax:
Change Order Request: 099 Date: 6/13/2016
To: Brian Hergott From: Christopher Meek
CITY OF FORT COLLINS ADOLFSON & PETERSON, INC.
Change Order Request Description Proposed Amount Days Req
PR 051 Irrigation Changes REVISED $7,818 0
COR Reference Reason Required By Status
PR 051 SK1-PR51, SK2-PR51, SK3-PR51 Mech
Pad, and Irrigation Plan
Design Change BIC - A&P
COR Notes
Install Multiple Sleeve through Mechanical Equipment enclosure wall for living wall fertilization system. Refer to Drawings
PCO Description Proposed Amount
Potential Change Order Details
137 - PART # 1 Bath Landscape - REVISED Cost dated 6/ 30 2016 on City Form $5,239
for Fertigation System
137 - Gregory Electric Cost dated 6 30 2016for 36x36x12 Nema 3R JBox for $500
Installation by Other for living wall
137 - 0.65% Performance Bond $37
137 - 1.00% General Liability Ins $58
137 - 1.25% Subguard Insurance $73
137 - 1.75% Fee $103
Total for PCO 137 $6,010
138 - Part 2 Bath Landscaping - Living Wall Lateral Lines and Mounting $1,726
Hardware - City Form dated 6/6/2016
138 - 0.65% Performance Bond $11
138 - 1.00% General Liability Ins $17
138 - 1.25% Subguard Insurance $22
138 - 1.75% Fee $31
Total for PCO 138 $1,808
Approved By:
Signature
Printed Name
Date
Change Order Request
BLOCK 32 UAB CONST PHASE Project # 7106.00
222 LAPORTE AVE, FORT COLLINS, CO 80522 Tel: Fax:
Change Order Request: 101 Date: 7/7/2016
To: Brian Hergott From: Christopher Meek
CITY OF FORT COLLINS ADOLFSON & PETERSON, INC.
Change Order Request Description Proposed Amount Days Req
CCA 001 Add Rough-in for Channel 14 Cable & Misc. Training Room Addds $2,377 0
COR Reference Reason Required By Status
CCA001- E201, Sk1-CCA1 Design Change BIC - A&P
COR Notes
Added Rough - In for Channel 14 Live Feed
Not to Exceed $2500.00
Even though drywall was removed and reinstalled - AP had additional backing and labor - there are no additional costs for the AP Scope.
PCO Description Proposed Amount
Potential Change Order Details
151 - Gregory T&M Cost for CCA 001 Channel 14 Cable dated 7 5 2016 $1,580
151 - Holsinger - No Cost Per EMAIL dated 7 1 2016 $0
151 - Colorado Doors -Project: 6160JAS -City of Ft Collins Utilities Admin Bldg.~ $690
-A & P
Per CCA-01 -Add card reader @140
1 Single Door #140
1 Wall Mount Reader MT15 BLACK LO
2 FIELD SERVICE LABOR MIHW
2 pull wire PULL WIRE MIHW
151 - 0.65% Performance Bond $15
151 - 1.00% General Liability Ins $23
151 - 1.25% Subguard Insurance $29
151 - 1.75% Fee $41
Total for PCO 151 $2,377
Approved By:
Signature
Printed Name
Date
Change Order Request
BLOCK 32 UAB CONST PHASE Project # 7106.00
222 LAPORTE AVE, FORT COLLINS, CO 80522 Tel: Fax:
Change Order Request: 113 Date: 6/28/2016
To: Brian Hergott From: Christopher Meek
CITY OF FORT COLLINS ADOLFSON & PETERSON, INC.
Change Order Request Description Proposed Amount Days Req
PR 057 Chair Rail in Training Room 112 $1,389 0
COR Reference Reason Required By Status
PR 057 Design Change BIC - A&P
COR Notes
Add Chair Rail in the Training Room Per PR 057
Install Chair Rail, Caulk and Paint per sample reviewed and approved at OAC Meeting 6 28 2016
PCO Description Proposed Amount
Potential Change Order Details
142 - AP Cost to Add Chair Rail in Training Room per PR 057 City Form Dated 6 $1,326
28 2016
142 - 0.65% Performance Bond $9
142 - 1.00% General Liability Ins $13
142 - 1.25% Subguard Insurance $17
142 - 1.75% Fee $24
Total for PCO 142 $1,389
Approved By:
Signature
Printed Name
Date
Change Order Request
BLOCK 32 UAB CONST PHASE Project # 7106.00
222 LAPORTE AVE, FORT COLLINS, CO 80522 Tel: Fax:
Change Order Request: 114 Date: 7/8/2016
To: Brian Hergott From: Christopher Meek
CITY OF FORT COLLINS ADOLFSON & PETERSON, INC.
Change Order Request Description Proposed Amount Days Req
April May and June Weather Conditions $3,117 0
COR Reference Reason Required By Status
Owner Change BIC - A&P
COR Notes
PCO Description Proposed Amount
Potential Change Order Details
153 - Material Billed for Weather Conditions in April, May, and June 2016- $486
Mawson
153 - Equipment Billed for Weather Conditions in April, May, and June 2016- $189
TempAir
153 - Labor Associated with Weather Conditions in April, May, and June 2016- AP $2,301
153 - 0.65% Performance Bond $19
153 - 1.00% General Liability Ins $30
153 - 1.25% Subguard Insurance $38
153 - 1.75% Fee $54
Total for PCO 153 $3,117
Approved By:
Signature
Printed Name
Date
Change Order Request
BLOCK 32 UAB CONST PHASE Project # 7106.00
222 LAPORTE AVE, FORT COLLINS, CO 80522 Tel: Fax:
Change Order Request: 120 Date: 6/7/2016
To: Brian Hergott From: Christopher Meek
CITY OF FORT COLLINS ADOLFSON & PETERSON, INC.
Change Order Request Description Proposed Amount Days Req
Ledger Angle - Lintel Brackets- Additional Steel Scope for Syntheon Panel Install $0 0
COR Reference Reason Required By Status
Contingency BIC - A&P
COR Notes
PCO Description Proposed Amount
Potential Change Order Details
136 - Steel Fab Additional structural steel scope / work to coordinate and install $35,237
Syntheon Panels - City Form Dated 5 9 2016
136 - Holsinger Lintel Foam infll at 3rd Floor - Proposal dated 5 2 2016 $3,210
136 - Contingency -$38,447
Total for PCO 136 $0
Approved By:
Signature
Printed Name
Date
Change Order Request
BLOCK 32 UAB CONST PHASE Project # 7106.00
222 LAPORTE AVE, FORT COLLINS, CO 80522 Tel: Fax:
Change Order Request: 121 Date: 7/1/2016
To: Brian Hergott From: Christopher Meek
CITY OF FORT COLLINS ADOLFSON & PETERSON, INC.
Change Order Request Description Proposed Amount Days Req
Landscape RFI # 156 Irrigation Controller -$922 0
COR Reference Reason Required By Status
RFI # 156 - PR 051 Design Change BIC - A&P
COR Notes
1) The irrigation master valve & flow sensor is stated as a Weather Trac Flow 3 model WTF3-150. Please provide
additional detail on this item, i.e., is it normally open or normally closed? Photo Diode”, etc.
--- Master valve should be normally CLOSED. with Photo Diode (PDH) register.
2) The controller stated in PR#51 is a change from the base irrigation controller from a Rainmaster Eagle to a Weather
Trac ET PRO3, Model WT-PRO 3-C-24-SWM. This is not a two wire controller. Please clarify spec for a Weather Trac two
wire controller.
--- This project will use standard wiring. Two-Wire will not be used.
3) Please clarify if the Rainbird Decoder as specified is still desired for the Weather Trac controller once the correct
model is specified.
---Decoders will not be required. This will not be a Two-Wire system.
PCO Description Proposed Amount
Potential Change Order Details
148 - Bath Price 6 16 2016 RFI # 156 - PR 051 Weather Trac Controllder and -$880
hydrometer in liew of specified controller, Master Valve and Flow Sensor
Deduct
148 - 0.65% Performance Bond -$6
148 - 1.00% General Liability Ins -$9
148 - 1.25% Subguard Insurance -$11
148 - 1.75% Fee -$16
Total for PCO 148 -$922
Approved By:
Signature
Printed Name
Date
Change Order Request
BLOCK 32 UAB CONST PHASE Project # 7106.00
222 LAPORTE AVE, FORT COLLINS, CO 80522 Tel: Fax:
Change Order Request: 123 Date: 7/1/2016
To: Brian Hergott From: Christopher Meek
CITY OF FORT COLLINS ADOLFSON & PETERSON, INC.
Change Order Request Description Proposed Amount Days Req
OBB - Graffiti and Water - Contingency $0 0
COR Reference Reason Required By Status
Owner Buy Back Contingency BIC - A&P
COR Notes
Add for Graffiti and Water Repellent on Building Exterior
Elevation 100-112 Building Perimeter
PCO Description Proposed Amount
Potential Change Order Details
149 - Maximum Painting LLC Cost Dated 7 1 2016 - Apply Sure Klean Block $5,470
Guard and Graffiti control from elevation 100 to 112 on building perimeter
149 - Maximum Painting LLC Cost Dated 7 1 206 - Apply Sure Klean Block Guard $3,535
and Graffiti control at all areas of owner supplied brick (indicated as WA01B
on A-602)
149 - Contingency Item - Owner Buy Back -$9,005
Total for PCO 149 $0
Approved By:
Signature
Printed Name
Date
Change Order Request
BLOCK 32 UAB CONST PHASE Project # 7106.00
222 LAPORTE AVE, FORT COLLINS, CO 80522 Tel: Fax:
Change Order Request: 124 Date: 7/1/2016
To: Brian Hergott From: Christopher Meek
CITY OF FORT COLLINS ADOLFSON & PETERSON, INC.
Change Order Request Description Proposed Amount Days Req
Mudd Room FRP and Shelving Contingency- Owner Buy Back $0 0
COR Reference Reason Required By Status
OBB Buyout Contingency BIC - A&P
COR Notes
Per OAC 6 28 2016
- Install New Boot Shelves (4) 12' Shelves
- Install FRP on 2 Walls 8' Height
Contingency - Owner Buy Back
PCO Description Proposed Amount
Potential Change Order Details
155 - AP Shelving install - 8' x 16" (6) Total $1,340
155 - ABS FRP 24 Linear Feet at 8' High $1,598
155 - Construction Contingency - Owner Buy Back -$2,938
Total for PCO 155 $0
Approved By:
Signature
Printed Name
Date
Change Order Request
BLOCK 32 UAB CONST PHASE Project # 7106.00
222 LAPORTE AVE, FORT COLLINS, CO 80522 Tel: Fax:
Change Order Request: 126 Date: 6/28/2016
To: Brian Hergott From: Christopher Meek
CITY OF FORT COLLINS ADOLFSON & PETERSON, INC.
Change Order Request Description Proposed Amount Days Req
RFI # 166 Painted Snap Caps $4,201 0
COR Reference Reason Required By Status
RFI # 166 Design Change BIC - A&P
COR Notes
During the submittal process an Extra Dark Bronze Anodized finish was desired for the snap cap at the exterior windows .
After review of the exterior mock-up, it was decided that a painted finish would match better. Please confirm that the
exterior snap clip is to be changed from an Anodized finish to the painted finish . The attached pdf shows the painted finish.
The painted finish is the desired direction. If this is the same finish that was reviewed on site then it
is acceptable.
PCO Description Proposed Amount
Potential Change Order Details
143 - Commercial Glass - City Form Dated 6 23 2016 for Extra Dark Bronze $4,011
Painted Dress Caps per RFI # 166
143 - 0.65% Performance Bond $26
143 - 1.00% General Liability Ins $40
143 - 1.25% Subguard Insurance $51
143 - 1.75% Fee $72
Total for PCO 143 $4,201
Approved By:
Signature
Printed Name
Date
Change Order Request
BLOCK 32 UAB CONST PHASE Project # 7106.00
222 LAPORTE AVE, FORT COLLINS, CO 80522 Tel: Fax:
Change Order Request: 130 Date: 6/21/2016
To: Brian Hergott From: Christopher Meek
CITY OF FORT COLLINS ADOLFSON & PETERSON, INC.
Change Order Request Description Proposed Amount Days Req
Moisture Mitigation $5,472 0
COR Reference Reason Required By Status
Owner Change BIC - A&P
COR Notes
PCO Description Proposed Amount
Potential Change Order Details
140 - Elements CO # 02 Dated 5 10 2016 for Moisture Mitigation Adhesive $5,225
140 - 0.65% Performance Bond $34
140 - 1.00% General Liability Ins $53
140 - 1.25% Subguard Insurance $66
140 - 1.75% Fee $94
Total for PCO 140 $5,472
Approved By:
Signature
Printed Name
Date
Change Order Request
BLOCK 32 UAB CONST PHASE Project # 7106.00
222 LAPORTE AVE, FORT COLLINS, CO 80522 Tel: Fax:
Change Order Request: 131 Date: 7/1/2016
To: Brian Hergott From: Christopher Meek
CITY OF FORT COLLINS ADOLFSON & PETERSON, INC.
Change Order Request Description Proposed Amount Days Req
Caulking Expansion At the Mech Yard $9,382 0
COR Reference Reason Required By Status
Field Condition Field Condition BIC - A&P
COR Notes
Option 1 - Recommended -EmSeal if gap is over 1"-1.5"
Option 2 - Owner Request for added backing rod and caulk.
Option 3 - Split Backing Rod / Caulking and EmSeal - Using both systems
PCO Description Proposed Amount
Potential Change Order Details
146 - OPTION 2 - RSI Cost Dated 6 9 2016 - For Added Backing Rod and $1,536
Caulking at the Mechanical Yard - Not Recommended over 1"
146 - 0.65% Performance Bond $10
146 - 1.00% General Liability Ins $15
146 - 1.25% Subguard Insurance $20
146 - 1.75% Fee $28
Total for PCO 146 $1,609
147 - OPTION 1 - RSI Dated 6 9 2016 EmSeal Color Seal - Recommended for $4,436
this application
147 - 0.65% Performance Bond $29
147 - 1.00% General Liability Ins $45
147 - 1.25% Subguard Insurance $56
147 - 1.75% Fee $80
Total for PCO 147 $4,646
158 - OPTION 3 - RSI to install both systems Interior and Exterior where $2,986
designated
158 - 0.65% Performance Bond $19
158 - 1.00% General Liability Ins $30
158 - 1.25% Subguard Insurance $38
158 - 1.75% Fee $54
Total for PCO 158 $3,127
Approved By:
Signature
Printed Name
Date
Change Order Request
BLOCK 32 UAB CONST PHASE Project # 7106.00
222 LAPORTE AVE, FORT COLLINS, CO 80522 Tel: Fax:
Change Order Request: 132 Date:
To: Brian Hergott From: Christopher Meek
CITY OF FORT COLLINS ADOLFSON & PETERSON, INC.
Change Order Request Description Proposed Amount Days Req
PR 059 R1 Custom Artwork Wall $1,777 0
COR Reference Reason Required By Status
PR 059 Design Change BIC - A&P
COR Notes
Architectural:
• Feature wall at entry shall be finished with custom art work as shown.
• SK1-PR59, SK2-PR59, SK3-PR59, SK4-PR59 ** Carpentry will be completed out of AP Budget.
PCO Description Proposed Amount
Potential Change Order Details
159 - Division 4 Cost Dated 7 8 2016 - Delta for Deletion of Brick and $1,297
Remobilization for Stone work after Art is set
159 - RSI Caulking Brick to Art Work Cost Dated 6 22 2016 $400
159 - 0.65% Performance Bond $11
159 - 1.00% General Liability Ins $17
159 - 1.25% Subguard Insurance $22
159 - 1.75% Fee $31
Total for PCO 159 $1,777
Approved By:
Signature
Printed Name
Date
Change Order Request
BLOCK 32 UAB CONST PHASE Project # 7106.00
222 LAPORTE AVE, FORT COLLINS, CO 80522 Tel: Fax:
Change Order Request: 133 Date:
To: Brian Hergott From: Christopher Meek
CITY OF FORT COLLINS ADOLFSON & PETERSON, INC.
Change Order Request Description Proposed Amount Days Req
RFI # 181 Door Hardware Set # 22 $852 0
COR Reference Reason Required By Status
RFI # 181 Design Change BIC - A&P
COR Notes
In lieu of the passage set noted in hardware set #22 use the following privacy set: ND40S SPA 10-025, 626.
PCO Description Proposed Amount
Potential Change Order Details
160 - COLORADO DOORWAYS Cost dated 6 26 2016 COR # 11 Add 3 ea $813
Privacy Set ND40S Spa 1025
160 - 0.65% Performance Bond $5
160 - 1.00% General Liability Ins $8
160 - 1.25% Subguard Insurance $10
160 - 1.75% Fee $15
Total for PCO 160 $852
Approved By:
Signature
Printed Name
Date
Change Order Request
BLOCK 32 UAB CONST PHASE Project # 7106.00
222 LAPORTE AVE, FORT COLLINS, CO 80522 Tel: Fax:
Change Order Request: 134 Date:
To: Brian Hergott From: Christopher Meek
CITY OF FORT COLLINS ADOLFSON & PETERSON, INC.
Change Order Request Description Proposed Amount Days Req
RFAI #182 East Alley Concrete Paving $2,608 0
COR Reference Reason Required By Status
RFI # 182 Design Change BIC - A&P
COR Notes
Drawing Ref: LS201 and attached pdf
After review of the Integral Color Concrete Paving with Brian Hergott of CoFC, please clarify that the Type 1 - Harvest Gold
is to extend in the North end of the East alley to the end of the curb as shown in the attached pdf. Yes Proceed and provide a detailed cost
breakout showing the credit for the asphalt paving and the add for the colored concrete.
PCO Description Proposed Amount
Potential Change Order Details
162 - AP - Best Way Concrete Material - Color Concrete $8,011
162 - Three Brothers Quote # 5029 Dated 6 23 2016 Labor for Colored Concrete $2,530
to Alley Inleu of Asphalt
162 - AP - Layout and Asphalt Delta - Credit back remaining Allowance -$8,050
162 - 0.65% Performance Bond $16
162 - 1.00% General Liability Ins $25
162 - 1.25% Subguard Insurance $32
162 - 1.75% Fee $45
Total for PCO 162 $2,608
Approved By:
Signature
Printed Name
Date
Change Order Request
BLOCK 32 UAB CONST PHASE Project # 7106.00
222 LAPORTE AVE, FORT COLLINS, CO 80522 Tel: Fax:
Change Order Request: 137 Date:
To: Brian Hergott From: Christopher Meek
CITY OF FORT COLLINS ADOLFSON & PETERSON, INC.
Change Order Request Description Proposed Amount Days Req
PR 060 IT Sleeves $2,662 0
COR Reference Reason Required By Status
PR 060 Design Change BIC - A&P
COR Notes
1.0X Drawing E-201
· Added: One-(1) NEMA 1 screw cover enclosure for meters
· Added: Four-(4) conduits for meters.
· Added: Five-(5) data junction boxes in Electrical 110.
· Added: One-(1) data junction box in Mechanical 106.
2.0X Drawing E-202
· Added: One-(1) data junction box in Electrical 212.
3.0X Drawing E-203
· Added: One-(1) data junction box in Electrical 312.
NOTE: This Costs includes the wiring from the box to the approximate meter locations but does not include terminations.
PCO Description Proposed Amount
Potential Change Order Details
161 - GE Cost Dated 7 5 2016 PR 060 Added IT Sleeving $2,542
161 - 0.65% Performance Bond $17
161 - 1.00% General Liability Ins $26
161 - 1.25% Subguard Insurance $32
161 - 1.75% Fee $46
Total for PCO 161 $2,662
Approved By:
Signature
Printed Name
Date
Change Order Request
BLOCK 32 UAB CONST PHASE Project # 7106.00
222 LAPORTE AVE, FORT COLLINS, CO 80522 Tel: Fax:
Change Order Request: 141 Date:
To: Brian Hergott From: Christopher Meek
CITY OF FORT COLLINS ADOLFSON & PETERSON, INC.
Change Order Request Description Proposed Amount Days Req
RFI # 195 Window System Infill $5,704 0
COR Reference Reason Required By Status
RFI # 195 - Design Change BIC - A&P
COR Notes
This is a confirming RFI.
Please confirm per conversations regarding the interior window infill process, that it is to go as follows (and shown in the
attached pdf):
1) Caulk window system to wood backing.
2) Insert 2-1/4" rip of Rigid Foam Insulation.
3) Caulk foam to window frame and caulk foam to wood backing, making sure to seal at the bottom of the window frame.
4) Screw stud to pinch foam to wood backing.
5) Infill with drywall allowing for reveal to be equal on both sides of the window.
The steps described above are accurate to what was discussed on site.
PCO Description Proposed Amount
Potential Change Order Details
165 - Holsinger COR # 19 Dated 7 13 2016 Cost for RFI # 195 Window System- $4,000
Delta cost adjusted for batt insulation and labor at Exterior Window
Openings
165 - AP MISC. Material $1,446
165 - 0.65% Performance Bond $35
165 - 1.00% General Liability Ins $55
165 - 1.25% Subguard Insurance $69
165 - 1.75% Fee $98
Total for PCO 165 $5,704