Mulberry Bridge Urban Design and Landscaping
MARCH 2, 2016 Pre-Bid Presentation
Mulberry Bridge
Urban Design and Landscaping
Bid Number: 8250
Pre-Bid Meeting
March 2, 2016
2:00 PM @ 215 N Mason St.
Conference Room 1A
City of Fort Collins – Engineering Department
Capital Projects Group
2
3/2/2016
2
Introductions
Engineering – Capital Projects
Kyle Lambrecht Project Manager 970-221-6566
Caleb Feaver Project Engineer 970-416-4229
Craig Farver Construction Inspector 970-222-0854
Purchasing
Elliot Dale Buyer 970-221-6777
3
Attendance
• Please be sure to register
• Bid Opening
March 16, 2016 @ 3:00 PM (our clock)
Location – 215 North Mason Street
Submit bids to Purchasing Department
4
3/2/2016
3
Reference Checks
• Required document for bid opening
• Project descriptions and owner contacts for:
• At least 3 projects
• Contract amount of $250,000 or greater
• Contractor must have used the same Project
Manager as proposed for this project
5
Important Contract Dates
• Pre-Award Meeting
At City’s discretion based on reference checks
Date and time to be determined prior to contract award
• Pre-Construction Meeting
Mandatory meeting prior to start of construction
Date and time to be determined after contract award
• Construction Start Date
Approximately first week of April, 2016
6
3/2/2016
4
Important Contract Dates
• Substantial Completion
Sixty (60) calendar days
Further defined in General Conditions slides
• Final Acceptance
Ten (10) calendar days from Substantial Completion
Further defined in General Conditions slides
7
Contract Documents
• Plan Sheets
Prepared by: BHA Design, Inc.
• Specification Book
Prepared by: City of Fort Collins & BHA Design, Inc.
8
3/2/2016
5
Project Limits
9
Summary of Work
• Irrigation
• Plants
• Shrubs
• Trees
• Boulders
• Organic and inorganic mulch
• Concrete planter pots
• Cast-in-place concrete planter beds
• Concrete pedestrian lookout pads
• Mobilization, traffic control, earthwork/site preparation,
erosion control
10
3/2/2016
6
Summary of Work
• Traffic Control is bid as Lump Sum
• Includes all necessary work and material
• Traffic Control Plans must be approved through City
Traffic Department prior to work
• Material Testing
• Paid for by the City of Fort Collins through CTL
Thompson
• Contractor will schedule testing as required through
Craig Farver (Construction Inspector)
11
Highlights of General Conditions
• Superintendents
The General Contractor SHALL employ a full time
superintendent whose sole responsibility is to monitor
and coordinate all facets of the work
12
3/2/2016
7
Highlights of General Conditions
• Liquidated Damages – Substantial Completion
If the Contractor goes past the calendar days for
Substantial Completion, damages in the amount of
One Thousand Dollars ($1,000.00) for each calendar
day will be assessed
• Substantial Completion Defined
Completion and acceptance of the following items as
awarded by alternative: placement of erosion control
items, removals, earthwork, topsoil placement, fine
grading, boulder placement, concrete placement,
native seeding, mulching and tackifier, landscaping
installation, and irrigation installed and fully functioning
13
Highlights of General Conditions
• Liquidated Damages – Final Acceptance
If the contractor goes past the calendar days for Final
Acceptance, damages in the amount of One
Thousand Dollars ($1,000.00) for each calendar day
will be assessed
• Final Acceptance Defined
Completed punch list items, erosion control items
removed, site clean-up, and demobilization
14
3/2/2016
8
Highlights of General Conditions
• Project Coordination Meetings
• Weekly meetings on site or at 281 N College
• Contractor to submit weekly a two week look-ahead
schedule. Contractor may be required to submit
additional schedules depending on progress of the
project and at the City’s discretion.
15
Highlights of General Conditions
• Construction Hours
• Standard working hours are from 7:00 am to 6:00
pm, Monday through Friday
• Lane Closures are ONLY allowed between 8:30 am
and 3:30 pm, Monday through Friday
• Weekend Work and/or Extended Hours Work may
be granted. Requests for either must be made it
writing a minimum of 48 hours in advance.
Requests are subject to approval by the City of Fort
Collins.
16
3/2/2016
9
Traffic Control
• Contractor Responsibilities
• Contractor responsible for developing and getting approval of
Traffic Control Plans prior to work
• Maintain vehicle, bicycle and pedestrian traffic at all times
using existing configuration or approved detours.
• ALL detours for ALL modes of transportation shall be approved
by the City prior to implementation
• Maintain access to all local businesses
• Review all upcoming lane closure needs and/or changes in
traffic control setup at Weekly Progress Meetings
• Traffic Control Plans need to be submitted to the City seven
(7) days prior to setup
• Additional information: http://www.fcgov.com/traffic/watc.php
17
Highlights of General Conditions
• Lane Rental – Revision of Section 104
• Approved Lane Rental
• Contractor granted allowance of fifty five (55) lane-days
• Lane-days in excess of allowance will be deducted from
payment to Contractor - $500 per lane-day
• Lane-day is measured as any closure of vehicular traffic
lane as shown in approved Traffic Control Plan
• Excludes bicycle lanes and sidewalks
• Lane closures will not be measured for approved night
work (8:00 pm to 5:00 am)
• Lane closures shall be documented in TCS diaries each
day a closure is in use. Copy of diary shall be given to
Engineer at the end of each day of lane closure
18
3/2/2016
10
Highlights of General Conditions
• Lane Rental – Revision of Section 104 (Continued)
• Unapproved Lane Rental
• Contractor charged hourly lane rental fee (rounded up to
nearest whole hour) for any lane closure set up outside of
working hours per approved Traffic Control Plan and/or
work performed without an approved Traffic Control Plan.
• Unapproved Lane Rental Fee is $1,000 per lane-hour
• Fee will be measured and applied separately to each lane
impacted by unapproved lane closure
• Fee does not constitute authorization to work without an
approved Traffic Control Plan
• Fee may be charged in addition to other fees as defined in
the Contract
19
Highlights of General Conditions
• Haul Routes
• Arterial and Collector Streets ONLY. Contractor will
not be allowed to use Residential Streets to access
the site
• Hauls to or from Martin Marietta Materials (MMM)
on Taft Hill Road must enter and exit MMM site from
the NORTH to CR 54G
• See Project Special Specification Section 107 for
haul route and covered load requirements
20
3/2/2016
11
Highlights of General Conditions
• Site Clean-Up
• Construction work shall be kept and accomplished
in a neat, clean and orderly fashion
• Street sweeping may be required in order to
minimize vehicle tracking and to meet EPA storm
water quality requirements
• Dust control will be required as necessary
21
Erosion Control
• Contractor Responsibilities
• Erosion Control in accordance with Sheets S1 – S4
in plans
• Contractor is responsible for maintaining and
repairing all erosion control devices throughout the
project
• Payment will be made under the “208” pay items
22
3/2/2016
12
Material Submittals
• Reviewed by the City
• Electronic submittals preferred
• Shop Drawings
• 2 copies (1 kept by City, 1 returned to Contractor)
23
Weather Days
• See “Summary of Work” Section
• Monthly anticipated calendar days lost to adverse
weather conditions
24
3/2/2016
13
Staging Area
• Contractor required to identify staging area if one is necessary
• This is outside of the contract
• Staging/stockpiling materials is NOT allowed inside floodplain
25
26
Highlights from Specifications
3/2/2016
14
Sections 201, 202, 203, 207, 208
Measurement and Payment
201 - Clearing and Grubbing Lump Sum
202 – Remove Sidewalk Square Yard
203 – Earthwork and Site Preparation Lump Sum
207 – Potting Soil in Raised Planters Cubic Yard
207 – Topsoil (Special) and Soil
Amendment
Cubic Yard
208 – Inlet Protection Each
208 – Erosion Log – 12 Inch Linear Foot
208 – Concrete Washout Structure Each
27
Sections 212, 213
28
Measurement and Payment
212 – Fine Grading Square Foot
212 – Upland Seed Mix and Crimped
Straw Square Foot
213 – Steel Landscape Edging Linear Foot
213 – Cobble Mulch – 1.5 Inch to 4
Inch and Weed Barrier Ton
213 – Cobble Mulch – 3 Inch to 6 Inch
and Weed Barrier Ton
213 – Cobble Mulch – 8 Inch to 12
Inch and Weed Barrier Ton
213 – Wood (Organic) Mulch – Haul
and Place Cubic Yard
213 – Wood (Organic) Mulch –
Material Only Cubic Yard
3/2/2016
15
Section 213 (Continued)
Measurement and Payment
213 – Boulder (Sandstone) – ‘A’
Boulder (24X24X48) Each
213 – Boulder (Sandstone) – ‘B’
Boulder (24X24X36) Each
213 – Boulder (Sandstone) – ‘C’
Boulder (24X24X24) Each
213 – Boulder (Sandstone) – ‘D’
Boulder (20X18X18) Each
29
Section 214
Measurement and Payment
Perennials Each
Ornamental Grasses Each
Shrubs – 1 Gallon Each
Shrubs – 3 Gallon Each
Shrubs – 5 Gallon Each
Shrubs – 10 Gallon Each
Shrubs – 4 Foot Height Each
30
3/2/2016
16
Section 214 (Continued)
Measurement and Payment
Deciduous Shade Tree – 2.5 Inch
Caliper Each
Ornamental Tree – 6 Foot Clump Each
Ornamental Tree – 2 Inch Caliper Each
Evergreen Tree – 6 Foot Height Each
Evergreen Tree – 15 Gallon Each
31
Landscape Establishment Period
• From Initial Installation through Final Acceptance
The City will be responsible for maintenance, repairs, and plant replacement
after Final Acceptance.
Lemay Medians
32
3/2/2016
17
Lemay Medians
33
Mulberry Medians
34
3/2/2016
18
601
Structural Concrete
Measurement and Payment
Raised Concrete Planters Each
35
Overlook Areas
36
3/2/2016
19
607
Fences
Measurement and Payment
Fence (Plastic) Linear Foot
37
• Fencing to be placed between work zone and floodway
• No work, staging, stockpiling, or construction traffic inside floodway
622
Planter Pots
Measurement and Payment
Type I Concrete Planter Pot Each
Type II Concrete Planter Pot Each
Type III Concrete Planter Pot Each
38
3/2/2016
20
Planter Pots
39
623
Irrigation System
Measurement and Payment
Irrigation Lump Sum
Irrigation Tap, Meter and Backflow Lump Sum
Ad Alternative
Irrigation – Spray (Northeast Quadrant) Lump Sum
Ad Alternative
Irrigation – Spray (Southeast Quadrant) Lump Sum
40
• Please reference specifications for meter, tap, backflow preventer, electric
installation
3/2/2016
21
Sections 626, 630
Measurement and Payment
626 – Mobilization Lump Sum
630 – Construction Zone Traffic Control Lump Sum
41
Addendum 1
• Pre-bid PowerPoint slides
• Water tap, meter, backflow preventer specifications and
details
• Revision to Specification 630 regarding approved lane
closure hours
• Answers to Contractor questions
42
3/2/2016
22
43
Questions?