HomeMy WebLinkAboutCHANGE ORDER - RFP - 7479 SOUTHEAST COMMUNITY PARK (3)F:\2013\2-13-0010 Ft Collins SE Community Park\management\01_proposal_contract\Change Order #4\2016 0606 SECP SCOPE Contract
Amendment_CA fees.docx
1200 Bannock Street
Denver, Colorado 80204
Tel 303 571.0053
Fax 303 825.0438
www.civitasinc.com
May 12, 2016
Kurt Friesen
Craig Kisling
City of Fort Collins
215 North Mason Street
Fort Collins, Colorado 80524
Re: Contract Amendment: Professional Landscape Architectural Services for
7479 Southeast Community Park
CVT# 2‐13‐ 0010
Dear Kurt and Craig,
Enclosed is a revised proposal for Construction Administration fees per your request. This
request includes Construction Administration fees from Civitas, JVA Inc., and Clanton &
Associates only. All fees pertaining to site visits and field reports have been excluded from this
proposal. It is our understanding that the city will contract directly with Ripley Design Inc, RB+B
Architects, Interwest Consulting Group, Abrahamson Engineering, and Hines Inc for
Construction Administration services, and that Civitas will not be included at any level with
coordination of these direct contracts.
This proposal also includes an add service request for work completed towards project
individual permit submittal to USACE
The fees are defined in the proposal and spreadsheet following this letter.
Please give me a call should you have any questions or comments.
Sincerely,
Craig Vickers
Principal
Attachments
F:\2013\2-13-0010 Ft Collins SE Community Park\management\01_proposal_contract\Change Order #4\2016 0606 SECP SCOPE Contract
Amendment_CA fees.docx
2
CONTRACT AMENDMENT: PROFESSIONAL LANDSCAPE ARCHITECTURE SERVICES FOR
7479 SOUTHEAST COMMUNITY PARK
CVT# 2‐13‐0010
PROJECT INFORMATION
Owner‐Client:
CITY OF FORT COLLINS
215 North Mason St.
Fort Collins, CO 80522
970.221.6367
Craig Kisling, Project Manager
970.416.2260
ckisling@fcgov.com
Prime and Landscape Architectural Consultant:
CIVITAS, INC.
1200 Bannock Street
Denver, CO 80204
Craig Vickers, Principal in Charge
cvickers@civitasinc.com
Robin Rooney, Project Manager
rrooney@civitasinc.com
Subconsultant(s) to Civitas:
ERO RESOURCES
CLANTON & ASSOCIATES
JVA, INC.
SITE INFORMATION
Jurisdiction: City of Fort Collins
Total Site Area: About 50 acres
Total Project Budget:
F:\2013\2-13-0010 Ft Collins SE Community Park\management\01_proposal_contract\Change Order #4\2016 0606 SECP SCOPE Contract
Amendment_CA fees.docx
3
GENERAL TEAM ROLES and SCOPE OF SERVICES Requested Add Service from ERO
Resources for work completed on revisions to USACE permit submittal.
B. Construction Administration services (detailed by firm)
Civitas
Civitas will participate in Construction Administration tasks for Southeast Community Park
to include the following:
1. Coordination with City of Fort Collins representatives during construction phase
2. Submittal Review of the following specification sections:
a. 05 52 13 Pipe & Tube Railings
b. 05 70 00 Decorative Metal (Signage)
c. 06 15 33 Wood Patio Decking
d. 12 93 00 Site Furnishings
3. Shop Drawing Review of the following specification sections:
a. Handrails for Stairs
b. Park Entry Signage
c. Gabion Walls
d. Log Bench A and B
e. Ipe Deck Plate Steel Fascia connections
f. Harvest Table
g. Greenscreen Walls
h. Zipgro walls
i. Hops Trellis
j. Arbor
4. Mock‐up Review of the following – to be done during Site Visits on a Time &
Material Basis.
a. Park entry sign
b. Gabion Walls
c. Log Bench A and B
d. Greenscreen Walls
e. Zipgro Walls
f. Hops Trellis
g. Arbor
5. Responses to RFI’s from contractor
6. Record drawings based upon redlines provided to design team by contractor.
EXCLUDED FROM CIVITAS PROPOSAL:
1. Participation in Pre‐construction meeting or site construction kick off meeting.
2. Any participation in locating, tagging or selection of plant material for the project.
3. Submittal Review of the following specification sections:
a. 05 73 00 Steel Wire Rope Railing Systems
b. 06 10 63 Exterior Rough Carpentry
c. 09 91 13 Paint (Silos)
d. 26 56 68 Exterior Athletic Lighting
e. 32 13 13 Shotcrete
f. 32 14 00 Unit Paving
g. 32 34 00 Pedestrian Bridge (new)
h. 32 91 00 Landscape Systems
i. 32 92 00 Turf and Grasses
j. 32 93 00 Trees, Plants and Groundcovers
4. Shop Drawing Review of the following:
F:\2013\2-13-0010 Ft Collins SE Community Park\management\01_proposal_contract\Change Order #4\2016 0606 SECP SCOPE Contract
Amendment_CA fees.docx
4
a. 05 73 00 Steel Wire Rope Railing Systems
b. 32 34 00 Pedestrian Bridge (new)
c. Compost Bin
d. Steel reinforcement in concrete site walls
e. Community garden fencing
f. Dog Park Fencing
5. Mock‐up Review of the following specification sections:
a. 09 91 13 Paint (Silos)
b. 32 13 13 Shotcrete
c. 32 14 00 Unit Paving
d. 32 91 00 Landscape Systems
e. Concrete site walls
6. All site visits will be billed on a time and material basis.
7. Any submittal, shop drawing or mock‐up review not specifically listed above.
8. This scope of work assumes that extensive revisions to the 100% Construction
Documents, dated 04.29.2016 will not be made during construction.
TO BE COMPLETED ON A TIME AND MATERIAL BASIS:
1. Site Visits to include (8) site visits during construction.
a. (2) site visits to include substantial completion walkthrough and final
acceptance walkthrough
b. (2) site visits to include review of mock‐ups for:
i. Park entry sign
ii. Gabion Walls
iii. Log Bench A and B
iv. Greenscreen Walls
v. Zipgro Walls
vi. Hops Trellis
vii. Arbor
c. (6) site visits as needed during construction
d. A field report will be prepared for each site visit
Clanton & Associates
Clanton & Associates will participate in Construction Administration tasks for Southeast
Community Park to include the following:
1. Submittal Review as required by specifications
2. Shop Drawing Review as required by specifications
3. Mockup Review as required by specifications
4. Responses to RFI’s from contractor
5. Record drawings based upon redlines provided to design team by contractor.
EXCLUDED FROM CLANTON & ASSOCIATES PROPOSAL:
1. All site visits will be billed on a time and material basis.
2. This scope of work assumes that extensive revisions to the 100% Construction
Documents, dated 04.29.2016 will not be made during construction.
3. Any review, coordination or direction regarding installation of sports field lighting
fixtures.
4. Site walkthroughs at either Substantial Completion or Final Acceptance
TO BE COMPLETED ON A TIME AND MATERIAL BASIS:
1. Site Visit to include (1) site visit during construction
F:\2013\2-13-0010 Ft Collins SE Community Park\management\01_proposal_contract\Change Order #4\2016 0606 SECP SCOPE Contract
Amendment_CA fees.docx
5
a. A field report will be prepared for this site visit
JVA Inc
JVA Inc will participate in Construction Administration tasks for Southeast Community Park
to include the following:
1. Submittal Review as required by specifications
2. Shop Drawing Review as required by specifications
3. Mockup Review as required by specifications
4. Responses to RFI’s from contractor
5. Record drawings based upon redlines provided to design team by contractor.
EXCLUDED FROM JVA Inc PROPOSAL:
1. All site visits will be billed on a time and material basis.
2. This scope of work assumes that extensive revisions to the 100% Construction
Documents, dated 04.29.2016 will not be made during construction.
3. Site walkthroughs at either Substantial Completion or Final Acceptance
TO BE COMPLETED ON A TIME AND MATERIAL BASIS:
1. Site Visits to include (4) site visits during construction at the following milestones:
a. Construction of bridge foundations
b. Construction of bathroom foundations
c. Construction of bathroom framing
d. Construction of site structures (Hops Trellis)
e. A field report will be prepared for each site visit
ERO Resources
Any Construction Administration tasks required by ERO Resources will be directed at the
request of the City of Fort Collins representative and completed on a Time and Material
basis.
TOTAL TEAM FEES FOR CONSTRUCTION ADMINISTRATION
The following outlines the fees for the defined team.
F:\2013\2-13-0010 Ft Collins SE Community Park\management\01_proposal_contract\Change Order #4\2016 0606 SECP SCOPE Contract
Amendment_CA fees.docx
6
TEAM CONTACTS AND BILLING RATES
Prime Consultant and Lead Designer:
CIVITAS Principal $225.00/hr
1200 Bannock Street Senior Project Manager $130.00/hr
Denver, CO 80204 Designer II $80.00/hr
303.571.0053
Craig Vickers, Principal in Charge
cvickers@civitasinc.com
Robin Rooney, Project Manager
rrooney@civitasinc.com
Ecology and Habitat:
ERO RESOURCES Principal $134.00/hr
842 Clarkson Street
Denver, CO 80218
303.830.1188
Mary Powell, Vice President
mpowell@eroresources.com
Lighting Design and Electrical Engineering:
CLANTON & ASSOCIATES Principal Engineer $200.00/hr
4699 Nautilus Court South, Suite 102 Electrical Designer $100.00/hr
Boulder, CO 80301
303.530.7229
David Roederer
david@clantonassociates.com
Structural Engineering:
JVA ENGINEERING Senior Project Manager $144.00/hr
25 Old Town Square, Suite 200 Project Engineer $96.00/hr
Fort Collins, CO 80524 Drafter $92.00/ hr
970.225.9099
Mike McDonald
mmcdonald@jvajva.com
Civitas reserves the right to amend billing rates should the work of this contract continue
past January 1 of the year following execution of this agreement.
FORM OF CONTRACT
Labor for services described in this proposal will be provided under a phased fixed‐fee
agreement, with reimbursable expenses above and beyond the labor fee.
REIMBURSABLE EXPENSES
Normal reimbursable expenses include printing, delivery services, local travel and photo
reproduction. Expenses will be billed at cost plus 10%. Printing multiple copies of approval
and bid documents beyond those listed above is not included.
ADDITIONAL SERVICES
When the Owner‐Client requests activities and/or work products that are above and
beyond the Scope of Work in this proposal, an Additional Services request will be made by
Civitas to the Owner‐Client. This request must be approved by the Owner‐Client prior to
F:\2013\2-13-0010 Ft Collins SE Community Park\management\01_proposal_contract\Change Order #4\2016 0606 SECP SCOPE Contract
Amendment_CA fees.docx
7
beginning the additional work. Based on the needs of the Owner‐Client and Civitas,
the additional service may be considered an additional billing group, or may be
included in the overall amended contract amount.
BILLING
Civitas will invoice the Client monthly. All invoices are due upon receipt. Invoicing will be
separate for contracted amount vs. Time And Material services.
APPENDIX
A ‐ Construction Administration Team Fees
Southeast Community Park
Contract Amendment ‐ Add Service Request for Construction Administration
May 5, 2016
BASE CONTRACT $414,650.00
CONTRACT AMENDMENT 01 $9,700.00
CONTRACT AMENDMENT 02 $166,432.95
CONTRACT AMENDMENT 03 $1,300.00
CURRENT AMENDED CONTRACT $592,082.95
CONTRACT AMENDMENT 04 ‐ ERO Add Service $3,619.00
CONTRACT AMENDMENT 04 ‐ Construction Administration $22,692.00
TOTAL AMENDED CONTRACT $618,393.95