HomeMy WebLinkAboutPrebid - BID - 8202 ARTHUR DITCH BRIDGE REPLACEMENT - OLIVE & LOOMIS INTERSECTION1
1
ARTHUR DITCH BRIDGE
REPLACEMENT – OLIVE / LOOMIS
BID NUMBER: 8202
PRE-BID MEETING
November 30th, 2015
10AM @ 215 North Mason – Rm 2D
City of Fort Collins – Engineering Department
Capital Projects Group
2
INTRODUCTIONS
Engineering – Capital Projects
Dean Klingner – Cap. Proj. Manager 221-6511
Tracy Dyer – Project Manager 222-0855
Jeff Usher – Project Inspector 720.270.2653
Purchasing
Elliot Dale – Buyer 221-6777
2
3
ATTENDANCE
Please be sure to register
Bid Opening
December 10th, 2015 @ 3:00pm (Our Clock)
Location - 215 North Mason Street
Submit Bids to Purchasing Department
4
IMPORTANT CONTRACT DATES
Pre-Construction Meeting
Mandatory Meeting prior to Commencing Construction
Date and Time to be determined after Contract Award
Construction Start Date
Approximately Early / Mid January 2016
One Hundred Thirty Day (130) Calendar Day Contract
3
5
IMPORTANT CONTRACT DATES
Substantial Completion
One-Hundred (100) Day Substantial Completion*
April 15th, 2016 Ditch flow target date
Final Acceptance
Thirty (30) Calendar Days from Substantial Completion*
*Date will be dependent on completion of contract and
notice to proceed.
6
CONTRACT DOCUMENTS BID #8202
Plan Sheets
Prepared by: JUB Engineering, Inc / Stantec
Specification Book
Prepared by: JUB Engineering / City of Fort Collins
Subgrade – Subsurface Investigation work on file with City.
4
7
PROJECT LIMITS
8
SUMMARY OF WORK
Erosion control
Concrete box removal*
Existing box must be removed according to specifications
Structural excavation
Waterline lowering extension w/ casing– page 16
Gas line lowering after excavation / .5 to 1 day (City)
Century Link Phone line relocation (City)
5
9
SUMMARY OF WORK
Cast in-place box installation
Inlet and stormwater pipe installation
Concrete curb and gutter, access ramps
Asphalt milling / overlay and full depth asphalt pavement
10
SUMMARY OF WORK
Parkway irrigation and turf restoration
Traffic control
6
11
SUMMARY OF WORK
Method for Handling Traffic
All Plans must be approved by Syl Mireles – COFC Traffic
Full Closure anticipated
12
SUMMARY OF WORK
Construction Staking
Provided by the City of Fort Collins
48 Hours (Minimum) Required for Notification
Testing
Paid for by the City of Fort Collins thru CTL Thompson
Contractor will coordinate w/ City PM, testing as required
Striping
Provided by the City of Fort Collins
Floodplain Use Permit
Will be obtained and managed by COFC - Engineering
7
13
PROJECT COORDINATION
Area residents
Access to temporary parking
Maintaining safe pedestrian access at all times
Southeast Property specifically
Joseph / wheelchair van / providing access to ramp
Northeast Property specifically
Multi-unit housing
14
HIGHLIGHTS OF GENERAL CONDITIONS
Superintendents
The General Contractor SHALL employ a superintendent
whose sole responsibility is to monitor and coordinate all
facets of the work, including project decision making.
8
15
HIGHLIGHTS OF GENERAL CONDITIONS
Substantial Completion - Defined
• Box Removals, Utilities, Structural Excavation, Box
installation, Backfill -- April 15th, 2016
Liquidated Damages – Substantial Completion
If the Contractor goes past the 100 calendar days* for
substantial completion, damages in the amount of One
Thousand Six Hundred Dollars ($1600.00) for each calendar
day will be assessed
16
HIGHLIGHTS OF GENERAL CONDITIONS
Final Acceptance - Defined
• Completion and Acceptance of: Completion of Sidewalks,
Curb and Gutter, Asphalt Patching / Paving, Landscape
Restoration, Removal of Tree Protection, Removal of
Erosion Control Items (except those as directed by the City
to remain in place), Irrigation / Landscape and Punch List
Items
Liquidated Damages – Final Acceptance
If the Contractor goes past the 30 calendar days for final
acceptance, damages in the amount of One Thousand Six
Hundred ($1600.00) for each calendar day will be assessed
9
17
HIGHLIGHTS OF GENERAL CONDITIONS
Project Coordination Meetings
Weekly pre-determined meetings (including
ticket collection)
Contractor to update Schedule weekly. The
Contractor may be required to submit
additional schedules dependent upon progress
of the project.
18
HIGHLIGHTS OF GENERAL CONDITIONS
Construction Hours
Standard Working Hours are from 7:00am to 6:00pm
Monday through Friday (no equipment idling)
Weekend Work and / or Extended Hours Work may be
granted. Requests for either must be made in writing a
minimum of 72 hours in advance. Requests are subject
to approval by the City of Fort Collins.
10
19
HIGHLIGHTS OF GENERAL CONDITIONS
Haul Routes
Request to keep construction related traffic on Loomis to
Mountain / Mulberry as much as possible
Site Clean Up
The construction work shall be kept and accomplished in
a neat, clean and orderly fashion
Street sweeping may be required in order to minimize
vehicle tracking and to meet EPA storm water quality
requirements
Dust control will be required as necessary
20
TRAFFIC CONTROL
Contractor Responsibilities:
Maintain vehicle, bicycle, and pedestrian traffic at all
times. ALL detours for ALL modes of transportation shall
be approved by the City prior to construction.
Maintain access to all residents.
Review all upcoming lane closure needs and /or changes
in traffic control set up at Weekly Progress Meetings
Traffic Control Plans need to be submitted to the City
seven (7) days prior to setup
11
21
EROSION CONTROL - SWMP
Contractor Responsibilities:
Erosion Control in accordance with Sheets 26-29
The Contractor is responsible for maintaining and
repairing all erosion control devices throughout the
project
Contractor will designate a SWMP Administrator prior to
the start of construction. The SWMP Administrator will
conduct weekly inspections and submit a signed, log of
activity weekly to the City.
22
MATERIAL SUBMITTALS
Reviewed by the City
Process Time – 5 days per submittal
WEATHER DAYS
See “Summary of Work” Section
Monthly Anticipated Calendar Days Lost to
Adverse Weather Conditions
12
23
COMPONENTS OF IMPROVMENTS
24
Removal Limits
Demo plan sheet
13
25
Removal of Portions of Structure (RCB) &
Structural Excavation
Material recycle options: Barker Construction, Colorado Iron /
Metal and City of Fort Collins
26
Utility Installation: Storm
storm line / inlet
14
27
Utility Installation: Waterline
Water line lowering extension
28
Cast in Place Box
Cast in-place single cell
15
29
Pedestrian Ramp Improvements
All four corners, ADA
Compliant slopes and
truncated dome
installation.
30
Pavement Section
HMA Repair Sections:
Note: Project is located in a defined flood plain, final surfaces
are designed to be built according to plan and floodplain controls.
16
31
Landscape Restoration
• Full Detail sheets for all four corners
• Lump sum for each corner
• Each corner has detailed list of plant material
• 1 year landscape establishment / maintenance line
item
32
Additional Notes / Reminders
• All addendum posted to Rocky Mountain E-Purchasing
System at www.rockymountainbidsystem.com
• Questions deadline: December 3rd, 5PM
• Bid Opening: December 10th, 3PM (our clock)
• All local funding
• Bid Bond no less than 5% of bid required
• Substantial Completion and Final Acceptance dates;
April 15th, 2016 substantial completion / 30 day final
completion
17
33
Thanks for Attending!
Questions and Clarifications can be Directed to:
Elliot – Buyer
Office (970) 221.6777
Email edale@fcgov.com
AND
Tracy Dyer – Engineering Proj. Mngr. - Capital Projects
Office (970) 222.0855
Email tdyer@fcgov.com