AGREEMENT FOR PROFESSIONAL SERVICES
FOR
ARTHUR DITCH REPLACEMENT
City of Fort Collins
February, 2016
Scope of Services, Schedule, and Basis of Fee
Traffic Calming Add Service
PROJECT UNDERSTANDING
The City of Fort Collins has requested J-U-B to look at traffic calming option at the intersection of Olive Street &
Loomis Avenue. Under task #1, J-U-B will first analyze three traffic calming options and supply the City with pros
and cons. If the City decides to proceed with a traffic calming option, J-U-B will fulfil tasks 2-4 of our scope. This
intersection is locations are within the city’s Old Town Basin floodplain, and will require coordination in this regard.
Specific scope items are covered below.
The following Scope, Schedule, and Basis of Fee covers additional services for the above contract as described
below.
PART 1 – SCOPE OF SERVICES
A. Basic Services –J-U-B’s Basic Services under this Agreement are limited to the following tasks. CLIENT
reserves the right to add subsequent phrases or related work to the scope of services upon mutual
agreement of scope, additional fees, and schedule. The following abbreviations are used in this
scope:
J-U-B – J-U-B Engineers, Inc.
City – City of Fort Collins
WORK TASKS
Task #1
a. Scope of Services:
i. Analyze three traffic calming options to include; Mini-roundabout, Bulb-out of the
Loomis curb and gutter, and the addition of medians within Loomis Avenue.
ii. Use currently unranked / unweighted factors for the above mentioned analyses.
iii. Analyze the following
1. Effectiveness of calming feature(s)
2. Surface drainage characteristics,
3. Long term maintenance
4. Neighborhood compatibility
5. Cost Estimating
6. Effect on flood plain
b. Deliverables:
i. Conceptual drawings of alternatives and matrix of the pros and cons of each.
Task #2
a. Scope of Services:
i. Once the City selects a preferred alternative, J-U-B will advance the plans to a 60%
level.
ii. Plan sheets that will be added too/updated include
1. Horizontal and geometrics
2. Grading
3. Drainage details
4. Flood Plain
5. Signing and Striping
6. Cross Sections
ii. Quantities and Opinion of Probable Construction Cost.
iii. Landscape / Hardscape Design. (See attached scope and Fee from BHA)
iv. Irrigation Design (Irrigation scope and fee is estimated)
v. QA/QC efforts
b. Deliverables:
i. 60% set of plan drawings developed to be presented as a change order to the current
contract
Task #3
a. Scope of Services:
i. After the Owner has collected information and input from various stakeholders
groups this information will be collected by J-U-B and we will advance the 60% level
drawing to the final 100% plan level. These plans will include vertical and horizontal
refinements, and design solutions to utility installations.
ii. Plan sheets that will be added too/updated include
1. Horizontal and geometrics
2. Grading
3. Drainage details
4. Flood Plain
5. Signing and Striping
6. Cross Sections
vi. Quantities and Opinion of Probable Construction Cost.
vii. Landscape / Hardscape Design. (See attached scope and Fee from BHA)
viii. Irrigation Design (Irrigation scope and fee is estimated)
ix. QA/QC efforts
b. Deliverables:
i. Final plan drawings developed to be presented as a change order to the current
contract
Task #4
a. Scope of Services:
i. Once the drawing go to construction, J-U-B will supply design services during
construction. These services include:
1. General correspondence
2. Answering RFI’s
3. BHA support (scope and fee is estimated)
4. Shop Drawing reviews.
b. Deliverables:
i. Correspondence for items 1-3 above.
B. CLIENT’s Responsibilities – CLIENT is responsible for completing, authorizing J-U-B to complete as
Additional Services, or authorizing others to complete all tasks not specifically included above in J-U-
B’s Basic Services that may be require for the project, including, but not limited to:
1. Transmit contractors shop drawings and RFI’s to J-U-B.
2. Relay J-U-B’s responses to the contractor.
PART 2 – SCHEDULE OF SERVICES
A. The following table summarizes the anticipated schedule for the identified Basic Services predicated upon
timely receipt of CLIENT-provided information, typical review periods, and active direction during work.
CLIENT acknowledges that J-U-B will not be responsible for impacts to the schedule by events or actions of
others over which J-U-B has no control.
Task Number Task Name Anticipated Schedule
1 Conceptual Analysis Feb 3 2016 - Feb 17 2016
2 60% Drawings March 2- 2016 – March 16 2016
3 100% Drawings March 30 – April 13, 2016
4 Construction Services May 2016 - July 2016
PART 3 – BASIS OF FEE
A. The hours and fees for each task are presented on the attached spreadsheet.
B. Period of Service: If the period of service for the task identified above is extended beyond 12 months, the
compensation amount for J-U-B’s services shall be appropriately adjusted to account for inflation and
salary adjustments.
BHA Design Incorporated
1603 Oakridge Drive
Fort Collins, CO 80525
voice: 970.223.7577
fax: 970.223.1827
landscape architecture | planning | urban design www.bhadesign.com
Jeff Temple February 1, 2016
JUB Engineering
4745 Boardwalk Drive, BLDG D suite 200
Fort Collins, CO 80525
RE: Arthur’s Ditch Reconstruction – Loomis & Olive – Traffic Calming Add
Dear Jeff,
Thank you for asking BHA Design to provide design services for the traffic calming add for
the intersection located at Loomis and Olive. It is a pleasure to get the opportunity to help
Fort Collins with these projects.
Our understanding of the Arthur’s Ditch Traffic Calming Add project is as follows:
• JUB will provide 3 options for traffic calming at the Looms and Olive intersection,
including mini-roundabout, bulb-out of the Loomis curb and gutter, and addition of
medians within Loomis Ave.
• BHA will provide landscape design and cost estimate for the preferred option, as well as
coordinate irrigation design.
DESIGN SERVICES
• BHA will provide 90% Complete Construction Document landscape plans for the
preferred option, including details, plant list, and irrigation sleeve sizes and locations,
which will be prepared using AutoCAD 2013 LT.
• 90% Complete Construction Specifications will be developed in CSI format using MS
WORD
• An Opinion of Probable Costs will be developed, based upon 90% documents
• Digital copies (pdf format) of the 90% submittal will be forwarded to JUB and the City
for review
• Review Meeting #1 – JUB and the City will discuss changes to the design with BHA
during a face-to-face meeting
• Bid Document landscape plans (details, plant list, and irrigation sleeve sizes and
locations) which incorporate changes requested by JUB and the City will be developed.
• Bid Document Construction Specifications will be developed
• An Opinion of Probable Costs will be developed, based upon Bid Documents
• Review Meeting #2 – JUB and the City will discuss final changes to the bid docs with
BHA during a face-to-face meeting
• An electronic version (pdf format) of the Bid Document Submittal will be forwarded to
JUB and the City for bidding purposes
• Construction Administration – material submittal reviews, and one substantial
completion walk & punch list
• Hines – Irrigation System Design , details, Specs, material submittal reviews, and one
substantial completion walk & punch list
BHA Design Incorporated
1603 Oakridge Drive
Fort Collins, CO 80525
voice: 970.223.7577
fax: 970.223.1827
landscape architecture | planning | urban design www.bhadesign.com
FEES SUMMARY
BHA Design Services $3,000
Hines Irrigation
TOTAL:
EXCLUSIONS
The following items are currently excluded from the scope of services/fees, but we would be
happy to revise the scope of services/fees to include them if you so choose:
ADDITIONAL SERVICES:
-color renderings
-hardscape and urban design features
-additional meetings above and beyond those listed above
-water meter & tap design services
-electrical design, lighting design
We request written authorization to work on an hourly basis. Our fees and reimbursable
expenses for hourly services will not exceed $3,000 + irrigation without written
authorization. Our labor and related expenses will be charged on a monthly basis as set
forth on Attachment C (BHA’s Standard Terms and Conditions). If these terms are
acceptable, signing below will serve as immediate authorization to proceed. Please return
one executed original to our office for our files.
Sincerely, AGREED TO BY:
JUB (“Client”)
___________________________ __________________________________
Roger B. Sherman Authorized Signature Date
Vice President
$165 $145 $117 $85 $65 $60
1 Task 1 - Traffic Calming Options ( up to 3 options)
Analyze Alternatives 3 8 24 2 $3,601 $3,601
Conceptual Lay outs of alternatives 3 15 $1,626 $1,626
Estimate Alternatives 3 6 $861 $861
Coordination with flood plain 4 $468 $468
Develop pros and cons matrix 1 2 6 $909 $909
Meeting with the City 1 2 $399 $399
5 0 22 51 2 0 $7,864 $0 Subtotal: $7,864
2 Task 2 - Advance selected alternative to 90% Plans
Horizontal Layout and geometrics 2 12 $1,254 $1,254
Grading Sheet(s) 4 16 $1,828 $1,828
Drainage Details 2 4 $574 $574
Flood plain sheet adjustments 4 $468 $468
Signing and Striping 1 2 $287 $287
Cross Sections 1 2 $287 $287
Quantities 2 4 $574 $574
Opinion of Probable Const. Cost (OPCC) and Summary of Approx. Quantities 1 2 $399 $399
Landscape of selected option 2 1 $294 $1,500 $1,794
Irrigation of selected option 1 1 $177 $750 $927
QA/QC 2 $330 $330
3 0 21 40 0 2 $6,472 $2,250 Subtotal: $8,722
3 Task 3 - Advance to Final plans
Horizontal Layout and geometrics 1 1 $202 $202
Grading Sheet(s) 2 2 $404 $404
Drainage Details 1 2 $287 $287
Signing and Striping 1 2 $287 $287
Cross Sections 1 2 $287 $287
Quantities 2 2 $404 $404
Opinion of Probable Const. Cost (OPCC) and Summary of Approx. Quantities 2 2 $404 $404
Landscape of selected option 1 $117 $1,500 $1,617
Irrigation of selected option 1 $117 $750 $867
QA/QC 2 $330 $330
2 0 9 10 0 0 $2,839 $2,250 Subtotal: $5,089
4 Task 4 - Construction Assistance
Review RFIs 2 4 $798 $798
Shop Drawings 4 $468 $468
BHA Assistance 4 $468 $468
$500 $500
2 0 12 0 0 0 $1,734 $500 Subtotal: $2,234
Total Design, Bidding & Construction Assistance Hours $23,909
Hour Subtotal:
Hour Subtotal:
Hour Subtotal:
Hour Subtotal:
J-U-B Hours
Arthur Ditch - Estimated Hours & Fees Traffic Calming
City of Fort Collins RFP 7525
Arthur Ditch
Conceptual Thru Construction Documents
Task
Number Task Description
Prepared By: J-U-B Engineers
2-Feb-16
Total
J-U-B
Labor
BHA
Hines
Admin
Proj. Man.
Clerical
Task Total Total
Proj. Eng.
EI
Structure
Engineer